Studios on Park, Stellenbosch

Student Accommodation using Modular Construction

17 January 2014

Page 2: UWP Consulting studios on park modular contruction

Fig 1: Interior of typical unit

Fig 2: Mock-up in factory

Page 3: UWP Consulting studios on park modular contruction

Fig 3: Delivery of unit

Fig 4: Unloading and stacking of units on site

Page 4: UWP Consulting studios on park modular contruction

Fig 5.1: Alignment and placement of pods

Fig 5.2: Alignment and placement of pods

Page 5: UWP Consulting studios on park modular contruction

Fig 6: Roof structure over

Fig 7: Typical elevation

Page 6: UWP Consulting studios on park modular contruction

Facts and figures

• Site handover on 15 August 2013 • Completion February 2014 • 62 units; 27m2 per unit • Maximum stack height on project: 4 storeys • Three storeys stacked onto concrete transfer slab over parking basement • Concrete walkways cast onto Bondek on structural steel cross beams

connected to pod frames • Structural steel staircases • Structural steel roof and gable end side cladding “clipped” onto pod frames • All structural aspects – including pod frame designed by UWP Consulting