New Challenge -تحدى جديد Hotel Management convert 4 Floors (43rd-46th) from standard Guestrooms to Restaurants which create a demand for 210TR extra to cool the extra Heat Load.
The Challenge is How to provide this extra load in existing building?
Where to locate the new Compressors?
From where to power these extra units?
How to per the extra work, space, cost & fees?
Static Pressure is Monitored and Maintained at Fixed Level
Fixed Static
Pressure
Dynamic Pressure is Monitored and Maintained at Fixed Level
Self Balancing Dynamic Pressure