P R E S E N T A T I O N ON ANNUAL DEVELOPMENT PROGRAMME 2015-16 1

Adp presentation january 2016 (forests)

Embed Size (px)

Citation preview

Page 1: Adp presentation january 2016 (forests)

P R E S E N T A T I O NON

ANNUAL DEVELOPMENT PROGRAMME 2015-16

1

Page 2: Adp presentation january 2016 (forests)

MONTHLY REVIEW PERFORMA (Rs in Million)

2

 SECTOR: FORESTS TotalTotal On-goingOn-going NewNewTotal No. of Schemes 30 22 8

Unapproved Schemes

i) As on 01.07.2015 8 0 8

ii) As on 31.01.2016 1 01

(Jallo Park) Proposed to be 

capped

Original Allocation 2015-16                                                        900.000 670.102 229.898Revised Allocation 2015-16                                                        900.000 670.102 229.898Approved Allocation 2015-16 882.807 670.100 212.707Proposed surrender 2015-16 22.102 20.953 1.149Funds Released by P&D As on 31.01.2016 432.852 335.232 97.620Funds  Released by FD As on 31.01.2016 432.852 335.232 97.620Funds  Released / Reconciled by FD as per MPRs incl. A/C-IV (31.01.2016) 432.852 335.232 97.620Funds utilized As on 31.01.2016 (incl. A/C-IV)  277.311 208.552 68.759

% Utilization on Releases (MPRs)As on 31.01.2016 64 62 70As on 31.01.2016 (PIFRA) 64 62 70As on 31.01.2015 51 73 45

Funds Released / transferred in Account-IV - - -Utilization in Account-IV - - -List of slow moving schemes (Less than 58 % utilization)  List attached 9 7 2List of Mega  Projects / Foreign Aided Projects                                                                           -Issues/Bottlenecks (If any)

Page 3: Adp presentation january 2016 (forests)

ZONE WISE DETAIL OF DEVELOPMENT SCHEMES DURING 2015-16

Name of Zone  No of Schemes Central Zone 16

Northern Zone 4

Southern Zone 3

All over Punjab 7

Total Schemes 30

3

Page 4: Adp presentation january 2016 (forests)

PROGRESS OF ADP UP TO 31.01.2016 Rs.In Million

Name/Status No. of Schemes

Original Allocation

Revised Allocation

as per PC-1

Funds released 2015-16

Utilization Utilization %

PROVINCIAL ADP

ON-GOING SCHEMES 22 670.102 670.100 335.232 208.552 62

NEW SCHEMES 08 229.898 212.707 97.620 68.759 70

Grand Total: - 30 900.000 882.807 432.852 277.311 64

4

Page 5: Adp presentation january 2016 (forests)

G.S No Name of Scheme Original

allocationRevised

allocation as per PC-I

Funds released2015-16

Utilization %age

ON-GOING SCHEMES

36301) Rehabilitation of Kamalia Irrigated plantation (36-months 2014-15 to 2016-17)

45.000 45.000 22.500 21.873 97

36312) Integrated Afforestation & Eco-Development of Karrianwala Forest (60 months 2012-13 to 2016-17)

7.285 7.285 3.643 3.642 100

36323) Ecological Afforestation in Kharian (48-months 2014-15 to 2017-18) 20.640 20.640 9.500 6.978 73

3633 4) Development of Jallo Forest Park Lahore (PC-II) (12-months 2014-15) 2.000 2.000 2.000 0.800 40

3634

5) Afforestation and landscaping of shahdra reserve forests land bank near mehmood booti landfill (36 months 2014-15 to 2016-17)

51.000 51.000 25.500 13.358 52

36356) Development of changa manga forest park (36 months 2014-15 to 2016-17 )

59.000 59.000 29.500 12.450 42

5

Page 6: Adp presentation january 2016 (forests)

G.S No Name of Scheme Original

allocationRevised

allocation as per PC-I

Funds released 2015-16

Utilization %age

36367) Afforestation of Blank Areas in Changa Manga(36-months 2014-15 to 2016-17)

4.000 4.000 2.000 1.974 99

36378) Environmental afforestation of degraded land in depalpur plantation(36-months 2014-15 to 2016-17)

42.673 42.672 21.337 14.107 66

36389) Establishment of shahbaz sharif forest park depalpur plantation(36-months 2014-15 to 2016-17)

34.596 34.596 17.297 7.960 46

3639

10) Afforestation of Forest Land Retrieved from Encroachers in Rajanpur Forest Division” (48-Months 2014-15 to 2017-18)

60.680 60.680 30.340 20.749 68

3640

11) Development of Patisar Lake and additional Recreational Facilities in Lal Suhanra National Park (36-Months 2014-15 to 2016-17)

37.500 37.500 18.750 7.098 38

3641

12) Mechanization of Forestry Operations and Fire Fighting Techniques (36-Months 2014-15 to 2016-17)

29.580 29.580 14.790 2.506 17

6

Page 7: Adp presentation january 2016 (forests)

G.S No Name of Scheme Original

allocationRevised

allocation as per PC-I

Funds released 2015-16

Utilization %age

364213) Afforestation along Important Highways in Punjab (60 Months 2011-12 to 2015-16)

14.964 14.964 7.482 6.385 85

3643

14) Afforestation under approved management plans in irrigated plantations of the Punjab (60 Months 2013-14 to 2017-18)

10.215 10.215 5.108 5.011 98

364415) Afforestation in Riparian forests of Central Zone (60 Months 213-14 to 2017-18)

22.500 22.500 11.250 10.443 93

3645

16) Satellite GIS based mapping of major forests in Punjab for REDD + Readiness (36 Months 2013-14 to 2015-16)

8.563 8.562 4.282 3.022 71

364617) Chief Ministers special initiative for mass afforestation in Punjab (48 Months 2013-14 to 2016-17)

23.066 23.066 11.533 10.599 92

3647

18) Establishment of Punjab Forest Academy for in-service and post graduate training(36 months 2014-15 to 2016-17)

37.740 37.740 18.870 0.684 47

Page 8: Adp presentation january 2016 (forests)

G.S No Name of Scheme Original

allocationRevised

allocation as per PC-I

Funds released 2015-16

Utilization%

Age

364819) Rehabilitation of Existing Forest Parks in Punjab (36-Months 2014-15 to 2016-17

57.000 57.000 28.500 23.778 83

364920) Development of Range Lands in Punjab (36 Months 2014-15 to 2016-17)

60.000 60.000 30.000 20.419 68

365021) Human resource development through research and training (24 months-2014-15 to 2015-16)

8.000 8.000 4.000 3.265 82

3651

22) Rehabilitation & Re-seeding of retrieved Rangeland in Bhakhar & Layyah District (24-Months 2014-15 To 2015-16)

34.100 34.100 17.050 11.451 67

TOTAL: - 670.102 670.100 335.232 208.552 62

8

Page 9: Adp presentation january 2016 (forests)

NEW SCHEMESGS.No Name of Scheme Original

allocation

Revised allocation

as per PC-I

Funds released 2015-16

Utilization%

Age

3652Afforestation of Marginal Lands in Murree(36 months 2015-16 to 2017-18)

10.000 10.000 5.000 5.000 100

3653Implementation of Master Plan for Jallo Forest Park (36-months 2015-16 to 2017-18)

20.000 20.000 0.000 0.000 0

3654

Implementation of Management Plan in Southern Zone (Inayat, Machu & Rajan Shah)(48-months 2015-16 to 2018-19)

40.000 32.061 17.298 14.499 84

3655

Propagation and promotion of Indigenous Forest Tree Species to conserve Biodiversity(24-months 2015-16 to 2016-17)

16.000 8.500 4.250 2.705 64

3656Promotion of Social Forestry(36-months 2015-16 to 2017-18) 40.000 40.789 20.395 11.942 59

3657

Establishment of Short Rotation Plantation in Punjab (Shorkot, MLN, BWP & Pakhowal)(48-months 2015-16 to 2018-19)

48.898 48.332 24.165 19.196 79

9

Page 10: Adp presentation january 2016 (forests)

GS.No Name of Scheme Original

allocation

Revised allocation

as per PC-I

Funds released 2014-15

Utilization%

Age

3658

Implementation of Management Plan in Northern Zone (Kundian & Bhakkar Plantation)(48-months 2015-16 to 2018-19)

35.000 33.025 16.512 8.008 48

3659Afforestation and Soil Conservation in Scrub Forest (36 months 2015-16 to 2017-18)

20.000 20.000 10.000 7.409 74

TOTAL: - 29.898 212.707 97.620 68.759 70

10

Page 11: Adp presentation january 2016 (forests)

THANKS

11

Page 12: Adp presentation january 2016 (forests)

ON-GOINGSCHEMES

12

Page 13: Adp presentation january 2016 (forests)

TOTAL COST 150.000

PERIOD (36 months, 2014-15 to 2016-17)

ALLOCATION OF FUNDS 2015-16 45.000

FUNDS RELEASED 2015-16 22.500

FUNDS UTILIZED 21.873

%AGE UTILIZATION 97%Date of Budget online 1st half: 13.08.2015

(3630) REHABILITATION OF KAMALIA IRRIGATED PLANTATION

(Rs. in million)

13

Page 14: Adp presentation january 2016 (forests)

 FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Circle Funds Released

Funds utilized

% age Physical Target Physical Achievement

upto 31.01.2016

Faisalabad 22.500 21.873 97

Afforestation = 333 Ac. (15.052M)Maint: of Aff: = 1110 Ac. (21.756M)Raising of Bed Nursery = 20 Ac. (1.400M)Maint: of Bed nursery = 20 Ac. (0.600 M)Raising of Potted plants = 3 Lac (2.400 M)Maint: of potted plants = 3 Lac (1.200M)Reconsturction/ Remodelling of mains/ irrigation system = 4690 Rft. (0.530 M)

E.Work in progressBeing MaintainedE.Work in progressBeing Maintained240000 raisedBeing MaintainedWork in Progress

Total 22.500 21.873 97

14

Page 15: Adp presentation january 2016 (forests)

(3631) Integrated Afforestation & Eco-Development of Karrianwala Forest

(Rs. in million)

TOTAL COST 40.673

PERIOD (48 months, 2012-13 to 2015-16)

ALLOCATION OF FUNDS 2015-16 7.285FUNDS RELEASED 2015-16 3.643FUNDS UTILIZED 3.642%AGE UTILIZATION 100%Date of Budget online 1st half: 13.08.2015

15

Page 16: Adp presentation january 2016 (forests)

FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Name of Circle

Funds Released

Funds utilized % age Physical Target

Physical Achievement upto

31.01.2016

Gujranwala 3.643 3.642 100

Maint: of Aff: = 350 Ac. (7.285 M) Being Maintained

Total 3.643 3.642 100

16

Page 17: Adp presentation january 2016 (forests)

TOTAL COST 93.722

PERIOD (48 months, 2014-15 to 2017-18)

ALLOCATION OF FUNDS 2015-16 20.640

FUNDS RELEASED 2015-16 9.500

FUNDS UTILIZED 6.978

%AGE UTILIZATION 73%Date of Budget online 1st half: 13.08.2015 &

10.11.2015

(3632) ECOLOGICAL AFFORESTATION IN KHARIAN (Rs. in million)

17

Page 18: Adp presentation january 2016 (forests)

FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Name of

Circle

Funds Released

Funds utilized

% age Physical Target

Physical Achievement upto

31.01.2016

Gujranwala 9.500 6.978 73

Afforestation Canal side = 110 Av. Mile (6.105 M)Afforestation Road side = 20 Av. Mile (3.130 M)Maint: of canal side = 90 Av. Mile (3.195 M)Maint: of road side = 68 Av. Mile (3.400 M)Provision and installation of water hydrants = 2 No. (0.330M)

Work in progressWork in progressBeing MaintainedBeing Maintained-

Total 9.500 6.978 73

18

Page 19: Adp presentation january 2016 (forests)

TOTAL COST 3.000

PERIOD (12 month 2015-16)

ALLOCATION OF FUNDS 2015-16 2.000

FUNDS RELEASED 2015-16 2.000

FUNDS UTILIZED 0.800

%AGE UTILIZATION 40%Date of Budget online 1st half: 09.10.2015

(3633) Development of Jallo Forest Park Lahore (PC-II)

(Rs. in million)

19

Page 20: Adp presentation january 2016 (forests)

FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Name of Circle

Funds Released

Funds utilized % age Physical Target Physical Achievement

upto 31.01.2016

Lahore 2.000 0.800 40

Preparation of PC-I (2.000 M) An amount of Rs 0.300 million is due on the submission of Draft Master Plan but no bill/demand is received from consultant

Total: - 2.000 0.800 40

20

Page 21: Adp presentation january 2016 (forests)

TOTAL COST 170.000

PERIOD (36 months, 2014-15 to 2016-17)

ALLOCATION OF FUNDS 2015-16 51.000

FUNDS RELEASED 2015-16 25.500

FUNDS UTILIZED 13.358

%AGE UTILIZATION 52%Date of Budget online 1st half: 20.08.2015

(3634) AFFORESTATION AND LANDSCAPING OF SHAHDRA RESERVE FORESTS LAND BANK NEAR MEHMOOD BOOT

LANDFILL (Rs. in million)

21

Page 22: Adp presentation january 2016 (forests)

 FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Circle Funds Released

Funds utilized

% age Physical Target

Physical Achievement upto

31.01.2016

Lahore 25.500 13.358 52

Afforestation = 50 Ac. (3.500 M)

Maint: of Aff: 600 Ac. (15.240 M) Purchase of Peter Pump = 2 Nos. (0.160 M)

Purchase of boring material = 2 Nos. (1.738 M)

Construction of Forest Hut = 1 No. ( 0.922 M)Construction of Forest Guard Quarter = 1 No. (2.078 M)Construction of Pacca Water Course = 1990 Rft. (2.189 M)P/F barbed wire fencing = 43935 Rft (11.165 M)

E.Work on 43 Ac. Completed. Being MaintainedPurchase will be made after 2nd half release.Contractor started work & will be completed within 2 monthsWork in progressWork in progress

Work in progress

Contractor started work & will be completed within 6 months

Total 25.500 13.358 52 Proposed Surrender = 2.881 million

22

Page 23: Adp presentation january 2016 (forests)

TOTAL COST 192.000

PERIOD (36 months, 2014-15 to 2016-17)

ALLOCATION OF FUNDS 2015-16 59.000

FUNDS RELEASED 2015-16 29.500

FUNDS UTILIZED 12.450

%AGE UTILIZATION 42%Date of Budget online 1st half: 13.08.2015

(3635) DEVELOPMENT OF CHANGA MANGA FOREST PARK

(Rs. in million)

23

Page 24: Adp presentation january 2016 (forests)

 FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTSCircle Funds

ReleasedFunds utilized

% age Physical Target Physical Achievement

upto 31.01.2016

Lahore 29.500 12.450 42

Two Row planting along boundary road = 18 KM (8.136 M)

Maint: of Grassy Lawn = 5 Ac. (0.451 M)Maint: of two row planting along boundary road = 20 KM (2.160 M)Maint: of arboretum = 5 Ac. (0.195 M)Maint: of ornamental nursery = 20000 Nos. (0.330 M)Maint: of ornamental planting = 50 Ac. (2.225 M)Construction of barbed wire = 15 KM. (18.671 M)

Construction of boundary wall = 5000 Rft. (14.600 M)Purchase and fixing of picnic gazeboes = 2 Nos. (0.264 M)Maint: of grass turfing on the bank of the lake = 89000 Sft. (0.431 M)Construction of Bridge = 3 No. (3.285 M)

Earth filling along boundary wall of plantation = 75600 Cft. (0.266 M)Construction of boundary wall with iron grill = 175 Rft. (0.324 M)

Plants purchased & jungle clearance/kanna mesquite stubbing completed

Being maintainedBeing maintained

Being maintainedBeing maintainedBeing maintainedContractor started work & will be completed within 3 months

2350 Rft. completedWill be purchased in 2nd halfBeing maintained

Contractor started work & will be completed within 2 months

Work in progress

Work in progress

Total 29.500 12.450 42 Proposed surrender = 5.429 million24

Page 25: Adp presentation january 2016 (forests)

TOTAL COST 15.940

PERIOD (36 months, 2014-15 to 2016-17)

ALLOCATION OF FUNDS 2015-16 4.000

FUNDS RELEASED 2015-16 2.000

FUNDS UTILIZED 1.974

%AGE UTILIZATION 99%Date of Budget online 1St half: 13.08.2015

(3636) AFFORESTATION OF BLANK AREAS IN CHANGA MANGA

(Rs. in million)

25

Page 26: Adp presentation january 2016 (forests)

 FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Circle Funds Released

Funds utilized

% age Physical Target

Physical Achievement upto

31.01.2016

Lahore 2.000 1.974 99

Maint: of Aff: = 200 Ac. (4.000 M) Being Maintained

TOTAL 2.000 1.974 99

26

Page 27: Adp presentation january 2016 (forests)

TOTAL COST 117.280

PERIOD (36 months, 2014-15 to 2016-17)

ALLOCATION OF FUNDS 2015-16 42.673

REVISED ALLOCATION 2015-16 42.672

FUNDS RELEASED 2015-16 21.337

FUNDS UTILIZED 14.107

%AGE UTILIZATION 66%Date of Budget online 1st half: 05.10.2015 &

10.11.2015

(3637) ENVIRONMENTAL AFFORESTATION OF DEGRADED LAND IN DEPALPUR PLANTATION

(Rs. in million)

27

Page 28: Adp presentation january 2016 (forests)

 FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Circle Funds Released

Funds utilized

% age Physical Target

Physical Achievement upto

31.01.2016

Lahore 21.337 14.107 66

Afforestation = 428 Ac. (15.622 M)

Raising of Bed Nursery = 10 Ac. (0.668 M)

Raising of Potted Nursery = 3 Lac (2.400 M)

Rehabilitation of area = 154 Ac. (2.925 M)

Maint: of Aff: = 391.2 Ac. (6.694 M)Maint: of Rehabilitated area = 183 Ac. (2.006 M)Maint: of Bed Nursery = 5 Ac. (0.045 M)P/F of water turbine = 2 Nos. (2.224 M)Construction of store/ shed of tractors = 1 No. (0.500 M)

Construction of brick lining = 800 Rft. (0.850 M)

Construction of Pacca Nakkas = 16 No. (0.128 M)

Jungle clearance & levelling ploughing on 428 Ac. completed10 Ac. Jungle clearance/ levelling ploughing completed1 lac plants raised & remaining work in progress154 Ac. Jungle clearance completedBeing maintainedBeing maintainedBeing maintainedContractor started work & will be completed within 1 monthContractor started work & will be completed within 2 monthsWork in progress

TOTAL 21.337 14.107 66 Proposed surrender = 1.644 million28

Page 29: Adp presentation january 2016 (forests)

TOTAL COST 77.870

PERIOD (36 months, 2014-15 to 2016-17)

ALLOCATION OF FUNDS 2015-16 34.596

FUNDS RELEASED 2015-16 17.297

FUNDS UTILIZED 7.960

%AGE UTILIZATION 46%Date of Budget online 1st half: 05.10.2015 &

10.11.2015

(3638) ESTABLISHMENT OF SHAHBAZ SHARIF FOREST PARK DEPALPUR PLANTATION

(Rs. in million)

29

Page 30: Adp presentation january 2016 (forests)

 FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTSCircle Funds

ReleasedFunds utilized

% age Physical Target Physical Achievement upto

31.01.2016

LHR 17.297 7.960 46

Dev of new grassy lawns = 15 Ac. (8.325 M)

Dev of botanical garden = 5 Ac. (0.400 M)Maint: of grassy lawn = 25 Ac. (2.225 M)Maint: of wooded area = 19 Ac. (0.133 M)Purchase of vehicle 4X2 (Diesel) = 1 No. (2.000 M)

P/F of benches = 10 Nos. (0.350 M)P/F of dust bins = 15 Nos. (0.150 M)Making & fixing of slide = 1 No. (0.450 M)Fixing of electrical/ solar lights (0.600 M)Provision of paddle boats = 4 Nos. (0.200 M)P/F of umbrella = 1 No. (0.100 M)

Construction of Hut = 1 No. (0.300 M)

Construction of steel/ wooden picnic shed = 2 Nos. (0.400 M)Construction of toilet blocks = 2 Sets (1.168 M)Construction of log hut = 1 No. (0.600 M)Construction of Lake = 1 No. (1.592 M)

Construction of bird cages = 2 Nos. (0.747 M)Construction of enclosure = 2 Nos. (3.429 M)

Lawn on 5 Ac. & dagh bailing layout on 10 Ac. completedcompletedBeing maintainedBeing maintainedSummary submitted for approvalWork in progress7 Nos. PurchasedWork in progressTender notice issued & work will be completed on 06.02.2016Tendering completed & work order in progressContractor started work & will be completed within 2 months-do-

-do--do-Contractor started work & will be completed within 3 months-do--do-

30Continued next sheet

Page 31: Adp presentation january 2016 (forests)

 FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Circle Funds Released

Funds utilized

% age Physical Target Physical Achievement upto

31.01.2016

Construction of ancient koas minar = 1 No. (1.500 M)

Construction of parking area = 40000 Sft. (1.980 M)Construction of tuff tiles = 2580 Rft. (3.515 M)Construction of store room = 1 No. (0.250 M)

Archaeological Department was requested to submit detail estimate of work and will be completed after receipt of estimate.Work in progressWork in progressContractor started work & will be completed within 2 months

Total 17.297 7.960 46 Proposed surrender = 2.896 million

31

Page 32: Adp presentation january 2016 (forests)

TOTAL COST 154.298PERIOD (48 months, 2014-15 to

2017-18)ALLOCATION OF FUNDS 2015-16 60.680

FUNDS RELEASED 2015-16 30.340FUNDS UTILIZED 20.749%AGE UTILIZATION 68%Date of Budget online 1st half: 05.10.2015

(3639) AFFORESTATION OF FOREST LAND RETRIEVED FROM ENCROACHERS IN RAJANPUR FOREST

DIVISION (Rs. in million)

32

Page 33: Adp presentation january 2016 (forests)

 FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Circle Funds Released

Funds utilized

% age Physical Target Physical Achievement

upto 31.01.2016

DG Khan 30.340 20.749 68

Afforestation = 1000 Ac. (26.940 M)

Maintenance = 800 Ac. (7.800 M)Purchase of Single Cabin = 1 No. (2.800 M)

Re-boring material & labour charges (0.400 M)Cost of store, tools & maintenance = (0.706 M)Construction of Boundary Pillars = 319 Nos. (4.370 M)

POL for Peter pump/ Vehicle = (17.204 M)Contingencies (0.460 M)

E.Work on 700 Ac. completed & remaining work in progressBeing maintainedCase sent to Austerity Committee for approvalWork in progressBeing maintainedTender opened on 28.12.15 & acceptance issued & Work in progressWork in progressWork in progress

TOTAL 30.340 20.749 68 Proposed surrender = 0.347 million

33

Page 34: Adp presentation january 2016 (forests)

TOTAL COST 115.675PERIOD (36 months, 2014-15 to

2016-17)ALLOCATION OF FUNDS 2015-16

37.500

FUNDS RELEASED 2015-16 18.750

FUNDS UTILIZED 7.098%AGE UTILIZATION 38%Date of Budget online 1st half: 09.10.2015

(3640) DEVELOPMENT OF PATISAR LAKE AND ADDITIONAL RECREATIONAL FACILITIES IN LAL

SUHANRA NATIONAL PARK (Rs. in million)

34

Page 35: Adp presentation january 2016 (forests)

 FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Circle Funds Released

Funds utilized

% age Physical Target Physical Achievement

upto 31.01.2016

Bahawalpur 18.750 7.098 38

Restocking 25% planting of big size plants in Lal Suhanra Children Park = 500 Nos. (0.250 M)Jungle clearance in Patisar Lake = 275 Ac. (3.330 M) Planting of big size plants = 1000 Nos. (0.500 M)Excavation/ desiltation of pond bed with dozer = 275 Ac. (5.970 M)Construction of lavatories = 4 Nos. (0.977 M)

Construction of steel/ wooden picnic shed = 3 Nos. (0.600 M)Construction of metaled road = 4.5 KM (12.850 M)

Construction of bridge portion = 2 Nos. (1.997 M)Construction of barbed wire fencing = 14950 Rft. (3.734 M)Purchase and installation of Water Points = 4 Nos. (0.200 M)Provision of Tango Lights = 2 Nos. (0.500 M)Purchase & fixing of water Pumps = 4 Nos. (0.060 M)Purchase & installation of wooden benches = 8 Nos. (0.150 M)

Work in Progress

Completed Purchased & Planted33 Ac. Completed

Work order issued & work startedWork in progress

Sub base completed & remaining work in progressWork in progressWork in progress

Purchased & Installed

Purchased & InstalledPurchased & InstalledPurchased & Installed

Total 18.750 7.098 38 Proposed surrender = 1.290 million 35

Page 36: Adp presentation january 2016 (forests)

TOTAL COST 105.493

PERIOD (36 months, 2014-15 to 2016-17)

ALLOCATION OF FUNDS 2015-16

29.580

FUNDS RELEASED 2015-16 14.790

FUNDS UTILIZED 2.506%AGE UTILIZATION 17%Date of Budget online 1st half: 09.10.2015

(3641) MECHANIZATION OF FORESTRY OPERATIONS AND FIRE FIGHTING TECHNIQUES

(Rs. in million)

36

Page 37: Adp presentation january 2016 (forests)

 FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Circle Funds Released

Funds utilized

% age Physical Target

Physical Achievement upto

31.01.2016

RWP 14.790 2.506 17

Purchase of Single cabin vehicles for firefighting = 11 Nos. (22.550 M)Photocopier = 1 Nos. (0.200 M)Purchase of skid pumps = 2 Nos. (1.200 M)Multi media = 1 No. (0.100 M)Fabrication of existing vehicles = 2 Nos. (2.000 M)Repair of vehicles = 15 Nos. (1.000 M)

Summary sent to CM for approvalPurchased

Tender CompletedPurchased

Work in progressWork in progress

Total 14.790 2.506 17 Proposed surrender = 0.190 million

Funds amounting to Rs 11.020 million onlined (Net %age is 23)

37

Page 38: Adp presentation january 2016 (forests)

(3642) AFFORESTATION ALONG IMPORTANT HIGHWAYS IN PUNJAB

(Rs. in million)

TOTAL COST 127.113

PERIOD (60 Months, 2011-12 to 2015-16)

ALLOCATION OF FUNDS 2015-16 14.964

FUNDS RELEASED 2015-16 7.482

FUNDS UTILIZED 6.385

%AGE UTILIZATION 85%Date of Budget online 1st half: 28.08.2015

38

Page 39: Adp presentation january 2016 (forests)

 FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Circle Funds Released

Funds utilized

% age Physical Target

Physical Achievement

upto 31.01.2016

B/ Pur 0.940 0.834 89 Maint of 2nd year Plantation = 50 Av. Mile (0.940 M) Being Maintained

DG Khan 0.268 0.268 100

Maint of 2nd year (Flow Irrigation) = 30 Av. Mile (0.205 M)Maint of Resting spots = 3 Nos. (0.063 M)

Being Maintained

FSD 0.301 0.301 100 Maint of 2nd year (Flow Irrigation) = 50 Av. Mile (0.301 M) Being Maintained

G/ wala 2.910 2.234 77

Maint: of 3rd year (Hand watering) = 62 Av. Mile (1.755 M)Maint: of 2nd year (Hand watering) = 50 Av. Mile (0.854 M)

Being Maintained

Lahore 1.305 1.038 80 Maint of 2nd year Aff (Hand Watering) = 62 Av. Mile (1.305 M) Being Maintained

R/pindi 0.453 0.452 100 Maint: of 3rd year (Hand watering) = 13 Av. Mile (0.453 M)Being Maintained

SGD 1.305 1.258 96Maint: of 3rd year (Hand watering)= 25 Av. Mile (0.708 M)Maint of 2nd year (Flow Irrigation) = 83 Av. Mile (0.398 M)

Being Maintained

Total 7.482 6.385 85 Proposed surrender = 0.618 million

39

Page 40: Adp presentation january 2016 (forests)

(3643) AFFORESTATION UNDER APPROVED MANAGEMENT PLANS IN IRRIGATED PLANTATIONS

OF THE PUNJAB (Rs. in million)

TOTAL COST 57.196

PERIOD (60 months, 2013-14 to 2017-18)

ALLOCATION OF FUNDS 2015-16 10.215

FUNDS RELEASED 2015-16 5.108

FUNDS UTILIZED 5.011

%AGE UTILIZATION 98%Date of Budget online 1st half: 24.08.2015

40

Page 41: Adp presentation january 2016 (forests)

FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Circle Funds Released

Funds utilized

% age Physical Target

Physical Achievement upto

31.01.2016

FSD 0.657 0.644 98Maint: of 2nd year = 150 Ac. (0.657 M) Being Maintained

G/wala 1.112 1.101 99

Maint: of 1st year = 123.29 Ac. (0.461 M)Maint: of 2nd year = 150 Ac. (0.651 M)

Being Maintained

Lahore 0.653 0.641 98Maint: of 2nd year = 150 Ac. (0.653 M) Being Maintained

Multan 1.363 1.312 96Maint: of 1st year = 200 Ac. (0.749 M)Maint: of 2nd year = 140 Ac. (0.614 M)

Being Maintained

PME 0.006 0.006 100 Miscellaneous expenditure (0.006 M) -

SGD 1.317 1.307 99

Maint: of 1st year = 160 Ac. (0.598 M)Maint: of 2nd year = 165 Ac. (0.719)

Being Maintained

Total: - 5.108 5.011 98

41

Page 42: Adp presentation january 2016 (forests)

(3644) AFFORESTATION IN RIPARIAN FORESTS OF CENTRAL ZONE

(Rs. in million)

TOTAL COST 112.009PERIOD (60 months, 2013-14

to 2017-18)ALLOCATION OF FUNDS 2015-16 22.500

REVISED ALLOCATION 2015-16 17.968

FUNDS RELEASED 2015-16 11.250

FUNDS UTILIZED 10.443

%AGE UTILIZATION 93%Date of Budget online 1st half: 24.08.2015

42

Page 43: Adp presentation january 2016 (forests)

FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Circle Funds Released

Funds utilized

% age Physical Target

Physical Achievement upto

31.01.2016

PME 0.043 0.043 100 Miscellaneous expenditure (0.043 M)

Gujranwala 11.207 10.400 93

Maint of Aff: = 810 Ac. (6.183 M) Being Maintained

Total: - 11.250 10.443 93 Proposed surrender = 1.242 million

43

Page 44: Adp presentation january 2016 (forests)

(3645) SATELLITE GIS BASED MAPPING OF MAJOR FORESTS IN PUNJAB FOR REDD + READINESS

(Rs. in million)

TOTAL COST 75.775PERIOD (36 months, 2013-14

to 2015-16)ALLOCATION OF FUNDS 2015-16 8.563

REVISED ALLOCATION 2015-16 8.562

FUNDS RELEASED 2015-16 4.282

FUNDS UTILIZED 3.022

%AGE UTILIZATION 71%Date of Budget online 1st half: 01.10.2015 &

12.11.201544

Page 45: Adp presentation january 2016 (forests)

FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Circle Funds Released

Funds utilized

% age Physical Target Physical Achievement upto

31.01.2016

PFRI FSD 0.950 0.748 79

REDD + activities-Field Exercise (0.950 M)

Completed

DWP Lahore 2.782 1.724 62

Pay of staff (0.359 million)GIS mapping of Riverain forests = 62 Nos.Irrigated Plantations = 27 Nos. (2.218 M)Procurement of GIS Lab furniture, Topo sheets, AC = 2 Nos., LCD = 2 Nos. & Desktop computer = 3 Nos. (0.934 M)Training of GIS Staff (0.300 M)

Recruitment in process47 completed & remaining in progress

Completed

Topo sheets, 1 LCD, 1 A.C, 1 Table & 3 chairs purchased while work station is in process. Tender work completed & purchase in process. 1st half training completed & 2nd will be imparted in 2nd half 2015-16.

PME 0.550 0.550 100Miscellaneous expenditure (0.550 M)

-

Total 4.282 3.022 71 Proposed surrender = 0.595 million

45

Page 46: Adp presentation january 2016 (forests)

(3646) CHIEF MINISTERS SPECIAL INITIATIVE FOR MASS AFFORESTATION IN PUNJAB (Rs. in million)

TOTAL COST 129.465

PERIOD (48 months, 2013-14 to 2016-17)

ALLOCATION OF FUNDS 2015-16 23.066

FUNDS RELEASED 2015-16 11.533

FUNDS UTILIZED 10.599

%AGE UTILIZATION 92%Date of Budget online 1st half: 20.08.2015

46

Page 47: Adp presentation january 2016 (forests)

FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Circle Funds Released

Funds utilized

% age Physical Target

Physical Achievement upto

31.01.2016DG

Khan 2.171 2.170 100 Maintenance = 483 Ac. (2.171 M) Being Maintained

FSD 2.580 2.010 78 Maintenance = 573.90 Ac. (2.580 M) Being Maintained

Gujranwala 1.043 1.043 100 Maintenance = 232.14 Ac. (1.043 M) Being Maintained

Lahore 2.869 2.863 100 Maintenance = 638.22 Ac. (2.869 M) Being Maintained

MLN 1.772 1.487 84 Maintenance = 394.3 Ac. (1.772 M) Being Maintained

SGD 0.940 0.939 100 Maintenance = 209.10 Ac. (0.940 M) Being Maintained

PME 0.158 0.087 55 Miscellaneous expenditure (0.158 M)

Total: 11.533 10.599 92

47

Page 48: Adp presentation january 2016 (forests)

TOTAL COST 58.735

PERIOD (36 months, 2014-15 to 2016-17)

ALLOCATION OF FUNDS 2015-16 37.740

FUNDS RELEASED 2015-16 18.870

FUNDS UTILIZED 0.684

%AGE UTILIZATION 4%Date of Budget online 1st half: 05.10.2015

(3647) ESTABLISHMENT OF PUNJAB FOREST ACADEMY FOR IN SERVICE AND POST COLLEGE TRAINING

(Rs. in million)

48

Page 49: Adp presentation january 2016 (forests)

 FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Circle Funds Released

Funds utilized

% age Physical Target

Physical Achievement upto

31.01.2016

Director PFRI 18.870 0.684 4

Purchase of car 1000 CC = 1 No. (1.150 M)

Purchase of Desktop Computers = 10 Nos. (1.00 M)Purchase of Laptop = 4 Nos. (0.320 M)Purchase of furniture (5.025 M)Purchase of Digital Camera = 2 No. (0.060 M)Purchase of Multi Media = 3 Nos. (0.450 M)Purchase of UPS = 3 Nos. (0.120 M)Purchase of Generator = 1 No. (0.300 M)Construction of double storey residential building = 1 No. (17.617 M)Renovation of mess building = 1 No. (2.685 M)Providing & Fixing of iron gates with construction of pillars = 3 Nos. (0.750 M)Repair, Maintenance & addition of old sewerage system (1.439 M)Staff component (4.560 M)

Case has been cleared by Austerity CommitteeTender process completed & work order issued with completion date of 24.03.2016

-do--do--do-Tender will be opened on 23.02.2016-do-

Tender process completed & work order issued with completion date of 23.04.2016In process

Total 18.870 0.684 4 49

Page 50: Adp presentation january 2016 (forests)

TOTAL COST 156.795PERIOD (36 months, 2014-15 to 2016-17)

ALLOCATION OF FUNDS 2015-16 57.000

FUNDS RELEASED 2015-16 28.500

FUNDS UTILIZED 23.778

%AGE UTILIZATION 83%Date of Budget online 1st half: 28.08.2015

(3648) REHABILITATION OF EXISTING FOREST PARKS IN PUNJAB

(Rs. in million)

50

Page 51: Adp presentation january 2016 (forests)

 FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Circle Funds Released

Funds utilized % age Physical Target

Physical Achievement upto

31.01.2016

Bahawalpur 6.040 4.936 82

Maint: of park area in LSNP = 75 Ac. (6.525 M)Purchase of Computer = 1 No. (0.100 M)Construction of Forest Huts = 2 Nos. (2.129 M)Provision & Fixing of Bridge = 2 Nos. (0.100 M)Provision of Mechanical Lawn Mower = 1 No. (0.040 M)Provision & fixing of dust bins = 20 Nos. (0.200 M)Provision & fixing of benches = 20 Nos. (0.400 M) Provision & fixing of tuff tiles on walk ways = 2000 Sft. (0.688 M)

Being MaintainedPurchasedWork order issuedWork in ProgressPurchase in ProcessWork in Progress10 Nos. purchased10 Nos. purchasedWork completed

Faisalabad 19.011 17.887 94

Maint: of wooded area in Gatwala park = 20 Ac. (0.640 M)Maint: of park area in Gatwala park = 64 Ac. (5.568 M)Purchase of Tractor = 1 No. (1.000 M)Construction of Forest Huts = 2 Nos. (2.129 M)Provision & Fixing of Bridge = 2 Nos. (0.100 M)Provision & Fixing of Umbrellas = 7 Nos. (0.525 M)Provision of Mechanical Lawn Mower = 1 No. (0.040 M)Construction of slides = 2 Nos. (1.000 M)Establishment of entry point = 4 Nos. (1.600 M)Construction of Picnic Shed = 3 Nos. (0.600 M)Provision & Fixing of signage = 20 Nos. (0.300 M)Provision & fixing of dust bins = 35 Nos. (0.035 M)Provision & fixing of tuff tiles on walk way = 44937 Sft. (7.729 M)Construction of boundary wall with iron grill = 4350 Rft. (12.702 M)Purchase of computer = 1 No. (0.100 Million)

Being MaintainedBeing MaintainedPurchase in Process75% completedFixed at siteWork in ProgressPurchase in ProcessWork in ProgressWork in ProgressWork in ProgressWork in ProgressWork in ProgressWork in Progress

75% completed

Purchased51

Continued next sheet

Page 52: Adp presentation january 2016 (forests)

 FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Circle Funds Released

Funds utilized % age Physical Target

Physical Achievement upto

31.01.2016

Rawalpindi 3.449 0.955 28

Maint: of grassy lawn in Lehri park = 1 Ac. (0.159 M)Maint: of aesthetic plantation = 1 Ac. (0.125 M)Provision & Fixing of Umbrellas = 2 Nos. (0.150 M)Provision & Fixing of signage = 25 Nos. (0.375 M)Remodeling of exiting pond = 2 Nos. (0.800 M)Development of Food court area = 2 Nos. (1.000 M)Provision & Fixing of Bridge = 1 Nos. (0.050 M)Purchase of Computer = 1 No. (0.100 Million)

Being MaintainedBeing Maintained1 No. fixedCompleted

Tendering in process--

Purchased

TOTAL 28.500 23.778 83 Proposed surrender = 0.341 million

52

Page 53: Adp presentation january 2016 (forests)

TOTAL COST 97.656

PERIOD (24 months, 2014-15 to 2015-16)

ALLOCATION OF FUNDS 2015-16 60.000

FUNDS RELEASED 2015-16 30.000

FUNDS UTILIZED 20.419

%AGE UTILIZATION 68%Date of Budget online 1st half: 05.10.2015

(3649) DEVELOPMENT OF RANGE LANDS IN PUNJAB (Rs. in million)

53

Page 54: Adp presentation january 2016 (forests)

 FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Circle Funds Released

Funds utilized

% age Physical Target Physical Achievement

upto 31.01.2016

RM Circle LHR

30.000 20.419 68

Pasture Development = 1150 Ac. (14.900 M)Making of Water spreading Bund = 1800 Nos. (10.066 M)

Soil Conservation = 250 Ac. (2.500 M) Maint: of Pasture Dev = 350 Ac. (1.228 M) Maint: of Dry Aff: = 200 Ac. (0.840 M)Maint: of Water spreading Bund = 1400 Nos. (1.518 M)Desiltation of old Tobas = 56 Nos. (17.927 M) Purchase of Honda Motorcycle 125 CC = 23 Nos. (2.875 M)

Work in progressLayout & Dagh bailing, eradication & Debris collection/ burning, embankment, surface dressing, leveling of seed bed, seed bed preparation & seed growing on 800 Nos. completed.Completed Being maintained Being maintained Being maintained 28 Nos. completedSummary sent to CM for approval

Total 30.000 20.419 68Proposed surrender = 2.680 million

54

Page 55: Adp presentation january 2016 (forests)

TOTAL COST 13.127

PERIOD (24 months, 2014-15 to 2015-16)

ALLOCATION OF FUNDS 2015-16 8.000

FUNDS RELEASED 2015-16 4.000

FUNDS UTILIZED 3.265

%AGE UTILIZATION 82%Date of Budget online 1st half: 27.08.2015

(3650) HUMAN RESOURCE DEVELOPMENT THROUGH RESEARCH AND TRAINING

(Rs. in million)

55

Page 56: Adp presentation january 2016 (forests)

 FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Circle Funds Released

Funds utilized

% age Physical Target Physical Achievement

upto 31.01.2016

PFRI Faisala

bad4.000 3.265 82

Purchase of Fax Machine = 1 No. (0.030 M)Purchase of Laptop = 1 No. (0.100 M)Purchase of computer including printers = 2 Nos. (0.200 M)Purchase of multimedia = 1 No. (0.150 M)Purchase of Power Generator = 1 No. (0.100 M)Purchase of Photo State Machine = 1 No. (0.450 M)Training of officer = 200 Nos. (1.400 M) Training of officials = 1540 Nos. (3.677 M)

Work in progress-Purchased

---

192 No. completed1478 No. completed

Total 4.000 3.265 82Proposed surrender = 0.800 million

56

Page 57: Adp presentation january 2016 (forests)

TOTAL COST 61.999

PERIOD (24 months, 2014-15 to 2015-16)

ALLOCATION OF FUNDS 2015-16 34.100

FUNDS RELEASED 2015-16 17.050

FUNDS UTILIZED 11.451

%AGE UTILIZATION 67%Date of Budget online 1st half: 24.08.2015

(3651) REHABILITATION & RE-SEEDING OF RETRIEVED RANGELAND IN BHAKKAR & LAYYAH DISTRICT

(Rs. in million)

57

Page 58: Adp presentation january 2016 (forests)

 FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Circle Funds Released

Funds utilized

% age Physical Target

Physical Achievement upto

31.01.2016

RM Circle Lahore

17.050 11.451 67

Reseeding of Grasses = 1520 Ac. (11.704 M)

Maint: of Reseeded Area = 1670 Ac. (3.549 M)Boundary Planting = 200 Ac. (7.236 M)

Maint: of Boundary Planting = 200 Ac. (5.127 M)Purchase of Peter Engine = 20 Nos. (0.600 M)Construction of FG Quarter = 1 Nos. (1.902 M)

Preparatory work in Progress Being Maintained Preparatory work over 200 Ac. in progress.Being MaintainedWork in progressWork order issued & work in progress

TOTAL 17.050 11.451 67Proposed surrender = 0.800 million

58

Page 59: Adp presentation january 2016 (forests)

NEWSCHEMES

59

Page 60: Adp presentation january 2016 (forests)

TOTAL COST 51.300

PERIOD (36 months, 2015-16 to 2017-18)

ALLOCATION OF FUNDS 2015-16 10.000

FUNDS RELEASED 2015-16 5.000

FUNDS UTILIZED 5.000

%AGE UTILIZATION 100%Date of Budget online 1st half: 21.10.2015

(3652) AFFORESTATION OF MARGINAL LANDS IN MURREE

(Rs. in million)

60

Page 61: Adp presentation january 2016 (forests)

 FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Circle Funds Released

Funds utilized

% age Physical Target

Physical Achievement upto

31.01.2016

Rawalpindi 5.000 5.000 100

Afforestation = 60 Ac. (9.659 M) Completed

TOTAL 5.000 5.000 100

61

Page 62: Adp presentation january 2016 (forests)

TOTAL COST 180.000

PERIOD (36 months, 2015-16 to 2017-18)

ALLOCATION OF FUNDS 2015-16 20.000

FUNDS RELEASED 2015-16 0.000

FUNDS UTILIZED 0.000

%AGE UTILIZATION 0%Date of Budget online -

(3653) IMPLEMENTATION OF MASTER PLAN FOR JALLO FOREST PARK

(Rs. in million)

62

Page 63: Adp presentation january 2016 (forests)

 FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Circle Funds Released

Funds utilized

% age Physical Target

Physical Achievement upto

31.01.2016

Lahore 0.000 0.000 0

Proposed to be capped

TOTAL 0.000 0.000 0

63

Page 64: Adp presentation january 2016 (forests)

TOTAL COST 94.256

PERIOD (48 months, 2015-16 to 2018-19)

ALLOCATION OF FUNDS 2015-16 40.000

REVISED ALLOCATION 2015-16 32.061

FUNDS RELEASED 2015-16 17.298

FUNDS UTILIZED 14.499

%AGE UTILIZATION 84%Date of Budget online 1st half: 28.10.2015

(3654) IMPLEMENTATION OF MANAGEMENT PLAN IN SOUTHERN ZONE (INAYAT, MACHU & RAJAN SHAH)

(Rs. in million)

64

Page 65: Adp presentation january 2016 (forests)

 FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Circle Funds Released

Funds utilized

% age Physical Target

Physical Achievement upto

31.01.2016

DG Khan 17.298 14.499 84

Afforestation on Flow by Canal Water = 664.60 Ac.(28.711 M)

Construction of Boundary Pillars & their fixing at Machu = 151 Nos.(2.235 M)Purchase of Laptop = 2 Nos. (0.200M)Repair of existing Tractor = 2 Nos. (0.300M)

50 Ac. completed & E.Work on 614 Ac. completed & remaining work in progress

Tender work completedPurchasedWork in progress

Total 17.298 14.499 84

65

Page 66: Adp presentation january 2016 (forests)

TOTAL COST 17.525

PERIOD (36 months, 2015-16 to 2017-18)

ALLOCATION OF FUNDS 2015-16 16.000

REVISED ALLOCATION 2015-16 8.500

FUNDS RELEASED 2015-16 4.250

FUNDS UTILIZED 2.705

%AGE UTILIZATION 64%Date of Budget online 1st half: 22.10.2015

(3655) PROPAGATION AND PROMOTION OF INDIGENOUS FOREST TREE SPECIES TO CONSERVE

BIODIVERSITY (Rs. in million)

66

Page 67: Adp presentation january 2016 (forests)

 FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Circle Funds Released

Funds utilized

% age Physical Target

Physical Achievement upto

31.01.2016

PFRI 4.250 2.705 64

Raising of Plants of indigenous forest tree species in nursery = 3 lac (7.100 M)Purchase of laptop = 1 No. (0.100 M)Purchase of nursery equipment (0.200 M)

Work in progress

Work in progressPurchased

TOTAL 4.250 2.705 64 Proposed surrender = 0.748 million

67

Page 68: Adp presentation january 2016 (forests)

TOTAL COST 85.557

PERIOD (36 months, 2015-16 to 2017-18)

ALLOCATION OF FUNDS 2015-16 40.000

REVISED ALLOCATION 2015-16 40.789

FUNDS RELEASED 2015-16 20.395

FUNDS UTILIZED 11.942

%AGE UTILIZATION 59%Date of Budget online 02.12.2015

(3656) PROMOTION OF SOCIAL FORESTRY (Rs. in million)

68

Page 69: Adp presentation january 2016 (forests)

 FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Circle Funds Released

Funds utilized

% age Physical Target Physical Achievement upto

31.01.2016

Extension 8.553 3.424 40

Raising of plants = 7.50 lac (6.400 M)

Purchase of vehicle Single Cabin 4x2 = 1 No. (2.650 M)Printing of publicity material (Broushers, Sun Shades, Bounties, Stickers, Tech. Posters ect. (1.800 M)

6 lak plants raised

Summary submitted to CM for approval Tenders advertised on 23.12.2015 and will be opened on 01.02.2015

Faisalabad 0.437 0.310 71 Raising of Plants = 2 Lac (1.600 M) P.Bags purchased & remaining work in progress

Gujranwala 1.750 1.148 66 Raising of Plants = 5 Lac (4.000 M) Work in progress

Rawalpindi 1.750 1.396 80 Raising of Plants = 4 Lac (3.200 M) Completed

Sargodha 2.187 1.503 69 Raising of Plants = 4.5 Lac (3.200 M) Completed

Multan 2.625 1.965 75 Raising of Plants = 6 Lac (4.800 M) Completed

Bahawalpur 1.313 0.712 54 Raising of Plants = 3 Lac (2.400 M) P.Bags purchased & punching filling completed

DG Khan 1.750 1.484 85Raising of Plants = 4 Lac (3.200 M) 40000 Plants raised & filling punching

of 2 Lac P.Pags completed & remaining work in progress

CCF PME 0.030 0.015 50 Contingencies

Total 20.395 11.942 59 Proposed surrender = 0.125 million 69

Page 70: Adp presentation january 2016 (forests)

TOTAL COST 168.954

PERIOD (48 months, 2015-16 to 2018-19)

ALLOCATION OF FUNDS 2015-16 48.898REVISED ALLOCATION 2015-16 48.332FUNDS RELEASED 2015-16 24.165

FUNDS UTILIZED 19.196

%AGE UTILIZATION 79%Date of Budget online 1st half: 22.10.2015

(3657) ESTABLISHMENT OF SHORT ROTATION PLANTATION IN PUNJAB (SHORKOT, MLN, BWP &

PAKHOWAL) (Rs. in million)

70

Page 71: Adp presentation january 2016 (forests)

 FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Circle Funds Released

Funds utilized

% age Physical Target Physical Achievement upto

31.01.2016

Lahore 2.702 2.701 100

Afforestation = 100 Ac. (2.160 M)

Raising of Plants = 0.120 million (0.480 M)

Jungle clearance/ debris collection & extraction of muddies on 100 Ac. & E.Work on 75 Ac. completedCompleted

FSD 13.316 11.874 89

Afforestation = 485.490 Ac. (10.486 M)

Raising of Plants = 0.670 million (2.680 M)

Jungle clearance, debris collection, ploughing/ leveling & layout on 270 Ac. completed & E.Work on 72 Ac. in progress.320000 raised & remaining work in progress

SGD 2.889 1.082 37

Afforestation = 111.77 Ac. (2.414 M)

Raising of Plants = 0.100 million (0.400 M)

Jungle clearance, debris collection & its burning on 66 Ac. & ploughing/ levelling & extraction of muddies on 25 Ac. completed & remaining work in progressRaised

Multan 5.258 3.539 67

Afforestation = 200 Ac. (4.320 M)

Raising of Plants = 0.200 million (0.800 M)

Planting on 55 Ac., E.Work on 15 Ac., Jungle clearance on 84 Ac. & levelling ploughing on 40 Ac. completed & remaining work in progress.Completed

Total 24.165 19.196 79 71

Page 72: Adp presentation january 2016 (forests)

TOTAL COST 108.759

PERIOD (48 months, 2015-16 to 2018-19)

ALLOCATION OF FUNDS 2015-16 35.000

REVISED ALLOCATION 2015-16 33.025

FUNDS RELEASED 2015-16 16.512

FUNDS UTILIZED 8.008

%AGE UTILIZATION 48%Date of Budget online 01.12.2015

(3658) IMPLEMENTATION OF MANAGEMENT PLAN IN NORTHERN ZONE (KUNDIAN & BHAKKAR

PLANTATION) (Rs. in million)

72

Page 73: Adp presentation january 2016 (forests)

 FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Circle Funds Released

Funds utilized

% age Physical Target

Physical Achievement upto

31.01.2016

Sargodha 16.512 8.008 48

Afforestation = 454.91 Ac. (21.555 M)

Raising of P.Plants = 0.578 million (4.623 M)Rehabilitation of irrigation system =57237 Rft. (5.408 M)Fixing of Pacca Nakka = 51 Nos. (0.464 M)Purchase of Computer = 5 Nos. (0.375 M)

E.Work on 112 Ac. in progress365226 raised.51085 Rft. Completed

--

TOTAL 16.512 8.008 48

73

Page 74: Adp presentation january 2016 (forests)

TOTAL COST 70.000

PERIOD (36 months, 2015-16 to 2017-18)

ALLOCATION OF FUNDS 2015-16 20.000

FUNDS RELEASED 2015-16 10.000

FUNDS UTILIZED 7.409

%AGE UTILIZATION 74%Date of Budget online 1st half: 28.10.2015

(3659) AFFORESTATION AND SOIL CONSERVATION IN SCRUB FOREST

(Rs. in million)

74

Page 75: Adp presentation january 2016 (forests)

 FINANCIAL ALLOCATION & PHYSICAL ACHIEVEMENTS

Circle Funds Released

Funds utilized

% age Physical Target

Physical Achievement upto

31.01.2016

Rawalpindi 7.444 5.840 78

Afforestation = 300 Ac. (4.050 M)Soil Conservation works = 138 Ac. (2.750 M)

150 Ac completed138 Ac completed

Sargodha 2.556 1.569 61

Afforestation = 100 Ac. (1.350 M)

Soil Conservation works = 50 Ac. (1.000 M)

E.Work on 50 Ac. in progressCompleted

TOTAL 10.000 7.409 74 Proposed surrender = 1.149 million