Etobicoke General HospitalSpecial Redevelopment
Town HallJ u n e 1 , 2 0 1 6
2
Submit now online at town.halls@williamosl
erhs.ca
QUESTIONS?
3
ETOBICOKE GENERAL MASTER SITE PLAN
4
THE RIVER
CAMPUS
LET’S START AT THE END…
5
THE RIVER
FORECOURT APPROACH
6
FRONT ENTRY
7
EGH PHASE 1 PATIENT TOWER
8
• Patient-inspired care• Patient/provider
connections• Outdoor space a natural
extension of indoor space• Family spaces• Clear accessibility and
wayfinding• Interior/exterior areas of
respite• Acoustic environment
DESIGN OBJECTIVES: PATIENT AND FAMILY-FOCUSED
9
• Connect with outdoors – ravine• Improve community accessibility• More gardens• Change the face of EGH
DESIGN OBJECTIVES: COMMUNITY CONNECTION
10
• A larger, state-of-the-art Emergency Department
• Critical Care and Intensive Care Units that are nearly four times larger than the current space
• Maternal Newborn Unit with birthing suites and a specialized nursery
• New Ambulatory Procedures Unit
• Cardiology, Respiratory and Neurodiagnostic Services
• Satellite DI
NEW AND EXPANDED SERVICES
11
BRIGHT, LIGHT-FILLED ATRIUM AND MAIN ENTRANCE
12
A HEALING ENVIRONMENT
MEDICAL DAYCARE UNIT WAITING SPACE
Emergency Waiting Area
13
NEW PATIENT TOWER – WHERE ARE WE?
Milestone Date
Commercial/Financial close May 2016
Mobilization/West Stair Reno's
May/June 2016
50% DD (1st round user mtgs)
May – August 2016
Excavation August 2016
100% DD (2nd round user mtgs)
August - Nov
Substantial Completion June 2018
Occupancy Fall 2018
WE ARE
HERE
14
EGH ANCILLARY SERVICES BUILDING (ASB)
15
ASB
Program Estimated Space Need (cgsf)
MOB – Osler Programs(i.e. DI/Fracture Clinic)
10,700
MOB – MD tenants (Docs)
30,600
MOB – Retail 8,300CKD – Dialysis Satellite 25,000
Education/Learning/Other
25,000
Hospital Ambulatory Clinics (i.e.Med/Surgical/Paeds/Mental Health/Admin)
53,400
Total 153,000
16
ASB – CURB APPEAL
17
ASB – WHERE ARE WE?
Milestone Date
Commercial/Financial close April 2016
Mobilization/Fencing May 2016
Detailed Design (fit-out user mtgs)
May – Oct 2016
Excavation June 2016
Substantial Performance (Core & Shell)
October 2017
Osler ASB Fit-outs June 2017 – March 2018
CKD Fit-out (pending MOH approvals)
Nov 2017 – July 2018
WE ARE
HERE
18
• Fencing/Hording installation for ASB and NPT– Ongoing adjustments as required– Site H&S – Updated Fire Safety Plan
• Internal Renovations (west stair modifications, morgue relocation)
• Excavation/Surplus Soil Removal– Generate noise/dust
• Ongoing Management of Parking Strategy – Ongoing staff/physician engagement– Adhere to tenats of ethical framework– Allow extra time– Consider alternate routes – Inventory deficit mitigation
WHAT TO EXPECT OVER THE NEXT FEW MONTHS
Share your feedback!
19
EGH PHASE 1 LOT ALLOCATION: MAY – JULY 2016
ASB
Physicians & Staff
Patient / Visitor
Patient / Visitor
Patient / Visitor
MOB
On-Call Physicians
Staff Overflow
NPT
MOB
20
EGH PHASE 2 LOT ALLOCATION: AUGUST – DEC 2016
ASB
Physicians & Staff
Patient / Visitor
Patient / Visitor
NPT
MOB
Staff Overflow
ASB
Patient / Visitor
Patient / Visitor Patient / Visitor
Physicians, Staff & MOB
On-Call Staff
NPT
NPT
21
• Physician and Staff– Departmental meetings– Huddles– Memos– Intranet– On-site Signage
• Patients– Display boards– Flyers at offices, businesses– Information through physician offices
COMMUNICATIONS
22
“Difficult roads often lead to beautiful destinations”
-proverb
LAST WORDS
Q: When redeveloping a hospital, how are projections made for future growth? How much of the facility is built toward future growth and an increase in services?
QUESTIONS?