Upload
moniaros
View
909
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Revithousa island is storage for LNG- Liquefied natural gas. During the visit our NGS supplies, had a meeting with the operational manager of the site and agreed about cooperation for the Israeli market in case that it will be decided to build LNG terminal in Israel. This facility has been accomplished with the cooperation of many companies which NGS is representing: The design and the engineering was made by a team of international companies under the management of Asprofos engineering. A large amount of pipes were supplied by Corinth Pipeworks. Many of the ball valves and other equipment ware supplied and built by Enimex. In addition, Totgas supplied a lot of the necessary equipment during the constructions. The construction of the LNG unit was built by a group of the international companies including Greek contractors such as J&P Avax, Elter and others.
Citation preview
1
REVITHOUSSA L.N.G. TERMINAL
X
2
Hellenic Main Gas Transport System
3
Revithoussa LNG Terminal Location
4
The Role of the LNG Terminal In the National Gas Network
STRATEGIC
The third entrance of natural gas to Greek natural gas network
PEAK DEMAND
Covers natural gas peak demands to Greek natural gas network
RELIABILITY
Enhances the Greek natural gas network reliability
5
Terminal Operation History First LNG cargo 3/02/2000
First gas send out 11/02/2000
Performance test (full gas send out) 3 and 6/05/2000
Hand over of the plant to Owner staff took place on the 6/11/2000
Terminal Expansion starts on June 2005 and construction phase is finished on September 2007
330 cargoes has been received since March 2011
10 YEARS OPERATION
0,76 0,84 0,83 0,75 0,73
0,99
1,49
1,62
1,36
1,82
0
0,2
0,4
0,6
0,8
1
1,2
1,4
1,6
1,8
2
2001 2002 2003 2004 2005 2006 2007 2008 2009 2010
YEAR
LNG RECEIVED PER YEAR
million m3 LNG
LNG vs GAS PIPELINE – HELLENIC NETWORK
0
10
20
30
40
50
60
70
80
90
100
%
2000 2001 2003 2004 2005 2006 2007 2008 2009 2010
YEAR
% LNG TO HELLENIC GAS NETWORK PER YEAR LNG
PIPELINE GAS
8
Jetty can handle LNG carriers • LOA up to 290m • Draft up to 11.5 m• Max. Deadweight 130.000 ton• Unloading rate up to 7,250m³
LNG/hr• 2x12" and 1x16’’ LNG unloading
arms and • 1x12" vapour return arm Storage facilities
2x65,000 m³ LNG storage tanks full containment with 9% Ni steel
inner tank pre-stressed concrete outer tank below ground in excavated pit
Unloading facilities
9
Terminal Infrastructure
Sendout Pumps 8 x 200 m3 LNG/hr In tank pumps 2 x 120 m3 LNG/hr LFHP pumps 2 x 225 m3 LNG/hr HFHP pumps 2 x 300 m3 LNG/hr maxFHP pumps
Vaporizers 2 x 125 m3 LNG/hr ORV 1 x 375 m3 LNG/hr ORV 2 x 125 m3 LNG/hr SCV 2 x 190 m3 LNG/hr SCV
10
Terminal Infrastructure
Boil off recovery system
3 x 4900 Kg/h boil off
reciprocating compressorsRecondenser at 7 barg
Send out capacity:
SMSR: 1.000 m3 LNG / hourPeak S.O.: 1.250 m3 LNG/ hour
11
Sendout Gas Specifications Pressure = 26 – 64 bar g
Temperature = 3,5 °C
All Boil off gas is re-condensed in order to be sent out. Possibility of Boil off gas to be used as fuel gas
No odorization is required for the send out gas
No High Heating Value or Wobbe Index adjustment is required
12
13
Supervision, Control and Safety Systems Distribution Control System (DCS)
Emergency Shut Down System (ESD)
Fire Gas Spill System (FGS)
- Fire Detection Panel
- Fire Protection Panel
Power Control System (PCS)
Earthquake Monitor System (2 levels)
- Operating Basis Earthquake (OBE)
- Safe Shut down Earthquake (SSE)
Civil Monitoring System (CMS)
Docking System
Mooring Hooks System
Intrusion System
14
15
The Construction of the LNG Tanks Two full containment type (double shell) tanks located in pits excavated
in the hill of the island.
Inner container made of 9 % Nickel steel.
Outer container made of concrete.
Isolating material of 1 m thickness between inner and outer containers.
Support by 212 seismic isolating absorbers.
These supports can absorb movements of the tank (in a distance up to 30 cm) in any direction in case of an earthquake with max. horizontal
acceleration of a magnitude of 0,5 g.
16
Power Integration StationCombined heat and power 13.000KWe and
12.270KWheat
At the same time, a 13MW High-Performance Combined Heat and Power (CHP) Unit is also in operation at the LNG facilities, applying innovative technology. This unit produces enough energy to cover the island’s needs with the most environmentally-friendly method. The surplus of electrical energy can by channeled to PPC’s network.All the produced heat is used for vaporizing of the L.N.G. before it is exported from the island to the consumers. In periods without heat demands the power plant can still produce electricity using the backup radiator cooling plant.
17
Power Integration StationCombined heat and power 13.000KWe and
12.270KWheat − Contract
Type : Turnkey with 3 months of operation assistance Contract award : November 2007 Handing over : July 2009
− Technical Data
Gas Engines Make : Caterpillar, Germany Type : V-type G16CM34 Speed : 750rpm
18
Power Integration StationCombined heat and power 13.000KWe and
12.270KWheat Alternators
Make : Leroy Somer, FranceType : LSA 58 UL105/8pRating : 8,165 kVAVoltage / Frequency 6 kV / 50 Hz
Gas Regulating StationMake : Flonidan, Denmark
Exhaust Gas Heat ExchangersMake : Danstoker, DenmarkType : Horizontal smoke tube, EEB-WCapacity : 3,478 Kw
19
Radiator Coolers
Make : Alfa LavalType : Induced draft, FBLGE-1260-8-7/8-186DN100S & 124DN100D-Ep & 124DN100D-Ep
Cooling Capacity : HT / LT : 1,720kW / 1,691kW
Power Integration StationCombined heat and power 13.000KWe and
12.270KWheat
20
Efficiency up to 88,5%
Electric efficiency : 41,3%
Thermal efficiency: 47,2%
21
REVITHOUSSA LNG TERMINAL