Upload
michael-audu
View
568
Download
0
Embed Size (px)
Citation preview
1
A REVIEW OF PROCUREMENT STRATEGIES IN THE BUILDING INDUSTRY
GROUP 8
2STRATEGIES IN BUILDING PROCUREMENT
Briefly explain the concept of procurement
Establish the methods of building procurement
Highlight the attributes, pros and cons of each strategy
Briefly compare the strategies
IN THIS SLIDE WE INTEND TO:
3STRATEGIES IN BUILDING PROCUREMENT
Procurement describes the merging of activities
undertaken by the client to obtain a building. It is
essentially a series of considered risk that can be
transferred between stakeholders in the building
industry.
4STRATEGIES IN BUILDING PROCUREMENT
Traditional procurement method Design and build procurement method Turnkey procurement method Direct labor procurement method Public private partnership method Management Method
BASIC METHODS OF PROCUREMENT
5STRATEGIES IN BUILDING PROCUREMENT
Selection of an absolute optimal procurement
method is difficult, because even the most
experienced client or contractor does not know
all the potential benefits or risks for each
method. Procurement is, therefore, a succession
of ‘calculated risks’
6TRADITIONAL PROCUREMENT METHOD
Traditional method is one of the most common strategies of procuring a building.
The traditional method is sometimes called Design-Bid-Build (or design/bid/build, and abbreviated D-B-B or D/B/B accordingly) (Akram, et al., 2012).
The client who is also referred to as the employer consents that the projects design work is done independently from the construction work. The design team is different from the construction team.
For the design work, consultants are appointed for the design and cost control while the contractor carries out the construction works.
DESIGN BID BUILD
7TRADITIONAL PROCUREMENT METHOD
CLIENT (EMPLOYER)
ARCHITECT
QUANTITY SURVEYOR ENGINEERS
OTHER CONSULTANTS
CONTRACTOR
NOMINATED SUBCONTRACTOR
S
DOMESTIC SUBCONTRACTOR
S
NOMINATED SUPPLIERS
The contractor’s responsibility extends to all workmanship and materials including all works by sub-contractors and suppliers.
The contractor is usually appointed by competitive tendering.
But may if necessary be appointed earlier by negotiation on the basis of partial or notional information.
There are three types of contract under the traditional procurement method:
1. Lump sum contracts 2. Measurement contracts 3. Cost reimbursement (Davis, Love, & Baccarini , 2008)
8SEQUENTIAL PHASES TO THE TRADITIONAL DELIVERY METHOD
Design Stage Schematic design is carried out,
reviewed and approved. Concept and preliminary
specifications are further developed.
Final drawings and specifications are prepared to form the contract documents
Bidding (Bid) Stage The Owner obtains competitive
bids from a number of qualified contractors.
Each contractor obtains a copy of tender documents which is fully priced by them or split by sub components.
Project is awarded to the lowest bidder.
Construction Stage In this stage, almost every component of the
project is supplied and installed by specialized subcontractors.
The contractor is responsible for undertaking all of the works including provision of all materials, labour, plant and equipment;
also controls the sequence and coordination of works to ensure that construction is undertaken in an ordered and logical way.
9ADVANTAGES
Easily understood by all
There is accountability due to
a competitive selection
It is design lead; the client is has direct
influence and control.
It is a ‘tried and test’ method of procurement
which the market is very familiar
with.
Price certainty at the award of the contract
Variations (changes) to the contract are relatively easy to
arrange and manage.
competitive equity as all tendering
contractors bid on the same basis
10DISADVANTAGES
Can be a timely process to produce the full
contract documentation.
Tenders documents from an incomplete design can be produced but can lead to cost and
time uncertainty, and may lead to disputes.
Overall project duration may be longer than other procurement
methods.
As the general contractor is brought to the team
post design, there is little opportunity for input on
effective alternates being presented.
11DESIGN AND BUILD PROCUREMENT
DEFINITION DESIGN-BUILD (D-B) - According to
the Design-Build Institute of America (DBIA), the design-build form of project delivery is a system of contracting whereby one entity performs both architectural & engineering and construction under one single contract.
12DESIGN AND BUILD PROCUREMENT
ATTRIBUTES OF D-B (NICHOLSON, 2005) Dynamic:
Efficient:
Single-source:
13DESIGN AND BUILD PROCUREMENTCATEGORIES OF DESIGN-BUILD
(D-B) STIPULATED PRICE: With stipulated price design-
build a public agency specifies how much it will pay for construction of a particular building
CONSTRUCTION MANAGEMENT: With construction management design-build the public agency awards a contract to a "construction manager"
14ADVANTAGES
Price CertaintyAgency May
Avoid Conflicts and Disputes
Builder Involved in Design Process
Faster Project Delivery
Agency Needs Less Technical
StaffBetter
communicationFewer disputes and
litigationHigher quality
outcomes
Clear roles, responsibilities and
accountabilityLess administrative
burden
Reduced risk to the client (because the design–build entity
assumes more)
15DISADVANTAGES
Limited assurance of quality control.
Subjective Contract Award
Limited access for small contractors.
Typical project management issues (establishing liability,
writing contracts, scoping estimates and
schedule)
Conflict of interest and ethical issues
Greater business and financial risks
associated with architect taking on general contractor
responsibilities
16TURNKEY PROCUREMENT
DEFINITION A turnkey or a turnkey project is a type of
project that is constructed so that it could be sold to any buyer as a completed product
17TURNKEY PROCUREMENT
DEFINITION It is also described as a contract which a
firm agrees to fully design, construct and equip a manufacturing, business, service facility and turn the project over to the purchaser when it is ready for operation for remuneration.
18ADVANTAGES
The project is usually owned by
the contractor.
It gives the client enough time to seek financing.
There is no room for inexperienced clients to make
wrong decisions.
Contractual relationship with
one person.
Total commitment from the
contractor.
19DISADVANTAGES
Lack of control by the client.
Remuneration is usually high.
Difficult to find clients.
No intervention by the client.
20TURNKEY PROCUREMENT
SUMMARY The project is usually owned by the
contractor until the end of the project.
Lack of control by the client over design decisions.
It takes more time to setup initially.
21DIRECT LABOUR PROCUREMENT
DEFINITION Direct labour is a system that entails the
client’s usage of own resources to realize his projects (Ogunsanmi et. al; 2003; )
CLIENT
TRADESMEN
22DIRECT LABOUR PROCUREMENT
ATTTRIBUTE It is a method whereby the client design
and produces his project by himself with the aid of in-house professionals void of the use of contractors (Kadiri & Odusami, 2003).
23ADVANTAGES
Tax effect, tax deduction is
almost impossible
Cheaper than the other
procurement methods
Cost monitoring and control is
easier compared to other methods
Greater client satisfaction
Safety in construction.
24DISADVANTAGES
Limited to non-complex projects
Sub-standard finished product, where the
client doesn’t have a good knowledge of
construction.
The client shoulders the greater risk
25PUBLIC PRIVATE PARTNERSHIP (PPP) PROCUREMENT
DEFINITION Is a legally-binding contract between
government and business for the provision of assets and the delivery of services that allocates responsibilities and business risks among the partners.
GOVERNMENT
BUSINESS
PPP
26PUBLIC PRIVATE PARTNERSHIP (PPP) PROCUREMENT
ATTRIBUTES In a P3s method, the government remains
actively involved throughout the project’s life cycle.
The private sector is responsible for the more commercial function such as PROJECT DESIGN, CONSTRUCTION, FINANCE & OPERATIONS.
The goal is to combine the best capabilities of both partners for mutual benefits.
PPP are best for large projectsSource: Google Images
27PUBLIC PRIVATE PARTNERSHIP (PPP) PROCUREMENT
CHARACTERISTICS Executed between public and private sectors.
Risk sharing between the parties.
Long-term relationship between the parties.
Ultimate regulatory responsibility remains in the public sector.
Encompass diverse types of infrastructure.
28ADVANTAGES
Increase in efficiency of a
project’s delivery, operations & management.
Availability of additional resources to meet the growing
need of investment in the sector.
Reduces public sector risks.
Makes better use of assets.
Encourages “Life cycle” approach
to planning & budgeting.
29DISADVANTAGES
The Private sector might not be interested in a project due to
perceived high risks or may lack technical, financial or managerial capacity to implement the project.
A P3s project may be more costly.
30MANAGEMENT BID
DEFINITION Management procurement has three
basic forms Management contracting Construction management (similar to
design and build) Design and manage
31MANAGEMENT BID
The client employs both the design consultant and a management contractor.
The Contractor is in charge of ensuring timely completion of project
MANAGEMENT CONTRACTINGClient
Design team
Management team
Worksmen
32MANAGEMENT BID
The client employs all the consultants, the project manager, and the tradesmen directly and goes into contractual agreement with them directly
CONSTRUCTION MANAGEMENT
Client
Design team Management team Worksmen
33MANAGEMENT BID
This is similar to management contracting, however, in this type the contractor is paid a fee to assume the responsibility for both the construction team and design team
DESIGN AND MANAGE Client
Management contractor
+ Design Works
Worksmen
34COMPARISM
FACTOR TRADITIONAL
DESIGN & BUILD TURNKEY DIRECT
LABOUR PPP MANAGEMENT BID
SCALE OF PROJECT
SMALL-MEDIUM
LARGE REPEATITIVE ALL SMALL VERY
LARGE MEDIUM-LARGE
RISK CONTRACTOR CONTRACTING FIRM
CONTRACTING FIRM CLIENT GOVT AND
PRIVATE BIZ SHARED
COMPLEXITY - - SPECIALIZED SIMPLE - -
35STRATEGIES IN BUILDING PROCUREMENT
Briefly explain the concept of procurement
Establish the methods of building procurement
Highlight the attributes, pros and cons of each strategy
Briefly compare the strategies
RECAP: WE HOPE WE HAVE BEEN ABLE TO:
36REFERENCES
Akram, S., Cavallini, C., Dizdar, A., Mukherjee, A., Kluczuk, P., Kujawa, Z., . . . Zaręba, K. (2012). Manual “Procurement Strategy In Construction”. Europe: Lifelong Learning Programme.
Davis, P., Love, P., & Baccarini , D. (2008). Building Procurement Methods. Bribane Qld 4001: Cooperative Research Centre For Construction Innovation.
37
THANK YOU`