24
PROJECTS PERFORMANCE ANALYSIS & FORECASTING ® Prepared By: WALEED ELBASYOUNI Sr. Architect, PMP , SFC, 6SigmaUsing Earned Value Management

Projects Performance Analysis & Forecasting

Embed Size (px)

Citation preview

Page 1: Projects Performance Analysis & Forecasting

PROJECTSPERFORMANCE ANALYSIS & FORECASTING

®

Prepared By:

WALEED ELBASYOUNISr. Architect, PMP , SFC™, 6Sigma™

Using Earned Value Management

Page 2: Projects Performance Analysis & Forecasting

Session Content :-

• Introduction • Overview of Key Performance Indicators ( KPI )• What Is The Earned Value Management ?• Why Project Managers Use EVM ?

• Earned Value Management Terms and Formulas• Planned value (PV)• Earned value (EV)• Actual cost (AC)

• Variance• Schedule Variance ( SV )

• Cost Variance ( CV )

• Performance Index • Schedule Performance Index (SPI)• Cost Performance Index (CPI)

• Example ( Case Study )

• Project Forecasting• Budget at Completion (BAC)• Estimate at Completion (EAC)• Estimate to Complete (ETC).• Variance at Completion (VAC)• To Complete Performance Index (TCPI)

Page 3: Projects Performance Analysis & Forecasting

1.1 Introduction

Page 4: Projects Performance Analysis & Forecasting

1.1 Introduction

Overview of Key Performance Indicators ( KPI )

• Key Performance Indicators ( KPI ) are a Set Of Quantifiable Measures That a Company Uses To Gauge Its Performance Over Time.

• These Metrics Are Used To Determine a Company's Progress In Achieving Its Strategic and Operational Goals, And Also To Compare A Company's Performance Against Other Businesses Within Its Industry.

Page 5: Projects Performance Analysis & Forecasting

What Is The Earned Value Management ?• Earned Value Management Is a Project Management Technique For Measuring Project Performance And

Progress.

• Earned Value Is An Approach Where You Monitor The Project Plan, Actual Work, And Work-completed Value To See If a Project Is On Track.

• Earned Value Shows How Much Of The Budget And Time Should Have Been Spent, With Regard To The Amount Of Work Done So Far.

Why Project Managers Use EVM ?• Project Managers Use EVM To Assess The Schedule and Cost Performance Of a Project To Know Exactly

Whether The Project Is:

(Ahead Of / On / Behind Schedule) - ( Under / On / Over Budget )

1.1 Introduction

Page 6: Projects Performance Analysis & Forecasting

1.2 Earned Value Management Terms and Formulas

Page 7: Projects Performance Analysis & Forecasting

Planned value

Earned value

Actual Cost

PV

EV

AC

1.2 Earned Value Management Terms and Formulas

Any Project Manager Use Earned Value Management To Assess The Schedule and Cost Performance Of a Project He Should Based On Three Terms.

EVMEVM

PVPV

EVEVACAC

Page 8: Projects Performance Analysis & Forecasting

Budgeted Cost For Work Scheduled (BCWS)Planned valuePV

• The Approved Budget For The Work Scheduled To

Be Completed By a Specified Date.

• Also Referred To As The Budgeted Cost Of Work

Scheduled (BCWS).

1.2 Earned Value Management Terms and Formulas

Page 9: Projects Performance Analysis & Forecasting

Budgeted Cost For Work Performed (BCWP)Earned valueEV

• The Approved Budget For The Work Actually

Completed By The Specified Date.

• Also Referred To As The Budgeted Cost Of

Work Performed (BCWP).

1.2 Earned Value Management Terms and Formulas

Page 10: Projects Performance Analysis & Forecasting

• The Costs Actually Incurred For The Work

Completed By The Specified Date.

• Also Referred To As The Actual Cost Of Work

Performed (ACWP).

Actual cost for work performed (ACWP)Actual CostAC

1.2 Earned Value Management Terms and Formulas

Page 11: Projects Performance Analysis & Forecasting

1.3 Project Variance & Performance Index

Page 12: Projects Performance Analysis & Forecasting

Project Variance

Schedule Variance

Cost Variance

SV CVEV – PV

EV – AC

Project Variance According To Earned Value Management Three Terms We Can Define The Project Variance :-

• Planned Value (PV)

• Earned Value (EV)

• Actual Cost (AC)

1.3 Project Variance & Performance Index

Page 13: Projects Performance Analysis & Forecasting

SV < 0Behind Schedule SV = 0

On Schedule

SV > 0Ahead of Schedule

Planned Value (PV) - Earned value (EV) - Actual Cost (AC)

Schedule Variance (SV) = EV – PV

1.3 Project Variance & Performance Index

Page 14: Projects Performance Analysis & Forecasting

CV < 0Over Budget CV = 0

On Budget

CV > 0Under Budget

Planned Value (PV) - Earned value (EV) - Actual Cost (AC)

Cost Variance (CV) = EV – AC

1.3 Project Variance & Performance Index

Page 15: Projects Performance Analysis & Forecasting

Project Performance

Index

Schedule Performance

Index

Cost Performance

Index

SPI CPIEV / PV

EV / AC

Performance Index According To Earned Value Management Three Terms We Can Define The Project Performance Index :-

• Planned Value (PV)

• Earned Value (EV)

• Actual Cost (AC)

1.3 Project Variance & Performance Index

Page 16: Projects Performance Analysis & Forecasting

SPI < 1Behind Schedule

SPI = 1On Schedule

SPI > 1Ahead of Schedule

Schedule Performance Index (SPI) = EV / PV

Planned Value (PV) - Earned value (EV) - Actual Cost (AC)

1.3 Project Variance & Performance Index

Page 17: Projects Performance Analysis & Forecasting

Cost Performance Index (CPI) = EV / AC

Planned Value (PV) - Earned value (EV) - Actual Cost (AC)

CPI < 1Over Budget

CPI = 1On Budget

CPI > 1Under Budget

1.3 Project Variance & Performance Index

Page 18: Projects Performance Analysis & Forecasting

Planned Value (PV) Earned value (EV) Actual Cost (AC) Schedule Variance (SV) Cost Variance (CV) Schedule Performance Index (SPI) Cost Performance Index (CPI)

1.3 Project Variance & Performance Index

Quantity Cost | Unit

Budget 100 500 S.R

Actual 120 600 S.R

Example ( Case Study )• This Schedule Shows Some Information About Budgeted

And Actual Cost To (XYZ) Construction Project , According To EVM Techniques Calculate The Following Terms Then Define The Project Status (Schedule & Budget) ?

• PV = 500 x 100 = 50.000 S.R

• EV = 500 x 120 = 60.000 S.R

• AC = 600 x 120 = 72.000 S.R

• SV = EV – PV = 60.000 – 50.000 = 10.000 S.R

• CV = EV – AC = 60.000 – 72.000 = -12.000 S.R

• SPI = EV / PV = 60.000 / 50.000 = 1.2

• CPI = EV / AC = 60.000 / 72.000 = 0.83

The Project (XYZ ) Status at this Time • According SV & SPI The Project Ahead Of Schedule.

• According CV & CPI The Project Over Budget.

Page 19: Projects Performance Analysis & Forecasting

1.4 Project Forecasting

Page 20: Projects Performance Analysis & Forecasting

1.4 Project Forecasting

Project Forecasting

• Consists Of Taking The Project Status

Information And Extrapolating The Current

Project Performance To The End Of The

Project and How The Future Will Turn Out

Based On Evidence Or Assumptions.

• The Purpose Of Forecasting Is To Give

Managers Insight Into How Profitable

Projects Are Likely To Be In The Future.

Page 21: Projects Performance Analysis & Forecasting

1.4 Project Forecasting

Forecasting Terms :-

• Budget at Completion (BAC)

• Estimate at Completion (EAC)

• Estimate to Complete (ETC)

Considering The Same Budgeted Rate

Considering CPI

Considering CPI and SPI

• Variance At Completion (VAC)

• To Complete Performance Index (TCPI)

Page 22: Projects Performance Analysis & Forecasting

1.4 Project Forecasting

• Estimate To Complete (ETC)Is The Estimated Cost Required To Complete The Remainder Of The Project There Are Various Methods To Calculate The (ETC):-

Considering The Same Budgeted RateEAC = AC + (BAC – EV) Considering CPIEAC = BAC / CPI Considering CPI and SPIEAC = AC + [ (BAC – EV) / (CPI x SPI) ]

• Budget At Completion (BAC) Is The Total Budget Allocated To The Project

• Estimate At Completion (EAC)Is The Expected Total Cost Of A Schedule Activity Component, EAC Is Equal To The Actual Cost Of Work Performed (ACWP) + The Estimate To Complete (ETC) For All Of The Remaining Work.

Page 23: Projects Performance Analysis & Forecasting

1.4 Project Forecasting

• Variance At Completion (VAC)Is The Difference Between The Budget At Completion(BAC) And The Estimate At Completion (EAC)

VAC = BAC – EAC• To Complete Performance Index (TCPI)

It’s The Cost Performance That Must Be Achieved On The Remaining Work To Meet A Specified Goal Like BAC Or EAC, It Represents The Ratio Between Remaining Works And Remaining Funds.

TCPI = (BAC- EV) / (BAC – AC) Or TCPI = (BAC-EV) / (EAC – AC)

From the Previous Example• PV = 500 x 100 = 50.000 S.R

• EV = 500 x 120 = 60.000 S.R

• AC = 600 x 120 = 72.000 S.R

• Assumed BAC = 500.000 S.R

TCPI = (BAC-EV)

---------------------(BAC – AC)

TCPI = 500.000 - 60.000-----------------------500.000 – 72.000

TCPI =1.028

TCPI = 440.000

--------------428.000

Page 24: Projects Performance Analysis & Forecasting