28
SEQUENCING - PORAS SANCHETI 201051 - DEEPAK MALCHE 200932

Mpc sequencing

Embed Size (px)

DESCRIPTION

good for sequencing example FCRIT, vashi, Navi mumbai, India

Citation preview

Page 1: Mpc   sequencing

SEQUENCING

- PORAS SANCHETI 201051

- DEEPAK MALCHE 200932

Page 2: Mpc   sequencing

Sequencing: Determine the order in which jobs at a work center will be processed.

Requires order for sequencing at all work centers as well as sequencing at individual work centers.

Workstation: An area where one person works, usually with special equipment, on a specialized job.

Job time: Time needed for setup and processing of a job.

Job Flow Time: The length of time a job is in the shop at a particular workstation or work center.

Job Lateness: This is the length of time the job completion date is expected to exceed the date the job was due or promised to a customer.

What is Sequencing..??

Page 3: Mpc   sequencing

Makespan: This is the total time needed to complete

a group of jobs. It is the length of time between the start of

the first job in the group and the completion of the last job in

the group.

Average Number of Jobs: Jobs that are considered in

a shop are considered to be work in process inventory.

Mathematically,

Average Number of Jobs= Total Flow Time / Makespan

PRODUCTION

AND

OPERATIONS MANAGEMENT

Page 4: Mpc   sequencing

FCFS - First Come, First Served: Jobs are processed in

the order in which they arrive at a machine or work center.

SPT-

Shortest Processing Time: Jobs are processed according to p

rocessing time at a machine or work center, shortest job first.

DD -

Due Date: Jobs are processed according to due date, earliest

due date first.

CR -

Critical Ratio: Jobs are processed according to smallest ratio

of time remaining until due date to processing time remaining.

Priority Rules

Page 5: Mpc   sequencing

S/O - Slack

Per Operation: Jobs are processed according to average slack

time (time until due date minus remaining time to process).

Compute by dividing slack time by dividing slack time by

number of remaining operations including the current one.

Page 6: Mpc   sequencing

The set of jobs is known, no new jobs arrive after processing

begins and no jobs are canceled.

Setup time is deterministic

There will be no interruptions in processing such as machine

breakdowns, accidents or worker illnesses.

ASSUMPTIONS TO PRIORITY RULE

S

Page 7: Mpc   sequencing

A. Setup Times

B. Processing Times

C. Changes in the set of jobs.

D. Breakdown Consequences.

FACTORS AFFECTING

SCHEDULING

I. Production capacity is reduced : Orders are delayed.

II. No production: Overhead continues.

III. Cost per unit increases: Quality issues.

IV. Product may be damaged.

V. Safety issues.

1. Injury to employees

2. Injury to customers

Page 8: Mpc   sequencing

Scheduling can hinder or help the Operations Strategy.

An on time delivery of a product or service is only possible if the

Operations Managers is able to do effective scheduling.

An ineffective scheduling would result in inefficient use of resou

rces and possible dissatisfied customers.

Scheduling as an operations strategy can provide an

organization a competitive advantage over its competitors.

Time based competition depends on good scheduling.

OPERATIONS STRATEGY

Page 9: Mpc   sequencing

‘n’ Jobs and 1 Machine.

‘n’ Jobs and 2 Machine.

‘n’ Jobs and 3 Machine.

1 Jobs and ‘m’ Machine.

2 Jobs and ‘m’ Machine.

TYPES OF SEQUENCING

Page 10: Mpc   sequencing

Two Resource Problems

( ‘n’ Jobs and 2 Machines)

Suppose you work with a classmate, Kim on multiple projects.

4 3 5 4 2

2 6 3 5 1

In each project you do the research, and Kim writes the report

Processing time (you):

Processing time (Kim):

You want to complete all projects as soon as possible.

What should be the order

for the projects?

Page 11: Mpc   sequencing

Johnson’s Rule

4 3 5 4 2

2 6 3 5 1

1. Find the smallest processing time.

• If its on the 1st machine, assign the task at the beginning of the sequence and

eliminate it from further consideration.

• If its on the 2nd machine, assign the task at the end of the sequence and

eliminate it from further consideration

2. Repeat step 1 for all unassigned tasks

Processing time (you):

Processing time (Kim):

What order should you

do the projects in?

Sequences tasks to minimize makespan

Two Resource Problems

Page 12: Mpc   sequencing

Johnson’s Rule

4 3 5 4 2

2 6 3 51

Processing time (you):

Processing time (Kim):

Sequence

English

Sequences tasks to minimize makespan

Two Resource Problems

1. Find the smallest processing time.

• If its on the 1st machine, assign the task at the beginning of the sequence and

eliminate it from further consideration.

• If its on the 2nd machine, assign the task at the end of the sequence and

eliminate it from further consideration

2. Repeat step 1 for all unassigned tasks

Page 13: Mpc   sequencing

Johnson’s Rule

4 3 5 4 2

2 6 3 5 1Processing time (you):

Processing time (Kim):

Sequence

English

Management

Sequences tasks to minimize makespan

Two Resource Problems

1. Find the smallest processing time.

• If its on the 1st machine, assign the task at the beginning of the sequence and

eliminate it from further consideration.

• If its on the 2nd machine, assign the task at the end of the sequence and

eliminate it from further consideration

2. Repeat step 1 for all unassigned tasks

Page 14: Mpc   sequencing

Johnson’s Rule

4 3 5 4 2

2 6 3 5 1Processing time (you):

Processing time (Kim):

Sequence

English

Management

Finance

Sequences tasks to minimize makespan

1. Find the smallest processing time.

• If its on the 1st machine, assign the task at the beginning of the sequence and

eliminate it from further consideration.

• If its on the 2nd machine, assign the task at the end of the sequence and

eliminate it from further consideration

2. Repeat step 1 for all unassigned tasks

Two Resource Problems

Page 15: Mpc   sequencing

Johnson’s Rule

4 3 5 4 2

2 6 3 5 1Processing time (you):

Processing time (Kim):

Sequence

Marketing

Sequences tasks to minimize makespan

1. Find the smallest processing time.

• If its on the 1st machine, assign the task at the beginning of the sequence and

eliminate it from further consideration.

• If its on the 2nd machine, assign the task at the end of the sequence and

eliminate it from further consideration

2. Repeat step 1 for all unassigned tasks

English

Management

Finance

Two Resource Problems

Page 16: Mpc   sequencing

Johnson’s Rule

4 3 5 4 2

2 6 3 5 1Processing time (you):

Processing time (Kim):

Sequences tasks to minimize makespan

1. Find the smallest processing time.

• If its on the 1st machine, assign the task at the beginning of the sequence and

eliminate it from further consideration.

• If its on the 2nd machine, assign the task at the end of the sequence and

eliminate it from further consideration

2. Repeat step 1 for all unassigned tasks

SEQUENCE

English

Management

Finance

Accounting

Marketing

Two Resource Problems

Page 17: Mpc   sequencing

Johnson’s Rule

4 3 5 4 2

2 6 3 5 1Processing time (you):

Processing time (Kim):

You

Kim

Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Sequences tasks to minimize makespan

SEQUENCE

English

Management

Finance

Accounting

Marketing

Two Resource Problems

Page 18: Mpc   sequencing

Johnson’s Rule

4 3 5 4 2

2 6 3 5 1Processing time (you):

Processing time (Kim):

You

Kim

Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Sequences tasks to minimize makespan

SEQUENCE

English

Management

Finance

Accounting

Marketing

Two Resource Problems

Page 19: Mpc   sequencing

Johnson’s Rule

4 3 5 4 2

2 6 3 5 1Processing time (you):

Processing time (Kim):

You

Kim

Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Sequences tasks to minimize makespan

SEQUENCE

English

Management

Finance

Accounting

Marketing

Two Resource Problems

Page 20: Mpc   sequencing

Two resource problems

Johnson’s Rule

4 3 5 4 2

2 6 3 5 1Processing time (you):

Processing time (Kim):

You

Kim

Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Sequences tasks to minimize makespan

SEQUENCE

English

Management

Finance

Accounting

Marketing

Two Resource Problems

Page 21: Mpc   sequencing

Two resource problems

Johnson’s Rule

4 3 5 4 2

2 6 3 5 1Processing time (you):

Processing time (Kim):

You

Kim

Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Sequences tasks to minimize makespan

SEQUENCE

English

Management

Finance

Accounting

Marketing

Two Resource Problems

Page 22: Mpc   sequencing

Two resource problems

Johnson’s Rule

4 3 5 4 2

2 6 3 5 1Processing time (you):

Processing time (Kim):

You

Kim

Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Sequences tasks to minimize makespan

SEQUENCE

English

Management

Finance

Accounting

Marketing

Two Resource Problems

Page 23: Mpc   sequencing

Two resource problems

Johnson’s Rule

4 3 5 4 2

2 6 3 5 1Processing time (you):

Processing time (Kim):

You

Kim

Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Sequences tasks to minimize makespan

SEQUENCE

English

Management

Finance

Accounting

Marketing

Two Resource Problems

Page 24: Mpc   sequencing

Two resource problems

Johnson’s Rule

4 3 5 4 2

2 6 3 5 1Processing time (you):

Processing time (Kim):

You

Kim

Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Sequences tasks to minimize makespan

SEQUENCE

English

Management

Finance

Accounting

Marketing

Two Resource Problems

Page 25: Mpc   sequencing

Two resource problems

Johnson’s Rule

4 3 5 4 2

2 6 3 5 1Processing time (you):

Processing time (Kim):

You

Kim

Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Idle time

Sequences tasks to minimize makespan

SEQUENCE

English

Management

Finance

Accounting

Marketing

Two Resource Problems

Page 26: Mpc   sequencing

INDUSTRIAL APPLICATIONS

Automobile Industry

DNA Sequencing

Page 27: Mpc   sequencing

Genome Sequencing

Tyre Manufacturing Industry

Page 28: Mpc   sequencing

Thank You