28
PLANNING, DESIGN AND ESTIMATION OF ROAD SIDE DRAINAGE SYSTEM by : SANJAY JATARIA TABLE OF CONTENTS ACKNOWLEDGEMENT DECLARATION ABSTRACT CHAPTER ONE 1.0 INTRODUCTION 1.1 Type of road 1.2 Problem statement 1.3 Objectives 1.4.1 Main objective 1.4.2 Specific Objectives 1.4.3 Scope of the project 1.4.4 Significant of the project 1.5 Summary of Methodology CHAPTER TWO 2.0 LITERATURE REVIEW 2.1 Surface drainage 2.2 Collection of surface water 2.3 Classification of side drainage 2.4 Sub surface drainage 2.5 Cross drainage 2.6 Requirement of Highway drainage system

planning, design and estimation of road side drainage system

Embed Size (px)

Citation preview

Page 1: planning, design and estimation of road side drainage system

PLANNING, DESIGN AND ESTIMATION OF ROAD SIDE DRAINAGE SYSTEM

by : SANJAY JATARIA

TABLE OF CONTENTS ACKNOWLEDGEMENTDECLARATIONABSTRACTCHAPTER ONE1.0 INTRODUCTION1.1 Type of road1.2 Problem statement1.3 Objectives1.4.1 Main objective1.4.2 Specific Objectives 1.4.3 Scope of the project1.4.4 Significant of the project1.5 Summary of MethodologyCHAPTER TWO2.0 LITERATURE REVIEW 2.1 Surface drainage2.2 Collection of surface water2.3 Classification of side drainage2.4 Sub surface drainage2.5 Cross drainage2.6 Requirement of Highway drainage system

Page 2: planning, design and estimation of road side drainage system

2.7 Design of surface drainage system2.8 Hydrological analysis2.9 Hydraulic designCHAPTER THREE3.0 Data presentation and analysis3.1 Rainfall data3.2 Surface run off coefficient3.2.1 Peak flow CHAPTER FOUR3.4 Rectangular section3.4.1 Required section3.4.2 Longitudinal slope3.5 Trapezoidal section3.5.1 Required section3.5.2 Longitudinal slope3.6 Comparison3.7 Conclusion5.0 Recommendation5.1 References

DECLARATION

Page 3: planning, design and estimation of road side drainage system

I, Sanjay Jataria student of B. Tech (Civil Engineering), seven semester batch 2012-2016, hereby declare that the major project report entitled “Planning and Design of Road Side Drainage System” which is submitted by us to the Department of Civil Engineering, ABES ENGINEERING COLLGE, GHAZIABAD for partial fulfilment of seven and eight semester minor and major project report. This is a comprehensive report based on analysis and study carried out during minor and major period.

PLACE: BHOPAL NAME:

DATE: SANJAY JATARIA

CERTIFICATE

On the basis of declaration submitted by Sanjay Jataria students of B. Tech Civil , seven and eight semester, batch 2012-2016, I hereby certify that the Major Project report entitled “PLANNING, DESIGN AND ESTIMATION OF ROAD SIDE DRAINAGE SYSTEM” which is submitted to the Department of Civil Engineering, ABES ENGINEERING COLLEGE, GHAZIABAD for partial fulfilment of the requirement for the award of the degree of Bachelor of Technology in Civil, is an original contribution with existing knowledge and faithful record of work carried out by him/them under my guidance and supervision.To the best of my knowledge this work has not been submitted in part or full for any Degree or Diploma to this University or elsewhere.

Page 4: planning, design and estimation of road side drainage system

Place: GHAZIABAD Date: 11/05/2015 Head of Department Department of civil engineering ABES ENGINEERING COLLEGE

ACKNOWLEDGEMENT

WE consider ourself privileged to express deep sense of gratitude to my faculty guide Mr.Ayush Kumar for his admirable and valuable guidance, keen interest, encouragement and constructive suggestions during the course of the project. WE would like to express our hearty gratitude Head of Department of Civil Engineering, without his insightful guidance and help, we could not have completed this work.

We would also like to thank our family and friends who have been our strength all throughout. Lastly, we thank our God for helping us to complete our report without any difficulties.

INTRODUCTION

Drainage is the process of interception and removal of water from over, and under the vicinity of the road surface. Drainage can be surface (where water is conveyed on the road surface and drainage channels),

Page 5: planning, design and estimation of road side drainage system

or subsurface (water flows underneath the pavement structure). Surface and subsurface drainage of roads critically affects their structural integrity, life and safety to users, and is thus important during highway design and construction. Road designs therefore have to provide efficient means for removal of this water; hence the need for road drainage designs. Drainage facilities are required to protect the road against damage from surface and sub surface water. Traffic safety is also important as poor drainage can result in dangerous conditions like hydroplaning. Poor drainage can also compromise the structural integrity and life of a pavement. Drainage systems combine various natural and man made facilities e.g. ditches, pipes, culverts, curbs to convey this water safely.

1.2 Type of Road:FREEWAYS:

Freeways have strict classification rules. • Multi-Lane, divided road • No cross traffic. • No stop lights (except for ramp meters). • No stop signs. • No parking. • No stopping (except for toll booths, freeway access metering) • Highest speed limits. (relative to region) • Some have minimum speed limits. • Limited access

MAJAOR HIGHWAYS:

Purposely built as a major throughway. • Higher speeds. Speed limits should be near or equal to Interstate

Page 6: planning, design and estimation of road side drainage system

or Freeway speed limits in the same area. (typically within 10-20 Kmph)

• Multiple lanes in each direction. • Separated directions of travel. • Turning traffic is typically limited to specified turn lanes or freeway

style ramps to minimize obstructions to thru traffic. • Partially limited access with few minor streets intersecting with

this road. Intersections are most often with primary roads or other highways.

MINOR HIGHWAYS:

Minor Highways vary widely from large multi-lane roads with stoplights and higher speed limits, to small residential streets with stops signs. Some minor highways may zigzag thru an area with many turns on local streets. A Minor Highway thru the main street of a small town often retains focus on local access with pedestrian traffic and on street parking.

1.3 Problem Statement

According to this problem of lacking side drainage along this road, the soil surrounding the ATC fence has been eroded by the water flowing during the rain, also because the water during the rain is passing on the road, potholes has occurred on top of this road. Therefore a drainage system has to be designed. However, the existing road along this street is showing signs of failure, caused mainly by lacking of drainage. Also it is better to have good method of designing a side drainage in order to overcome these problems arises on this road. 1.4 Objectives 1.4.1 Main objective: Design of an efficient drainage system along the road.

Page 7: planning, design and estimation of road side drainage system

1.4.2 Specific Objectives:

• To determine the catchment area and the expected flow.

• To collect design information for drainage system.

• To determination of runoff onto the road and discharge of water.

• To design of the drainage channels using results obtained.

1.4.3 Scop of the project: This project is confined only to designing a drainage system for the road along this road.

1.5 Significance of the project:The outcome of this project shall help to propose the lay out for the new side drainage in order to fulfill its requirements as a drainage, such as to drain off excess water on shoulder and pavement edge which cause considerable damage and improve pedestrian safety using side walk ways near side drainage.

Methodology:

• Site visiting

• Visiting web sites and Internet

• Literature review

• Questionnaire method

• Photographing

• Leveling

Page 8: planning, design and estimation of road side drainage system

2.0 LITERATURE REVIEW 2.1 Introduction

Highway drainage is the process of interception and removal of water from over, under and in the vicinity of the pavement. Highway drainage is one of the most important factors in road design and construction. If every other aspect of the highway design and construction is done well but drainage is not, the road will quickly fail in use due to ingress of water into the pavement and its base. The damaging effects of water in the pavement can be controlled by keeping water out of places where it can cause damage or by rapidly and safely removing it by drainage methods. Improper drainage of roads can lead to;

• Loss of strength of pavement materials

• Hydroplaning

• Mud pumping in rigid pavement

• Stripping of the bituminous s surface in flexible pavementsTypes of drainage There are basically three types of drainage applied to highways that ;

• Subsurface drainage

• Surface drainage

• Cross drainageSUBSURFACE DRAINAGE Subsurface drainage is concerned with the interception and removal of water from within the pavement. Some of the sources of subsurface water include; infiltration through surface cracks, capillary rise from lower layers, seepage from the sides of the pavement to mention but a few.

Page 9: planning, design and estimation of road side drainage system

Application of side slopes on the road surface, installing of drainage beds in the pavement and use of transverse drains are some of the measures of effecting subsurface drainage.SURFACE DRAINAGE Surface drainage deals with arrangements for quickly and effectively leading away the water that collects on the surface of the pavement, shoulders, slopes of embankments, cuts and the land adjoining the highway. The main source of surface water in most places is precipitation in form of rain. When precipitation falls on an area, some of the water infiltrates in to the ground while a considerable amount remains on top of the surface as surface run off.MEASURES ADOPTED FOR SURFACE DRAINAGE

• The proper cross slope should be provided for both to pavement and shoulders

• The subgrade should be sufficiently above the highest level of ground water table or the natural ground level

• Side drainage should have to be provided at edges of right-of-way where the road is in embankment and the edge of the roadway in cutting

• On hill roads, water may flow towards the road depending on the slope and rainfall

• Catch water drains should be provided to intercept the flow down.

COLLECTION OF SURFACE WATERThe water collected is lead into natural channels or artificial channels so that it does not interfere with the proper functioning of any part of the highway.Surface drainage must be provided to drain the precipitation away from the pavement structure. CLASSIFICATIONOF SIDE DRAINAGE

Page 10: planning, design and estimation of road side drainage system

There are different types of road side drainage, classified according to the type of construction, which is as follows;

• Trapezoidal surface drainage

• V-shaped lined surface drainage

• Urban surface drainageCROSS DRAINAGE

When stream have to cross a roadway or when water from a side drainage have to be diverted to water course across the roadway, then a cross drainage work such as culvert or small bridge is provided. On less important roads, in order to reduce the construction cost of drainage structures, sometimes submersible bridges or course way are constructed. During the flood the water will flow over the road.REQUIREMENT OF HIGHWAY DRAINAGE SYSTEM

• The surface water from the carriage way and shoulder should effectively be drained off without allowing it to percolate to sub grade

• The surface water from the adjoining land should be prevented from entering the roadway.

• The surface drainage should have sufficient capacity and longitudinal slope to carry away all the surface water collected.

• Flow of surface water across the road and shoulders and along slopes should not cause formation of erosion.

DESIGN OF SURFACE DRAINAGE

• Hydrological analysis

• Hydraulic analysis

Page 11: planning, design and estimation of road side drainage system

2.3 Hydrological analysis This deals mainly with precipitation and runoff in the area of interest. When rainfall, which is the main source of water, falls onto an area some of the water infiltrates into the soil while the remaining portion either evaporates or runs off. The portion that remains as runoff is the one of major importance in the design of surface drainage facilities. 2.4 Determination of runoff Runoff at a particular point is determined with respect to a given catchment area and depends on a number of factors such; type and condition of the soil in the catchment, kind and extent of vegetation or cultivation, length and steepness of the slopes and the developments on the area among others. The following formula known as the rational formula is used for calculation of runoff water for highway drainage. Q= 0.028CIA Where: Q = maximum runoff in m3 per sec C = a constant depending upon the nature of the surface

I = the critical intensity of storm in mm per hour occurring during the time of concentration. A = the catchment area in km2 HYDRAULIC DESIGNOnce the design runoff Q is determined, the next is the hydraulic design of drains. The side drainage and other structures are designed based on the principles of flow through open channels.If Q is the quantity of surface water (m3/sec) to be removed by a side drainage and V is allowable velocity of flow (m/s) on the side drainage, the area of cross section A of the channel (m2) is found from the relation below: Q=A.VThe velocity of unlined channel must be high enough to prevent silting

Page 12: planning, design and estimation of road side drainage system

and it should not be too high as to cause erosion. The allowable velocity should be greater than one (1m/sec) for lined channel.The slope S of the longitudinal drain of known or assumed cross section and depth of flow ,may determined by using Manning’s formula for the design value of velocity of flow V, roughness coefficient n and hydraulic radius R.Manning’s Formula V=1/n*R2/3*S1/2

Where: V=Average velocity m/sec n=Manning’s roughness coefficient R=Hydraulic radius S=Longitudinal slope of channel.Manning’s Roughness coefficientN= 0.02 for unlined ordinary ditches =0.05 to 0.1 for unlined ditches with heavy vegetation =0.013 for rough rubble =0.04 for stone riprap =0.015 for pipe culverts

Hydraulic Radius = Cross sectional area Wetted perimeter

Time of concentration (t c)Time of concentration is that time required for water to travel all the way from catchments area to the designed element.The time taken by water to flow along the longitudinal drain is determined from the length of the longitudinal drain L the nearest cross drainage or a water course and allowable velocity of the flow V in the drain. T = V/L

Page 13: planning, design and estimation of road side drainage system

The total time for inlet flow and flow along the drain is taken as time of concentration or the design value of rain fall duration. T c = T1+ T2Where, T1 = overland flow time in minutes T2 = channel flow time in minute

T1 = [(0.885x L3)/H]0.385

Where, L = the length of overland flow in km from critical point the mouth of the drain. H = total fall of level from the critical point to the mouth of the drain in meters.Note: From the rainfall intensity –duration- frequency curves the rainfall I is found in mm/sec. Corresponding to duration T and frequency of return period.The required depth of flow in the drain is calculated for convenient bottom width and side slope of drain. The actual depth of the open channel drain may be increased slightly to give a free body. The hydraulic mean radius of flow R is determined.The required longitudinal slope S of the drain is calculated using Manning formula adopting suitable value of roughness coefficient.

DATA ANALYSISRainfall dataThe following are the rainfall data, which obtained from the Metrological Department at Bhopal, No……………., the data are of 10 years from 2004 to 2013, the data are in mm/hrMAXIMUM RAINFALL INTENSITY DURATION FREQUENCY DATA IN ONE DAY PER YEAR (mm/hour)

MAXIMUM MONTHLY RAINFALL

Page 14: planning, design and estimation of road side drainage system

YEAR JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

200451.3 0 0 10 20.9 194.2 147.3 108.1 189.4 34.9 0 0.2

20059.9 5.1 8.6 0.3 33.6 57.6 263 80.1 125.4 2.1 0 0.6

20060 0 13.7 30.8 55.3 246.5 342 151.1 32.9 31.3 6.7 4.1

20070.5 66.1 18.1 1.3 61.9 91.6 246.7 197.1 118 2.6 0 0.8

20080.1 2.2 0 18.7 66.1 215.2 444.3 377.5 330.6 4.7 0 0

20090 5.8 10.5 1.6 10.6 36.5 166.1 256.5 229.9 105.8 4 4.4

20101.6 15.8 0 0 36.5 49.4 342.2 199.9 144.2 11.7 8.6 0.6

2011 2.5 6.7 10 2.4 35.1 128.1 246.3 323.6 109.6 0.5 0.0 0.02012

39.7 14.4 0.2 4.9 0.0 1.2 288 210.1 194.9 0.0 0.0 0.02013 3.8 59.0 0.3 0.0 0.0 252.3 196.6 193.5 40.3 42.2 0.0 1.9

DATA PRESENTATIONIn case of this road, open side drain of trapezoidal and rectangular have to be provided for disposing of surface water collected. The first step will be to estimate the amount of surface water flowing, the amount of surface water depend upon the intensity of rainfall, amount of rainfall, nature of the soil and topographical of the area.. Therefore the quantity of water that can be handled by this ditch or drain can be estimated

Year Maximum rainfall per month (mm)

2005 194.2

2006 263.0

2007 246.5

Page 15: planning, design and estimation of road side drainage system

2008 246.7

2009 444.3

2010 256.5

2011 342.2

2012 323.6

2013 288.02014 252.3

Maximum Rainfall Per Month(mm)From the graph the maximum rainfall intensity in the given years (2000-2010) is 444.3mm/hrDETERMINATION OF RUNOFF

Run off at a particular point is determined with respect to a given catchment area and depends on a number of factors such as type and condition of the soil, kind and extent of vegetation (cultivation), length and steepness of the slope and development of the area among the others. PEAK DESIGN FLOWThis is the maximum flow rate of a flood wave passing a point along a stream. As the wave passes the point, its flow increases to the maximum and recedes. It is a major factor in culvert designs, and its magnitude is dependent on the section of the return period.CATCHMENT AREAS (Area data)

• Unpaved gravel road surface and shoulders Length of the area = 0.685km Width of the area = 0.008km

Area=Length×Width

Page 16: planning, design and estimation of road side drainage system

= 0.685 × 0.008Area = 0.00548km2

• Area of land on the other side drain(Build up area) = 0.021×0.8 =0.02km2

• Area covered with grass =0.0234×0.35 =0.005km2

Total catchments area = (0.00548+0.02+0.005) km2

=0.03km2

Surface runoff coefficient (C)-:

• Coefficient of gravel surface = 0.35

• Coefficient of build up = 0.8

• Coefficient of soil covered with grass = 0.1Therefore C1= 0.35, C2= 0.8, C3= 0.1Weighted value of runoff Coefficient C = (C1A1 + C2A2 + C3A3)/A1 + A2 + A3C = 0.35×0.00548 + 0.8×0.02 + 0.1×0.005C = 0.604

Therefore the runoff coefficient (C) =0.604Peak flow (Q)-:From the formula below; Q=1/36×(C×I×A)Where;

Page 17: planning, design and estimation of road side drainage system

Q = Quantity of rain water surface runoff in m3/sec C = Surface runoff coefficient I = Maximum rainfall intensity in mm/hour A = Size of surface area to be drained in km2

C = 0.604 I = 444.3mm/hour A = 0.03km2

Q = 1×0.604×444.3×0.03×10 6 36 ×60 ×60×1000 Q = 0.0621m3/secTherefore, Quantity of rain water surface runoff (Q) =0.0621m3/secDESIGN OF NEW SIDE DRAINAGE Trapezoidal sectionCross section area (A) of the side drainage required will be

obtained from the formula below; Q = A×VWhere; Q = Quantity of rain water surface runoff in m3/sec A = Cross section area in m2

V = Velocity of flow in m/sec Q = 0.0621m3/sec V = 1.5m/sec for lined structure A =? A = Q/V A = 0.0621/1.5

Page 18: planning, design and estimation of road side drainage system

A = 0.0414m2

Therefore, the required cross section area is 0.0414 m2 .Consider the trapezoidal section below: B=0.5+2D

B = 0.5+2d 150mm free water bodyS=1:1 d D b = 500mm

Required dimensions;

• Suppose the bottom width (b) =0.5m

• Side slope (S) = 1:1

• Free water body = 0.15m

• Vertical height (d) =?

• Horizontal length (B) =?

From the formula Area = 0.5× (B + b) ×d Area (A) = 0.0414 m2

B = 2d+0.5 m b = 0.5m d =? 0.0414 = 0.5× (2d + 0.5+ 0.5) ×d 0.0414 = 0.5 (2d + 1) ×d d2 + d-0.0414 = 0

Page 19: planning, design and estimation of road side drainage system

d = 0.072m B = (2×0.072) + 0.5 = 0.644m D = 0.44 + 0.15 = 0.222m Top Width = (0.222x2) + 0.5 = 0.944mRequired section 0.94m B=0.644m S=1:1 d=0.072m D=0.22m b=0.5m

Effective Area (A) =0.5× (0.5+0.644) ×0.072 A effective = 0.041m2

Wetted perimeter is equal to the total length of the wetted area. = Length of two side slope + Bottom lengthWhere; Bottom length = 0.5m Length of side slope is calculated below d=0.072mFrom Pythagoras theorem,s2 = d2+d2

s2 = (0.0722+0.0722)1/2

s = 0.102mWetted perimeter (P) = 0.102+0.102+0.5

Page 20: planning, design and estimation of road side drainage system

= 0.704mLongitudinal slopeFrom Manning’s formula V = 1/n×R2/3×S1/2

S = (n*V/R2/3)2

Where; S = Longitudinal slope V = Velocity of flow in m/sec R = Hydraulic Radius n = Manning’s roughness coefficientHydraulic Radius (R) = Cross section area (A) ÷ Wetted perimeter (P) R = 0.0414 ÷ 0.704 = 0.0588 R = 0.0588 n = 0.04 V = 1.5m/secS = [0.04*1.5 / (0.058)2/3]2

S = 0.1603Therefore, the proposed slope for the side drainage is 0.1603.Design for rectangular sectionFrom the formula Q = A × VWhere Q, A and V are already defined before Q = 0.0621m/sec V = 1.5m/sec A = ? Q = A×V 0.0621 = A×1.5

Page 21: planning, design and estimation of road side drainage system

A = 0.0414m2

Required dimension

• Suppose the bottom width = 0.8m

• Free water body = 0.15m

• Vertical height =?Consider the formula of rectangular section Area (A) = Height × Width Height (D) =? Width (b) = 0.8m Area = 0.0414m0.0414 = 0.8×d d = 0.052m D = 0.052 + 0.15 = 0.202 mDIAGRAM :

Longitudinal slopeAlso is calculated from the Manning’s formula V = 1/n×R2/3×S1/2

R = Area/ Wetted perimeter Wetted perimeter = 0.8 + (0.052×2) = 0.904m

Page 22: planning, design and estimation of road side drainage system

R = 0.0414 0.904R = 0.0457n = 0.04 V = 1.5m/secS = 1.5×0.04/0.04572/3

S =0.468Therefore, the proposed slope for the side drainage is 0.468.

Page 23: planning, design and estimation of road side drainage system

Estimation And Costing CONCLUSIONAfter this research many problems were discovered such as potholes, corrugations, water lodging, ruts ,erosion on the edge of the road as the result of inspection, practical checking of the whole road and all areas surrounding the road. In order to maintain the life span and purpose of the road as designing Road side drainage of adequate size and capacity, the discharge and all dimensions produced can be used for the construction as it designed.Terefore we conclude our major project by researching and knowing the major problems and thus understanding it. APENDICES

• BOOKING SHEET FOR LEVELLINGBS IS FS RISE FALL RL REMARKS

0.080 BM 0.0800.235 0.080 0+000

1.160 0.925 0.845 0+0301.372 0.212 0.633 0+0601.465 0.093 0.540 0+090

1.710 0.245 0+1200.710 0+120

1.173 0.463 0+1501.513 0.34 0+180

2.169 0.656 0+210

Page 24: planning, design and estimation of road side drainage system

0.115 0+2100.989 0.874 0+2401.825 0.836 0+2702.621 0.796 0+300

3.300 0.679 0+3300.249 0+330

2.179 1.930 0+3600.949 0.933 0+360

1.882 0+3903.349 1.467 0+420

0.120 0+4201.687 1.567 0+450

3.232 1.545 0+4800.232 0+480

1.559 1.327 0+5102.323 0.764 0+540

2.870 0.547 0+570

3.672 0.802 0+6001.295 0+600

1.773 0.478 0+630

RECOMMENDATION

Due to the condition of the drainage along road is not satisfactory, this problem must be taken into consideration together with the information gathered on the road condition.

Page 25: planning, design and estimation of road side drainage system

THANK YOU