Upload
i-made-wiratha-nungrat
View
1.249
Download
5
Embed Size (px)
Citation preview
SOLAR PV ASSEMBLY PROCESS FLOWManufacturing processes of conventional PV module
Author I Made Wiratha N. (PV Technologist)
SOLAR PANEL ANATOMY Front & Rear
2
Solar Cell
Ribbon
Frame
Locking Mechanism
Mounting Hole + Ground Backsheet
Junction Box/Electrical Contact Point
Cable
3
SOLAR PANEL ANATOMY Module Sandwich
Aluminum Frame
String Ribbon
Bus Bars
SOLAR PANEL ANATOMY Structure
Stringing Process
Lay Up Process
• Panel dimension: 1650mm x 992mm• Cell count per panel: 60 cells (6 x 10)• Output: 4.23 watt/cell• Panel overall output: 250 watt
5
SOLAR PANEL Technical Spec
7
PROCESS FLOW
8
PROCESS FLOW Glass Preparation
Tempered Glass Stack
Glass Loading Conveyor
Bidirectional Conveyor
Manual Loading
Upper EVA Lay Up
The cleaning agent is H2O and it has vapor chamber to dry the
clean glass.
If glass washing machine is out of
action, we proceed with plan B, manual
indeed .
Ethylene-Vinyl Acetate (EVA)
Stack)
This is the second layer after glass. We
put EVA on top of clean glass
Glass Washing Machine(55-90 glass/hour)
9
X-Cell Stringer MachineCell
MagaineLoading
Glass Queue Conveyor & String Lay Up
Operator load the magazine with cells, the X2P machine integrate the cell into string using soldered ribbon (10
cells per string).
The GL30 lay-up robot then picks the string, measure and lay them up onto the
queued glass + EVA 1.
Ribbons on each string is connected together using bus bar forming solar module
Ethylene-Vinyl Acetate (EVA)
Stack
Robotic Lay-Up
Machine
3 Bussing Station (<2.5 minutes/panel)
Backsheet Stack
Glass queue
Five layers: Glass, EVA, Cells, EVA,
Backsheet
PROCESS FLOW Stringing Cells
Centering Station
Stringer is the most complicated machine and has a lot of parts. Stringer peak throughput is 1400 cells/hour, and it average
1200 cells/hour
10
Diffluence Conveyor
Reject Defect Module
Rotating Station
Bidirectional Conveyor
PROCESS FLOW Electroluminescence Test
Computer for EL Test
EL Test for any defect such as chipping, cracks, micro
cracks and bad interconnection.
If some module messed up in the chamber, then the
panel will be kicked out from the race. The defected
module will go to rework station.
Electroluminescence Test Chamber
Then the line is split into two
thread for faster
process
LAMINATOR 1
LAMINATOR 2
If electrical current flowing through the circuit, the cell will go reverse bias mode
and emit near-infrared wave then camera with special
filter will capture the image.
11
Bidirectional Conveyor
Loader to Laminator
Bidirectional Conveyor
Unloader to Laminator
Bidirectional Conveyor
Bidirectional Conveyor
LAMINATOR 2
The module will be encapsulated under near-vacuum condition at certain
temperature. All the layers will be fused together and form solid panel which can withstand over 25 years of weathering.
LAMINATOR 1
LINE 1
LINE 2
Three important parameters: Temp, Pressure, Time (T-P-t).
Fine tuned this parameter will maximize the module quality. this The maximum capacity of laminator is 12 panels/hour.
PROCESS FLOW Lamination
12
Visual Inspection Bidirectional Conveyor
Reject Defect Module
In this station, visual inspection is conducted by
QA/QC team before the panel encapsulated in metal frame
at the framing station.
Rotate & Trimming
After lamination there are excess of material on the panel’s edges need to be remove by manual
cutting using special knife.
Visual Inspection
If defect or imperfection is spotted, the panel will go to the
reject tray. It is up to the QA engineer to determine whether
the panel will be ditch or still usable with special
circumstances
Visual Inspection means “eyeballing” the panel. QA/QC team will decide if defected panel will be
passed or not
PROCESS FLOW Trimming & Visual Inspection
13
Framing Junction Box Assembly
Glue Dispenser for Frame
Silicon glue is added to the frame before it attached to
the panelGlue
Dispenser for J-Box
Pre-FramingFraming Cleaning & Corner
Chamfering
CURING
The duration of curing process is about 6
hours. This is intended to make sure that every
glue is firmly stick
Junction Box Assembly
The module and the frame pressed by hydraulic
cylinder to guarantee the perfect rectangle shape of
the module
PROCESS FLOW Framing & J-Box AssemblyInside J-Box there are several diodes to by-pass dead string
prevent the module from total shut down.
14
Cleaning Conveyor
Insulation & Hi-Voltage Test
I-V Characteristics Test/Sun Simulator
Electroluminescence Test 2 Chamber
Computer for I-V Test
Computer for EL Test
Before module get tested, its surface must
be clean out. The cleaning agent for this
process is Isopropyl Alcohol (IPA).
This test is intended to check the
isolation, conductor, build and assembly quality of the panel.
Current & Voltage output
characteristic will be tested on this station using sun
simulator
Sun simulator is calibrated so that the
irradiance of the flash is analogous to the Sun
which is 1000 watt/m2
Sun Simulator
Charge Source
PROCESS FLOW Final Product Test
Hi-Pot Test is technically application of high voltage to stress the
insulation beyond what it will encounter during normal operation.
15
Cartesian Robot Sorting
FINISH GOODLabelling
After several test, solar module is given their output parameter based on previous measurement such as I-V characteristic and power rated.
Centering Station
Cartesian robot sorting distributes the finish good to the proper
position and awaits for the packaging and
shipping.
PROCESS FLOW Goods ManagementSorter machine classifies modules into different bins such as grade A,
B, C based on the test data and module grading agreement.
Thank You
16
For more information please send inquiry to:
Email: [email protected]: +62 856 9213 7616