14
Canterbury Earthquake Response Strategic Information for Businesses, 2015

New Zealand Economic Update - Construction March 2015

Embed Size (px)

Citation preview

Page 1: New Zealand Economic Update - Construction March 2015

Canterbury Earthquake Response

Strategic Information for Businesses, 2015

Page 2: New Zealand Economic Update - Construction March 2015

Canterbury earthquake response – key questions

1. How big is the rebuild expected to be? • $35 bn in 2012 dollars (15% of annual national GDP)

2. How long do we expect activity to continue?

• Peak in 2015/16, long tail for non-residential activity

3. What is the profile for activity? • Construction has increased, further increases expected over the coming year

• Construction to remain elevated through to 2017

• Shift towards higher value residential construction, increases in non-residential spending

4. What are some of the key challenges? • Costs of construction• Availability of labour• Prices and rents• Duration of demand

Page 3: New Zealand Economic Update - Construction March 2015

How big is the rebuild expected to be?

• Westpac estimate: $35 bn (2012 dollars, i.e. excluding cost increases)

• Lower estimate than government

• Cost increases will make some planned spending uneconomic, especially in the commercial sphere

• Spending will still occur, but at a later date (BAU vs. rebuild)

• Around half of spend is residential, half non-residential (breakdown over page).

Reconstruction profile

Westpac forecasts

Page 4: New Zealand Economic Update - Construction March 2015

How big is the rebuild expected to be?$bn

(2012 dollars)

Estimated spend to date

(% complete)

Comment

Residential Land

Westpac’s assumption

$5 Assumed $1 to $3 bil

(20 to 60%)

• As of January EQC had completed around 77% of land settlements.

Some of this will relate to cash settlements.

Repairs (properties with damage

less than $100k)

Source: EQC/Fletchers

$2.5 $2.2

+ Privately funded repairs

(95%)

• Around 69,000 properties in the repair program.

• As of 23 January, Fletchers EQR had completed 64,802 repairs.

• Completion targeted in early 2015.

Rebuilds/major repairs

(damage over $100k, funded

privately or through insurance)

Source: ICNZ and Westpac

estimates

$7 to $10 Insurers: $1.1 bil

+ Private: Around $1 bil

(10 to 20%)

• Around 24,000 properties, many are likely to be rebuilt to higher than

pre-quake standard. There will also be a number of new builds.

• As of 1 Jan 15: 2,890 homes fully rebuilt by insurers, work on

another 1,744 homes was underway and 5,700 in pre-construction.

TOTAL RESIDENTIAL $14.5 to $17.5 $5 to 7 bil

Non-residential Public and infrastructure

SCIRT (Horizontal)

Source: CERA/SCIRT

>$2.5 Around $1.6 bil

(65%)

• At the 12 February 2015 around 65% of the total SCRIT program

was complete

• Targeted completion at end of 2016.

Other including councils

and community assets

Source: CERA/CCDU

$7.5 to $8.5 $0.9 to 1.1 bil

(~13%)

• Design and construction has begun on a number of projects.

• Spending to remain elevated over 2015/16.

Commercial

Westpac’s assumption based on

insurance payouts

Around $7.5 to

$10

$1.3 to 2 bil

(around 20%)

• Includes replacement of damaged assets, and significant betterment,

excludes costs acceleration

• $8 bil in commercial claims paid (current dollars)

TOTAL NON-RESIDENTIAL $17.5 to $21 $4 to 5 bil

TOTALAround $35

$9 to 12 bil

(around 30%)

Page 5: New Zealand Economic Update - Construction March 2015

How long do we expect activity to continue?

• Total rebuild spending projected to peak over 2015/2016, 80% completion around 2018.

• Residential construction has been increasing strongly • Peak projected over 2015/16, 80% completion by end of 2017• Completion around 2020

• SCIRT (horizontal infrastructure) peak spend of around $40 mil month, completion in 2016 targeted,

• Public/social asset spending ramping up now, planned spending to remain at high level through 2015 and 2016 before tapering off through to 2020

• Commercial spending ramping up more gradually, projected peak over 2016/2017, long tail

Page 6: New Zealand Economic Update - Construction March 2015

Profile of activity - Residential

• Work to date has predominantly related to EQC’s repair program. The vast majority of spending in this program will be complete in early-2015.

• Residential construction is shifting towards full-rebuilds/overcap repairs (around 24,000 homes), plus some new builds

• Current consent issuance consistent with around 7000 new homes a year (around 21,000 new homes between 2015 and 2017)

• Questions around strength of activity further ahead, and how many new builds/medium-density projects will be required

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

0

500

1000

1500

2000

2500

2000 2003 2006 2009 2012 2015

Number$m

Number (RHS)

Value

Source: Statistics NZ, Westpac

Sept 2010

Residential consents (annual totals)

Page 7: New Zealand Economic Update - Construction March 2015

Profile of activity – Infrastructure and public

• Spending to rise over 2015, remaining elevated though 2016, tail out to ~2020.

• CERA - $1.1 to 1.2 bn (e.g. Metro sports, stadium, convention centre)

• Councils - around $1.1 to 1.2 bn (e.g. art gallery, library)

• Education (Ministry of Education and tertiary providers) - $2.1 to 2.4 bn

• Lyttelton Port - around $1 bn

• Also health, justice, roading

Public sector construction profile (Source: CERA, MBIE)

Page 8: New Zealand Economic Update - Construction March 2015

Profile of activity - Commercial

• Around $800 mil of work was consented in 2014 (roughly double the pre-quake level), with a significant increase expected over the coming year

• Extended period of strong activity

• Betterment of assets occurring

• Questions around timing of spending vs cost (economics of investment decisions)

• Rents• Building size• Cost increases

• When will spending occur? Is it rebuild or BAU?

0

500

1000

1500

2000

2500

3000

0

200

400

600

800

1000

1200

1400

2000 2003 2006 2009 2012 2015

Number$m

Floor area (RHS)

Value

Source: Statistics NZ, Westpac

Sept 2010

Non-residential consents (annual totals)

Page 9: New Zealand Economic Update - Construction March 2015

Labour market

0

2

4

6

8

10

12

14

0

2

4

6

8

10

12

14

1990 1993 1996 1999 2002 2005 2008 2011 2014 2017

%%

CanterburyAucklandNZ

Source: Statistics NZ, Westpac

Sept 2010

• Unemployment in Canterbury is 3.5%, not far from pre-recession levels

• Net immigration an important source of labour

• Increases in construction and economic activity more generally will absorb spare capacity

• Increasing construction activity in other regions, especially Auckland, will result in increased competition for resources

• Between Dec 2011 and Dec 2014 base rates for construction labour rose 10% in Canterbury vs. 6% in the rest of NZ

Unemployment by region

Page 10: New Zealand Economic Update - Construction March 2015

Residential building costs

500

750

1000

1250

1500

1750

2000

500

750

1000

1250

1500

1750

2000

2000 2003 2006 2009 2012 2015

$/sq mtr$/sq mtrCanterbury

Auckland

NZ

Source: Statistics NZ, Westpac

Sept 2010

Ave. build cost in Canterbury: June 2011: $1307 sq mtrDec 2014: $1753 sq mtr (up 34%)

Page 11: New Zealand Economic Update - Construction March 2015

Non-residential building costs

0

500

1000

1500

2000

0

500

1000

1500

2000

2000 2003 2006 2009 2012 2015

$/sq mtr$/sq mtrCanterbury

AucklandNZ

Source: Statistics NZ, Westpac

Sept 2010

Page 12: New Zealand Economic Update - Construction March 2015

House prices and rents in Christchurch (s.a.)

500

1000

1500

2000

2500

3000

500

1000

1500

2000

2500

3000

2000 2003 2006 2009 2012 2015

IndexIndex

House prices

Rents

Sept 20102012 2013 2014

House prices 11.8 7.1 3.7

Rents 16.4 8.9 1.7

Source: Statistics NZ, MBIE, Westpac

Year to Dec % change

Page 13: New Zealand Economic Update - Construction March 2015

Population growth and housing demand

• Most of the damaged housing stock forecast to be repaired or replaced by end of 2017.

• Rebuild estimates also include new builds.

• Stats NZ projections imply growth in Canterbury’s population of around 53,100 people between 2018 to 2028 (range of estimates: 13,400 to 92,800)

• Medium estimate implies the need for about 23,000 homes over 10 years (around 2,300 per year).

• Comparison• Current: around 7000 new homes consented over the past year• Pre-quake: around 2500 to 4500 new homes built per annum.

Page 14: New Zealand Economic Update - Construction March 2015

So, now what?

CLICK HERE

How can you best use this information? If you’d like a one-on-one meeting with me to

discuss the implications for your business