26
Sheath Bonding Method in Underground cables Ahmed Adel - Project Manager (Brugg Cables) Introduction Now days, the underground cables became the fastest solution for electric transmission in urban areas or crowded cities when the overhead transmission line can’t be installed. In the 21 centauries, The HV cables industry in the world wide had taken a lead in the commercial market offering a reasonable cable prices with the suitable HV accessories and proper earthing methods. HV companies had proven through years their ability to compete against each other with a longer life XLPE cables and high quality cable accessories. Before designing HV cable, many aspects should be taken into consideration like: Cable voltage, short circuit calculation, cable ampacity many questions should be asked like: cable laid in trench or buried in sand? Cable length? Is there any cable sections? What is the earthing method used...? Cable grounding is a very important aspect, without it, induced voltage will be generated in the cable sheath causing over heat and leading to decrease the cable ampacity. To overcome this issue, a lot of grounding methods had been implemented just to choose the proper one to be compatible with the installed cable system.

Sheath bonding method for underground cables

Embed Size (px)

Citation preview

Page 1: Sheath bonding method for underground cables

Sheath Bonding Method in Underground cables

Ahmed Adel - Project Manager (Brugg Cables)

Introduction

Now days, the underground cables became the fastest solution for electric

transmission in urban areas or crowded cities when the overhead transmission

line can’t be installed. In the 21 centauries, The HV cables industry in the world

wide had taken a lead in the commercial market offering a reasonable cable

prices with the suitable HV accessories and proper earthing methods. HV

companies had proven through years their ability to compete against each other

with a longer life XLPE cables and high quality cable accessories.

Before designing HV cable, many aspects should be taken into consideration

like: Cable voltage, short circuit calculation, cable ampacity many questions

should be asked like: cable laid in trench or buried in sand? Cable length? Is

there any cable sections? What is the earthing method used...?

Cable grounding is a very important aspect, without it, induced voltage will be

generated in the cable sheath causing over heat and leading to decrease the

cable ampacity. To overcome this issue, a lot of grounding methods had been

implemented just to choose the proper one to be compatible with the installed

cable system.

Page 2: Sheath bonding method for underground cables

1. Cable components

Fig (1)

Shown in Fig (1):

- The main conductor which is responsible for current transferring could be

stranded or segmented depending on the conductor cross section.

- The conductor screen is a semiconducting screen to achieve homogeneous

field within insulation.

- The insulation is XLPE (cross-linked poly ethylene) with dielectric properties

surrounding the cable conductor, the surface of the insulation should be clean

from any dust or voids which can cause partial discharge leading to complete

breakdown.

- The insulation screen is a semiconductor screen to achieve homogenous

electric field within insulation.

- The metallic screen is the moisture barrier and provides the main grounding for

the cable against short circuit current in case of faults or the capacitive charging

current.

Page 3: Sheath bonding method for underground cables

Sheath type Moisture Protection

Mechanical protection

Corrosion Protection

Diameter Costs

Lead Sheath Excellent Good Excellent + ==

Lead Sheath & copper wires

Excellent Good Excellent

+ =

CU corrugated Sheath

good Excellent Good o =

AL corrugated Sheath

good Good Good o o

Cu wires & laminated Sheath

fair Fair Good ++ o

Al wires & laminated Sheath

fair Fair Good ++ +

Table (1)

- Outer protective jacket is the mechanical protection for the metallic sheath and

anticorrosion layer, usually it consist of polymeric material PE (Polyethylene) or

PVC (poly vinyl chloride).

2. Faradays law

According to the basic theory of faradays law in fig(2) that: if an AC current flow

in any wire it will produce magnetic field which rotates around the wire and the

rate of change of the magnetic field will induce voltage generating electric

current, if there is a path, flows in the opposite direction of the main current.

Page 4: Sheath bonding method for underground cables

Fig (2)

In case of the high voltage cable in fig (3), the cable conductor are surrounded by

insulation and metallic sheath, when the current flow in the main conductor the

produced magnetic field will induce voltage on the metallic sheath and if the

sheath is grounded from both ends a circulating current will start to flow which is

will affect the cable ampacity and can cause harm to personal maintenances

Fig (3)

Page 5: Sheath bonding method for underground cables

3. Sheath losses

Applying faradays law on the high voltage cable, we will find that the sheath of

the cable acts as a secondary of a transformer; where the current in the

conductor induces voltage in the sheath.

The induced voltage depends on:

- The mutual inductance between core & sheath

- The conductor current

- The length of the cable

Assuming there is no proper grounding method for the cable, the induced e.m.f

will generate two types of losses: circulating current losses (λ1’) and eddy

current losses (λ1’’), so the total losses in cable metallic sheath:

λ 1 = λ 1’ + λ 1’’

3.1 The eddy current (λ 1’’):

Is generated on similar principle of skin and proximity effect; i.e. they are induced

by the conductor current, sheath circulating current and by current circulating in

close proximity current carrying conductor.

The induced voltage is maximum in the internal side of the sheath and minimum in its external side. This situation induces the circulation of eddy currents in the sheath as shown in fig (4).

Page 6: Sheath bonding method for underground cables

Fig (4)

The eddy currents are generally of smaller magnitude when comparing with

circulating currents of solidly bonded cable sheaths and may be neglected in

case of large segmental conductors.

3.2 Circulating current (λ 1’):

Is generated when the cable sheath is forming a closed loop and grounded from

either ends or intermediate points along the cable route fig (5).

Page 7: Sheath bonding method for underground cables

Fig 5

The value of the circulating current can be determined by the magnitude of

current in cable conductor, frequency, mean diameter, the resistance of cable

sheath and the distance between single-core cables; i.e. the mutual inductance.

As a consequence the calculation of the circulating current and the induced

voltage is done by using specialized computer program (Power cable current

Analyzer).

4. Sheath losses effect

According to IEC 287, the permissible current of an AC cable is written as Equation in buried cables where drying out of the soil does not occur on cables installed in the air

Page 8: Sheath bonding method for underground cables

- Δθ: permissible temperature rise of conductor above ambient temperature.

- Wd: dielectric losses per unit length per phase.

- n: number of conductors in a cable.

- λ1,λ2: ratio of the total losses in metallic sheaths and armour respectively to the total conductor losses.

- R: alternating current resistance of conductor at its maximum operating

temperature.

- T1: thermal resistance per core between conductor and sheath.

- T2: thermal resistance of between conductor and cable armour.

- T3: thermal resistance of external serving

- T4: thermal resistance of surrounding medium.

By computing Δθ which is the conductor maximum temperature rises above the ambient temperature:

Δθ = (I²R + ½ Wd) T1 + [I²R (1 + λ1) + Wd] nT2 + [I²R (1+ λ1 + λ2) + Wd) n (T3 +T4)

However in the case of a simplified cable circuit consisting of single-core cables (n=1) provided with metallic sheath and no metallic armour (λ2 = 0 and T2 =0) and ignoring the environmental thermal resistance (T4) the temperature rise between conductor and cable outer surface is given with the following equation:

Page 9: Sheath bonding method for underground cables

Δθ = I²R [T1+ T3 (1 + λ1)] + Wd (½T1 +T3) From the above relation its clear that λ1 (losses generated due to circulating

current) is increasing the temperature rise which will reduce the cable ampacity.

as shown in fig (6) the relation between sheath current and the temperature rise

affecting the cable permissible current.

Fig (6)

Therefore, the sheath circulating current must be reduced for the increment of transmission capacity. In addition, the high sheath current has an effect on individuals and may cause the fault by the breakdown of insulation.

Page 10: Sheath bonding method for underground cables

4. Sheath bonding methods

Various methods of bonding may be used for the purpose of minimizing sheath

losses. Formerly, where special bonding was employed for the prevention of

sheath losses on lead-sheathed cables without an insulating jacket, the sheaths

were subjected to ac voltages, and the bonding was designed to keep the

magnitude of the induced voltages within small limits so as to prevent the

possibility of sheath corrosion due to ac electrolysis.

Any sheath bonding or grounding method must perform the following functions:

(1) Reduce or eliminate the sheath losses

(2) Limit sheath voltages as required by the sheath sectionalizing joints.

(3) Maintain a continuous sheath circuit to permit fault-current return, and

adequate lighting and switching surge protection

4.1. Both ends bonding

- The metallic sheaths are grounded at least at the two extremes of the cable.

- This system doesn’t allow high values of the induced voltages in the metallic

sheaths. When dealing with both ends bonding cables, sheath circulating current

loss occurs because there is a closed circuit current.

- This type is applied for MV and LV cable system with short distance.

Page 11: Sheath bonding method for underground cables

Fig (7)

Advantage:

- The two cable ends are directly connected to earth with no sheath voltage

limiter

- No need for parallel continuity earthing cable

- No stand voltage at the end of the cable

Fig (8)

Disadvantage:

- Establishing a closed circuit for the induced current causing over heat and

consequent reduction in the cable ampacity as discussed before.

Page 12: Sheath bonding method for underground cables

Recommended:

In order to minimize the losses caused by both ends bonding, cables

should be laid in a trefoil formation and a proper balance of cable spacing for

good heat dissipation.

4.2. Single point bonding

- The simplest form of special bonding consists in arranging for the sheaths of the

three cables to be connected and grounded at one point only along their length.

- At all other points, a voltage will appear from sheath to ground that will be a

maximum at the farthest point from the ground bond. The sheaths must therefore

be adequately insulated from ground. Since there is no closed sheath circuit,

except through the sheath voltage limiter (if any), current does not normally flow

longitudinally along the sheaths and no sheath circulating current loss occurs

(sheath eddy loss will still be present) shown in fig (9).

Fig (9)

Page 13: Sheath bonding method for underground cables

Types of single point bonding

- Types are divided according to cable length in fig (10), if the cable length is less

than 500 m or one drum length then one side bonding is applied, but if the cable

length is from 300m to 1000m long cable section then split bonded system is

applied.

Fig (10)

Advantage:

- The ampacity is higher compared with both sides bonding, as there are practically no circulating current in cable sheath.

Disadvantage: -

- As the screen is open, there are no circulating currents, but there is an induced voltage appearing at the open cable screen, where sheath voltage limiters must be installed in order to protect the cable outer jacket against transient overvoltage.

Page 14: Sheath bonding method for underground cables

- The length of one section is limited as the magnitude of the induced voltage is

increasing with length.

Recommended

- During a ground fault on the power system, the zero-sequence current carried by

the cable conductors could return by whatever external paths are available. A

ground fault in the immediate vicinity of the cable can cause a large difference in

ground potential rise between the two ends of the cable system, posing hazards

to personnel and equipment.

- For this reason, single-point bonded cable installations need a parallel ground

conductor, grounded at both ends of the cable route and installed very close to

the cable conductors, to carry the fault current during ground faults and to limit

the voltage rise of the sheath during ground faults to an acceptable level.

Fig (11)

Page 15: Sheath bonding method for underground cables

- The parallel ground continuity conductor (PGCC) is usually insulated to avoid

corrosion and transposed, if the cables are not transposed, to avoid circulating

currents and losses during normal operating conditions.

- The sheath voltage reduction rate of transposed PGCC is compared with no

transposed PGCC. As shown in Fig. 11, the effect of transposed PGCC is better

than no transposed PGCC. The average reduction rate in the sheath voltage of

transposed PGCC is 70.8 %, about 8.7 % better than no transposed PGCC.

Consequently, the difference is not big compared with duct formation or directly

buried formation because the spacing between phase conductors is closer than

duct or directly buried formation fig (12).

Fig (12)

Page 16: Sheath bonding method for underground cables

5. Cross-bonding method

- For underground circuits, longer than 1 km, the losses on the metallic sheaths

can be minimized making in each joint a cross bonding of the cable shields.

- The most basic form of cross bonding consists of sectionalizing the cable into

three minor sections of equal length and cross connecting the sheaths between

each two-minor section. Three minor cable sections form a major section fig (13).

- The natural points to establish the crossings are the joints, where appropriate

cross bonding boxes connected to the sheaths, these boxes include SVL. This

method provides balanced induced voltages at a vectorial angle of 120°of no

resultant circulating current when phasorial summation was applied.

Fig (13)

Page 17: Sheath bonding method for underground cables

5.1. Laying formation:

5.1.1 Flat formation

a) Un Transposed:

If the single-core cables are installed in flat formation un transposed the

voltages induced in the cable sheaths of outer cables are higher than the

induced voltage in the middle cable and the vectorial (phasor) summation is

not zero fig (14). As a consequence, it is not possible to eliminate the

circulating currents in a cable circuit where only the cable sheaths are cross-

bonded. The imbalanced phasorial voltage is generating a residual voltage

which, in return would generate circulating currents.

Ub (smaller induced voltage leading to imbalance)

Uc

Ua

Fig (14)

Page 18: Sheath bonding method for underground cables

b) Transposed: When the cable sheaths of transposed cables occupying the same position in circuit configuration are straight connected, the vectorial summation of induced voltage would be zero if the system would be of balanced parameters: currents, spacing and length.

Fig (15)

- By connecting in series the cable sheath of the three phases (120° phasor displacement) the circulating currents could be eliminated; the phasor sum of induced voltages could be zero if the geometrical data of cable circuit is uniform along the three cable sections as fig (16). Uc Ub Ua Fig (16)

Page 19: Sheath bonding method for underground cables

- So, it is obvious that in order to significantly reduce or to eliminate the circulating current losses the cable and cable sheaths must be transposed at every joint bay position and the sheaths cross-connected with phase rotation in opposition to that of cable transposition.

- The maximum induced voltage in respect to earth depends on the position of

each minor transposition section within the major transposition section. At the

ends of major transposition sections the cable sheaths are at earth potential as

shown in fig (17) ,while at all other points along the cable the voltage is

proportional to cable length in respect to earthing points or, for the median (2nd)

minor section, of measuring point in respect to the other two minor sections.

Fig (17)

5.1.2. Trefoil formation

- When the cables are laid in trefoil formation, the induced voltage in the sheath of

the three cables is similar so the cross-bonding method will be applied like the

flat type system with transposition. As in fig (17).

Page 20: Sheath bonding method for underground cables

5.2. CROSS BONDING COMPONENTS

To a cross bonding system implementation the following equipments are applied:

a) Cross bonding boxes to execute the crossing of the sheaths. These boxes include SVL and each box should have an earth electrode itself for create an earth return circuit in each divided section of the line. These boxes should be watertight and capable of containing the effects of the thermal or electrical failures of any element inside the box, including a possible internal short circuit.

To facilitate its maintenance, these boxes should be installed in joints boxes with easy access (for example through the placement of manholes) and they should not be at more than one meter below the ground level [3].

b) Direct bonding boxes to connect the sheath directly to earth. These boxes include earth electrode but, unlike cross bonding boxes, they do not include SVL.

c) Kits for shield interruption: it is necessary for each phase joint to introduce an additional kit to remove the shield outside the respective box and to connect a concentric cable.

d) Cables to the sheaths connection to cross bonding boxes: should be coaxial cables insulated with XLPE (cross linked polyethylene) or flexible monopole conductors. The section of these cables is determined by the maximum value of short circuit current of the power line. Thus, the monopole conductors are directly connected to the cross bonding boxes. The sheaths connections should be designed to minimize the cable length, which should not exceed the 10 meters

5.3. Un balanced Conditions

In cross-bonded cable system, there are so many unbalanced conditions. These unbalanced condition cause circulating current along the metallic sheath. Various unbalanced conditions are considered:

- Length of minor sections - Mixed cable arrangement in same major section - Multiple circuits - earthing resistance - etc

Page 21: Sheath bonding method for underground cables

5.3.1 Correlation of the sheath current and length imbalance

We consider unified burying formation, which is constructed by the same formation as trefoil or duct. When the cables in each minor section have the same length, the cables are referred to balance and the length imbalance rate is zero. In trefoil and duct formation like Fig 18. Supposing the normal length of the cable is 300 meters, and the lengths of the cables in the first minor section are changing, then the imbalance rate of the system and the sheath circulating currents are indicated in Fig 19.

Fig 19

Page 22: Sheath bonding method for underground cables

Fig 20

The current marked with square represent the cable in trefoil formation and the

other is the duct formation:

- Its obvious that the circulating current are nearly the same in the both formation.

- The circulating current reaches Zero when all the minor sections are equal in

length which means balanced system.

- The change in length of the minor section affect the circulating current leading to

un balanced conditions.

5.4 Scenarios of Cross-bonding:

The basic form of the cross-bonding system is each major section consists of

3 minor section equal in length, and between the three minors sections the

sheath is connected to a sheath voltage limiter and earthed at the beginning

and at the end of the major section.

It is not generally possible to divide the route length into exactly matched

minor section lengths, nor is it always possible to maintain a constant spacing

of the cables throughout the route, Due to the different site situations, other

scenarios had been applied to the cross-bonding achieving the same results,

and reducing the induced sheath voltage as well.

Page 23: Sheath bonding method for underground cables

5.4.1 Modified Cross-bonding:

In this modified version of the sectionalized cross-bonding system, it is not necessary to have the number of minor sections exactly divisible by three. Balanced voltage conditions within a given major section consisting of four minor sections can be achieved by subdividing one minor section into two subsections, as follows:

(1) One short length (or subsection) followed by two equal lengths (or minor sections) with another short length (or subsection) completing the major section; the combined length of the two subsections should be equal to the length of one minor section as shown

Fig 21

(2) One short length (or subsection) followed by one longer length (or minor section) then another short length (or subsection) followed by one longer length (or minor section) to complete the major section; the two longer lengths (or minor sections) should be equal and the combined length of the two subsections should be equal to the length of one minor section as shown on Fig 22. In this case, the first cross bonding must be reversed

Page 24: Sheath bonding method for underground cables

Fig 22

5.4.2 Continuous Cross Bonding.

In this system the sheaths are cross bonded at the end of each minor section throughout the whole cable route. The three sheaths are bonded and grounded at the two ends of the route only, as shown in Fig 23. It is again generally desirable that the cables are transposed so that each conductor occupies each of the three positions for one third of the total length. The number of matched minor sections should preferably be exactly divisible by three, but this becomes less important as the total number of minor sections increases. Its preferable to apply this system when there is large number of minor sections with unequal lengths.

Page 25: Sheath bonding method for underground cables

5.4.3 Mixed Systems.

When the number of minor sections is not exactly divisible by three, the system may consist of a mixture of (regular or modified) cross-bonded system and single-point bonded lengths. When necessary, on account of a large number of minor sections having unequal lengths, the cross bonding may be of the continuous type. Figure 24 shows the arrangement of a final single point bonded length at the end of a cross-bonded system.

Fig 24

References:

[1] IEC 287-1-1: “Electric cables-calculation of the current rating, part 1: current rating equations (100%

load factor) and calculation of losses, section 1: general”. IEC publication 287, 1994.

[2] ANSI/IEEE Std 575-1 988, IEEE Guide for the Application of Sheath-Bonding Methods for Single

Conductor Cables and the Calculation of Induced Voltages and Currents in Cable Sheaths.

[3] J.S. Barrett, G.J.Anders. “Circulating current and hysteresis losses in screens, sheaths and armour of

electric power cables-mathematical models and comparison with IEC Standard 287”. IEE Proc.-Sei.

Meas. Technol., Vol. 144, No. 3, pp. 101-110, May 1997

[4] Peter Graneau. “Underground power transmission. The science, technology & economics of high

voltage cables”. Ed. John Wiley & Sons, 1979.

[5] Manuel Llorente Antón. “Cables eléctricos aislados. Descripción y aplicaciones practices”. Editorial

Paraninfo, 1994..

Page 26: Sheath bonding method for underground cables

[6] Víctor Sierra Madrigal, Alfonso Sansores Escalante. “Manual técnico de cables de energía”. Ed. Mc

Graw Hill, 2ª Edición, 1984

[7] Enrique Ras. “Teoría de líneas eléctricas”. Ed. Marcombo 1986

[8] Jordi-Roger Riba, Xavier Alabern. “Experimental behavior of a magneticfield shield for an underground

power line”. Internacional Conference on Renewable Energy and Power Quality. Zaragoza, 2005.