AURUM – PHASE 02 – Photo Report
• Key Plan showing the Camera positions , Click on the Icon to review respective status:
1
2
3
5
4
6
AURUM_Photo Report - Phase 02
Key Plan
Comments :
• TOWER-A&B, BLOCKWORK, PLASTERINGB WORK IN PROGRESS.
Phase 02 – Photo report Position - 01
12
3
5
4
6
AURUM_Photo Report - Phase 02
Key Plan
Comments :
• Tower A : 8th & 9th , 10th floor Block work & 2nd and 3rd floor plastering work in progress.
Phase 02 – Photo report Position - 02
12
3
5
4
6
AURUM_Photo Report - Phase 02
Key Plan
Comments :
• Tower A & D ; Block work , Plastering work in progress
Phase 02 – Photo report Position - 03
12
3
5
4
6
AURUM_Photo Report - Phase 02
Key Plan
Comments :
• Tower D : 10th,11th,12th,14th floor block work and 1st and 2nd floor Plastering work is in progress.
Phase 02 – Photo report Position - 04
12
3
5
4
6
AURUM_Photo Report - Phase 02
Key Plan
Comments :
• Tower A : 8th & 9th , 10th floor Block work & 2nd and 3rd floor plastering work in progress.
Phase 02 – Photo report Position - 05
12
3
5
4
6
AURUM_Photo Report - Phase 02
Key Plan
Comments :
• Tower B : 14th & 15th floor Block work and 5th 6th floor plastering work is in progress.
Phase 02 – Photo report Position - 06
12
3
5
4
6
AURUM_Photo Report - Phase 02
Key Plan
Comments :
• RETAINING WALL FOOTING AND STARTER- REINFORCEMENT AND CONCRETE IN PROGRESS.
Phase 02 – Photo report
12
3
5
4
6
AURUM_Photo Report - Phase 02
Key Plan
Comments :
PODIUM RAMP-1 SHUTTERING IN PROGRESS
Phase 02 – Photo report
12
3
5
4
6
AURUM_Photo Report - Phase 02
Key Plan
Comments :
• CENTER PODIUM COLUMN, FOOTING,GRADE SLAB-SHUTTERING,REINFORCEMENT.CONCRETE IN PROGRESS.
Phase 02 – Photo report
12
3
5
4
6
AURUM_Photo Report - Phase 02
Key Plan
Comments :
• CENTER PODIUM COLUMN, FOOTING,GRADE SLAB-SHUTTERING,REINFORCEMENT.CONCRETE IN PROGRESS..
Phase 02 – Photo report Position - 08
12
3
5
4
6
AURUM_Photo Report - Phase 02
Comments :
• INTERNAL PLASTERING WORK IN PROGRESS.
Phase 02 – Photo report
AURUM_Photo Report - Phase 02
Comments :
• INTERNAL PLASTERING WORK IN PROGRESS.
Phase 02 – Photo report
AURUM_Photo Report - Phase 02
COMMENTS :
• TYPICAL FLOOR BLOCKWORK IN PROGRESS.
Phase 02 – Photo report
AURUM_Photo Report - Phase 02
COMMENTSTYPICAL FLOOR BLOCKWORK IN PROGRESS.
Phase 02 – Photo report
AURUM_Photo Report - Phase 02