Developing Context Sensitive Solutions:A Tale of Two Toll RoadsMike Heiligenstein, Executive DirectorIBTTA Facilities Maintenance
33
183A Project
• Built using a comprehensive development agreement Design-build Guaranteed price and
completion date Original contractor aesthetics/
landscape commitment 2.5%; raised to 4%
Context sensitive solutions process to be contractor’s responsibility
“Context Sensitive Design is thinking
beyond the pavement.”
US Department of Highways Federal Highway
Administration
44
Context Sensitive Solutions Approach
• Partner with developer Establish community outreach
Engage community in design and construction
Initiate dialogue regarding betterments
• Input from stakeholders Aesthetics
Shared Use Path
Landscaping
Field Operations Building
Opportunities for betterments
55
183A CSS: Developer’s Role
• 4% allocation for aesthetics/landscape
• Provide aesthetic concepts and treatments
• Participate in community outreach
• Provide options and costs to Aesthetic Committee
66
183A CSS: Mobility Authority’s Role
• Establish Aesthetics Committee
• Manage community outreach
• Provide direction on aesthetic concepts/ treatments
• Provide timely decisions to ensure adherence to design-build schedule
• Approve costs and budgets
77
Lessons From CDA Approach
• Aesthetics not contractor’s top priority
• Very difficult in design build environment. Mobility Authority detailed CSD with more specificity in next RFP
• Client had to drive process and develop vision with both design build team and consultant team
• Pricing of aesthetics elements left to negotiation – after award of CDA-DB, leverage shits to contractor
Difficult to pin down budget
• Unable to establish clear community vision for overall aesthetics
Pace of development schedule
Lack of previous experience
99
290E Project
• Originally planned to be built using comprehensive development agreement Design-build Guaranteed price and
completion date Contractor provided with
detailed description of aesthetic and landscaping design requirements
• 183A CDA did not provide this level of detail
1010
290 East CSS Process:
• Engage stakeholders through workshops
• Gather input from stakeholders
• Identify issues and concerns
• Define a solution that works within the context of the community
• Incorporate solution into the design
Goal: Design a facility that meets mobility and safety needs but also complements the community.
1111
Engage the Community to Determine:
• What are some existing community characteristics? What makes the area unique? How can the look and character of
the roadway reflect the values of the community?
Are there existing themes upon which we can build?
• Character of design elements Bridges and retaining walls Lighting Signs Pedestrian facilities Landscaping and hardscape
1212
Visual Preference Survey
• Preference Surveys were solicited
• Input from these meetings inspired 3 design concepts
1313
Final Community Wide Workshop
• Entire community was invited to attend a final meeting to identify a preferred design concept
• On-line input was also taken via the Mobility Authority’s Web site
1414
290 East CSS Design Guidelines
• Aesthetic guidelines for project based on input from workshops
• Look and character reflect region
• Provide shared-use path/pedestrian facilities
• Address safety considerations• Address mobility
considerations • Provide a flexible document:
Used for Design Build or Design Bid Build
1515
290 East Measures of Success
• Community Acceptance
• Environmental Compatibility
• Engineering and Technical Functionality
• Financial Feasibility
• Hopefully! Timely Delivery