Clean Air Leeds
Polly Cook
25th October 2017
National Air Quality Plan
• Move from a very clear mandate from central gov.to complete focus on Local Authorities• Have to explore all options• Technical appendices• Original 5 cities must introduce their plan by 2019• Difficult to plan when national policy is still to be announced
Current Issues
Inner Ring Road
Current Issues
Air Quality Management Areas (AQMAs)
Current Issues
Neville Street
Progress to date
• Additional Monitoring installed
• ANPR data collection
• Detailed data analysis
• Transport model converted for potential car
impact
• Various scenarios run to assess impact
Increasing sustainable and clean modes
of transport
City Connect Scheme
Leeds Transport Plan
Accelerate the uptake of cleaner
vehicles within the domestic market
Increased uptake of plug in vehicle registration
in Leeds 2014 - 2016
Free LCC ULEV Parking Permit
introduced March 2016
Fleet Changes and Alternative Fuels
Body copy
Improved Promotion and Profile
Body copy
Lessons Learned
• Cross cutting
• Governance
• Resources
• Timescales
• Engagement
• Early evidence gathering
Challenges
• Data inputs:
• Set charge
• Compliance expectation
• Future vehicle mix
• Average versus local correction factors
• Target determination process
• Steep learning curve
• Complexity has led to delays
Modelling
Challenges
Public Understanding
• Air Quality vs. Global Warming
• “What impact can I really have? I’m just one person.”
Challenges
Timescales for Implementation
• Effects of implementation on the second hand car market
• Lack of EV second hand stock
• Lease agreements
• Infrastructure
Challenges
Practicalities
• Database issues
• Procurement framework
• Data transfer costs
• Manufacturer readiness
Challenges
Lack of national incentives/measures
• Government funding
• Diesel lobby
TimescalesActivity TimescaleExecutive Board (outline solution) December 2017Consultation Initiation – Stage 1 December 2017 (soft launch)
January 2018 (official launch)Consultation Close – Stage 1 February 2018Report Drafted incorporating consultation feedback
April 2018
Purdah March/ April 2017Elections 3rd May 2018
Executive Board (final solution) June 2018Formal Consultation Initiation –Stage 2 (if required)
June 2018
Consultation Close – Stage 2 July 2018Final Executive Board Report September 2018Final business case and scheme presented to government
September 2018
Scheme approval October 2018Project Implementation October 2018
Questions?