Sustainability indicators for environmental geotechnics
I. Jefferson PhD, D. V. L. Hunt PhD, C. A. Birchall MSc and C. D. F. Rogers PhD, CEng, MICE, MIHT
Environmental geotechnics (EG) has the potential to make
a substantial contribution to the field of sustainable
construction, which in turn affects sustainable
development. Indicators for measuring sustainable
performance within the construction sector are well
developed because the concepts have been around for
many years. However, within the EG sector they are not,
probably due to the combined difficulties of inherent site-
specific complexity and scale. In addressing this shortfall,
the aim of this paper is to present a new suite of
environmental geotechnics indicators (EGIs). The new EGI
system is formulated from existing construction sector
indicators, from which a set of 108 separate indicators for
assessing progress towards achieving greater sustainability
are presented. Using a point score system (1 (harmful) to 5
(significantly improved)), the set of indicators can cover the
entire timeline of a project in eight distinct stages
(feasibility to long term). The set includes 76 ‘generic
indicators’ used to assess the sustainability of any
geotechnical project and a set of 32 additional ‘technology-
specific’ indicators used to assess the sustainability of
specific techniques for treating contaminated land. This
latter indicator set can be modified, or substituted by any
appropriate technology-specific indicator set, to address
whatever geotechnical processes are proposed in a project.
The final output of the assessment is an eight-pointed rose
diagram that can be used to highlight areas of weakness
within a project. The indicators within this new model are
not split into various sustainability pillars (economic, social
and environmental), thereby reducing the risk of an end-
user focusing on the economic pillar alone. The indicators
are applied to a case study site.
1. INTRODUCTION
Sustainability is not an abstract principle but a concept to inform
society across all scales, locally and internationally.1 Various
definitions of sustainability have been formulated over more
than 30 years, the most notable being that by Brundtland in
1987,2 which is often quoted due to its overarching simplicity
Sustainable development is development that meets the needs of the
present without compromising the ability of future generations to
meet their own needs.
Unfortunately, many would advocate that no single definition
can truly capture the essence of what sustainability is, due in part
to it being a concept that we are beginning to understand but for
which we are still looking for an adequate delivery procedure,
including methods of measurement (i.e. assessment tools). Whilst
a traditional triple bottom line approach (economic, social and
environmental) is typically used to describe sustainability,
identification of the overlapping zones, and thus dealing with the
tensions between them, is not easy. Indeed, some would argue
that currently available sustainability assessment tools do not
help in this respect.3 Sustainable assessment tools are, however,
vital for developing sustainable goals and shaping project
outcomes. They can be truly effective as long as consideration is
given to the conflicts and associated trade-offs that exist between
the three pillars within the many fields that contribute towards
sustainable development. There is also merit in adopting
Brundtland’s approach by introducing higher level views of the
problem in dealing with conflicts and trade-offs, as this paper
will attempt to demonstrate.
One of the key contributing fields to sustainable development,
almost no matter what the project, is geotechnical engineering,
which faces an extremely challenging dichotomy between
delivering project goals and maintaining sustainability.1 In an
era when we are striving for minimal adverse environmental
impact and high added value, geotechnical engineers are in an
unenviable position at the start of any construction project where
the environmental and arguably sustainability costs are largest.
Geotechnical engineering has a crucial role in shaping and
achieving the sustainability credentials of a project, therefore
better geotechnical practices would help reduce adverse impacts
at the point in a construction project when some of the greatest
gains can be made.1 However, to achieve such advances, there is
a need to develop a suitable set of assessment tools applicable to
all areas of geotechnical engineering.1 Environmental
geotechnics (EG) (which, for the purpose of this paper, is
considered to deal principally with contaminated land
remediation and waste management) covers one of these
important topic areas and, where this issue is relevant, has
significant impact on all aspects of sustainable construction and
sustainable development, not least the ability to develop on
previously contaminated land thereby improving economic,
environmental and social wellbeing for a local community
(e.g. Greenwich Millennium Village, UK). If the true extent of
the impact of such geotechnical works is to be assessed
objectively, a suitable sustainability indicator system is required.
Whilst indicators exist for measuring the sustainability of a
project as a whole (e.g. Sustainable Project Appraisal Routine
(Spear)) and the environmental impact of buildings (e.g. BRE
Ian JeffersonSenior Lecturer, University ofBirmingham, UK
Dexter V. L. HuntResearch Fellow, Universityof Birmingham, UK
Charles A. BirchallMSc student, University ofBirmingham, UK
Chris D. F. RogersProfessor, University ofBirmingham, UK
Proceedings of the Institution ofCivil EngineersEngineering Sustainability 160June 2007 Issue ES2Pages 57–78doi: 10.1680/ensu.2007.160.2.57
Paper 1100003Received 13/12/2006Accepted 05/07/2007
Keywords:environment/research &development
Engineering Sustainability 160 Issue ES2 Sustainability indicators for environmental geotechnics Jefferson et al. 57
Environmental Assessment Method (Breeam)), no system at
present addresses the issue of sustainability in the field of EG.
One of the key aims of this paper is to address this omission. It
seeks to do so by reporting on current indicators being used for
measuring or assessing sustainability within the UK. Drawing
selectively from these tools, an environmental geotechnics
indicator (EGI) system is presented, which can be used to assess
the sustainable characteristics at project level with regard to EG.
The system offers a measure of sustainability along the timeline
of a project (visioning to long-term use) and, crucially, does not
segregate indicators using a traditional ‘three pillar’ approach,
thereby reducing the risk of an end-user focusing on the
economic pillar alone. This is considered to be one of the greatest
benefits of the EGI system since it focuses attention on the issues
and how they might beneficially be addressed before the question
of cost is raised. This system therefore aims to provide innovate
insights into how to advance down the path of sustainability by
avoiding, at least initially, one of the greatest perceived barriers
to sustainable development. Finally the EGI system is tested using
a case history site to illustrate its potential for application.
2. ENVIRONMENTAL GEOTECHNICS
A large part of EG is encapsulated within the risk management
framework (RMF) for dealing with contaminated land.4 The RMF
allows proportional and targeted remedial actions to take place in
a resource-efficient way.5 These remedial actions can be
classified into four broad categories, which include engineering-
based and process-based methods6
(a) removal
(b) containment
(c) rehabilitation
(d) treatment.
These can be further broken down into more specific
techniques5–7 that may overlap (Fig. 1).7 To be considered
‘sustainable’ the technique(s) chosen must be suitable for the task
in hand and so a number of technical factors are needed to enable
appropriate choices to be made.4 Of the techniques shown in
Fig. 1, removal to landfill now faces severe restrictions through
landfill regulations.8 However, ‘dig and dump’ to landfill or land
raising is still considered a potential option as part of current and
future waste management systems, albeit as a much reduced
component and as an increasingly financially unattractive
option. This is in part because there are still many landfill sites
catering for such a process in operation in the UK. Treatment
technologies in land remediation provide an effective way to
render contaminants into less toxic forms5 and their adoption is
actively encouraged by agencies in many countries because of
perceived added values within all three pillars of sustainability.
As remediation technologies improve and sustainable principles
are adopted, it is anticipated that pre-treatment of wastes prior to
landfill, already a requirement in the UK, will become a more
sophisticated element of site treatment methodologies. Therefore
an urgent need has been identified for deriving a system for
measuring sustainability within the EG field, not least with
respect to remediation technologies.
The above arguments are not meant to imply that effective waste
management through mechanisms such as waste reduction,
material recycling/reuse and foundation reuse is not an
important aspect of ‘sustainable geotechnics’. However,
contaminated land thinking in this regard is well advanced and
so this topic has been used to build the EGI system. It is intended
that the EGI system can be adapted to assess other geotechnical
processes by modification and/or substitution of the
‘technology-specific’ elements of the system.
3. SUSTAINABLE INDICATOR SYSTEMS
3.1. Introduction to indicator systems
An indicator system should provide a measure of current
performance, a clear statement of what might be achieved in
terms of future performance targets and a yardstick for
measurement of progress along the way. However, it is important
to recognise that sustainability is a journey without an end9 and
that a system based on absolute numerical values is unlikely to
prove satisfactory. As such, indicator systems can provide a
crucial guide for decision-makers in a variety of ways. Not least,
they enable physical and social scientific knowledge to be broken
down into smaller units that can be analysed in detail to facilitate
sustainable decision-making processes from the start of a project
through to the end.
There are many sustainable indicator systems that can be used
to assess a whole range of issues related to sustainable
development at international levels (e.g. United Nations (UN)
indicators10) and national levels (e.g. the UK Government’s
headline indicators11 and the currently developing code for
sustainable homes). Sustainable construction within the built
environment is an essential element of sustainable development
and a range of well-established indicators exists within the UK.
In turn, EG has an important role to play in achieving greater
sustainability in construction and yet, as already stated, a
specific set of indicators relevant to this area has yet to be
developed. The aim of this section is to examine construction-
related sustainability indicators in order to establish the
necessary guidance for creating a robust assessment framework
for an indicator system specific to EG. Important aspects to
consider when using existing indicator systems or deriving new
ones are scale, validity and level of application (i.e. whether
they are applied at strategic, company or operational level).12
In order to make the distinction clear, a range of well-known
construction-related sustainability indicators is outlined in the
following sections; these summarise the key aspects of each
system and their potential impact when used in the context of
EG. The validity of any existing or new indicator is highly
dependent on widespread application within projects, as well as
its appreciation in a wider context,13 and the necessary
encouragement for its future adoption will involve a great
deal of stakeholder participation (a core thread of
sustainability). The adoption of the EGI system presented in this
paper will only take place once the system’s key benefits
have been demonstrated through case histories. To this end, one
case history is presented to illustrate the use of the EGI system.
It is hoped that this will stimulate other case history
assessments of EG projects in the future, thus allowing
refinement of the proposed EGI system.
3.2. Sustainability integrated guidelines for management
(Sigma)
Sigma,14 launched in 1999 with the support of the UK
Department for Trade and Industry (DTi), provides three key tools
58 Engineering Sustainability 160 Issue ES2 Sustainability indicators for environmental geotechnics Jefferson et al.
(a) guiding principles that operate at organisational level to
promote sustainability (human, social, financial,
manufactured and natural capital)
(b) a management framework that integrates sustainability
issues and practices (ISO 14001,15 ISO 900116 and Investors
in People (IiP)17) into core processes and mainstream
decision-making at a company level
(c) a toolkit for assessment.
The system is vastly different from the others considered in this
section of the paper since it focuses on developing an ethos of
sustainability within an organisation. It concentrates on the
business vision of the company and links its activities to the
vision with a total emphasis on sustainable development. The
rejection of a financial ‘bottom-line’ can be seen as an attempt to
retain an accurate and balanced focus on sustainability issues.
3.3. Sustainable Project Appraisal Routine (Spear)
Spear,18 established by Arup, uses a colour-coded rose
diagram to assess the sustainability of a project under four main
pillars (economic, environmental, social and natural resources).
Using qualitative scores from –3 (worst case) to þ3 (optimum
case), problem areas can be highlighted within typically around
20 sub-themes (dealing with issues such as air quality, land use,
water, ecology, cultural heritage, design and operation, transport,
materials, energy, waste, health and welfare, user satisfaction,
form and space, access, amenity, inclusion, viability, social costs
and benefits, competitive effects, employment/skills). The
method is ideal for gauging where a project stands both pre- and
post-construction, although the lack of a weighting system can
lead to misrepresentation of risk areas for certain types of project
(e.g. a nuclear repository). In these cases it may be necessary to
add weightings according to clients’ needs during a second round
of assessment. The indicators have been used successfully in
helping to achieve sustainable outcomes within the UK and
internationally, such as Hong Kong and Australia.18 This
indicator system provides an overarching indication of the
sustainable outcome of a project, and in so doing it does not
necessarily focus on individual buildings (even though it was
originally developed, and is still used, for this purpose).
3.4. Building Research Establishment Environmental
Assessment Method (Breeam)
Breeam falls under the environmental indicator pillar and in
different forms can be used to assess the environmental
sustainability of specific buildings (e.g. offices, homes, schools,
industrial and retail units, laboratories and leisure centres), both
new and existing. The main issues of assessment under this
system are management, energy use, health and wellbeing,
pollution, transport, land use, ecology, materials and water.
Within the EcoHomes19 rating (essentially Breeam for homes)
energy use is broken down into carbon dioxide emissions,
building envelope performance, drying space, eco-labelled white
goods and external lighting. Using both qualitative and
quantitative pre-weighted point scores within themes, a final
rating can be given. In the EcoHomes system, a percentage score
will relate to a certain category, that is pass (40%), good (50%),
very good (60%) and excellent (70%). For the Breeam office
system, the score is converted to an environmental performance
index (EPI) that ranges from 1 (poorest) to 10 (best). Both of these
provide a good eco-label for buildings and are becoming widely
used and accepted within the UK. This system does not, however,
concentrate on the social or economic pillars.
3.5. Ecopoints
The Ecopoints20 system is a single-score environmental
assessment tool that can be used to assess the impact of a building
Fig. 1. Remedial actions for contaminated land showing areas of topic overlap (after Evans et al. 7)
Engineering Sustainability 160 Issue ES2 Sustainability indicators for environmental geotechnics Jefferson et al. 59
or process on the environment using a scale from 1 (lowest
impact) to 100 (highest impact). It takes into account impacts of
climate change, fossil fuel depletion, ozone depletion, freight
transport, human toxicity to air and water, waste disposal, water
extraction, acid deposition, ecotoxicity, eutrophication, summer
smog and minerals extraction. Ecopoints are used within the
Green Guide to Specification 21 (fourth edition published January
2007), life cycle assessment tools, Breeam and the web-based
software tool Envest2.22
3.6. Ceequal
Ceequal is a civil engineering equivalent to Breeam promoted by
the Institution of Civil Engineers (ICE), the Building Research
Establishment (BRE), the Construction Industry Research and
Information Association (Ciria) and, to a limited extent, industry.
It falls under the environmental pillar and encourages excellence
in environmental performance within areas of water, energy,
land, ecology, landscape, nuisance to neighbours, archaeology,
waste minimisation/management and community amenity
during specification, design and construction. A percentage score
and rating, not dissimilar to that found in Breeam, is given,
although 25% relates to a pass and 75% relates to excellent. The
method has been, and continues to be, used successfully on many
engineering projects throughout the UK. Again, social and
economic pillars do not feature strongly in this assessment
method, perhaps as a result of the essential nature of civil
engineering projects, that is they must address the economic
pillar in providing best value for money and they ultimately
address society’s needs.
3.7. Key performance indicators
Key performance indicators (KPIs)23 fall under the social pillar
and are used currently by civil engineering companies in the UK
for assessing performance. Using a percentage score under two
themes (client satisfaction for the product and client satisfaction
for the service) and using equal weightings within eight sub-
themes (four under each heading), a radar plot is presented to
show how good a company is in comparison to a sample group.
The findings of workshops into the measurement of KPIs have
repeatedly stated that measurement alone adds no value unless it
is relevant and encourages a positive step towards improvement.
3.8. Discussion
The preceding sections have shown that there are numerous
available indicators that allow the measurement of sustainability
at many scales (i.e. project level down to specific building
materials). Closer inspection of these indicators has highlighted
the following important features.
(a) Economic and environmental sector indicators are well
developed, whereas those for social sectors are much less so.
This is in broad agreement with previous research.12
(b) Well-established scoring systems can be subjective, leading
to a variance in final output.
Chronological project stages Considerations made within project stage Typical actions within project stages Points (1–5)
A Feasibility (Table 2) Impacts/benefits considered † Desk study 4.3Local sustainable priorities assessed † Site investigation
† Chemical analysis
B Design (Tables 3(a), (b)) Detailed design solutions developed † Quantified risk assessment 3.9Design solutions rejected or accepted † CDM regulations
† Regulatory approvals† Design options
C Award (Table 4) Assessment of sustainability credentials † Procurement process 3.7Alternatives proposed † Pre-qualification
† Contractor credentials
D Mobilisation (Table 5) Use resources from the most efficient locationsto the project
† Geographical location 3.4† Amount of equipment† Access† Logistics† Materials
E Construction (Tables6(a), (b))
Incorporate sustainable methods into theconstruction programme
† Materials 3.5† Plant† Energy† Labour† Water usage
F Demobilisation (Table 7) Feedback into sustainability accounting system † Removal of equipment 3.8† Ongoing to next site
G Monitoring (Tables 8(a), (b)) Ensure that the system is achieving itssustainability goals
† Choice of instrumentation 2.5† Monitoring categories† Length of time† Invasiveness
H Long Term (Tables 9(a), (b)) Adapt as necessary to maintain sustainability † Immediate vicinity 4.1† Regional effect† Life cycle
Table 1. Project stage outputs for the EGI system (points relate to the case study described in Section 5)
60 Engineering Sustainability 160 Issue ES2 Sustainability indicators for environmental geotechnics Jefferson et al.
(c) Sustainability indicators need to be related to sustainability
and not simply be a measure per se.13
(d) Wider adoption and application of existing systems is
needed so they may be refined. In August 2003 it was
reported that Ecohomes had been applied to only 3400 units
in 100 developments in the UK24 and in August 2006
Ceequal had been applied to just 14 projects in the UK.25 In
June 2005, Leadership in Energy and Environmental Design
(Leed)26 had been applied to 200 projects in the USA and
Hong Kong Building Environmental Assessment Method
(HK-Beam)27 applied to 100 projects in Hong Kong. The
problem is global.
(e) Research is needed to develop complementary indicator
suites that look at impacts of specific civil engineering sub-
sectors and are complementary to generic sustainable
construction indicators.
(f) One area requiring urgent development is that of EG, in
particular contaminated land,28 hence the development of
the EGI system now described.
4. ENVIRONMENTAL GEOTECHNICS INDICATOR
SYSTEM
4.1. Formation of the EGI system
The EGI system was devised for use solely within the ground
engineering sub-sector of EG. Throughout the development of
the EGI system, UK standard practice has been taken into
account. The EGI system was derived from reformulated
sustainable construction indicators used within the UK (i.e. those
summarised in Section 3), supplemented with additional ideas
taken from environmental indicators used in other countries,
for example, Leed26 (USA) and HK-Beam27 (Hong Kong). The EGI
system was designed for use in the UK. Although most of the
ideas are directly transferable elsewhere, it should be noted that
its application in other countries may require reformulation of
certain existing indicators or the addition of new indicators for
country-specific factors to be taken into account.
In all, 108 separate indicators (76 generic indicators and 32
technology-specific indicators) were adopted, based on lessons
learnt from existing indicator systems (Section 3) and experience
gained from several projects. The indicators were chosen to
ensure full integration with current and possible future
management frameworks for EG, such as model procedures for
management of land contamination.4 The EGI system
incorporates all of the key sustainability issues covered within a
number of existing indicator systems, but has tailored these to EG
projects through the use of technology-specific indicators. Built
into these are other elements of scale that directly impinge on EG
projects, including, for example, factors ranging from company
policies through to site-specific assessments (such as spacing of
chemical tests used in pre-treatment assessments). Using a dual-
phased approach, both generic and EG technology-specific
assessments can be undertaken for various project stages along a
project timeline.
The various stages (A–H) of the EGI assessment are shown in
Table 1. The stages of the assessment method (referred to as
project stages) are presented in chronological order along the
project timeline, that is from feasibility (A) through to the long
term (H). Each stage is designed to measure key aspects of the
Feas
ibility
indic
ator
Effe
cton
sust
aina
bility
Poin
ts(1
–5)
Har
mfu
lR
educ
tion
Neu
tral
Impro
ved
Sign
ifica
ntly
impro
ved
(i)
Does
the
clie
ntha
vea
sust
aina
bility
polic
y?A
ctiv
ely
avoid
ssu
stai
nability
Pas
sive
lyav
oid
ssu
stai
nability
No
polic
yin
pla
cePas
sive
lypro
mote
ssu
stai
nability
Act
ivel
ypro
mote
ssu
stai
nability
3
(ii)
Isth
ere
aco
mm
unity
cons
ulta
tion
pla
n?A
ctiv
ely
avoid
sco
nsul
tatio
nN
one
Bas
icD
etai
led
usin
gsing
lem
ediu
mD
etai
led
usin
gm
ultip
lem
edia
5
(iii)
Does
the
site
have
redev
elopm
ent
pote
ntia
l?N
one
Ver
ylo
wLo
wH
igh
Ver
yhi
gh5
(iv)
Isth
esite
suita
ble
for
itsfu
ture
use?
Det
rim
enta
lQ
uest
ions
rem
ain
unan
swer
edN
oef
fect
Yes
Ver
ysu
itable
5
(v)
Perc
enta
geofsite
inve
stig
atio
nco
stag
ains
tpro
pose
dto
talc
ost
,0. 5
%0. 5
–1. 0
%1. 0
–3. 0
%3. 0
–4. 0
%.
5. 0
%4
(vi)
Che
mic
alsa
mple
spac
ing
15
mþ
,15
m,
5m
,3
m,
1m
3(v
ii)Ty
pes
ofte
sts
No
anal
ysis
Sim
ple
on-
site
field
test
sonl
yLa
bora
tory
test
sonl
yFi
eld
tria
lsonl
yLa
bora
tory
and
field
tria
ls5
Ave
rage
EGIsc
ore
for
the
feas
ibility
pha
se(i–vi
i)ofth
eca
sest
udy
4. 3
Table
2.GenericstageAfeasibility
indicators
(points
relate
tothecase
studydescribed
inSection5)
Engineering Sustainability 160 Issue ES2 Sustainability indicators for environmental geotechnics Jefferson et al. 61
Des
ign
indic
ator
Effe
cton
sust
aina
bility
Poin
ts(1
–5)
Har
mfu
lR
educ
tion
Neu
tral
Impro
ved
Sign
ifica
ntly
impro
ved
(i)
Land
inte
nded
for
use
that
was
pre
vious
lyun
usab
le
Land
loss
incr
ease
dN
och
ange
Par
tialr
euse
ofsite
100%
but
with
nore
crea
tiona
lfac
ilitie
s100%
ofth
esite
with
som
ere
crea
tiona
lfac
ilitie
s4
(ii)
Land
inte
nded
for
use
by
bus
ines
ses
and
or
infr
astr
uctu
re(h
ealth/
educ
atio
n/tr
ansp
ort
)th
atco
ntribut
esto
the
loca
leco
nom
y
No
influ
xofne
wbus
ines
s/in
fras
truc
ture
,20%
ofsite
allo
cate
dto
new
bus
ines
ses/
infr
astr
uctu
re
20–50%
ofsite
allo
cate
dto
new
bus
ines
ses/
infr
astr
uctu
re
Maj
ority
ofsite
allo
cate
dto
new
bus
ines
ses/
infr
astr
uctu
re
Who
lesite
allo
cate
dto
new
bus
ines
ses/
infr
astr
uctu
re5
(iii)
Qua
ntifi
edrisk
asse
ssm
ent
(QR
A)
No
atte
mpt
atpro
duc
ing
aQ
RA
Par
tialQ
RA
that
does
not
cove
ral
lasp
ects
ofth
esite
Full
QR
A,o
ffice
bas
edw
ithout
ability
topro
cure
furt
her
test
ing
Full
QR
A,o
ffice
bas
edw
ithab
ility
topro
cure
furt
her
test
ing
Full
QR
Alin
ked
with
field
tria
lpro
gram
me
5
(iv)
Has
the
des
ign
follo
wed
adefi
ned
risk
man
agem
ent
pla
n?
None
dev
ised
Par
tialp
lan
dev
ised
cove
ring
aspec
tsof
the
pro
ject
Initi
alrisk
man
agem
entpla
ndev
ised
Inte
gral
asse
ssm
entdev
ised
cove
ring
most
aspec
tsof
the
pro
ject
Full
inte
gral
asse
ssm
ent
dev
ised
cove
ring
all
aspec
tsofth
epro
ject
5
(v)
Isth
ere
ahe
alth
&sa
fety
(H&
S)pla
nag
reed
?
Com
pan
yha
sno
H&
Spolic
yC
om
pan
yha
sH
&S
polic
y,but
nopla
nin
stig
ated
Com
pan
yha
sH
&S
polic
ybut
pla
nonl
yco
vers
the
most
dan
gero
usas
pec
ts
Com
pan
yha
sH
&S
polic
yan
dpla
ndra
wn
upby
ano
n-ded
icat
edH
&S
emplo
yee
cove
ring
all
aspec
ts
Full
pla
ndev
ised
by
ded
icat
edH
&S
emplo
yee
cove
ring
all
aspec
ts
5
(vi)
Will
the
pla
nm
eet
natio
nalr
egul
atory
(EA
)gu
idel
ines
?
No
Yes
with
maj
or
alte
ratio
nYe
sw
ithm
odifi
catio
nYe
sw
ithm
inor
alte
ratio
nYe
s5
(vii)
Are
targ
etco
ntam
inan
tco
ncen
trat
ions
des
igne
dto
mee
tle
gislat
ion?
Min
imum
need
edfo
rsh
ort
-ter
mus
eofsite
Min
imum
requi
red
by
legi
slat
ion
Exce
edta
rget
sre
qui
red
by
legi
slat
ion
Exce
edm
inim
umne
eded
for
even
the
most
sens
itive
pote
ntia
lfut
ure
site
use
Com
ple
tere
mova
lof
pollu
tant
3
(viii)
Has
alif
ecy
cle
asse
ssm
ent
bee
ndone
?
None
No
cate
gory
Par
tial
No
cate
gory
Yes
3
(ix)
Has
asu
stai
nability
optio
nap
pra
isal
bee
ndone
?
No
awar
enes
sof
sust
aina
bility
optio
nap
pra
isal
tech
nique
s
No
form
alap
pra
isal
but
awar
eof
sust
aina
bility
Yes,
cove
ring
the
min
ority
ofas
pec
tsYe
s,co
vering
the
maj
ority
ofas
pec
tsYe
s,co
vering
alla
spec
tsoft
hepro
ject
2
(x)
Bio
div
ersity/h
abita
tcr
eatio
nas
sess
men
tw
ithap
pro
priat
em
itiga
tion
Har
mfu
lto
bio
div
ersity
No
asse
ssm
ent
bee
nca
rrie
dout
Ass
esse
das
noef
fect
May
aid
impro
vem
ent
Cont
ribut
esto
impro
ving
bio
div
ersity
5
(xi)
Esta
blis
hmen
tofth
edes
ign
team
atan
early
stag
e
No
nece
ssar
ypar
tyin
volv
edea
rly
One
nece
ssar
ypar
tyin
volv
edea
rly
Two
nece
ssar
ypar
ties
invo
lved
early
More
than
two
nece
ssar
ypar
ties
invo
lved
early
All
nece
ssar
ypar
ties
invo
lved
early
—
(xii)
Has
the
des
ign
team
bee
ntr
aine
din
‘just
suffi
cien
t’des
ign
met
hods?
None
oft
hete
amha
sbee
nM
inority
ofth
ete
amha
sbee
nEq
uals
plit
Maj
ority
ofth
ete
amha
sbee
nA
llofth
ete
amha
sbee
n4
62 Engineering Sustainability 160 Issue ES2 Sustainability indicators for environmental geotechnics Jefferson et al.
geotechnical engineering process that affect sustainability and
occur along an EG project timeline. The timeline scale provides a
clear, concise overview of a project’s phases (A–H) and allows for
ease of reference from key stakeholders who may not be experts
in the field of EG. From here it is possible to show potential
interactions between each project phase along a project timeline.
Each stage of the assessment is given a final score out of 5, which
can be calculated from the ‘generic indicators’ shown in
Tables 2–9 (detailing stages A–H respectively). These can be
applied at an operational level within any geotechnical project
being undertaken. In addition to, and allied with, these indicators
is a set of ‘technique-specific indicators’ relating to remediation
methods (i.e. removal, containment, ex situ, in situ and passive)
and these should be applied where appropriate (see Tables 3(b),
6(b), 8(b) and 9(b)). For example, when assessing a site that is
using removal techniques, additional indicators will be required
in the design stage (Table 3(b)) only, whereas containment
techniques will require additions in the design (Table 3(b)),
construction (Table 6(b)) and long-term stages (Table 9(b)). Each
generic indicator gives a measure of the ‘effect on sustainability
by use of points’: 1 (harmful) to 5 (significantly improved). The
rating system allows for ease of allocation of points against
individual indicators. These are measured using a full range of
options that adopt quantitative rather than qualitative measures
where appropriate, thereby eliminating variance in the output of
an assessment, this being arguably one of the primary failings of
the current systems described in Section 3.
The scores (including additions) from each stage are totalled,
averaged and plotted as shown in Fig. 2. From here it is possible
to identify the project stage with the weakest ‘sustainability
credentials’. The process of applying the indicators is iterative
and improvements can be incorporated into the assessment
system as the project stages progress (Fig. 3). Each of the project
stages is now discussed briefly.
. Stage A. Feasibility covers the initial idea phase of a project and
will usually include a desk study to highlight areas where
further investigation is necessary, a site investigation to look for
‘hot spots’ of contamination and chemical analyses.29 The seven
generic indicators (i–vii) within this stage are shown in Table 2.
. Stage B. Design options have an extremely significant effect on
a project and it is here where risks to the project and health and
safety can be highlighted (corporate design management
(CDM) and quantified risk assessment respectively) and where
costs (life cycle assessment and whole life) can be assessed.1
Legislation (e.g. refs 30–34) in conjunction with option
appraisal35 is of vital importance in reducing the risk of
contamination and this should be considered at the earliest
stages in design. In addition, the design stage is where the
majority of sustainability criteria (e.g. habitat creation,
sustainable materials) can and should be incorporated; hence
appropriate indicators are assigned here also. ‘Just sufficient
design’ acknowledges the practice of providing oversized
systems to ‘worst case’ design principles36 and the principle is
acknowledged in the EGI as it can reduce sustainability costs.
The establishment of a design team with the right people
(i.e. geotechnical engineers, engineering geologists, geo-
environmental engineers) at the earliest stage in the project
timeline is vitally important—a full team will enable the right
site investigation and site appraisal to be carried out and,
importantly, will facilitate a more sustainable outcome by their
Table
3(a).
Continued
Des
ign
indic
ator
Effe
cton
sust
aina
bility
Poin
ts(1
–5)
Har
mfu
lR
educ
tion
Neu
tral
Impro
ved
Sign
ifica
ntly
impro
ved
(xiii)
Perc
enta
geofsu
pplie
ssp
ecifi
edfr
om
sust
aina
ble
sour
ces
or
recy
cled
mat
eria
l
,20%
20–30%
30–40%
40–50%
.50%
1
(xiv
)D
oes
the
des
ign
asse
ssw
hole
life
cost
s?
No
Cost
sac
coun
ted
for
until
the
end
ofth
eco
ntra
ctors
’w
arra
nty
Inte
rnal
asse
ssm
ent
by
untr
aine
ddes
igne
rIn
tern
alas
sess
men
tby
trai
ned
des
igne
rYe
s,us
ing
are
cogn
ised
sust
aina
bility
tool(
BR
E)4
Ave
rage
EGIsc
ore
for
the
awar
dpha
se(i–xi
v)3. 9
Table
3(a).
GenericstageBdesignindicators
(points
relate
tothecase
studydescribed
inSection5)
Engineering Sustainability 160 Issue ES2 Sustainability indicators for environmental geotechnics Jefferson et al. 63
Des
ign
indic
ator
Effe
cton
sust
aina
bility
Poin
ts(1
–5)
Har
mfu
lR
educ
tion
Neu
tral
Impro
ved
Sign
ifica
ntly
impro
ved
(xv)
Cont
amin
ant
conc
entr
atio
nobje
ctiv
e(s
olid
ifica
tion)
Sign
ifica
ntly
low
erth
angu
idel
ines
usin
gpro
ven
bin
der
s
Low
erth
angu
idel
ines
usin
gpro
ven
bin
der
sM
inim
umto
achi
eve
legi
slat
ion
with
pro
ven
bin
der
s
Min
imum
toac
hiev
ele
gislat
ion
with
non-
pro
ven
bin
der
s
Hig
her
than
guid
elin
es—
(xvi
)D
oes
the
rem
edia
tion
choic
ele
ave
any
issu
esfo
rong
oin
gco
nstr
uctio
n?(a
llco
ntai
nmen
tty
pes
)
Cont
amin
ant
cont
aine
dbut
futu
repiling
will
be
inva
sive
Cont
amin
ant
cont
aine
dbut
futu
repiling
may
be
inva
sive
No
piling
pla
nned
Cont
amin
ant
cont
aine
dout
side
ofpiling
loca
tion
Cont
amin
ant
rem
ove
d—
nore
strict
ions
on
piling
5
(xvi
i)C
hang
esto
groun
dw
ater
(all
cont
ainm
ent
types
)
Bui
ldup
ofw
ater
notpla
nned
for
Bui
ldup
ofw
ater
pla
nned
toonl
ybe
apro
ble
min
extr
eme
circ
umst
ance
s
No
chan
geC
om
ple
tein
tegr
ated
dra
inag
esy
stem
inco
rpora
ted
into
and
aroun
dth
etr
eate
dar
ea
Pre
fere
ntia
lflow
pat
hsdes
igne
dto
allo
wbet
ter
natu
rald
rain
age
aroun
dth
esite
2
(xvi
ii)G
roun
dim
pro
vem
ent
(GI)
pla
nned
inth
efu
ture
(cap
pin
g)
GIm
ayno
tre
duc
eth
ebui
ldle
vele
noug
hto
pro
vide
adeq
uate
cove
r
GIlo
wer
sth
ebui
ldle
vel
requi
ring
more
clea
nso
ilto
pro
vide
cove
r
No
GIpla
nned
GIin
troduc
escl
ean
soil
dee
per
than
the
cove
rC
ove
rpro
vides
aw
ork
ing
pla
tform
for
ong
oin
gG
Ioper
atio
ns
—
(xix
)Ex
cava
tion
pla
n(e
xsitu
trea
tmen
ts)
Soil
rem
ove
dco
mple
tely
requi
ring
tem
pora
rysu
pport
then
bac
kfille
daf
ter
trea
tmen
t
Soil
rem
ove
din
cells
requi
ring
tem
pora
rysu
pport
then
bac
kfille
daf
ter
trea
tmen
t
Soil
rem
ove
din
cells
requi
ring
atm
ost
grad
edslopes
Exca
vatio
npar
tofth
est
ruct
ure,i
.e.b
asem
ents
,us
ing
per
man
ent
mat
eria
ls(c
onc
rete
,etc
.)
Exca
vatio
npar
tofth
est
ruct
ure,i
.e.b
asem
ents
,us
ing
tem
pora
rym
ater
ials
(reu
sed
shee
tpile
s,et
c.)
5
(xx)
Sam
plin
gra
te(e
xsitu
trea
tmen
ts)
Het
eroge
neous
soil
with
sam
ple
freq
uenc
yno
tlin
ked
torisk
asse
ssm
ent
Hom
oge
neous
soil
with
sam
ple
freq
uenc
yno
tlin
ked
torisk
asse
ssm
ent
Sam
plin
gca
rrie
dout
usin
ghi
storica
l/em
piric
alfr
eque
ncy
pla
n
Het
eroge
neous
soil
with
min
imum
sam
ple
slin
ked
torisk
asse
ssm
ent
Hom
oge
neous
soil
with
min
imum
sam
ple
slin
ked
torisk
asse
ssm
ent
4
Table
3(b).
Technique-specificstageBdesignindicators
(points
relate
tothecase
studydescribed
inSection5)
64 Engineering Sustainability 160 Issue ES2 Sustainability indicators for environmental geotechnics Jefferson et al.
Award indicator
Effect on sustainability
Points (1–5)Harmful Reduction Neutral ImprovedSignificantlyimproved
(i) What type ofprocurement?
Lowest cost-competitivetender
Negotiatedcontract
Pre-qualificationlist
Contractor/sub-contractorpartnership
Public–privatepartnership
4
(ii) At what stagedoes thespecialistremediationcontractorbecomeinvolved in thedesign?
No input fromspecialist sub-contractor
Tender stage withmore than 1month beforesubmission
Concurrently withthe maincontractor
Pre-detaileddesign inconsultationwith the client’sengineer
Pre-detaileddesign inpartnershipwith theengineer
5
(iii) Does thecontractor haveISO 14001 (or aformal EMS)?
No Undergoingaccreditation
A minority ofbusiness unitsare accredited
The majority ofbusiness unitsare accredited
All business unitsare accredited
5
(iv) Percentage ofsub-contractsupply by valuefrom ISO 14001accreditedsuppliers
,10% 10–20% 20–35% 35–50% .50% 2
(v) Does thecontractor haveInvestors InPeople (IiP)accreditation?
No Undergoingaccreditation
A minority ofbusiness unitsare accredited
The majority ofbusiness unitsare accredited
All business unitsare accredited
3
(vi) Percentage ofsub-contractsupply by valuefrom IiPaccreditedsuppliers
,10% 10–20% 20–35% 35–50% .50% 3
(vii) Has thecontractor hadany formalnuisance noticesserved?
More than 1 in theprevious threeyears
1 in the previousthree years
1 in the previous 5years
1 prior to ISO14001certification
Never 3
(viii) Safety record byreportableincidents
50% higher thanthe sectoraverage
25% higher thanthe sectoraverage
Within 5% of thesector average
25% lower thanthe sectoraverage
50% lower thanthe sectoraverage
3
(ix) Does thecontractor carryout internalevaluation usingKPIs?
NeverimplementedKPIs
Developing a KPIsystem
A minority ofbusiness unitsuse KPIs
The majority ofbusiness unitsuse KPIs
All business unitsuse KPIs
4
(x) Does thecontractorproduce formalreports forstakeholders?
No Irregularenvironmentalor socialperformancereports
Irregularenvironmentaland socialperformancereports
Annualenvironmentalor socialperformancereports
Annualenvironmentaland socialperformancereports
2
(xi) Whatpercentage ofemployeesundergoawarenesstraining?
,10% 10–50% 50–75% 75–100% 100% 5
(xii) Does thecontractor havea qualitymanagementsystem, e.g.ISO 9001?
No Undergoingaccreditation
A minority ofbusiness unitsare accredited
The majority ofbusiness unitsare accredited
All business unitsare accredited
5
Average EGI score for the award phase (i–xii) of the case study 3.7
Table 4. Generic stage C award indicators (points relate to the case study described in Section 5)
Engineering Sustainability 160 Issue ES2 Sustainability indicators for environmental geotechnics Jefferson et al. 65
Mobilisa
tion
indic
ator
Effe
cton
sust
aina
bility
Poin
ts(1
–5)
Har
mfu
lR
educ
tion
Neu
tral
Impro
ved
Sign
ifica
ntly
impro
ved
(i)
How
muc
hpla
ntis
need
ed?
Pla
ntm
obilise
dth
atis
not
for
cont
inge
ncy
and
neve
rus
edPla
nthe
ldin
cont
inge
ncy
but
neve
rus
edM
inim
umpla
nthe
ldin
cont
inge
ncy
but
even
tual
lyus
ed
All
pla
ntus
edat
som
est
age
on
site
All
pla
ntut
ilise
d100%
ofth
etim
eon
site
4
(ii)
Hav
eal
ldel
iver
ies
(pla
ntan
dm
ater
ials)
bee
nch
ose
nto
min
imise
acce
ssdisru
ptio
n?
Mul
tiple
acce
ssro
utes
that
do
not
avoid
residen
tiala
reas
Sing
leac
cess
rout
ecr
eate
dth
atdoes
not
avoid
residen
tiala
reas
All
del
iver
ies
use
sing
leex
istin
gac
cess
rout
ebut
do
not
avoid
residen
tiala
reas
Sing
lene
wac
cess
rout
ecr
eate
dth
atav
oid
sre
siden
tiala
reas
All
del
iver
ies
use
sing
leex
istin
gac
cess
rout
ean
dav
oid
residen
tiala
reas
3
(iii)
Ingr
ess
and
egre
ssR
oad
closu
res
nece
ssar
yto
cran
epla
ntont
oth
esite
No
traf
ficm
anag
emen
tsy
stem
Traf
ficm
anag
emen
tsy
stem
inpla
cew
ithno
ticea
ble
cont
rolle
ddisru
ptio
n
Traf
ficm
anag
emen
tsy
stem
inpla
cew
ithm
inor
cont
rolle
ddisru
ptio
n
Traf
ficm
anag
emen
tsy
stem
inpla
cew
ithno
disru
ptio
nan
dro
adcl
eani
ngsc
hem
ein
effe
ct
4
(iv)
Tran
sport
atio
nPla
ntm
obilise
dfr
om
stora
ge(.
40
mile
s)Pla
ntm
obilise
dfr
om
stora
ge(,
40
mile
s)Pla
ntbro
ught
direc
tfr
om
oth
erpro
ject
natio
nally
(.40
mile
s)
Pla
ntbro
ught
direc
tfr
om
oth
erpro
ject
loca
lly(,
40
mile
s)
Pla
nthi
red
from
loca
lfirm
1
(v)
Labour
No
loca
llab
our
emplo
yed
,10%
ofw
ork
forc
eis
loca
l(w
ithin
20
mile
s)10–25%
ofw
ork
forc
eis
loca
l(w
ithin
20
mile
s)25–50%
ofw
ork
forc
eis
loca
l(w
ithin
20
mile
s).
50%
ofw
ork
forc
eis
loca
l(w
ithin
20
mile
s)5
(vi)
Perc
enta
geofm
ater
ials
(by
volu
me)
del
iver
edfr
om
sust
aina
ble
sour
ces
or
recy
cled
mat
eria
l
,20%
20–30%
30–40%
40–50%
.50%
2
(vii)
Mat
eria
lsso
urce
dlo
cally
,20%
20–30%
30–40%
40–50%
.50%
5A
vera
geEG
Isc
ore
for
the
mobilisa
tion
pha
se(i–vi
i)ofth
eca
sest
udy
3. 4
Table
5.GenericstageD
mobilisationindicators
(points
relate
tothecase
studydescribed
inSection5)
66 Engineering Sustainability 160 Issue ES2 Sustainability indicators for environmental geotechnics Jefferson et al.
Cons
truc
tion
indic
ator
Effe
cton
sust
aina
bility
Poin
ts(1
–5)
Har
mfu
lR
educ
tion
Neu
tral
Impro
ved
Sign
ifica
ntly
impro
ved
(i)
Wha
tper
cent
age
ofm
ater
ials
are
dispose
dofin
rela
tion
tom
ater
ials
supplie
d?
.30%
30–15%
15–10%
10–5%
,5%
4
(ii)
Hav
ere
new
able
ener
gysy
stem
sbee
nus
edon
site
?N
one
Cons
ider
edbut
igno
red
Cons
ider
edbut
not
pra
ctic
alM
inor
usag
eSi
gnifi
cant
usag
e3
(iii)
Isus
eofm
ains
wat
erre
duc
ed?
No
rest
rict
ions
on
mai
nsw
ater
Mai
nsw
ater
with
usag
eco
ntro
lG
rey
wat
erus
ed—
nore
use
ofpro
cess
wat
erPro
cess
wat
erre
used
inco
mbin
atio
nw
ithm
ains
wat
er
Pro
cess
wat
erre
used
inco
mbin
atio
nw
ithgr
eyw
ater
2
(iv)
Isth
ere
adus
tsu
ppre
ssio
npla
n?N
oPla
nto
reduc
edus
tcr
eatio
nW
ater
spra
ydam
pen
ers
usin
gm
ains
wat
erW
ater
spra
ydam
pen
ers
usin
ggr
eyw
ater
Inte
grat
eddus
tpre
vent
ion
pla
nim
ple
men
ted
2
(v)
Foss
ilfu
elus
age
No
rest
rict
ions
on
use
of
foss
ilfu
els
Foss
ilfu
elus
age
limite
dby
awar
enes
str
aini
ngFo
ssil
fuel
use
min
imised
by
actio
npla
nSo
me
foss
ilfu
elus
ere
pla
ced
by
alte
rnat
ives
All
foss
ilfu
elus
ech
ange
dto
alte
rnat
ive
pow
erso
urce
s2
(vi)
Cal
cula
tion
ofC
O2
emissions
and
embodie
den
ergy
(EE)
Not
cons
ider
edC
ons
ider
edbut
not
under
take
nPar
tiala
naly
sis
for
eith
erC
O2
or
EEPar
tiala
naly
sis
for
CO
2an
dEE
Full
anal
ysis
for
CO
2an
dEE
—
(vii)
Air
qua
lity:
sulp
hur
dio
xide
and
NO
x
Onl
yco
al/o
ilus
edon
site
Maj
or
coal/o
ilra
tioto
gas
Equa
lcoal/o
ilra
tioto
gas
Min
or
coal/o
ilra
tioto
gas
Cle
ante
chno
logy
used
(sola
r,et
c.)
4
(viii)
Air
qua
lity:
ozo
neV
OC
san
dN
Ox
allo
wed
toco
mbin
eN
oac
tion
No
cate
gory
Pre
vent
ion
pla
nto
min
imise
and
separ
ate
NO
xan
dV
OC
s
No
VO
Cs
allo
wed
into
the
atm
osp
here
on
site
4
(ix)
Air
qua
lity:
par
ticul
ate
No
pla
ntfit
ted
with
par
ticul
ate
filte
rM
inority
ofpla
ntfit
ted
with
par
ticul
ate
filte
rEv
ensp
litM
ost
pla
ntfit
ted
with
par
ticul
ate
filte
rA
llpla
ntto
be
fitte
dw
ithpar
ticul
ate
filte
r5
(x)
Obst
ruct
ion
ofl
ight
by
smoke
.10%
ofon-
site
time
10–5%
ofon-
site
time
5–1%
ofon-
site
time
,1%
ofon-
site
time
No
visible
smoke
pro
duc
ed5
(xi)
Isth
ere
ano
ise
pre
vent
ion
pla
n?N
oise
issu
esig
nore
dA
war
enes
sofno
ise
issu
esSi
tecu
rfew
sin
forc
eA
llpla
nttr
eate
dw
ithno
ise
cont
rolm
easu
res
Inte
grat
edno
ise
pre
vent
ion
pla
nim
ple
men
ted
3
(xii)
Are
alli
tem
sof‘w
et’p
lant
(e.g
.fue
lbow
sers
)pro
per
lypro
tect
edag
ains
tsp
ills?
No
bun
ds
on
site
Som
epro
tect
ion
inpla
ce.
Stat
icpla
ntpro
tect
edM
ajority
ofpla
ntpro
tect
edfr
om
leak
sA
ll‘w
et’p
lant
pro
tect
edfr
om
leak
s5
(xiii)
Has
the
site
super
viso
rac
tivel
yw
ork
edto
reduc
em
ove
men
ts?
No
rest
rict
ions
Pla
nin
pla
cebut
not
fully
imple
men
ted
On-
site
move
men
tsm
inim
ised
Del
iver
ies
tosite
min
imised
All
traf
ficm
ove
men
tsas
sess
edan
dm
inim
ised
4
(xiv
)Lo
calc
om
mun
ityse
rvic
esdisru
ptio
nM
ajor
utility
lost
on
more
than
one
occ
asio
ndue
tosite
activ
ity
Maj
or
utility
lost
on
one
occ
asio
ndue
tosite
activ
ity
No
serv
ices
disru
pte
dby
def
ault
Maj
or
utility
unab
leto
be
mai
ntai
ned,b
utco
mm
unity
info
rmed
ofdisru
ptio
nan
dco
mpen
sate
d
Pla
nned
actio
nta
ken
tono
tdisru
pt
any
serv
ices
5
(xv)
Isan
ytim
elo
stth
roug
hre
gula
tory
rest
rict
ions
bei
ngim
pose
d?
Site
close
dte
mpora
rily
and
afin
eis
issu
edSi
tecl
ose
dte
mpora
rily
with
nofin
esissu
edW
arni
ngpro
vided
and
acte
don
imm
edia
tely
No
rest
rict
ions
No
rest
rict
ions
and
deb
rief
pro
vides
feed
bac
kat
end
ofpro
ject
4
(xvi
)Pla
ntw
ashi
ngfa
cilit
ies
No
pla
ntw
ashi
ngPla
ntw
ashi
ngus
ing
mai
nsw
ater
and
non-
bio
deg
radab
ledet
erge
nts
Pla
ntw
ashi
ngus
ing
mai
nsw
ater
and
bio
deg
radab
ledet
erge
nts
Pla
ntw
ashi
ngw
ithgr
eyw
ater
syst
eman
dbio
deg
radab
ledet
erge
nts
Pla
ntw
ashi
ngw
ithgr
eyw
ater
recy
clin
gsy
stem
and
nodet
erge
nts
3
Ave
rage
EGIsc
ore
for
the
cons
truc
tion
pha
se(i–xv
i)ofth
eca
sest
udy
3. 7
Table
6(a).
GenericstageEconstructionindicators
(points
relate
tothecase
studydescribed
inSection5)
Engineering Sustainability 160 Issue ES2 Sustainability indicators for environmental geotechnics Jefferson et al. 67
Construction indicator
Effect on sustainability
Points (1–5)Harmful Reduction Neutral ImprovedSignificantlyimproved
(xvii) Groundobstructions (allcontainmenttypes)
Site investigationoverlookedtheobstructionrisk; time loston site;treatmentincomplete
Obstructions notpredicted andtime lost buttreatmentcompleted
Obstructionspredicted andcontingencyplan allowedfull completionof treatment
Obstructionspredicted butnoneencountered
No obstructionsencounteredin accordancewith siteinvestigation
3
(xviii) Sheet pileconstruction(verticalbarriers)
Normal impacthammer usedless than 50 mfrom nearestresidential area
Normal impacthammer usedmore than 50 mfrom nearestresidential area
Silent hammerused less than50 m fromnearestresidential area
Silent hammerused more than50 m fromnearestresidential area
Hydraulic pressinstallationsystem used
—
(xix) Slurry wall(verticalbarriers)
Bentonite fluidused onceprior todisposal
Bentonite fluidreused prior todisposal
Bentonite fluidreused thendewateredprior todisposal
Bentonite fluidused once thendewatered priorto disposal; greywater reused
Bentonite fluidreused thendewateredprior todisposal; greywater reused
3
(xx) Slurry wallbatching plant(verticalbarriers)
High silos locatednear to siteboundary.De-sandingunit usingfossil fuels
Visual impact ofsilos notaddressed.De-sanding unitusing fossil fuels
Silos located toreduceexternalimpact.De-sandingunit using fossilfuels
High silos locatednear to siteboundary.De-sanding unitusing alternativefuels
Silos located toreduceexternalimpact.De-sandingunit usingalternativepower
3
(xxi) Surface waterrun-off (capping,solidification)
Soakaway wherewater mayre-enter thecontaminatedarea
Drains runningthrough thecontaminatedarea; risk of pipeburst
No action Drains linked tomains sewer
Soakawaysplanned
outside oftreatmentareas
—
(xxii) Pre-screening(all ex situtreatments)
Pre-screeningdoes notreduce amounttreated; VOCemissions notcollected
Pre-screeningreduces amounttreated; VOCemissions notcollected
No pre-screeningcarried outsince it wouldbe ineffective
Pre-screeningreduces amounttreated; VOCemissionscontrolled thendisposed
Pre-screeningreducesamounttreated; VOCemissionscollected andreused
4
(xxiii) End use of offgas(all ex situtreatments)
Burnt offwith noenergycollection
Collected andtransported offsite for electricitygeneration, butrequiringextensivetreatment
No offgasgenerated
Collected andtransported offsite for electricitygeneration; notreatmentrequired
Used on site forelectricitygenerationwith notreatmentrequired
3
(xxiv) What is the enduse of removedspoil? (all ex situtreatments)
Untreated andcompletelyremoved tolandfill(includingwastebyproducts)
Treated andpartially used offsite, someremoval tolandfill(excluding wastebyproducts)
Treated andpartially usedon site, someremoval tolandfill(excludingwastebyproducts)
Treated andcompletely usedas fill off site(excluding wastebyproducts)
Treated andcompletelyused as fill onsite (excludingwastebyproducts)
4
(xxv) Chemicaladditives (allex situtreatments)
Additives requirefurthertreatment andare notcompletelyremoved
Additives requirefurthertreatment andare completelyremoved
No additivesneeded
All additivesbiodegradable inthe long term
All additivesbiodegradablein the shortterm
3
(xxvi) Treatmentlocation (allex situtreatments)
Transportedto off-sitetreatment inopencontainers
Transported tooff-sitetreatment inclosedcontainersthen disposed of
Transported tooff-sitetreatment inclosedcontainersthen reused
Treated on site andtransported tobe reused off site
Treated on siteand reusedon site
3
(Table continued )
68 Engineering Sustainability 160 Issue ES2 Sustainability indicators for environmental geotechnics Jefferson et al.
Table 6(b). Continued
Construction indicator
Effect on sustainability
Points (1–5)Harmful Reduction Neutral ImprovedSignificantlyimproved
(xxvii) Control ofparticulateemissions (TD)
Particulategenerationignored onexcavation andunfiltered ontreatment
Particulategenerationcontrolled onexcavation(dust), butunfiltered ontreatment
Particulategenerationfiltered ontreatment(smoke), butuncontrolledon excavation
Controlled onexcavation(dust) andfiltered ontreatment(smoke)
Monitored andcontrolled onexcavation(dust) andfiltered ontreatment(smoke)
—
(xxviii) Addition ofcatalysts/reagents totreat pH (exsitu bio)
Production oforganic acidsnot controlleddue toinsufficientaddition ofcatalyst
Production oforganic acids notcontrolled
No organic acidsproduced
Production oforganic acidscontrolled byaddition ofcatalyst (e.g.lime)
Production oforganic acidscontrolled byselection ofbiologicalagent
—
(xxix) Plant, materialand workingspace (ex situbio)
None of (a)to (c) shownon right, plusmaterialimported forlinerconstruction
None of (a) to (c)shown on right
One of (a) to (c)shown on right
Two of (a) to (c)shown on right
(a) Existingsurface usedfor treatmentarea. (b) Noimportation ofmaterial forhaul road.(c) All ancillaryplant (i.e.blower pipes)reusable.
—
(xxx) Determinationof temperatureregime (ex situbio)
Thermophilicrequiringheatingelements; noincrease inrange treated;no timeconstraints
Thermophilicrequiring heatingelements;increased rangetreated; no timeconstraints
Thermophilicrequiringheatingelements;increasedtreatmenteffect due totimeconstraints
Meso/thermophilicusing naturalheating withinproject timescale
Mesophilic withcompletetreatment of allcontaminantswithin projecttimescale
—
(xxxi) Addition ofbulking agents(ex situ bio)
Bulking agentsaddedcausing adeteriorationin geotechnicalpropertiespreventingreuse
Bulking agentsadded byguesswork, nochange ingeotechnicalproperties butnot reused
Bulking agentsessential toprovidethoroughremediation,minimised butnot reused
Bulking agentsminimised (bylab. tests) anddesigned toassist reuse oftreated spoil offsite
Bulking agentsminimised (bylab. tests) anddesigned toassist reuse oftreated spoilon site
—
(xxxii) Projectflexibility andoptimisation(all in situ)
System fixedthroughoutproject
Small changespossible throughvariation ofpumps but withno monitoringfeedback
Small changespossiblethroughvariation ofpumps andwithmonitoringfeedback
Capacity toimplementmajor changeslinked tofeedback frommonitoring
Monitoring linkedto system withall elementshavingalternativeplans
—
(xxxiii) Hazardprotectionmeasures (all insitu)
No specificexplosioncontrols inplace
Some explosioncontrol but notmeeting H&Sfully
Minimum tomeet H&Srequirements
(a) Spark arrestersfitted. (b)Discharge unittemperaturecontrol. (c) Fireprotectionequipmentprovided
All of (a) to (c)plus low-lyinggas collectionareascontrolled (i.e.excavations)
—
(xxxiv) Groundwaterfluid flow (all insitu exceptSVE)
Actions creatediversion offlow outsideoriginal zonenot noticeduntil afterdemobilisation
Actions createsmall diversionof flow outsideoriginal zone,but this isnoticed andtreated
Actions have nodetrimentalnor beneficialeffect on flow
Actions show smallbeneficial effectupon flow
Actions create apositive effecton flowincreasing theremediationrate
—
(Table continued )
Engineering Sustainability 160 Issue ES2 Sustainability indicators for environmental geotechnics Jefferson et al. 69
early interaction. Therefore points are awarded accordingly.
There are 14 generic indicators (i–xiv) and 6 technology-
specific indicators (xv–xx) within this stage, as shown in
Tables 3(a) and 3(b) respectively. Indicator (xi) was added after
application of the EGI system to the case history to allow the
impact of the inclusion of the right balance of skills at the
design stage to be assessed.
. Stage C. Award. The award stage (i.e. the procurement process)
has a variety of options and directions. In major projects many
benefits can derive from partnering agreements, not least
because a specialist geotechnics contractor can be involved at
the feasibility and design stage. This is unlikely to occur if the
client opts for the lowest competitive tender, hence credit is
given here. The ‘sustainability credentials’ of a sub-contractor
are important to the overall assessment and these can be
measured by looking at the sub-contractor’s previous history
(e.g. safety and nuisance records) and current methods of self-
evaluation (e.g. KPIs, international environmental standards
such as ISO 14001,15 quality control standards covered by the
ISO 9000 series, IiP17 (awards that measure the social
credentials of a contractor)). The 12 generic indicators (i–xii)
within this stage are detailed in Table 4.
. Stages D–F. Mobilisation, construction and demobilisation
refer to the commissioning stage of the project (these
indicators are applied simultaneously). The EGI system
assesses the sustainability of the methods of construction on
site rather than what is actually being built. Minimal
movement of people and equipment and use of transport are
encouraged, as are improvements to air quality and reduction
in noise. Points are awarded for using local suppliers, local
workforces and reclaimed materials (e.g. ground granulated
blast-furnace slag to replace cement37 or pulverised fuel-ash to
provide resistance against ammonia attack), all of which
comply with important sustainability principles. Disposal of
materials and use of fossil fuels is discouraged, while
alternative energy supply technologies are encouraged (e.g.
solar, wind) as is reduction in mains water use (e.g. through
water-saving devices or grey water usage, rainwater
harvesting or process water recovery and reuse). All of these
can help reduce the effects of climate change, not least by
reducing CO2 emissions. The calculation of all CO2 emissions
and embodied energy (EE) is deemed an important benchmark
for construction, such that innovative methods of
construction, materials or energy sources can be expressed
quantifiably in terms of increased sustainability within the
construction sector and therefore points are awarded for this
also. In the EGI system, the introduction of any chemicals into
the ground as solvents, reagents or surfactants is discouraged
and these are reflected in the scoring system. The mobilisation
stage consists of 7 generic indicators (i–vii), as shown in
Table 5. The construction stage consists of 16 generic
indicators (i–xvi) and 21 technology-specific indicators (xvii–
xxxvii), as shown in Tables 6(a) and 6(b) respectively. Table 7
details the 4 generic indicators (i–iv) of the demobilisation
stage. Indicator (vi) was added to the construction stage
(Table 6(a)) after application of the EGI system to the case
history to allow CO2 emission and EE assessments to be
encouraged, thus allowing the important impact that these
have on sustainability to be embedded in any assessment.
. Stage G. Monitoring is required to ensure that contaminant
levels are reduced and maintained at guideline values. There
are 4 generic indicators (i–iv) and 2 technology-specific
indicators (v–vi), as shown in Tables 8(a) and 8(b) respectively.
. Stage H. Long-term factors include a range of societal effects,
such as the use of the land after remediation (e.g. new
employment opportunities, residential areas, infrastructure
and leisure facilities, reduced risk of pollution incidents). The
EGI system encourages low maintenance and minimal
Table 6(b). Continued
Construction indicator
Effect on sustainability
Points (1–5)Harmful Reduction Neutral ImprovedSignificantlyimproved
(xxxv) Disposal ofspoil fromtrenchexcavations(PRB & verticalbarrier)
Untreated andcompletelyremoved tolandfill
Treated andpartially used offsite, someremoval tolandfill
Treated andpartially usedon site, someremoval tolandfill
Treated andcompletely usedas fill off site
Treated andcompletelyused as fillon site
—
(xxxvi) Addition ofhydrogenperoxide(EISB)
.150 ppb,extensiveinhibition ofmicro-organismactivity
150–100 ppb,some inhibitionof micro-organism activity
100–50 ppb, noinhibition ofmicro-organismactivity
50–25 ppb, noinhibition ofmicro-organismactivity
,25 ppb, noinhibition ofmicro-organismactivity
—
(xxxvii) Amount ofwaterextracted(dual-phasevacuum)
Lower thanexpectedcontaminantconcentration;very largewatervolumesextracted
Medium to lowcontaminantconcentration;above averagewater volumesextracted
Mediumcontaminantconcentrationsallow averagewater volumesto beextracted
Medium to highcontaminantconcentrationsallow smallwater volumesto beextracted
High contaminantconcentrationsallow verysmall watervolumes to beextracted
—
Table 6(b). Technique-specific stage E construction indicators (points relate to the case study described in Section 5) (SVE, soil vapourextraction; PRB, permeable reactive barrier; EISB, enhanced in situ bioremediation)
70 Engineering Sustainability 160 Issue ES2 Sustainability indicators for environmental geotechnics Jefferson et al.
disruption so as to keep sustainability costs as low as possible.
Information dissemination to locals is encouraged. Companies
may benefit from reduced contamination (e.g. better insurance
rates) and improved relations with the community, and hence
points are awarded for these categories also. There are 12
generic indicators (i–xii) and 3 technology specific indicators
(xiii–xiv), as shown in Tables 9(a) and 9(b) respectively.
4.2. Implementation of the EGI system
The EGI system developed from a need to take a higher level view
of the very many issues that must be faced and decisions that need
to be taken that have the potential to impact on the ‘sustainability
credentials’ of a project. It is often stated that sustainability is so
ill-defined that it is difficult to judge whether any one action is
better or worse; in turn, this argument is used to justify the lack of
change in approach. The adoption of a series of indicators that
address each issue or decision in a tangible manner is important if
the system is to be practically applicable.38 Stating each of the
issues in their own right, rather than in the context of the
economic, social and environmental pillars, facilitates better
decision-making. Firstly it informs the decision-maker of the issue
and what might be done; it then allows alternative solutions to
suggest themselves; and finally it allows (economic) costing
decisions to be taken on an informed basis (i.e. knowing what
should be done and consciously choosing to compromise where
necessary, although it should be noted that very often
sustainability does not mean an increase in financial cost).
The EGI system was developed by analysing in great detail the
practices associated with the built environment, applying
considerable engineering experience and deriving relevant
indicators. All of this is encapsulated in the tables. The essential
structure is based on the timeline ideas being developed in the
Birmingham Eastside project39 and reflects the fact that decisions
taken at one stage have the potential to impact on every
subsequent stage. Thus, once a first attempt to model a sequence of
decisions and actions associated with a particular site development
has been taken, the effect of changing any one decision can be
reassessed at each stage of the timeline or more graphically by
rotation around the rose diagram to explore whether the line
depicting the averaged score moves inwards or outwards. This is
important in the context of EG for two reasons. The first is related
to the criticism, often repeated in industry,38 that the remediation
process adopted for a particular site is found to cause other
unwanted environmental, social or economic consequences that
are as serious as the original problem. While such statements
might prove to be exaggerations of the true situation, it is precisely
because of the lack of a measurement system to place the
consequences into a proper context that such comments go
unchallenged. The EGI system provides the means to do this by
accounting for all future consequences of such an action.
Secondly, what happens in or to the ground at the start of a project
is widely considered3, 6, 38 to be the most important in contributing
or otherwise to the sustainability of a development, that is,
impacts throughout the life cycle of a development are strongly
affected by the decisions taken on geotechnical processes. In short,
these processes appear early in the timeline and their effects are
generally very difficult to change after the processes have been
carried out; they therefore have a greater opportunity to make an
impact than later, more ‘easily reversible’ decisions.
Of equal importance is the flexibility of the system to adapt to
changes in the context of the site or understanding of the issues.
The EGI system is formulated on a set of generic and a set of site-
specific processes (or technology-specific) indicators. These are
drawn up on the basis of experience and best available
knowledge at any one time. A process, termed the redevelopment
assessment framework,38 has been proposed for the development
of suitable site-specific indicators associated with brownfield
development, and this represents an excellent way to formulate
robust indicators that have consensual relevance. Both generic
and technology-specific indicators can, and should, be reviewed
in the future in response to developing technologies and
environmental legislation. The indicators and/or their target
values can be amended as appropriate and new averages
calculated. As a result of this process, ideas will be refined and
indicators can be added or removed, and their importance can be
reflected by so doing. This process will further inform the
Demobilisationindicator
Effect on sustainability
Points (1–5)Harmful Reduction Neutral ImprovedSignificantlyimproved
(i) How muchplant is reused?
Majority unusable Majority withmaintenance
All reused butwith everythingneedingmaintenance
All reused withsome needingmaintenance
All reused;maintenancefree
4
(ii) Where willequipmentgo ondemobilisation?
All equipmentreturned tocentral storage
Majority ofequipmentreturned tocentral storage
50/50 splitbetween nextjob andreturned tostorage
Majority ofequipment toanother sitedirectly
All equipment toanother sitedirectly
4
(iii) Did theproject overrunon time?
Completed late(.5% ofspecifiedproject time)
Completed late Completed ontime
Completed early Completed early(.5% ofspecifiedproject time)
4
(iv) Did theproject overrunon cost?
.10% costoverrun
5–10% costoverrun
On target (within5% of cost)
5–10% cost saving .10% cost saving 3
Average EGI score for the demobilisation phase (i–iv) of the case study 3.7
Table 7. Generic stage F demobilisation indicators (points relate to the case study described in Section 5)
Engineering Sustainability 160 Issue ES2 Sustainability indicators for environmental geotechnics Jefferson et al. 71
decision-makers and assist in the development of ‘sustainable
thinking’. The rose diagram will change accordingly and will
reflect the situation as currently perceived. Finally, the system
can be used to determine the impact of ‘what if?’ scenarios. For
example, if energy costs were to triple, what would be the impact
on the rose diagram? The EGI system therefore satisfies the
demand for a dynamic and flexible system.38
During the development of the EGI system, the focus for project
use was primarily on the ground, specifically looking at
contaminated land remediation. Less emphasis was given to those
elements that are more ‘construction process’ oriented, such as
reuse of foundations, recycling of materials on site (although
considered briefly in terms of using recycled materials in Stage D
(vi)) and other specialist geotechnical processes for brownfield
sites. The EGI system is sufficiently flexible to readily allow
inclusion of additional criteria (e.g. integrated resource
modelling or carbon footprinting) to address some of these
omissions, although it should be recognised that competent tools
such as Ceequal already exist. Moreover, it should be recognised
that the EGI system was not developed to replace indicator
systems like Ceequal; rather, it is envisaged that it will be used in
parallel as part of a full sustainability project appraisal. The
advantage of the EGI system is that it includes parameters for
measuring the social quality of a project (rather than just
environmental), but more specifically it includes a development
timeline to show where these indicators should be applied for best
effect—this is something not considered in existing systems. As
such, the EGI system offers a timeline framework within which
other indicators can be applied.
4.3. Criticism of the EGI system
No weighting system has been incorporated into the EGI system.
This is both a potential strength and a potential weakness—the
approach can lead to a skewing of the outcome. By including no
weighting procedure, it means that, by default, some indicators in
stages with few indicators (stages A, D and F, for example) appear
to be given a higher value than those withmany indicators, such as
stage E. This judgement of value is graphically provided by the
rose diagram, in which a better colour can be gained by a relatively
small number of improvements in those stages with fewer
indicators to influence. However, attempting to manipulate the
overall look of a diagram in this way is to adopt a superficial
approach to sustainability. This argument can be extended to the
relative weighting within stages. In defence of the EGI system,
weightings can be readily included and achieving an overall
balance via such means must be at the joint discretion of the
engineers and other professionals engaged on the project.
Similarly, no justification has been given to the quantified values
contained within the tables; these were arrived at on the basis of
engineering judgement and experience. It is appreciated that
amongst the grouping of engineers and other professionals
engaged on such projects, collective professional judgement and
experience should be taken into account when setting or adjusting
values. Only with greater use and experience of the system will
consensus values be reached. However, it must be acknowledged
that initial proposals for values are necessary in the first instance.
It is appreciated that many of the indicators rely upon policies
being in place and/or trained people being in post, rather than
implementation of the ideas as a project progresses. The obvious
criticism of this approach is that it is easy to have a policy or
strategy, but harder to implement them against set targets. It is
also appreciated that the terms used in the development of the
indicators might be interpreted differently by people from
different backgrounds. For example, Table 2 refers to the
suitability of the site for its future use and this could be
interpreted in terms of its ease of development, the cost or the
social need, amongst other viewpoints. This potential
discrepancy is removed when a consensus agreement is derived
from an appropriately balanced group of professionals working
on a project. A more serious shortcoming from the geotechnical
engineering perspective is in the adoption in stage A indicator (v)
Monitoringindicator
Effect on sustainability
Points (1–5)Harmful Reduction Neutral ImprovedSignificantlyimproved
(i) How aremonitoringstationspowered?
Mannedinterventionregularlyrequired
Mannedinterventionoccasionallyrequired
Mannedinterventionrarely required
Remote datacollection fromconventionalenergy source(e.g. battery)
Remote datacollection fromsustainableenergy source(e.g. solarpower)
2
(ii) Contingencyplanning
Monitoring datanot used
Data collected butno plan in place
Plan in place butnot linked todata
Plan coverstreatment linkedto data
Plan covers allaspects
4
(iii) How long ismonitoringnecessary?
.12 months afterend of siteworks
6–12 months afterend of siteworks
3–6 months afterend of siteworks
0–3 months afterend of siteworks
Completed by endof site works
1
(iv) Do monitoringsystemsinterfere withtheirenvironment?
Equipment causeslocalstakeholdercomplaints
Equipmentrequiresfrequent visits togather data
Equipment placedoutside projectboundary withlocalstakeholderconsultation
Equipment placedoutside projectboundary butoperatesremotely
None outsideprojectboundary
3
Average EGI score for the monitoring phase (i–iv) of the case study 2.5
Table 8(a). Generic stage G monitoring indicators (points relate to the case study described in Section 5)
72 Engineering Sustainability 160 Issue ES2 Sustainability indicators for environmental geotechnics Jefferson et al.
of a percentage cost of the site investigation against the total
project cost. Appropriate levels of site investigation depending
on the complexity of the geotechnical problems (and thus based
on technical need rather than percentage cost) would be an
appropriate measure. The argument against a percentage cost is
that it fails to reflect sustainable design if it encourages waste;
nevertheless this would require a complex set of judgements, and
a simple indicator value was adopted in recognition of the fact
that all projects dealing with contaminated land will require
considerable attention to detail in the site investigation.
There are omissions from the EGI system as a result of the types of
development initially considered and tested by the ‘typical’ case
history. Arguably they should have been included and perhaps
omitted from the scoring system when dealing with the case
history. Examples of omitted indicators include protection of
cultural heritage and archaeological significance, topographical
constraints and site access, improvement of logistics to reduce
traffic (e.g. delivery by rail or sea rather than road), developing
relationships with neighbours when carrying out the works in
heavily built-up urban areas and loss of local amenities during
construction. However, it is emphasised that the system of
indicators is inevitably going to be tailored to the site in question
and that some degree of site specificity is warranted. It is hoped
that such additional indicators will be included where relevant
for specific projects and, more importantly, a comprehensive set
of indicators will ultimately develop from which a relevant sub-
set can be chosen for individual projects.
5. APPLICATION OF THE EGI SYSTEM TO A CASE
STUDY
This study refers to an un-named 9 ha site that was ultimately
developed for mixed residential and commercial use between 1999
and 2001. The final assessment output, which followed a detailed
study of the site and its operations by the third author, is shown in
Fig. 4. The various stages of the assessment are now described.
5.1. Stage A: feasibility
The site was located in a river estuary and shown to be underlain
by variable-depth made ground, ranging from between 0.7 and
4.7 m below ground level in the exploratory boreholes, which
was placed on the natural soil sequence of soft alluvial and
estuarine deposits, glacial and post-glacial gravels, and cohesive
glacial tills, all of which overlay a limestone bedrock. The
relatively large thickness of made ground consisted of reclaimed
local soils, which were placed across the site to bring the ground
level above high tide level. Most of the fill had been laid in an
uncontrolled manner in the mid 1700s, was found to be
predominantly granular in nature and generally ranged from
loose to medium dense. The ground was contaminated through
byproducts of ‘town gas’ production (the site previously housed a
gasworks, long since decommissioned and demolished). Spent
oxides (ferric ferrocyanide) and coal tar contaminants (BETX, tar
acids, naphtha, anthracene and phenanthrene) were shown
through the desk study to be leaching from poorly constructed
underground bunkers. Site levels prior to excavation ranged from
1.5 to 4.0 m OD with groundwater fluctuating from20.5 to 0.5 m
OD; excavation to 21.0 m OD was required for the provision of
underground car parking. The site investigation consisted of
approximately 100 trial pits, 60 boreholes, laboratory and field
tests, and .200 chemical analyses (samples being taken at a
spacing of ,1 m across the site). The client actively promoted its
sustainability policy and consulted with the public using multiple
media at this stage. The site was deemed to have very high
redevelopment potential and was deemed very suitable for its end
use. The total averaged point score for this stage was 4.3
(individual scores can be seen in Table 2); the value to two
decimal places is 4.29, and yet the inherent degree of ‘allowable
precision’ in this procedure dictates that only one decimal place is
warranted in the case of all averages.
5.2. Stage B: design
During the design stage, a quantitative risk assessment (QRA)
established that build up of water on site would not affect
groundwater, but large volumes of material (195 000 tonnes)
required either disposal or treatment. During the design stages
several techniques were ruled out for the following reasons.
(a) Containment by a capping layer would not prevent
groundwater from transporting the contaminant into an
adjacent river.
Monitoringindicator
Effect on sustainability
Points (1–5)Harmful Reduction Neutral ImprovedSignificantlyimproved
(v) Heterogeneitycausesincompletetreatment(EISB)
Soil tests showthat .10% ofsoil remainsuntreated duetoheterogeneity;not acceptable
Soil tests showthat 5–10% ofsoil remainsuntreated duetoheterogeneity,butunacceptable
Soil tests showthat 5–10% ofsoil remainsuntreated duetoheterogeneity,but acceptable
Soil tests showthat .95% ofsoil is treated totarget level
Soil tests confirmall soil treatedto target level
—
(vi) Monitoringcosts (MNA)
Long-termpollutionconfers highmonitoringcosts andsignificanttesting input
High monitoringcosts butnaturalremediationcompletes toacceptable level
Monitoring costsare similar to anactiveremediationsolution
Monitoring costsare slightly lessthan an activeremediationsolution
Monitoring costsare significantlylower than anactiveremediationsolution
—
Table 8(b). Technique-specific stage G monitoring indicators (points relate to the case study described in Section 5) (MNA, monitoringof natural attenuation)
Engineering Sustainability 160 Issue ES2 Sustainability indicators for environmental geotechnics Jefferson et al. 73
(b) The scale of the site was too large for solidification; in
addition, the lack of licensed landfills would require spoil to
be shipped overseas.
(c) Multiple in situ treatments techniques would be required for
the different pollutant types.
(d) The use of passive input (monitored natural attenuation)
was not an option as the risk assessment provided a source,
a pathway and a target.
(e) Other ex situ treatments (e.g. bioremediation and thermal
desorption (TD)) could not have treated the contaminants in
a reasonable timescale, if at all.
(f) A ‘do nothing’ approach or waiting for natural attenuation
would have rendered the site permanently unusable.
Soil washing was thus chosen as the ‘best option’, enabling 100%
of previously unusable land to be used for mixed residential and
Long term indicator
Effect on sustainability
Points (1–5)Harmful Reduction Neutral ImprovedSignificantlyimproved
(i) Land rendereduseable thatwas previouslyunusable
Land lossincreased
No change Partial reuse ofsite
100% but with norecreationalfacilities
100% of the sitewith somerecreationalfacilities
5
(ii) Land createdfor use bybusinesses thatcontribute tothe localeconomy
No influx of newbusiness
,20% of siteused by newbusinesses
20–50% of siteused by newbusinesses
Majority of siteused by newbusinesses
All site used bynew businesses
5
(iii) Land createdfor use byinfrastructure(health/education/transport) thatcontributes tothe localeconomy
No newinfrastructure
,20% of siteused by newinfrastructure
20–50% of siteused by newinfrastructure
Majority of siteused by newinfrastructure
All site used bynewinfrastructure
2
(iv) Maintenance Regularmaintenancerequired withmaterial/plantinput
Periodicalmaintenancerequired withmaterial/plantinput
Periodicalmaintenancerequiredwithoutmaterial/plantinput
Occasionalmaintenancerequiredwithoutmaterial/plantinput
No maintenancerequired
5
(v) Clientsatisfaction
,50% 50% 70% 85% 100% 4
(vi) Client feedback No debriefcarried out
Internal feedbackonly
Feedbackavailable ifasked for byclient
Full debrief toclient atproject teamlevel
Full debrief toclient atdirector level
5
(vii) Defects raised .1 defect notcorrectable
Single defect notcorrectable
.1 defectcorrected
Single defectcorrected
No defects 3
(viii) Benchmarking Companyunaware ofKPIs
Nobenchmarkingon the project,but companyhas a KPI policyin place
Minimum numberof aspectsbenchmarked
Partial aspects ofthe projectbenchmarked
All aspects of theprojectbenchmarked
4
(ix) Did the projectoverrun ontime?
Completed late(.5% ofspecifiedproject time)
Completed late Completed ontime
Completed early Completed early(.5% ofspecifiedproject time)
4
(x) Did the projectoverrun oncost?
.10% costoverrun
5–10% costoverrun
On target (within5% of cost)
5–10% costsaving
.10% cost saving 3
(xi) Informationplan with localcommunity
Actively avoidsinteraction
None Basic Detailed usingsingle medium
Plannedprogramme ofcommunity PR
5
(xii) Insurance andwarranties
Remediationchoice unableto be insured
Remediationchoiceincreasesinsurance costs
Standardinsurance costs
Remediationreducesinsurance costs
Remediationsignificantlyreducesinsurance costs
5
Average EGI score for the long term phase (i–xii) of the case study 4.2
Table 9(a). Generic stage G long term indicators (points relate to the case study described in Section 5)
74 Engineering Sustainability 160 Issue ES2 Sustainability indicators for environmental geotechnics Jefferson et al.
commercial use (new business). Subsequently the choice of
method meant that no restriction was placed on piling and
excavated material, once washed, could be reused. The plan met
Environment Agency guidelines and exceeded targets required
by legislation. A risk management plan and a health and safety
plan were fully integrated into all aspects of the project, and the
majority of the design team was trained in ‘just sufficient’ design
methods. A partial life cycle assessment was carried out and
whole life costs were assessed by an internally trained designer.
While no formal sustainability appraisal had been carried out, the
contractor was aware of sustainability. The plan contributed to
improving biodiversity, although ,20% of supplies were from
sustainable sources. The total averaged point score for this stage
was 3.92 (individual scores can be seen in Table 3). When adding
‘technology-specific’ indicators, this increased to 3.94 (see
Table 1).
5.3. Stage C: award
The procurement consisted of a contractor/sub-contractor
partnership and the remediation contractor was involved at the
pre-detailed design stage. The contractor involved is ISO 14001
and ISO 9001 accredited in all business units (.10% of sub-
contractors accredited to ISO 14001) and has IiP accreditation in
a minority of units (,20% for suppliers). The safety record of the
contractor is within 5% of the sector average and only one
nuisance notice had been served in the last five years.
Environmental and social performance reports were produced on
an irregular basis, but all employees underwent awareness
training. The total averaged point score for this stage was 3.7
(individual scores can be seen in Table 4).
5.4. Stage D: mobilisation
All plant was mobilised from storage (.40 miles away) and used
at some stage on site. Deliveries used a single existing route that
cut through a residential area and a traffic management system
was put in place to control disruption. Between 20 and 30% of the
materials delivered were from sustainable sources and .50% of
the materials and workforce were sourced locally. The total
averaged point score for this stage was 3.4 (individual scores can
be seen in Table 5).
5.5. Stage E: construction
Important features within this treatment programme were the
provision of a 24 000 m2 perimeter cut-off wall to prevent further
cross-contamination with adjacent sites and the provision of a
structural retaining element to the excavations. (It should be
noted that use of a slurry wall with bored concrete piles as
structural support used significantly less EE than steel sheet
piles.) A temporary embedded wall was put in place and all of the
contaminated material was removed, thus providing a break in
the pathway to receptor. Plant washing facilities used mains
water (with control facilities) and biodegradable detergents.
Deliveries to site were minimised and,10% of supplied materials
needed to be disposed of. Planned action was taken to minimise
disruption to community services, site curfews restricted noise
levels and no time was lost through regulatory restrictions. Gas
was used in preference to coal and oil; renewable energy systems
were considered but found impractical. Fossil fuel usage was
minimised (through awareness training), thereby reducing CO2
emissions, although calculations of CO2 emissions and EE use
were not made. No smoke was produced and dust-suppression
plant was implemented. All plant was fitted with particulate
filters and NOx and VOCs were reduced through a prevention
plan. No ‘offgas’ was generated. No additives were introduced
into the soil, which was transported in closed containers to a
permanent washing facility40 off site, washed and subsequently
reused in earthworks on other projects. This option was still
economically beneficial (not least in terms of reduced time taken
to wash soil compared to other methods) even after accounting
Long term indicator
Effect on sustainability
Points (1–5)Harmful Reduction Neutral ImprovedSignificantlyimproved
(xiii) Monitoring (allcontainmenttypes)
Monitoring has tobe increased fora long period(years)
Monitoring has tobe increased fora short period(months)
Monitoring regimeneeds matchthe planningestimate
Long-termcontainmentdegrades slowlyand monitoringneeds reduce tominimum
Long-termcontainmentdegradesnaturally andthe monitoringregimebecomesobsolete
3
(xiv) Provision offuture services(solidification)
Treated areaunable to beexcavated forinstallation ofservices
Treated areacreatescomplicationsfor installationof services
Treated strengthspresent noproblem tostandard futureexcavations
Clean graveltrenches built into treated areasto allowinstallation ofservices
Treated arealinked intodesign tominimisedisruption byfuture services
—
(xv) Outcome ofmonitorednaturalattenuation(MNA)
Pollutants degradeto a moremobile phaseand causeintervention
Pollutants remainimmobile butdo not degrade.Potentialremains forfuture action
Plume degrades inthe long termbut causesrestriction onpotential landuse in the shortterm
Plume degrades inthe mediumterm with norestriction onproposed landuse
Pollutant plumedegrades,reduces inmobility andshrinks in extentwithinacceptabletimeframe
—
Table 9(b). Technique-specific stage G long term indicators (points relate to the case study described in Section 5)
Engineering Sustainability 160 Issue ES2 Sustainability indicators for environmental geotechnics Jefferson et al. 75
for the cost of shipping and the small encapsulation costs of the
waste byproducts after soil washing. The total averaged point
score for this stage was 3.7 (individual scores can be seen in
Table 6(a)). When adding technology-specific indicators
(Table 6(b)) this score reduced to 3.5 (see Table 1).
5.6. Stage F: demobilisation
All of the plant was reused, with some needing maintenance. The
project was finished early, enabling appropriate equipment to be
sent directly to another project, and with costs on target. The total
averaged point score for this stage was 3.8 (individual scores can
be seen in Table 7).
5.7. Stage G: monitoring
Monitoring stations were placed outside the project boundary
with agreement and consultation from the local stakeholders.
The stations required manned intervention occasionally and were
utilised for .12 months. A contingency plan for additional
treatment was linked directly to data collected. To halve
economic costs, the combined retaining/containment wall was
designed to be a temporary rather than permanent structure;
being an unproven technique, this required closer supervision
than would normally be expected. Whilst the length of
monitoring could have been reduced to improve the score for this
stage, this would have been to the detriment of other stages. This
raises an interesting scenario within any assessment method and
merely highlights that trade-offs may need to be made. The total
averaged point score for this stage was 2.5 (individual scores can
be seen in Table 8).
5.8. Stage H: the long term
Long-term monitoring of the project was completed early and
costs were on target. Some defects were corrected during the
project, but no maintenance was required. The client was fully
debriefed and reported 85% satisfaction. Monitoring did not
overrun and matched the planning estimate. Some aspects of the
project were benchmarked and a public relations programme was
carried out throughout the project and beyond. The whole of the
site is currently used by new businesses with ,20% used by new
infrastructure. The total averaged point score for this stage was
4.2 (individual scores can be seen in Table 9). When adding
technology-specific indicators this reduced to 4.1 (see Table 1).
6. CONCLUDING DISCUSSION
This paper has presented an EGI assessment tool consisting of 108
separate indicators that can be used to assess an EG project at any
scale. The system offers complete flexibility and is made up of 76
generic and 32 technology-specific indicators derived based on
both experience gained from several projects and existing
Fig. 2. A typical rose diagram, showing various project stagesfor use with the EGI system
Fig. 3. Continual EGI review process for a single project
Fig. 4. Averaged sustainability points using EGI for a case studysite
76 Engineering Sustainability 160 Issue ES2 Sustainability indicators for environmental geotechnics Jefferson et al.
indicator systems. During its derivation, it has been necessary to
ensure that the system ties into current and possible future
management frameworks from EG projects and this has been
achieved successfully. The EGI system, and the reasoning behind
each indicator, has been presented and applied to an actual
remediation project (although the project is anonymous). From
the case study it is clear that the indicator system can be applied
with relative ease and with no expected variance. Whilst the case
study presented here is specific to soil washing, application of the
indicator system to other remediation projects is without limits.
The EGI system has been shown to be completely versatile,
allowing a project to be broken into eight clear and logical stages
that consider the timeline of a project. The time element of a
project is rarely addressed within an indicator system and yet its
effects are not insignificant, hence its addition in this current
system. Within each stage it has been shown that the
‘sustainability performance’ within an EG-related project can be
assessed over time by a manageable set of indicators using a fully
quantitative method of analysis. As with other indicator systems
(e.g. Spear), the system can readily be used to bring about
improvements in practice and can be used as a learning and
awareness tool.
It is envisaged that the EGI system will allow a visual report to be
created within a project to provide a clear and easily
understandable overview of sustainability at all eight project
stages. By removing the pillars of sustainability, it is hoped that
segregation of the different sustainability aspects of the project
will not occur, thereby leading to a more sustainable outcome.
This approach further removes the need for weightings, which
can be subjectively biased and therefore cause skewing of an
assessment to give a desired result; however it is equally possible
to introduce weightings on the basis of experience and thereby
produce a more balanced output. This aspect is left to the
discretion of the engineers and other professionals involved.
It is appreciated that any proposed indicator system is unlikely to
be sufficiently comprehensive to cater for every perspective, and
some of the shortcomings of the EGI system have been
highlighted. In order that refinements can be made to the EGI
system, discussion is welcomed and indeed actively encouraged
from those within and outside the EG field. The successful
adoption of the EGI system as an assessment tool will ultimately
depend on its widespread acceptance and implementation, and
thus incorporation into contracts and perhaps ultimately
legislation. As such there is a need for more case histories,
education of clients and stakeholders, and the fostering of
increasing awareness in the construction industry, the built
environment sphere more generally and the field of EG. This is a
large undertaking and will require access to decision-makers at
all levels within construction projects. The decision-making
process forms a significant contributing facet of the Eastside
research project,39 where strong links to such decision-makers
have been made; it is hoped that active involvement of
sustainability researchers in such projects will facilitate such
implementation.
ACKNOWLEDGEMENTS
The authors thank the UK Engineering and Physical Sciences
Research Council (EPSRC) for financial support during this
research under grants GRS/20482, EP/C513177 and EP/E
021603. We also acknowledge the contribution of Professor Peter
Braithwaite, who provided valuable comments during
finalisation of the paper.
REFERENCES
1. JEFFERIS S. A. Geotechnology in harmony with the global
environment: dream or deliverable? Proceedings of the 16th
International Conference on Soil Mechanics and Geotechnical
Engineering, Osaka, 2005, 4, Paper No. UK15, 2387–2390.
2. BRUNDTLAND G. H. Our Common Future: Report of the World
Commission on Environment and Development. Oxford
University Press, London, 1987.
3. JEFFERIS S. A. Can we identify sustainable remediation
techniques for contaminated land? Proceedings of the 4th
International Congress On Environmental Geotechnics, Rio de
Janeiro (de Mello and Almeida (eds)), 2002, 2, 1039–1058.
4. ENVIRONMENT AGENCY.Model Procedures for the Management
of Land Contamination. EA, Bristol, 2004, CLR 11.
5. NATHANIAL P. C. and BARDOS P. R. Reclamation of
Contaminated Land. Wiley, Chichester, 2004.
6. SHACKELFORD C. D. and JEFFERIS S. A. Geoenvironmental
engineering for in situ remediation. Proceedings of
International Conference on Geotechnical and
Geoenvironmental Engineering (GeoEng2000) (Ervin et al.
(eds)). Technomic, Lancaster, PA, 2000, Vol. 1, pp. 121–185.
7. EVANS D., JEFFERIS S. A., THOMAS A. O. and CUI S. Remedial
Processes for Contaminated Land—Principles and Practice.
CIRIA, London, 2001, Report C549.
8. The Landfill (England and Wales) Regulations 2002:
Statutory Instrument No. 1559. Her Majesty’s Stationary
Office, 2002.
9. BUNCE D. and BRAITHWAITE P. A. Reclamation of
contaminated land with specific reference to Pride Park,
Derby. Proceedings of Symposium on Problematic Soils
(JEFFERSON I. (ed.)). Thomas Telford, London, 2001, 121–126.
10. UNITED NATIONS. Indicators of Sustainable Development
Guidelines and Methodologies. See www.un.org/esa/
sustdev/publications/indisd-mg2001.pdf for further details.
Accessed 10/11/2006.
11. DEPARTMENT OF THE ENVIRONMENT, TRANSPORT AND THE
REGIONS. Building a Better Quality of Life; A
Strategy for More Sustainable Development. DETR,
London, 2000, report 99CD1065.
12. W. S. ATKINS CONSULTANTS. Sustainable Construction:
Company Indicators. CIRIA, London, 2002, Report C563.
13. ENTEC UK LTD. Sustainability Indicators for Waste, Energy
and Travel for Scotland. Scottish Executive Central Research
Unit, Edinburgh, 2001, report 156654.
14. BRITISH STANDARDS INSTITUTION. Sigma Guidelines: Putting
Sustainable Development Into Practice. BSI, London, 2003.
See www.projectsigma.co.uk for further details. Accessed
8/10/2006.
15. BRITISH STANDARDS INSTITUTION. Environmental Management
Systems. BSI, London, 2004, ISO 14001.
16. BRITISH STANDARDS INSTITUTION. ISO 9001, Quality
Management and Quality Assurance Standards, Part 2. BSI,
London, 1997, ISO 9001, ISO 9002, ISO 9003.
17. INVESTORS IN PEOPLE. Investors in People Standard, 2nd edn.
HMSO, London, 2006.
18. MCGREGOR I. M. and COLE R. Using the SPeARTM assesment
tool in sustainable msasterplanning. Proceedings of US Green
Engineering Sustainability 160 Issue ES2 Sustainability indicators for environmental geotechnics Jefferson et al. 77
Building Conference, Greenbuild 2003, Pittsburgh, 2003,
CD-rom.
19. RAO S., YATES A., BROWNHILL D. and HOWARD N. ECOHOMES:
The Environmental Rating for Homes. Building Research
Establishment, Garston, 2003, Report 389.
20. DICKIE I. and HOWARD N. Assessing Environmental Impacts of
Construction: Industry Consensus. BREEAM and UK
Ecopoints. Building Research Establishment, Garston, 2000,
BRE Digest 446.
21. ANDERSON J., SHIERS D. E. and SINCLAIR M. Green Guide to
Specification, 3rd edn. Blackwell, Oxford, 2002.
22. ENVEST2. Environmental Impact and Whole Life
Costs Analysis for Buildings. See http://envestv2.bre.co.uk/
for further details. Accessed 15/10/2006.
23. DEPARTMENT FOR TRADE AND INDUSTRY. Construction Products
Industry Key Performance Indicators, Part of the
Construction Industry KPI. DTi, London, 2005.
24. ENVIRONMENTAL DATA SERVICES. Demand Grows for
Sustainable Homes. ENDS, London, 2003, Report 343.
25. VENABLES R. K. and MILNE J. CEEQUAL Scheme for
Exemplary Environmental Performance on Civil Engineering
Projects Sails Past £1bn Milestone. Press release, 2006. See
www.ceequal.com/downloads/CQ-Press-Release-Aug06.pdf
for further details. Accessed 17/10/2006.
26. UNITED STATES GREEN BUILDING COUNCIL. LEED-NC: The
Leadership in Energy and Environmental Design—New
Construction, Version 2.2. USGBC, Washington, DC, 2005.
27. HK-BEAM. Hong Kong Building Environmental Assessment
Method 4/04: New Buildings. Business Environment
Council, Kowloon, 2004.
28. BUTLER B. E. Consultation with national experts: managing
contaminated land. UNEP Industry and Environment
Quarterly Review, 1996, 19, No. 2, 55–56.
29. CL:AIRE. Improving the Reliability of Contaminated Land
Assessment using Statistical Methods. Contaminated Land:
Applications in Real Environments, London, 2004, Technical
Bulletin TB7.
30. DEPARTMENT FOR THE ENVIRONMENT TRANSPORT AND REGIONS.
Environmental Protection Act Part IIA. DETR, London, 2000,
Draft Circular.
31. Town & Country Planning Act 1990. Her Majesty’s
Stationary Office, 1990.
32. Pollution Prevention and Control (England & Wales)
Regulations. Statutory Instrument No. 503. Her Majesty’s
Stationary Office, London, 2000.
33. Groundwater Regulations. Statutory Instrument No. 2746.
Her Majesty’s Stationary Office, London, 1998.
34. Waste Management Licensing and Integrated Pollution
Control Measure. Statutory Instrument No. 937. Her
Majesty’s Stationary Office, London, 2006.
35. LERNER D. Sustainable reclamation of contaminated
brownfields. Sustainability in Ground Engineering,
Northern Geotechnical Group Seminar. Institution of
Civil Engineers, Newcastle-Upon-Tyne, 2005.
36. LAWRENCE RACE G. A ‘Just Sufficient’ Approach to
Building Services Design. DTi, London, 2003, BSRIA report
70176/1. Accessed 01/10/2006.
37. ONTARIO ASSOCIATION OF ARCHITECTS. Sustainable Building: A
Materials Perspective. 2005. See www.oaa.on.ca for further
details.
38. PEDIADITI K., WEHRMEYER W. and CHENOWETH J. Sustainability
evaluation for brownfield redevelopment. Proceedings of the
Institution of Civil Engineers, Engineering Sustainability,
2006, 159, No. 1, 3–10.
39. HUNT D. V. L., LOMBARDI R. D. JEFFERSON I. and ROGERS C. D.
F. The development timeline framework: a tool for
engendering sustainable use of underground space.
Geocongress 2008, New Orleans. To be published.
40. TAYLOR C. Soil washing: costing the earth. New Civil
Engineer, 2005, 18/08/2005, 21–22.
What do you think?To comment on this paper, please email up to 500 words to the editor at [email protected]
Proceedings journals rely entirely on contributions sent in by civil engineers and related professionals, academics and students. Papersshould be 2000–5000 words long, with adequate illustrations and references. Please visit www.thomastelford.com/journals for authorguidelines and further details.
78 Engineering Sustainability 160 Issue ES2 Sustainability indicators for environmental geotechnics Jefferson et al.