21
1 REVITHOUSSA L.N.G. TERMINAL X

Revithoussa l.n.g. terminal_presentation

Embed Size (px)

DESCRIPTION

Revithousa island is storage for LNG- Liquefied natural gas. During the visit our NGS supplies, had a meeting with the operational manager of the site and agreed about cooperation for the Israeli market in case that it will be decided to build LNG terminal in Israel. This facility has been accomplished with the cooperation of many companies which NGS is representing: The design and the engineering was made by a team of international companies under the management of Asprofos engineering. A large amount of pipes were supplied by Corinth Pipeworks. Many of the ball valves and other equipment ware supplied and built by Enimex. In addition, Totgas supplied a lot of the necessary equipment during the constructions. The construction of the LNG unit was built by a group of the international companies including Greek contractors such as J&P Avax, Elter and others.

Citation preview

Page 1: Revithoussa l.n.g. terminal_presentation

1

REVITHOUSSA L.N.G. TERMINAL

X

Page 2: Revithoussa l.n.g. terminal_presentation

2

Hellenic Main Gas Transport System

Page 3: Revithoussa l.n.g. terminal_presentation

3

Revithoussa LNG Terminal Location

Page 4: Revithoussa l.n.g. terminal_presentation

4

The Role of the LNG Terminal In the National Gas Network

STRATEGIC

The third entrance of natural gas to Greek natural gas network

PEAK DEMAND

Covers natural gas peak demands to Greek natural gas network

RELIABILITY

Enhances the Greek natural gas network reliability

Page 5: Revithoussa l.n.g. terminal_presentation

5

Terminal Operation History First LNG cargo 3/02/2000

First gas send out 11/02/2000

Performance test (full gas send out) 3 and 6/05/2000

Hand over of the plant to Owner staff took place on the 6/11/2000

Terminal Expansion starts on June 2005 and construction phase is finished on September 2007

330 cargoes has been received since March 2011

Page 6: Revithoussa l.n.g. terminal_presentation

10 YEARS OPERATION

0,76 0,84 0,83 0,75 0,73

0,99

1,49

1,62

1,36

1,82

0

0,2

0,4

0,6

0,8

1

1,2

1,4

1,6

1,8

2

2001 2002 2003 2004 2005 2006 2007 2008 2009 2010

YEAR

LNG RECEIVED PER YEAR

million m3 LNG

Page 7: Revithoussa l.n.g. terminal_presentation

LNG vs GAS PIPELINE – HELLENIC NETWORK

0

10

20

30

40

50

60

70

80

90

100

%

2000 2001 2003 2004 2005 2006 2007 2008 2009 2010

YEAR

% LNG TO HELLENIC GAS NETWORK PER YEAR LNG

PIPELINE GAS

Page 8: Revithoussa l.n.g. terminal_presentation

8

Jetty can handle LNG carriers • LOA up to 290m • Draft up to 11.5 m• Max. Deadweight 130.000 ton• Unloading rate up to 7,250m³

LNG/hr• 2x12" and 1x16’’ LNG unloading

arms and • 1x12" vapour return arm Storage facilities

2x65,000 m³ LNG storage tanks full containment with 9% Ni steel

inner tank pre-stressed concrete outer tank below ground in excavated pit

Unloading facilities

Page 9: Revithoussa l.n.g. terminal_presentation

9

Terminal Infrastructure

Sendout Pumps 8 x 200 m3 LNG/hr In tank pumps 2 x 120 m3 LNG/hr LFHP pumps 2 x 225 m3 LNG/hr HFHP pumps 2 x 300 m3 LNG/hr maxFHP pumps

Vaporizers 2 x 125 m3 LNG/hr ORV 1 x 375 m3 LNG/hr ORV 2 x 125 m3 LNG/hr SCV 2 x 190 m3 LNG/hr SCV

Page 10: Revithoussa l.n.g. terminal_presentation

10

Terminal Infrastructure

Boil off recovery system

3 x 4900 Kg/h boil off

reciprocating compressorsRecondenser at 7 barg

Send out capacity:

SMSR: 1.000 m3 LNG / hourPeak S.O.: 1.250 m3 LNG/ hour

Page 11: Revithoussa l.n.g. terminal_presentation

11

Sendout Gas Specifications Pressure = 26 – 64 bar g

Temperature = 3,5 °C

All Boil off gas is re-condensed in order to be sent out. Possibility of Boil off gas to be used as fuel gas

No odorization is required for the send out gas

No High Heating Value or Wobbe Index adjustment is required

Page 12: Revithoussa l.n.g. terminal_presentation

12

Page 13: Revithoussa l.n.g. terminal_presentation

13

Supervision, Control and Safety Systems Distribution Control System (DCS)

Emergency Shut Down System (ESD)

Fire Gas Spill System (FGS)

- Fire Detection Panel

- Fire Protection Panel

Power Control System (PCS)

Earthquake Monitor System (2 levels)

- Operating Basis Earthquake (OBE)

- Safe Shut down Earthquake (SSE)

Civil Monitoring System (CMS)

Docking System

Mooring Hooks System

Intrusion System

Page 14: Revithoussa l.n.g. terminal_presentation

14

Page 15: Revithoussa l.n.g. terminal_presentation

15

The Construction of the LNG Tanks Two full containment type (double shell) tanks located in pits excavated

in the hill of the island.

Inner container made of 9 % Nickel steel.

Outer container made of concrete.

Isolating material of 1 m thickness between inner and outer containers.

Support by 212 seismic isolating absorbers.

These supports can absorb movements of the tank (in a distance up to 30 cm) in any direction in case of an earthquake with max. horizontal

acceleration of a magnitude of 0,5 g.

Page 16: Revithoussa l.n.g. terminal_presentation

16

Power Integration StationCombined heat and power 13.000KWe and

12.270KWheat

At the same time, a 13MW High-Performance Combined Heat and Power (CHP) Unit is also in operation at the LNG facilities, applying innovative technology. This unit produces enough energy to cover the island’s needs with the most environmentally-friendly method. The surplus of electrical energy can by channeled to PPC’s network.All the produced heat is used for vaporizing of the L.N.G. before it is exported from the island to the consumers. In periods without heat demands the power plant can still produce electricity using the backup radiator cooling plant.

Page 17: Revithoussa l.n.g. terminal_presentation

17

Power Integration StationCombined heat and power 13.000KWe and

12.270KWheat − Contract

Type : Turnkey with 3 months of operation assistance Contract award : November 2007 Handing over : July 2009

− Technical Data

Gas Engines Make : Caterpillar, Germany Type : V-type G16CM34 Speed : 750rpm

Page 18: Revithoussa l.n.g. terminal_presentation

18

Power Integration StationCombined heat and power 13.000KWe and

12.270KWheat Alternators

Make : Leroy Somer, FranceType : LSA 58 UL105/8pRating : 8,165 kVAVoltage / Frequency 6 kV / 50 Hz

Gas Regulating StationMake : Flonidan, Denmark

Exhaust Gas Heat ExchangersMake : Danstoker, DenmarkType : Horizontal smoke tube, EEB-WCapacity : 3,478 Kw

Page 19: Revithoussa l.n.g. terminal_presentation

19

Radiator Coolers

Make : Alfa LavalType : Induced draft, FBLGE-1260-8-7/8-186DN100S & 124DN100D-Ep & 124DN100D-Ep

Cooling Capacity : HT / LT : 1,720kW / 1,691kW

Power Integration StationCombined heat and power 13.000KWe and

12.270KWheat

Page 20: Revithoussa l.n.g. terminal_presentation

20

Efficiency up to 88,5%

Electric efficiency : 41,3%

Thermal efficiency: 47,2%

Page 21: Revithoussa l.n.g. terminal_presentation

21

REVITHOUSSA LNG TERMINAL