MAHALAXMI HERITAGE
Development Linked Payment Plan
BSP‐ Rs.13499/‐ Sq. Yd.
S.No. INSTALLMENT DUE ON AMOUNT DUE (%)
1‐
2‐
3‐
4‐
5‐
6‐
7‐
8‐
9‐
10‐
11‐
On Booking
Within 45 days of Booking
At the time of Allotment
At the time of Bhoomi Poojan
Commencement of demarcation work for the Roads and
Block
Commencement of demarcation work of Plot Clusters
Commencement of demarcation work of individual Plots
Commencement of Electrification Work of the Block
Commencement of Sewerage/ Drainage Work
Commencement of Water Tank & metalling work of
Roads for the Blocks
On Offer of Sale Deed & Possession
10% of BSP Welcome Letter
10% of BSP
Provisional Allotment Letter
10% of BSP
10% of BSP
10% of BSP
10% of BSP
10% of BSP
10% of BSP
10% of BSP + Sewarage
Charges (Approx. Rs.250/‐sq.
yd.)
5% of BSP
5% of BSP+ PLC
* Service tax/Any govt Tax if applicable or charged later by Govt. would be payable by
Buyer only.
* PLC will be charged 10% for corner plot, 10% on wide road,10% for park facing.(Two
PLC 12% and Three PLC 15%.
* All cheques /DD are payable in favour of MAHALAXMI INFRAREALTY PVT. LTD.
* Time of possession within 36 Months from the date of allotment.
* Price indicated above are subject to revision at sole discretion of company without any notice.
* PLC would be payable at the time of Registry.