Project Progress – 06 th Jan,2014

My home abhra status report as on 06.01.2014

Embed Size (px)

DESCRIPTION

My Home Abhra Status Report on January 6th 2013

Citation preview

Page 1: My home abhra status report as on 06.01.2014

Project Progress – 06thJan,2014

Page 2: My home abhra status report as on 06.01.2014

STATUS REPORT OF MY HOME ABHRA Tower-”A” As On 06.01.14

1.1st To 14th Floor Slabs : Completed2.15th Floor Slab : Flat No 1 & 2 flats Slab Completed, 4 & 5 flats Slab Bar Bending Completed ,3rd flat

Shuttering Completed. 3.Brick Work: 10th Floor External walls in Progress

Page 3: My home abhra status report as on 06.01.2014

STATUS REPORT OF MY HOME ABHRA Tower-”B” As On 06.01.14

1.1st To 14th Floor Slabs : Completed2.15th Floor Slab : Flat No 1 & 2 flats Slab Completed, 4 & 5 flats Slab Planning Today ,3rd flat Slab Bar Bending

Progress . 3.Brick Work: 10th Floor External walls in Progress

Page 4: My home abhra status report as on 06.01.2014

STATUS REPORT OF MY HOME ABHRA Tower-”C” As On 06.01.14

1.1st To 11th Floor Slabs : Completed

2.12th Floor Slab : Flat No 01 Completed ,Flat No 02 Bar bending In Finishing Stage

2. Brick Work: 9th Floor External walls in Progress

Page 5: My home abhra status report as on 06.01.2014

STATUS REPORT OF MY HOME ABHRA Tower-”D” As On 06.01.14

1.1st To 15th Floor Slabs : Completed2.16th Floor Slab : Flat No 1 and 2 Bar Bending Completed ,Flat No : 4 and 5 shuttering Work Started 3rd Flat Columns work

Progress 3.Brick Work: 11th Floor External walls in Progress

Page 6: My home abhra status report as on 06.01.2014

STATUS REPORT OF MY HOME ABHRA Tower-”E” As On 06.01.13

1.1st To 15th Floor Slabs : Completed2.16th Floor Slab : Flat No 1&2 Slab Completed , 4 & 5 flats Shuttering work Progress, 3rd Flat Columns work In

Progress 3. Brick Work: 11th Floor External walls in Progress