Upload
shosein2011
View
497
Download
1
Embed Size (px)
Citation preview
Building the Next Major Iron OreBuilding the Next Major Iron Ore Mine in the Labrador Trough
Corporate PresentationCorporate PresentationFebruary 24, 2012
FSE: P02
FORWARD-LOOKING STATEMENTS
Certain information contained herein regarding Champion Minerals Inc., including management’s assessment of future plans and operations, may constitute forward-looking statements under applicable securities law and necessarily involve risks, including but not limited to risks associated with mining exploration operating costs production costs volatilitylimited to risks associated with mining exploration, operating costs, production costs, volatility of share prices, currency fluctuations, imprecision of resource and reserve estimates, environmental risks and ability to access sufficient capital from internal and external sources.
As a consequence, actual results may differ materially from those anticipated in any forward q , y y p ylooking statements. Plans, intentions or expectations disclosed in any forward-looking statements or information should not be read as guarantees of future results or events, and will not necessarily be accurate indications of whether or when or by which such results or events will be achieved.
Except as required by law, Champion Minerals Inc., expressly disclaims any intention and undertakes no obligation to update any forward looking statements or information as conditions change.
The historical mineral resources mentioned are strictly historical in nature and are non-compliant to National Instrument 43-101 mineral resources and mineral reserves standards, and should therefore not be relied upon. A qualified person has not done sufficient work to upgrade or classify the historical mineral resources as current National Instrument NI-43-101
2
upgrade or classify the historical mineral resources as current National Instrument NI 43 101 compliant.
About Champion Minerals
Fermont Projects (710 km2)
Advanced iron ore exploration and development projects located in Canada’s principal iron ore district, the Labrador Trough
Fermont Projects (710 km ) 17 properties in the Fermont Quebec mining camp Flagship Fire Lake North Project-currently in the
Feasibility stageFeasibility stage Over 2.2 billion tonnes of NI 43-101 compliant iron
mineral resource estimate 82.5% direct interest, 3% NSR (C$3 million buyback for
an additional 1% NSR)*
Attikamagen Property (310 km2)Champion Minerals holds a 49% interest Champion Minerals holds a 49% interest
Century Iron Mines Corp. (51% interest) has option to earn up to a 60% interest in the property by funding a further $5.5 million in exploration expenditures by May 2014**
3
exploration expenditures by May 2014** * Fancamp Exploration Ltd. holds remaining 17.5% interest** CHM 49% / Century Iron Ore Mines 51%; Investment by WISCO of 25% ($60M) and Minmetals of 5% ($12M)
Quebec’s Next Major Iron Ore MineMajor Iron Ore Mine
Fire Lake North (FLN) Development Project Nov. 21 2011 PEA indicates ability to produce 8.7 million tonnes of
concentrate per annum for the first 25 years of a 40 year mine life the firstconcentrate per annum for the first 25 years of a 40-year mine life the first 5 years will average approximately 10 million tonnes of concentrate per annum
Net Present Value of $4 billion at a discounted cash flow rate of 8% with an Internal Rate of Return of 41.5% and a payback period of 2.3 years
Established Iron Ore District Canada produces 44 mtpy of iron ore concentrate in the southern end of the
Labrador Trough this is expected to grow to 200 mtpy over the next 10 years if all proposed development projects are realized.
Established rail, power and port infrastructureQuebec’s Plan Nord: $80 billion investment over the next 25 years in- Quebec s Plan Nord: $80 billion investment over the next 25 years in northern Quebec for various projects including infrastructure projects
- Competitive power rates: ~ $0.04 - $0.045; price to be negotiated in 2012- Initiative for world-class port facilities underway
Proven Team Strengthened advisory board and board of directors includes former
Consolidated Thompson Iron Mines management and officers
4
Capital Structure
Share Data and Cash Position as of February 23, 2012.
Shares Outstanding 89.3 million *Warrants 6.1 million @ C$1.52
(246,645 @ C$1.15 expiring 04/20122.17 million @ C$1.50 expiring 04/20122.8 million @ C$1.50 expiring 10/2013, of which 79% are owned by insiders and advisors.)
Options 12.1 million @ C$1.04
Fully Diluted Shares Outstanding 107.6 million *Market Capitalization
(based on $1.98 share price)C$176.8 million
( $ p )
Cash Position C$14.8 million
Fully Diluted Cash Position C$36.5 million *Management Ownership ~ 8%
Analyst Coverage Canaccord GenuityFraser MackenzieHaywood SecuritiesJennings CapitalMacquarie Capital Markets
Paradigm CapitalRaymond JamesRBC Capital MarketsSalman PartnersStifel NicolausTD SecuritiesTD Securities
* Does not include $30 million (15 M shares) bought deal financing scheduled to close on or about March 12, 2012
5
Experienced Management TeamOver 200 years of combined exploration and mine operations experience
Board of Directors Management TeamTom Larsen Tom Larsen
Over 200 years of combined exploration and mine operations experience
Chairman President and CEO
Alexander Horvath, P.Eng. Director
Alexander Horvath, P.Eng.Executive Vice President, Exploration
Jean Depatie, P.Geo. Martin Bourgoin, P. Geo.Jean Depatie, P.Geo.Director
Martin Bourgoin, P. Geo. Executive Vice President, Operations
Ashwath MehraDirector
Jeff Hussey, P.Geo.Executive Vice President, Development
Donald A Sheldon LLB P Eng Bruce Mitton P GeoDonald A. Sheldon, LLB., P.Eng.Director
Bruce Mitton, P.Geo.Vice President, Exploration
Paul AnkcornDirector
Jean-Luc Chouinard, P.Eng.Director of Projects
F i S Mil N t CAFrancis SauveDirector
Miles Nagamatsu, CAChief Financial Officer
Joseph S. C. ChanDirector
Jorge EstepaVice President, Secretary-Treasurer
Richard Quesnel: Senior Technical Advisor and Head of the Advisory BoardAdvisory Board: Richard Quesnel, Mick McMullen, and Doug BacheProject Finance Advisor: Marc Duchesne 6
Why invest in Champion Minerals?
Favourable Operating Environment
• Established iron ore mining district the
Champion Minerals’ Competitive Advantage
• Fermont: 17 iron ore (710 km2) brownfieldmining district the
Labrador Trough• Favourable tax
environment (40% tax rebate on
(710 km2) brownfield projects
• Feasibility Stage Fire Lake North Surface Deposits contain( %
exploration expenditures)• Access to low-cost power
and close to rail and port infrastructure
Deposits contain coarse grained specular hematite
Easier to liberate Deleterious elements
• Quebec`s Plan Nord $80 billion over the next 25 years
• Quebec is known to be a
Deleterious elements are below industry specifications limits
• Experienced team of project developers and
world class area to develop mines
• Unprecedented Iron Ore Price Range and Forecast
p j pmine builders
• Upside Potential for Growth
• Several De-Risking
7
• Skilled Labor Work ForceSeveral De Risking Initiatives Underway
Attikamagen
Rail InfrastructureQuebec North Shore & Labrador Railway (“QNS&L”)
High Voltage Power Lines
y ( ) QNS&L links to Sept-Iles and Pointe Noire Bloom Lake and QNS&L railways are
considered common carriersC
Cluster 1
Cluster 3
Cluster 2 Common carriers allocate capacity on a first-come, first-serve basis Fire Lake North PEA Base Case connection
to Bloom Lake railway requires 94 km of rail incl des t rnaro nd loop and sidings
Cluster 1
Fermont
Cartier Private Rail
QNS&L Rail
Common
– includes turnaround loop and sidings Participation in a private multi user rail
solution as an alternative transportation / haulage option is also under study
Three Ports/ Stockpile
Rail Carrier
Cartier Railway: Linked to Port-Cartier Privately owned by ArcelorMittal
88
pLocations
Gulf of St Lawrence
Adjacent to the west of Fire Lake North Proj.
Multi-User Port Infrastructure Expanding to Meet DemandExpanding to Meet Demand
Port of Sept-Iles
RTZ-IOC shipping facility
Pointe Noire 50Mtpy Multi User Port Project to be
announced; Phase 2 Planning….Cliff N t l R hi i
Sept-Iles
Cliffs Natural Resources shipping facility New multi-user port to be expanded
in two phases: phase one expansion of 40 50 Mtpy and phase two
Pointe Noire
of 40-50 Mtpy and phase two expansion of 100 Mtpy
Port-Cartier ArcelorMittal shipping facility $2.1B expansion is underway and
will include concentrator expansion with port and rail infrastructure upgrades
China Max ship capacity 300kt
9
Located 62 km west of Sept-IlesCourtesy of the Port de Sept Isles
Development: Fire Lake North ProjectOil Can Project 6 km
from FLN Concentrator
10
1111
Fire Lake North Project Growth through Development
Preliminary Economic Assessment indicates a production rate of 8.7 million tonnes of concentrate per annum for the
Growth through Development
pfirst 25 years of a 40-year mine life, average of approximately 10 million tonnes of concentrate per annum for the first 5 years (released November, 2011).
Net Present Value of $4 billion at a discounted cash flow rate of 8% with an Internal Rate of Return of 41.5% and a payback period of 2.3 years.
Recent Mineral Resource Estimate update (October 6, 2011)
Measured and Indicated Resources of 400 1 million tonnes gradingof 400.1 million tonnes grading 30.6% total iron
Inferred Resources of 661.2 million tonnes grading 27.7% total iron
Feasibility Study underway with several de-risking initiatives ongoing
12See www.championminerals.com for reports maps and assays12
Fire Lake North - Metallurgy Coarser grained: At 600 - 700 micron liberation grind size the SiO2 content is
very low (3-4%) allowing for optimization; 2nd Phase tests underway SPI tests indicate a relatively softer ore; 2nd Phase of tests underway Current Mill Design: Gravity separation Deposits of quartz specularite iron ore are typical of the Fermont area
− Coarse liberation grind size; product will be sold as “Sinter Fines” − 80% of the global iron ore market seeks this product− Low deleterious elemental levels will help to secure market share
13High Grade - Coarse Specular Hematite Typical Quartz-SpecularHematite-Magnetite Mineralization
Fire Lake North Development Project
1414
Fire Lake North Development Project
15
Fire Lake North Development ProjectNovember 2011 Preliminary Economic Assessment Update – Highlights
Key Results Pre-Tax Basis
Internal Rate of Return (IRR) (8% Discount Rate) 41.5%
November 2011 Preliminary Economic Assessment Update – Highlights
( ) ( )
Undiscounted Cash Flow US$10.9B
Net Present Value @ 5% Discounted Cash Flow US$5.6B
Based upon the following assumptions:
Net Present Value @ 8% Discounted Cash Flow US$4.0B
Net Present Value @ 10% Discounted Cash Flow US$3.2B
Payback Period (8% Discount Rate) 2 3 YearsPayback Period (8% Discount Rate) 2.3 Years
Capital Costs:
Operating Costs:
US$1,368 million (includes rail and port infrastructure)
US$51.01 per tonne (average 25 years); US$39.46 per tonne (average years 1 to 5)
Price assumptions:
Mine-Life:
Exchange rate:
Total Resources(1):
US$115 per tonne of concentrate at 65% Fe
40 years (average of 8.7 million tonnes/year for the first 25 years)
$1.00 USD to $1.00 CDN
400 million tonnes grading 30 6% Fe (NI43 101 Measured and Indicated Resources)
16
Total Resources(1):
In Pit Resources
400 million tonnes grading 30.6% Fe (NI43-101 Measured and Indicated Resources)661 million tonnes grading 27.7% Fe (NI43-101 Inferred Resources)
921.8 million tonnes grading 28.8% Fe at an 8% cut-off grade
Fire Lake North ProjectPreliminar Economic Assessment St d
OPERATING EXPENDITURES (US$/TONNE OF CONCENTRATE)
COST PARAMETERS AVERAGE 25 YEARS AVERAGE YEARS 1 TO 5
Preliminary Economic Assessment Study
COST PARAMETERS AVERAGE 25 YEARS AVERAGE YEARS 1 TO 5
Mining 22.56 12.13Concentrating, crushing and processing 4.52 3.97Site infrastructure, sales and general administration 4.40 3.39Environmental tailings and management 0.29 0.26g gRail transport 15.52 16.14Port facilities 3.72 3.57
Total 51.01 39.46Equipment Lease Cost (not included in above total) 1.67 5.17
CAPITAL EXPENDITURES (US$ MILLIONS)
COST CENTRES $ MILLIONSPre-stripping of open pit areas 97.5Concentrator and site infrastructure including loadout facilities 682.3Railway (62km distance and 94km total including turnaround loop and sidings) 228.8Port Facilities: Railcar unloading, stacker/reclaimer, conveyors 96.8Environmental and Tailings Management 27.9Other Pre Production Costs 34.0
17
Other Pre Production Costs 34.0Sub-total 1,167
Contingency 201Total 1,368
Fire Lake North Project ScheduleDevelopment, Construction, and Production
2014 201520132011 2012
Diamond Drilling
Scoping Study
Q2 Q3 Q4 Q1 Q2 Q3 Q4Q1 Q2 Q3 Q4 Q1Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Feasibility Study
Environmental / Social Studies
Community Consultationy
Permitting
Construction
P d tiProduction
18
Oil Can Project Exploration UpsideExploration Upside
The 2011 drill program returned long magnetite-hematite iron formation up to 546 metres in length
The 400 metre spaced drill program is now complete, Mineral Resource Estimate Q1 2012
SELECTED* COMPOSITE ASSAY RESULTS
HOLE-ID HOLE LENGTH AZIMUTH DIP FROM TO INTERVAL** GRADE***metres degrees degrees metres metres metres Total Fe%
OC11 02 594 310 45 188 53 590 03 401 50 30 7OC11-02 594 310 -45 188.53 590.03 401.50 30.7including 246.86 460.40 213.54 33.1OC11-05 545.00 020 -45 241.56 545.00 303.44 34.7including 407.24 538.00 130.76 36.5OC11-08 616.00 180 -50 67.00 612.73 545.73 33.7Including 67.00 509.34 442.34 36.4
* Selected Composite Assay Results are stated only for results recently received. The Selected Composites are not necessarily representative of the average grade or thickness of the mineral zones or potential resource.
19
not necessarily representative of the average grade or thickness of the mineral zones or potential resource.** Intervals are down-hole lengths and not true widths of the mineral zones.*** Grades are calculated from Total Fe% sample assays completed by ALS Chemex Laboratories using the “High Grade/Ores Method” and XRF analysis.
20
Oil Can Project Exploration Upside
To view a larger more detailed version of this map please visit:
http://www.championminerals.com/vns-site/page-oil_can.html
Up to 546m 33.7% total iron
Initial Mineral Resource
Estimate: Q1 2012
Billion tonne potential
Potential for low strip ratio < 1 : 1
Bench width 100- 350m
9800N
5800E
CENTRAL
South & East ZonesSection 9800N (Facing North)
Oil Can ProjectExploration Upside ( g )
South Zone
p p
OC11-02Ovb OC11-19 OC11-01
OC11-08OC11-07OC11-05
East ZoneSouth Zone
Assay Pending
303.4m @ 34.7%incl. 130.8m @
36.5%
IFIF
190.0m @ 30.6%
Assay Pending545.7m @ 33.7%
incl. 442.3 @ 36.4%
197 2m @ 26 8%401.5m @ 30.7%
incl. 213.5 @ 33.1%
197.2m @ 26.8%incl. 145.5 @
28.1%
200 metres
21
Central Zone(Facing Northwest)
Oil Can ProjectExploration Upsidep p
OC11-10OC11-03OC11-16OC11-14
191.7m @ 28.2% Ovb
224 0m @ 28 1%
311.4m @ 27.6%incl. 269.0m @
29.2%
472.2m @ 28.0%incl. 119.6m @
35.2%
224.0m @ 28.1%incl. 140.0m @
30.0% IF
200 metres
22
North ZoneSection 5800E (Facing East)
Oil Can ProjectExploration Upside Section 5800E (Facing East)p p
OC11-04OvbOC11-09
OC11-12 OC11-13 OC11-15
221.2m @ 25.0%incl. 128.9m @
141.5m @ 29.2%
IF
@28.7%
Assays Pending 179.5m @ 32.8%
472.2m @ 28.0%incl. 119.6m @
35.2%
414.1m @ 25.1%incl. 139.0m @
29.5%
200 metres
23
Moire Lake Project Exploration Upsidep p
Arcelor
2011: 9,347 m drill program completed
Mineral Resource Estimate Q1 2012Mittal P
roperty
Drill results include: 503 metres grading 31% total iron (LM11-12)
Potential to significantly increasey Boundary
Potential to significantly increase Historical Resource: 101 million tonnes grading 31% iron
Kilometric Synform with Hematite and Magnetite
t t f500 meters
outcrops at surface
Adjacent to the East of ArcelorMittal Mont Wright Mine
24
10 km from QNS&L Railway
24
Fermont Project Resource BaseCurrent NI 43-101 Compliant Resources
Over 2.2 Billion Tonnes of NI 43-101 Compliant Iron Ore Resources
661
947
700
800
900
1000
Measured and Indicated (M&I)
215300
400
500
600
400
0
100
200
Project Bellechasse Fire Lake North Harvey Tuttle
Location Quebec, Canada Quebec, Canada Quebec, Canada
Grade 28.7% 30.6% (M&I)27.7% (Inferred)
23.2%
Mineralization Magnetite Specular Hematite Magnetite
Historical 91 Mt @ 30 0% Iron 41 Mt @ 31 0% iron n/a
25
Historical Resources
91 Mt @ 30.0% Iron 41 Mt @ 31.0% iron n/a
* 15 % cut-off grade
Mil tMilestones
Fire Lake North Definition Drilling OngoingFire Lake North Definition Drilling Ongoing
Updated PEA on Fire Lake North Completed
Initial NI 43-101 Mineral Resource Estimate for Moire Lake Project Q1 2012
O’Keefe Purdy Drill Results Remaining Q1 2012
Initial NI 43-101 Mineral Resource Estimate for Oil Can Project (adjacent to Fire Lake North Project) Q1 2012
Metallurgical results at Fire Lake North, Moire Lake and Oil Can Projects Q1-Q2 2012
Fire Lake North Feasibility Study Q3 2012
Fire Lake North Construction Start Q4 2013Fire Lake North Construction Start Q4 2013
Fire Lake North Production 2015
Marketing Study Q2 2012
26
Why Invest in Champion Minerals?Champion Minerals? Fire Lake North NPV: $4 Billion @ 8% DCF
Adjacent Oil Can shows great promise and plans are j g p punderway to develop it; Metallurgical tests underway…
17 Brownfield Projects (710 km2) near 5 operating mines
Experienced Team: Exploration, Development, Construction, pe e ced ea p o at o , e e op e t, Co st uct o ,Commissioning, & Operations Management
Financed through to feasibility; Favourable tax environment
Quebec`s Plan Nord Quebec s Plan Nord
Access to power and close to rail and port
Multi User Port is planned ; Trans-Shipping is an option
Several Railway options are under study
Iron Price Range and Forecasts is Unprecedented
Several De-Risking Initiatives Underwayg y
27
Exploration ProjectsExploration Projects
Coarse Grained Specular Hematite
Fire Lake North Exploration Camp
p
28
O’Keefe Purdy ProjectExploration UpsideExploration Upside
29
Advanced Exploration
Harvey Tuttle Project NI 43-101 Inferred Resource Estimate:
717Mt @ 25% iron; magnetite rich
Intersected multiple significant iron formation
Bellechasse Project NI 43-101 Inferred Resource Estimate: 215Mt @
29% Iron; Magnetite Rich iron formation Intersected multiple significant iron formation
intervals in 2010 drill program
Total of 13,165m of drilling completed
Less than 50% of the kilometric scale
Historical Resources increased from 91Mt remaining upside potential.
Adjacent to Hwy 389; 10km from Fire Lake North
Synform Geometry is good for Open Pit Less than 50% of the kilometric scale magnetic anomalies have been tested
Metallurgical tests underway
Located 25 km NW of Fire Lake North
Synform Geometry is good for Open Pit
Within conveying distance from Fire Lake North planned concentrator (20-30km)
30
Labrador Trough Annual ProductionIron Ore Production Upsidep
Company Current Annual Production
ProjectedAnnual Forecast
IOC/RTZ 17 mtpy 26 mtpy1IOC/RTZ 17 mtpy 26 mtpy1
ArcelorMittal 13 mtpy 24 mtpy2
Cliffs Natural Resources (Wuhan)
12 mtpy 28 mtpy(Wuhan)Labrador Iron Mines 2 mtpy 5 mtpy
Adriana Resources (Wuhan) 0 50 mtpy
New Millennium (Tata) 0 27 mtpy
Century Iron Mines (Wuhan) 0 ~20 mtpy
Champion Minerals 0 ~18 mtpy
Alderon Iron Ore Corp. 0 ~8 mtpy
Total current and forecasted production
44 ~ 200 mtpy
1. Possibility of expanding production up to 50 mtpy2. Possibility of expanding production to 50 mtpy
31
Global Steel Production Shows Continued Demand for Iron Ore
1 400 000
1,600,000
Continued Demand for Iron Ore
China’s CAGR* is 9 88% over
1,200,000
1,400,000 China s CAGR is 9.88% over the last 30 years vs. 2.30% for total global steel production
over the same period.
800,000
1,000,000 China
Japan
400,000
600,000 Rest of the World
200,000
,
32
-1980 1985 1990 1995 2000 2005 2010
Source: World Steel Association website* Compound annual growth rate
Thank You
33
33
Iron Ore Types
Coarse Grained Specular HematiteDirect Shipping Ore
Coarse Grained Specular Hematite
34Coarse Grained Specular HematiteMagnetite Rich Taconite34
Fermont Iron Ore DistrictFermont Iron Ore District(“FIOD”)
Historically the Fermont and b d C hLabrador Camps have produced 33 Mta
RTZ/IOC = 17 MtaA l Mitt l 13 MtArcelorMittal = 13 Mta
Wabush = 3 Mta
For 30-40 years pre 2003th i tthe price per tonne
concentrate was $25- $30/ tonne
C t 3 iCurrent 3 year moving average is $130/ tonne
2012 Spot Price averaged $170/t
35
~$170/tonne