Transcript

11.  PROJECT PROCUREMENT MANAGEMENT: PMBOK® Guide  Chapter 12 

 

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 303

 

 

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 304

 

 

   

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 305

“MAKE OR BUY” DECISION1 

Here is a check‐list that could be helpful in reaching a make‐or‐buy decision. The scenario is that an item 

of hardware (or software) is needed for your project, and there is some debate about developing it in‐

house, or buying it from a vendor. There are many issues to be considered, but the basic question is, will 

the project be better served by buying the product than making it, followed by will the company be 

better served? The latter generally implies a wider discussion. 

#  Issue to be Addressed  Make  Buy 

1 Item/product is readily available in the marketplace,   √ 

2 In use in applications similar to yours, with documented success,   √ 

3 Available at a reasonable price,   √ 

4 Delivered when you need it, and   √ 

5 We have time for a competitive procurement process   √ 

6 Your company wishes to develop such a product for future program use, or as a new market entry

√   

7 Having it subcontracted could establish others as future competitors to you √   

8 You have the internal resources to develop it. Will not deflect from your current program attention, or eat up resources.

√   

9 Is doing it in-house being pushed by engineering or R&D? √   

10 The application is special, and integration into your hardware is critical/ difficult/finicky

√   

11 There is much documentation required with each delivered item, hence more CADM work and “paper policing” is required

  √ 

12 The item will require specialized test equipment   √ 

13 Substantial spares are required   √ 

14 You can enter into the contract type you prefer   √ 

These are just a few of the thoughts one might have when deciding on “make or buy”. The bottom line 

would seem to be, if your company will be stronger, and the project will be less risky (overall), by doing 

a make, then do so. However, if the customer has any hesitation about your in‐house capability in 

respect of this item, and you cannot make a water‐tight case for doing so, better seek a way to 

outsource. 

   

                                                            1 Courtesy of Terry Ussher, formerly of Spar Aerospace, Program Manager for the Canadarm 

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 306

 

Firm Fixed Price (FFP) 

Known scope, known price 

AKA “stipulated price”, “lump sum” 

Fixed Price with Economic Price Adjustments (FP‐EPA) 

Considers inflation 

Fixed Price Incentive Fee (FPIF) 

Price may vary according to actual cost, schedule, or performance 

May have a price “ceiling” 

 

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 307

 

 

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 308

CONTRACT TYPES – HOUSE PAINTING EXAMPLE 

You want to paint the rooms on the ground floor of your house. There are about 2000 square feet of 

wall space. It would take about 200 hours for the painters to do the work. The painting contractor would 

have to pay about $180 for the paint. The contractor would have to pay the union rate for painters of 

$8.09/hr. It would be normal in these market conditions for the painter to expect to get about a 10% 

“fee” on top of the labour and material costs to cover corporate overhead and profit.  

If everything goes according to plan, any of the methods below will result in a final price of about $2000. 

Firm Fixed Price (FFP): 

I’ll paint all the rooms on the ground floor of your house for $2,000. That includes supplying the paint. 

Cost Plus Percentage of Cost (CPPC): 

I have to pay my painter $8.19 per hour, and I will buy the paint. You reimburse me for those actual 

direct costs and pay me 10% “fee” on the labour and materials to cover my overhead and profit. 

Cost Plus Fixed Fee (CPFF): 

I’ll paint all the rooms on the ground floor of your house. I have to pay my painters $8.19 per hour, and I 

will buy the paint. You reimburse me for those actual direct costs and pay me a $180 “fee” to cover my 

overhead and profit. 

Cost Plus Incentive Fee (CPIF): 

I’ll paint all the rooms on the ground floor of your house. I have to pay my painters $8.19 per hour, and I 

will buy the paint. You reimburse me for those actual direct costs and pay me a $180 “fee” to cover my 

overhead and profit. I estimate that the direct cost will be $1,818. If the direct costs actually cost less, 

then my “fee” increases by 10% of the under‐run. If the direct costs actually cost more, then my “fee” 

decreases by 10% of the overrun. 

Time & Materials (T&M): 

I’ll paint any rooms you want. You pay me $9.10 per hour for the painters. I will also buy the paint and 

bill you for the cost of it. 

Unit Price: 

I’ll paint any rooms you want for $1.00 per square foot of wall. That includes supplying the paint. 

 

 

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 309

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 310

 

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 311

CUSTOMER MIGHT CHOOSE COST‐REIMBURSABLE WHEN… 

The scope is vague and the cost is hard to estimate. 

There are uncertainties in the future that would affect the cost. 

The customer wants to be involved in managing the work and might change the scope 

significantly or frequently. 

The customer is in a hurry and does not want to wait for the scope to be more fully defined or 

does not want to wait for a competitive fixed‐price procurement process. 

The customer is willing and able to take the cost risk. 

Cost reimbursable works best if the customer is willing to exert some supervision of the seller’s 

management of the work, and/or if trust exists in the relationship. 

CUSTOMER MIGHT CHOOSE FIXED PRICE WHEN… 

The scope is tightly defined, can be tightly estimated, and is not subject to many future changes 

by the customer. 

The customer needs to know the final cost before deciding to go ahead. (In other words, is not 

willing to assume the cost risk.) 

There are potential sellers interested in doing the work, willing to offer competitive prices, and 

willing to take the cost risk. 

A possible advantage of fixed price contracts is that it discourages the customer from making 

changes.  

With fixed price, the customer usually just has to monitor the schedule and quality being 

delivered.  

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 312

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 313

 

   

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 314

PROJECT DELIVERY STRATEGIES 

Traditional Design‐Bid‐Build 

The owner signs two contracts: 

With the design consultant 

With the general contractor  The design consultant is typically designated as an agent of the  owner.  The  general  contractor  signs  contracts  with various  vendors  and  sub‐contractors  specializing  in particular aspects of project delivery.  Traditionally, projects used “master builders” who     looked after  design  and  construction.  About  100  years  ago,  we started to separate design and construction, and that is now considered “traditional”. The intent was to obtain the best design  and  then  have  builders  compete  on  price.  Since 

design costs are typically considerably less than construction costs, this model was considered good “value for money”.  It is a slower process as the design and construction are sequential, but is considered less risky, because the “final” price is known before starting construction. 

 To apply the traditional design‐bid‐build delivery strategy, there should be: 

• An evaluation process of potential designers and contractors • Clear detailed specifications and drawings at the time of construction award • Appropriate standard contracts (OAA, CCDC or Owner‐developed) • A process for handling changes and disputes  

 This  process may  pit  the  design  consultant  against  the  general  contractor  in  the  case  of  disputes  or conflicts between the design objectives and the project objectives of time and cost. 

Design‐Bid‐Build Schedule 

 

Design

Construct

Procure

Start

Award

Complete

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 315

Design‐Build 

The owner signs one contract with the contractor. 

The contractor is responsible for developing the design and 

constructing to the design. As with the design‐bid‐build delivery 

strategy, the contractor signs contracts with various vendors and sub‐

contractors specializing in particular aspects of project delivery. 

This approach has regained popularity since the 1970’s. It tends to be 

used more in the private than public sector, industrial rather than 

building projects, and in larger rather than smaller projects. For 

Owners, Design‐Build offers better performance on “schedule, changes, 

re‐work and practice use”, in accordance to the Construction Industry 

Institute (CII). 

If the contract is awarded on a fixed price basis, cost performance can 

be quite good or even better than the design‐bid build delivery 

strategy, as the designer and builder are motivated to be cost‐conscious in the design. Schedule 

performance tends to also be better than design‐bid‐build if design and construction can be performed 

concurrently.  

To apply the design‐build strategy, there should be: 

Well defined performance specifications before award 

Monitoring for quality and schedule performance 

A well‐defined change process 

A fixed price contract, except for change orders 

For good cost performance, in additional to the above bullet points, there should be also good pre‐

project planning and the owner should not meddle in the relationship between the designer and 

constructor.  

Dispute resolution can be more efficient as only two parties are legally involved in any dispute.  

As an example, a developer might sign a contract with 

a municipality, gas supplier, pipeline and electrical 

utility. The developer is then responsible for the design 

and build but in this case hires a constructor to design 

and build on a fixed price basis with tight performance 

specifications and liquidated damages.  

   

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 316

Design‐Build Schedule 

 

 

   

 

 

 

Public‐Private Partnership 

This project delivery strategy has been developed to reduce financial risk for the owner, usually a 

government entity. A long‐term partnership contract is signed between the owner and contractor. The 

contractor is responsible for the financing, design and construction, and remuneration from the owner is 

linked to performance criteria. Under this arrangement, the owner may sign a design‐build‐finance, 

design‐build‐finance‐maintain contract or a design‐build‐operate‐finance‐maintain contract. 

Remuneration is awarded with any combination of completion, maintenance and operate phases. These 

arrangements motivate a contractor to build quickly and minimize the “total cost of ownership”. 

Key elements for these arrangements are: 

Very well‐defined performance specifications before award, 

A well‐defined change process, 

Price is fixed, except for change orders, and 

Clearly defined responsibilities. 

These projects can suffer from poor maintenance, especially towards the end of contract term. 

   

Construct

Design

Procure

Start

Award

Complete

Specify

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 317

Integrated Project Team Delivery 

 

Overlapped sequence of planning, design 

and construction. Owner signs one contract 

with Designer and Contractor (some are 

calling this a tri‐partite contract). 

There is more cost and effort in design and 

planning to maximize construction efficiency 

and potentially reduce construction costs. 

The objective is to have the design expertise 

work with the constructability expertise to 

minimize rework, mistakes, 

misinterpretations of the design and 

disputes. The schedule would likely be iterative as for the design‐build. 

Construction Management 

The owner signs a number of contracts: 

With the design consultant 

With the construction manager 

With the specialty vendors and contractors  In this case, the construction manager is an agent of the owner.  This  delivery  strategy  achieves  good  schedule performance  as  it  allows  for  concurrent  design  and construction. The owner can have considerable  input to the  design  and  direct  changes  during  the  design  and construction.  This  strategy  is  best  suited  for  a sophisticated Owner.  The Construction Management  at  Risk  project  delivery 

strategy is a version of the construction management delivery strategy where the construction manager is NOT an agent of the Owner. The construction management firm signs the contracts with the specialty vendors and subcontractors. This reduces the risk for the owner, but, correspondingly raises the risk for the construction manager. 

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 318

Project Management 

The owner signs a number of contracts: 

With the design consultant 

With the project manager 

With specialty vendors and contractors  The  project  manager  is  an  agent  of  the  Owner  and manages both the design and construction process.     

Engineer‐Procure‐Construction Management (EPCM) 

The owner signs a number of contracts with: 

The EPCM contractor 

Specialty vendors and contractors  The  EPCM  contractor  acts  as  the  agent  of  the  owner  and  is responsible for the design and engineering work.       

 

 

Engineer‐Procure‐Construct (EPC)     

This  strategy  is  similar  to  the  design‐build  project  delivery strategy  in  that  the  owner  signs  one  contract  with  the  EPC vendor, who is responsible for the design and engineering as well  as  the  construction.  The  EPC  contractor  engages  the specialty vendors and subcontractors. 

 

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 319

 

 

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 320

EXAMPLE OF A PROCUREMENT MANAGEMENT PLAN2  

This is an example of a procurement management plan, of a scale which is probably only justifiable on a 

very large, complex and unique project.  

TABLE OF CONTENTS 

1. Contract packages breakdown structure 

2. Reason(s) for procuring instead of “making” 

3. Roles and responsibilities 

4. Sourcing plan 

5. Pre‐qualification plan, including pre‐qualification criteria 

6. Budget 

7. Schedule 

8. Quality level and plan 

9. Specification types 

10. Contract types 

11. Plan for the solicitation process, including: 

Standard instructions to bidders 

Proposal/bid evaluation criteria 

Pre‐bid meetings 

Alternate proposals 

12. Source selection plan 

13. Contract administration plan 

14. Contract closure plan 

APPENDIX 

A. Standard forms 

B.  Referenced documents 

                                                            2 Thanks to Michael Stefanovic, Procept Associates Ltd. 

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 321

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 322

 

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 323

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 324

 

   

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 325

THE LAW OF COMPETITIVE TENDERING IN CANADA 

If we want to award a contract to a seller, we can either negotiate directly with a seller, or we can use 

competition (competitive tendering) between two or more potential sellers to reach a deal. 

Through precedent, the courts have built up a body of law about competitive tendering. If a customer 

goes to the marketplace with competitive procurement documents (e.g. request for proposals or 

invitation to bid, or request for quotation), then it means the customer has decided to use competition 

among the bidders to select the best bid (or tender or proposal). During this competitive tendering 

process, the customer should not short‐circuit the competitive tendering process by negotiating directly 

with one of the bidders.  

The Canadian courts have described a short‐lived “Contract A” which is formed between the customer 

and each seller which submits a bid. This Contract A is in place until it is replaced by “Contract B” being 

formed by the customer awarding the actual performance of the work to one of the bidders. 

In this Contract A, the customer promises that: 

All bidders will be treated equally and fairly. For example, they will each be provided the same 

information and the same opportunities. 

A non‐compliant bid (one that fails to meet a mandatory requirement) will be rejected. 

The customer promises to follow whatever process it described in its procurement documents. 

For example, if evaluation criteria are described, then they must be followed. 

The customer promises to award the Contract B according to the process described, usually by 

accepting the lowest compliant bid, or the proposal which offers the best value to the customer. 

The bidder goes to some trouble and expense to prepare the bid, and promises that: 

The bid is irrevocable (cannot be withdrawn) for some period of time specified in the bid 

documents. 

An owner is allowed to reject all the bids and award it to no‐one, if it has said so in the procurement 

documents. 

   

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 326

MJB ENTERPRISES v. DEFENCE CONSTRUCTION3 

A significant case in tendering law was decided by the Supreme Court of Canada in 1999.  

MJB, a losing bidder was awarded damages of $398,000 based upon its expected loss of profits. The 

company had responded to a tender package issued by Defence Construction that included a privilege 

clause saying that the “….lowest or any tender would not necessarily be accepted.” Four tenders, 

including MJB’s second lowest tender, were submitted. Defence awarded the contract to the lowest 

tenderer although the bid did not comply with the tender specifications. 

MJB sued Defence for breach of its tendering obligations saying that the winning tender should have 

been disqualified and that MJB’s tender should have been accepted.  

The Court held that “Contract A” had an implied term that only a compliant bid would be accepted. The 

“lowest or any tender” clause did not override Defence’s Constructions obligation to accept only 

complaint bids. As the accepted bid was non‐compliant, Defence breached its obligations to MJB. 

 

EXAMPLE OF FAIRNESS TO THE BIDDERS 

Two bids identical down to the last cent: 

Coin toss may decide winner4 

I guess you would have to call it a fluke. 

Toronto officials can’t make heads or tails out of two identical bids to repaint lane markings on 

Etobicoke streets, which were the same down to the last penny. Their proposed solution: What else? A 

coin toss. 

Two companies offered to do the work for the exact same amount: $111,242.55. 

The bids from Guild Electric Ltd. and Mark‐All Services Inc. were opened back in February and the city 

has been struggling with what to do ever since. 

They couldn’t eliminate one because both meet the bid conditions and have good track records with the 

city, said John Thomas, director of transportation services in District 2, which includes Etobicoke. 

“We couldn’t discount one for bad performance or anything like that,” Thomas said yesterday. 

Stumped for an answer, they turned to the legal department, which is suggesting flipping a coin in public 

at a date, time and location to be determined. 

If city council agrees, Guild Electric would be assigned heads and Mark‐All Services would get tails. 

A coin will be tossed into the air by purchasing and materials management staff and after it lands, the 

face showing upward (head or tail) will be announced as the winner, says a proposed procedure to be 

discussed to‐day at council’s policy and finance committee. 

                                                            3 adapted from The Legal Edge newsletter, published by National Education Consulting Inc.  4 Paul Moloney, Toronto Star, July 2003 

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 327

 

 

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 328

EXAMPLE OF PROPOSAL EVALUATION CRITERIA5 

The following is adapted from a Government of Canada request for proposals. It provides a good 

example, and it illustrates a way to include both quality and price into a single figure comparison. Note 

that if we specify our solicitation and evaluation process in our procurement documents, then we must 

follow that process. 

I. MANDATORY REQUIREMENTS  YES  NO 

1. Compliance with the Request for Proposal submission requirements     

2. Minimum corporate experience (number of similar assignments) per requirements     

3. Minimum personnel qualification per requirements     

4. Compliance with the terms and conditions of the Request for Proposal. The 

Proponent must sign and return a copy of page one (1) of the RFP (or equivalent 

form) 

  

 

     

II. RATED REQUIREMENTS  MAX PTS  SCORE 

1, TECHNICAL PROPOSAL 

a) understanding of the scope and importance of the requirement  10.0   

b) proposed approach, methods of handling  8.0   

c) level of effort  5.0   

d) potential problems & methods of handling  5.0   

e) originality  and innovation  4.0   

Minimum acceptable points (75%)                                                         24/32   

2. TRAINING & EXPERIENCE 

a) relevant training & experience of personnel  15.0   

b) corporate background & experience  12.0   

c) references  8.0   

Minimum acceptable points (75%)                                                    26/35   

3. ORGANIZATION 

a) adequacy, availability and allocation of personnel  8.0   

                                                            5from a Government of Canada RFP, 2002 

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 329

b) time management, including work schedule and commitment to completion dates  10.0   

c) liaison with necessary parties  5.0   

d) overall organization of the project  10.0   

Minimum acceptable points (75%)                                                     25/33   

TOTAL POINTS AVAILABLE  100   

     

III. CONTRACTOR SELECTION‐ASSESSED BEST VALUE     

MERIT: Proponent’s Overall Total Point Score/Highest Overall Total Point Score X 80     

COST: Lowest Total Estimated Cost/Proponent’s Total Estimated Cost X 20     

ASSESSED BEST VALUE ( MERIT + COST)     

 

EVALUATION 

Each evaluation criterion has a point allotment that reflects its importance in personal submissions. The 

degree to which the proposal satisfies the requirement of each criterion will be assessed and a score will 

be assigned ranging from 0 to the total point allotment meaning the proposal fully meets the outlined 

criterion. 

Your proposal must meet all of the mandatory requirements set out in the evaluation criteria. Proposals 

which fail to meet these requirements will be discarded at this stage without further consideration. 

Your proposal will archive a minimum score of 75% of the maximum points available in EACH category 

subject  to  point  rating.  Proposals  which  fail  to  achieve  this  score  will  be  considered  technically 

unacceptable and will be given no further consideration. 

SELECTION METHOD 

The contractor will be selected on the basis of the ASSESSED BEST VALUE to the Crown taking into account 

merit and cost factors. Best value to the Crown will be determined on the basis of the highest combined 

rating of merit and price. The scoring of merit is done by giving full marks to the highest rated proposal, 

with other proposals being given a prorated score. The scoring of price is done by giving full marks to the 

lowest price proposal, with the other proposals given a prorated score. The proposal which offers  the 

highest combined point score for merit and cost will be recommended for award. 

   

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 330

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 331

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 332

 

   

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 333

CASE STUDY6 

Dowler‐Karn, which runs a fleet of oil delivery trucks in London, Ontario, wanted to upgrade its entire 

computer system. JDH Microsystems, a Toronto‐based company, was contacted by Dowler‐Karn to 

develop and install a custom truck dispatch, route planning and billing system. A fixed‐price contract 

was signed, and work began. 

Soon after work started, it became apparent that the supplier had grossly underestimated the time and 

effort required to develop the custom software. For example, of the amount originally budgeted by the 

supplier for writing the program, very quickly the time spent amounted to almost three times that 

amount, and still the system did not work. 

Several testing/acceptance dates were missed, and it became obvious that major problems plagued the 

new system, including the fact that it ran much too slowly on its intended hardware ‐ when it ran at all, 

as it had a nasty habit of crashing or seizing. 

The user soon had its lawyer send a letter to the supplier requiring a detailed correction plan for the 

problems that continued to plague the system. At this point the supplier did a relatively unusual thing ‐ 

it sued the user for final payment for the system. 

[The true case was argued in the Ontario Court of Justice in April 1994, and is recorded in 47 A.C.W.S. 

(3d) 282.] 

Q. What would Dowler‐Karn likely do at this point? 

 

 

 

Q. What could Dowler‐Karn have done to have avoided this situation? 

 

 

Q. What do you think the court decided? 

                                                            6"Crafting effective software development contracts", George Takach, partner in law firm McCarthy 

Tetrault, The Legal Edge, Vancouver, June 1995. 

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 334

 

SAMPLE DISPUTE RESOLUTION CLAUSES7 

8.1.3 If  a  dispute  is  not  resolved  promptly,  the  Consultant will  give  such  instructions  as  in  the Consultant's opinion are necessary  for  the proper performance of  the Work and  to prevent delays  pending  settlement  of  the  dispute.  The  parties  shall  act  immediately according  to such instructions, it being understood that by so doing neither party will jeopardize any claim the  party  may  have.  If  it  is  subsequently  determined  that  such  instructions  were  in  error or  at  variance  with  the  Contract Documents,  the Owner shall  pay  the Contractor costs incurred  by  the  Contractor in  carrying  out  such  instructions  which  the  Contractor was required  to  do  beyond what  the Contract Documents correctly  understood  and  interpreted would  have  required, including costs resulting from interruption of the Work. 

GC 8.2  

8.2.1 In accordance with the Rules for Mediation of Construction Disputes as provided in CCDC 40 in effect at the time of bid closing, the parties shall appoint a Project Mediator .1 within 20 Working Days after the Contract was awarded, or .2 if the parties neglected to make an appointment within the 20 Working Days, within 10 Working

Days after either party by Notice in Writing requests that the Project Mediator be appointed.

8.2.2 A  party  shall  be  conclusively  deemed  to  have  accepted  a  finding  of  the Consultant under GC  2.2  ‐  ROLE  OF  THE CONSULTANT  and  to  have  expressly waived  and  released  the other party  from  any  claims  in  respect  of  the  particular  matter dealt with  in  that  finding unless, within 15 Working Days after receipt of that finding, the party sends a Notice in Writing of dispute to the other party and to the Consultant, which contains the particulars of the matter in dispute and the  relevant provisions of the Contract Documents. The responding party shall 

                                                            7 CCDC2 stipulated price contract, Canadian Construction Documents Committee, 2008.

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 335

send a Notice in Writing of  reply  to  the dispute  within  10  Working Days after  receipt  of such Notice in Writing setting  out  particulars  of  this  response  and  any  relevant  provisions of the Contract Documents. 

8.2.3 The parties shall make all reasonable efforts to resolve their dispute by amicable negotiations and agree to provide, without  prejudice, frank, candid and timely disclosure of relevant facts, information and documents to facilitate these negotiations. 

8.2.4 After  a  period  of  10  Working Days following  receipt  of  a  responding  party's  Notice in Writing of   reply   under  paragraph 8.2.2,  the  parties  shall  request  the  Project Mediator  to assist the parties to reach agreement on any unresolved dispute. The mediated negotiations shall be conducted  in accordance with  the Rules  for Mediation of Construction Disputes  as provided in CCDC 40 in effect at the time of bid closing. 

8.2.5 If the dispute has not been resolved within 10 Working Days after the Project Mediator was requested under  paragraph 8.2.4  or within  such  further  period  agreed  by  the  parties,  the Project Mediator shall terminate the mediated negotiations by giving  Notice in Writing to the Owner, the Contractor and the Consultant. 

8.2.6 By  giving  a  Notice in Writing to  the  other  party  and  the  Consultant,  not  later  than  10 Working Days after  the  date  of  termination of the mediated negotiations under paragraph 8.2.5, either party may refer the dispute to be finally resolved by  arbitration under the Rules for Arbitration of Construction Disputes as provided  in CCDC 40  in  effect at  the  time of  bid closing.  The arbitration shall be conducted in the jurisdiction of the Place of the Work. 

8.2.7 On expiration of the 10 Working Days, the arbitration agreement under paragraph 8.2.6 is not binding on the parties and, if a  Notice in Writing is not given under paragraph 8.2.6 within the required time, the parties may refer the unresolved dispute to  the courts or to any other form of dispute resolution, including arbitration, which they have agreed to use. 

8.2.8 If neither party, by Notice in Writing, given within 10 Working Days of the date of Notice in Writing requesting  arbitration  in  paragraph  8.2.6,  requires  that  a  dispute  be  arbitrated immediately, all disputes referred to arbitration as provided  in  paragraph 8.2.6 shall be .1 held in abeyance until 

(1) Substantial Performance of the Work, (2) the Contract has been terminated, or (3) the Contractor has abandoned the Work, whichever is earlier; and

.2 consolidated into a single arbitration under the rules governing the arbitration under paragraph 8.2.6. 

 

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 336

EXAMPLE OF A PROCUREMENT CONTROL REPORT 

Status RFx issued

Proposal Received

Proposal Evals

Complete6 5 3 3.5 3

P 9-Sep-19 21-Oct-19 25-Nov-19 16-Dec-19 9-Jan-20 30-Jan-20FA

P 9-Sep-19 21-Oct-19 25-Nov-19 16-Dec-19 9-Jan-20 30-Jan-20F 22-Oct-19 26-Nov-19 17-Dec-19 10-Jan-20 31-Jan-20A 10-Sep-19

5P 9-Sep-19 21-Oct-19 25-Nov-19 16-Dec-19 9-Jan-20 30-Jan-20F 22-Oct-19 26-Nov-19 17-Dec-19 10-Jan-20 31-Jan-20A 10-Sep-19

5

LEGEND:P - Planned

F - Forecast

A - Actual

- Progress bar

Project Name: Status Date:

Remarks

Duration in Weeks*

1 Pkg.1

Contract Pkg. No. Contract Pkg. Name

SOW Spec Issued and Approved

PROPOSAL Recom-mendation to Award

Issued

Recom-mendation to

Award Approved, Contract Award

2

3

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 337

 

 

   

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 338

APPENDIX: CHAPTER 10 

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 339

 

UN0603 Project Management for Nuclear Engineers 11. Procurement Management

v2019.1 (c)4DPM & Procept Associates 2019 340