4
ID Task Mode Task Name Duration Start Finish Predecessors Resource Names 1 Tire Company Website 59 days? Tue 16-01-26 Fri 16-04-15 Alex,Jonah,Cameron 2 TOA Agreement 2 days? Tue 16-01-26 Wed 16-01-27 Alex,Jonah,Cameron 5 Client Questionnaire 2 days Thu 16-01-28 Fri 16-01-29 2 Alex,Cameron,Jonah 10 Research 8 days Mon 16-02-01 Wed 16-02-10 2,5 Alex,Cameron,Jonah 20 Client Brief 2 days Thu 16-02-11 Fri 16-02-12 2,5,10 Alex,Cameron,Jonah 23 Planning 5 days Thu 16-02-11 Thu 16-02-18 2,5,10,20 Jonah 34 Information Architecture 13 days Thu 16-02-18 Tue 16-03-08 2,5,10,20,23 Jonah 52 Create and Collect Assets 7.5 days? Tue 16-03-08 Thu 16-03-17 2,5,10,20,23,34 Cameron 64 Creative Design Process 8.5 days? Tue 16-03-08 Fri 16-03-18 2,5,10,20,23,34 Cameron 75 Technical Development 20.5 days? Tue 16-03-08 Tue 16-04-05 2,5,10,20,23,34 Alex 115 Website Testing 7 days? Wed 16-04-06 Thu 16-04-14 2,5,10,20,23,34 Alex 136 Launch 1 day? Fri 16-04-15 Fri 16-04-15 2,5,10,20,23,34 Alex,Cameron,Jonah S M T W T F S '16 Jan 25 Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 1 Project: INM410-Work-Breakdow Date: Tue 16-12-13

Inm410 work-breakdown-schedule v2

Embed Size (px)

Citation preview

Page 1: Inm410 work-breakdown-schedule v2

ID Task Mode

Task Name Duration Start Finish Predecessors Resource Names

1 Tire Company Website 59 days? Tue 16-01-26 Fri 16-04-15 Alex,Jonah,Cameron

2 TOA Agreement 2 days? Tue 16-01-26 Wed 16-01-27 Alex,Jonah,Cameron

5 Client Questionnaire 2 days Thu 16-01-28 Fri 16-01-29 2 Alex,Cameron,Jonah

10 Research 8 days Mon 16-02-01 Wed 16-02-10 2,5 Alex,Cameron,Jonah

20 Client Brief 2 days Thu 16-02-11 Fri 16-02-12 2,5,10 Alex,Cameron,Jonah

23 Planning 5 days Thu 16-02-11 Thu 16-02-18 2,5,10,20 Jonah

34 Information Architecture 13 days Thu 16-02-18 Tue 16-03-08 2,5,10,20,23 Jonah

52 Create and Collect Assets 7.5 days? Tue 16-03-08 Thu 16-03-17 2,5,10,20,23,34Cameron

64 Creative Design Process 8.5 days? Tue 16-03-08 Fri 16-03-18 2,5,10,20,23,34Cameron

75 Technical Development 20.5 days? Tue 16-03-08 Tue 16-04-05 2,5,10,20,23,34Alex

115 Website Testing 7 days? Wed 16-04-06 Thu 16-04-14 2,5,10,20,23,34,52,64,75Alex

136 Launch 1 day? Fri 16-04-15 Fri 16-04-15 2,5,10,20,23,34,52,64,75Alex,Cameron,Jonah

S M T W T F S'16 Jan 18 '16 Jan 25

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 1

Project: INM410-Work-BreakdowDate: Tue 16-12-13

Page 2: Inm410 work-breakdown-schedule v2

S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W'16 Jan 25 '16 Feb 01 '16 Feb 08 '16 Feb 15 '16 Feb 22 '16 Feb 29 '16 Mar 07

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 2

Project: INM410-Work-BreakdowDate: Tue 16-12-13

Page 3: Inm410 work-breakdown-schedule v2

W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S'16 Mar 07 '16 Mar 14 '16 Mar 21 '16 Mar 28 '16 Apr 04 '16 Apr 11

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 3

Project: INM410-Work-BreakdowDate: Tue 16-12-13

Page 4: Inm410 work-breakdown-schedule v2

S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W'16 Apr 11 '16 Apr 18 '16 Apr 25 '16 May 02 '16 May 09 '16 May 16 '16 May 23

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 4

Project: INM410-Work-BreakdowDate: Tue 16-12-13