Monitor Drilling performance based on (Time – Depth – Cost) Curve Operation Geologist Practical use and reference

Monitor drilling performance

Embed Size (px)

Citation preview

Page 1: Monitor drilling performance

Monitor Drilling performancebased on

(Time –Depth –Cost) CurveOperation Geologist

Practical use and reference

Page 2: Monitor drilling performance

PROPOSED WELL

0

10

20

30

40

50

60

70

80

90

100

0

20

40

60

80

100

120

140

160

1/J

an/8

9

1/J

an/9

0

1/J

an/9

1

1/J

an/9

2

1/J

an/9

3

1/J

an/9

4

1/J

an/9

5

1/J

an/9

6

1/J

an/9

7

1/J

an/9

8

1/J

an/9

9

1/J

an/0

0

1/J

an/0

1

1/J

an/0

2

1/J

an/0

3

1/J

an/0

4

1/J

an/0

5

1/J

an/0

6

1/J

an/0

7

1/J

an/0

8

1/J

an/0

9

wc(

%)

Gro

ss/O

il R

ate

(bbl

per/

day)

Date

Gross (BFPD) Oil Rate (BOPD)

0.0

10.0

20.0

30.0

40.0

50.0

60.0

70.0

80.0

1 2 3 4 5 6 7

Daily oil perwell (bbl/day)Water Cut (%)

0

13-3/8" 20 Meter

100 9 5/8" 100 Meter

200

300

400

5.1/2"

TD 440 Meter

500

Well ABC

MBLB

z z

Well ABC

Well ABC Forecast

Example in Well ABC Drilling

Page 3: Monitor drilling performance

DRILLING WELL OPERATION7 Nov 2012 Day 1

Prepare to Spud-In and Pree Job Safety Meeting. SPUD-IN

WELL ABC At 07:00 hours on 07 november 2012 Drill out

form 12 1/4" Hole to 58 M. stop drill Doe To problem on

shale shaker . Repair shale shaker. Continue drill out

formation from 58 M to 122 M.

8 Nov 2012 Day 2

Continued drill out formation from 122 M to 135 M.

Circulated for cleaning hole (GPM: 400, SPP: 240 psi. POOH

12-1/4" TCB + BHA Assembly from 135 M to surface (found

balling on 12-1/4" bit and 6-1/2" DC. RIH back 12-1/4" TCB

+ BHA Assembly from surface to 135 M. Circulated for

cleaning hole (GPM: 390, SPP: 210 psi. POOH 12-1/4" TCB

+ BHA Assembly from 135 M to surface. Prepared for RIH

csg 9-5/8". PJSM prior to run 9-5/8 "csg. RIH 9-5/8" casing

(11 jts # 40 ppf, K-55, BTC-R3) to 132 M (set shoe 9-5/8"

csg). RIH stinger + DP 5" to 132 M for Cementing 9-5/8" csg.

Circulated prior to cementing job. No Cementing engineer

stand by at location Well ABC. Wait on cementing engineer

while break circulated (GPM: 425, SPP: 180 psi).

9 Nov 2012 Day 3

Continue wait on cementing engineer while break circulated

(GPM: 425, SPP: 180 psi). R/U Cementing line and presure

test to 2000 psi, Hold 5 min - ok. Hold safety meeting prior

cementing job;- Pump preplush as water ahead, 0,5 m3 @ rate

0.8 m3/min; Mix and pump slurry 15.8 ppg, 6.62 m3 @ rate

0.8 m3/min; Displace w/ water 1.16 m3 @ rate 0.8 m3/min.

Cip (cement in place) @ 08:25 hours. WOC

10 Nov 2012 Day 4

Continue WOC. Break off landing joint and L/D same.

Moved 44 jts 5-1/2 casing F/Yard to KM#606 location (RIG

SITE); Moved 10 big saxs of bentonite F/Yard to Well ABC

location

Example in Well ABC Drilling

Page 4: Monitor drilling performance

DRILLING WELL OPERATION

11 Nov 20xx Day 5

Continue rolling crane from KME base camp to XJ-450 rig

site. N/U BOP 11-5/8" X 5 K & relate, fungtion test BOPS

"OK". Press test annular, pipe rams and blind rams to 1000 psi

each for 5 minutes "OK". RIH W/8-1/2 PDC BIT TO TAC

SHOE (132). Drill out shoe and CMT to 134 M. /134 M to

175 M."

12 Nov 20xx Day 6

Continue drill out formation with 8-1/2" PDC + BHA from

175 m to 222 m (WOB/RPM/SPP/GPM/Last ROP/ROP

Ave.= 1- klbs/58/480 psi/404 GPM/10.2 mph/19.6 mph).

Founded mud loss 12 bbls/mnt @ interval 220 m - 222 m with

lithologi: coal. Circulate while mixing mud in active tank.

/RPM/SPP/GPM/Last ROP/ROP Ave.= 1-5 klbs/58/500

psi/448 GPM/47,20 mph/17.9 mph). Stop drilling formation

due to founded loss total @ interval 374 m - 378 m. total mud

loss = 280 bbls. Continue drill out formation with 8-1/2" PDC

+ BHA from 222 m to 378. Stop drilling formation due to

founded loss total @ interval 374 m - 378 m. total mud loss =

280 bbls. Last lithologi: sandstone (80%), Claystone(20%).

POOH 8-1/2" PDC + BHA from 378 m to 250 m while

mixing mud to active tank. Mixing mud to active tank.

13 Nov 20xx Day 7

Continue mixing mud to active tank. RIH Back 8-1/2" PDC

+BHA from 250 m to 378 m. Circulate (GPM: 444, SPP: 400

psi). Blind drill with 8-1/2" PDC + BHA from 378 m to 380

m. founded loss totally. Total mud loss: 390 bbls. POOH 8-

1/2" PDC + BHA FROM 378 M TO 318 M while mixing mud

to active tank. wait on water for fill active tank and mixing

mud. circulate f/check annulus and still founded loss. pull out

bit 8-1/2" PDC + BHA from 318 m to 125 m (casing shoe)

while mixing mud + LCM to active tank. Break circulate

(GPM: 444, SPP: 400 psi). At shoe no loss (OK). run back

from 132 m (casing shoe) to 241 m (6 stand). Break circulate

(GPM: 444, SPP: 400 psi). Good return. run back from 241 m

to 378 m (botton). drill out formation f/378 to 436 m

(WOB/RPM/MFI/SPP/Last ROP/ROP Ave = 1-9 klbs/40-

60/430 GPM/480 psi/25,76 mph/25,21 mph). Founded partial

loss 2 - 4 bpm.

Example in Well ABC Drilling

Page 5: Monitor drilling performance

DRILLING WELL OPERATION

14 Nov 2012 Day 8

Continue drill out formation f/ 436 m to 456 m (Total Depth).

Circulate for clening hole (GPM: 391, SPP: 460 psi). POOH

8-1/2" PDC + BHA from 456 m to surface for run electrical

logging. R/u DQWL and prepare Tools. Run wireline logging.

1.MSFL - DLL - DT - GR - SP - CAL. 2.HRL - GR, R/D

DQWL Unit. RIH 8-1/2" Bit PDC + BHA to botton (456).

Circulate for cleaning hole (GPM: 391, SPP: 460 psi). /2".

LTD 5 jts DC 6-1/2", 1 jts DC7", Bit Sub, 8-1/2" PDC. POOH

8-1/2" PDC + BHA from 456 m to surface for running casing

5-1/2". LTD 5 jts DC 6-1/2", 1 jts DC7", Bit Sub, 8-1/2" PDC.

N/D BOP S 11-5/8" x 5K psi

15 Nov 2012 Day 9

Continue N/D BOP S 11-5/8" x 5K psi. /surface to bottom

casing at shoe 447 Mkb , FC at 436.42 m . Prepare and RIH 5-

1/2" caing (# 17 ppf, L-80, BTC-R3) f/surface to bottom

casing at shoe 447 Mkb , FC at 436.42 m . P/up kelly for

circulate clean hole. R/U cementing line and pressure test to

2000 psi, hold 5 min - OK. Hold safety meeting prior

cementing job. Pump preflush as water ahead 0.5 m3/min @

rate 0.8 m3/min. Displace w/water 1.16 m3 @ rate 0.8

m3/min. Bumped to 500 psi no cement return to surface. CIP

(cement In Place) @ 16:00 Hrs. WOC

16 Nov 2012 Day 10 Lay down 40 jts 5" DP and Kelly. Clean up mud tank.

prepare to Rig down

17 Nov 2012 Day 11 Continue WOC for 48 hrs - Lower mast. Clean up

subtruckture. 40 % Rig Down

18 Nov 2012 Day 12

Continue Rig Down to 60 %. Modify mouse Hole pipe to

make longer in progress. While waiting on road condition to

move out Rig equipment. Wait on day

Example in Well ABC Drilling

Page 6: Monitor drilling performance

COST CONTROLERFrom To Elapsed

6:00 7:00 1:00 1 1 214.05$ Prepare to Spud-In and Pree Job Safety Meeting

7:00 15:00 8:00 8.00 8 2,854.00$ SPUD-IN WEEL ABC At 07:00 hours on 07 november 20xx Drill out

form 12 1/4" Hole to 58 M. stop drill Doe To problem on shale shaker

15:00 17:00 2:00 2 2 570.80$ Repair shale shaker

17:00 0:00 7:00 7.00 7 2,497.25$ Cont'd drill out formation from 58 M to 122 M

0:00 2:30 2:30 2.5 2.5 891.88$ Continued drill out formation from 122 M to 135 M

2:30 3:00 0:30 0.5 0.5 178.38$ Circulated for cleaning hole (GPM: 400, SPP: 240 psi

3:00 6:00 3:00 3.0 3 1,070.25$ POOH 12-1/4" TCB + BHA Assembly from 135 M to surface (found

balling on 12-1/4" bit and 6-1/2" DC

6:00 8:00 2:00 2.0 2 713.50$ RIH back 12-1/4" TCB + BHA Assembly from surface to 135 M

8:00 8:30 0:30 0.5 0.5 178.38$ Circulated for cleaning hole (GPM: 390, SPP: 210 psi

8:30 11:00 2:30 2.5 2.5 891.88$ POOH 12-1/4" TCB + BHA Assembly from 135 M to surface

11:00 15:00 4:00 4 4 1,141.60$ Prepared for RIH csg 9-5/8". PJSM prior to run 9-5/8 "csg

15:00 16:30 1:30 1.5 1.5 535.13$ RIH 9-5/8" casing (11 jts # 40 ppf, K-55, BTC-R3) to 132 M (set shoe 9-

5/8" csg)

16:30 19:30 3:00 3.0 3 1,070.25$ RIH stinger + DP 5" to 132 M for Cementing 9-5/8" csg

19:30 20:00 0:30 0.5 0.5 178.38$ Circulated prior to cementing job. No Cementing engineer stand by at

location ABC

20:00 0:00 4:00 4 4 856.20$ Wait on cementing engineer while break circulated (GPM: 425, SPP:

180 psi)

0:00 7:00 7:00 7 7 1,498.35$ Cont'd wait on cementing engineer while break circulated (GPM: 425,

SPP: 180 psi)

7:00 8:30 1:30 1.5 1.5 535.13$

R/U Cementing line and presure test to 2000 psi, Hold 5 min - ok, '-

Hold safety meeting prior cementing job, Pump preplush as water

ahead, 0,5 m3 @ rate 0.8 m3/min, Mix and pump slurry 15.8 ppg, 6.62

m3 @ rate 0.8 m3/min, Displace w/ water 1.16 m3 @ rate 0.8 m3/min.

Cip (cement in place) @ 08:25 hours.

8:30 15:00 6:30 6.5 6.5 2,318.88$ Pull Out out DP 5" + stringer and L/D same

15:00 0:00 9:00 9 9 1,926.45$ WOC

0:00 9:00 9:00 9 9 1,926.45$ Cont'd WOC

9:00 0:00 15:00 15.0 15 5,351.25$

Break off landing joint and L/D same '- Instaled 9-5/8" x 2000 well head

and prepare to N/U 11" x 5 K BOPS, Moved 44 jts 5-1/2 casing F/Yard to

ABC location (RIG SITE), Moved 10 big saxs of bentonite F/Yard to ABC

6 location

0:00 7:00 7:00 7 7 1,997.80$ Continue rolling crane from ABC base camp to XJ-450 rig site.

7:00 18:00 11:00 11 11 3,924.25$

N/U BOP 11-5/8" X 5 K & relate, fungtion test BOPS "OK". Press

test annular, pipe rams and blind rams to 1000 psi each for 5

minutes "OK".

18:00 20:30 2:30 2.5 2.5 891.88$ RIH W/8-1/2 PDC BIT TO TAC SHOE (132).

20:30 21:30 1:00 1 1 356.75$ Drill out shoe and CMT to 134 M.

21:30 0:00 2:30 2.5 2.5 891.88$ Continue Drill formation 8-1/2" Hole F/134 M to 175 M.

0:00 5:00 5:00 5 5 1,783.75$

Continue drill out formation with 8-1/2" PDC + BHA from 175 m

to 222 m (WOB/RPM/SPP/GPM/Last ROP/ROP Ave.= 1-

klbs/58/480 psi/404 GPM/10.2 mph/19.6 mph), Founded mud

loss 12 bbls/mnt @ interval 220 m - 222 m with lithologi: coal

5:00 6:00 1:00 1 1 356.75$ Circulate while mixing mud in active tank

6:00 23:00 17:00 17 17 6,064.75$

Continue drill out formation with 8-1/2" PDC + BHA from 222 m

to 378 (WOB/RPM/SPP/GPM/Last ROP/ROP Ave.= 1-5

klbs/58/500 psi/448 GPM/47,20 mph/17.9 mph). Stop drilling

formation due to founded loss total @ interval 374 m - 378 m.

total mud loss = 280 bbls. Last lithologi: sandstone (80%),

Claystone(20%)

23:00 23:30 0:30 0.5 0.5 178.38$ POOH 8-1/2" PDC + BHA from 378 m to 250 m while mixing mud

to active tank

23:30 0:00 0:30 0.5 0.5 107.03$ Mixing mud to active tank

0:00 2:30 2:30 2.5 2.5 535.13$ Continue mixing mud to active tank

2:30 3:30 1:00 1 1 356.75$ RIH Back 8-1/2" PDC +BHA from 250 m to 378 m

3:30 4:00 0:30 0.5 0.5 178.38$

Circulate (GPM: 444, SPP: 400 psi). Blind drill with 8-1/2" PDC +

BHA from 378 m to 380 m. founded loss totally. Total mud loss:

390 bbls

4:00 5:00 1:00 1 1 356.75$ POOH 8-1/2" PDC + BHA FROM 378 M TO 318 M while mixing

mud to active tank

5:00 10:00 5:00 5 5 1,070.25$ wait on water for fill active tank and mixing mud

10:00 11:00 1:00 1 1 356.75$ circulate f/check annulus and still founded loss

11:00 13:00 2:00 2 2 713.50$ pull out bit 8-1/2" PDC + BHA from 318 m to 125 m (casing shoe)

while mixing mud + LCM to active tank

13:00 13:30 0:30 0.5 0.5 178.38$ Break circulate (GPM: 444, SPP: 400 psi). At shoe no loss (OK)

13:30 15:00 1:30 1.5 1.5 535.13$ run back from 132 m (casing shoe) to 241 m (6 stand)

15:00 15:30 0:30 0.5 0.5 178.38$ Break circulate (GPM: 444, SPP: 400 psi). Good return

15:30 17:30 2:00 2 2 713.50$ run back from 241 m to 378 m (botton)

17:30 0:00 6:30 6.5 6.5 2,318.88$

drill out formation f/378 to 436 m (WOB/RPM/MFI/SPP/Last

ROP/ROP Ave = 1-9 klbs/40-60/430 GPM/480 psi/25,76

mph/25,21 mph). Founded partial loss 2 - 4 bpm

0:00 1:30 1:30 1.5 1.5 535.13$ Continue drill out formation f/ 436 m to 456 m (Total Depth)

1:30 3:00 1:30 1.5 1.5 535.13$ Circulate for clening hole (GPM: 391, SPP: 460 psi)

3:00 7:00 4:00 4 4 1,427.00$ POOH 8-1/2" PDC + BHA from 456 m to surface for run electrical

logging

7:00 10:00 3:00 3 3 642.15$ R/u DQWL and prepare Tools

10:00 15:30 5:30 5.5 5.5 1,962.13$ Run wireline logging 1. MSFL - DLL - DT - GR - SP - CAL 2. HRL -

GR, R/D DQWL Unit

15:30 18:30 3:00 3 3 1,070.25$ RIH 8-1/2" Bit PDC + BHA to botton (456)

18:30 19:00 0:30 0.5 0.5 178.38$ Circulate for cleaning hole (GPM: 391, SPP: 460 psi)

19:00 23:00 4:00 4 4 1,427.00$ POOH 8-1/2" PDC + BHA from 456 m to surface for running

casing 5-1/2". LTD 5 jts DC 6-1/2", 1 jts DC7", Bit Sub, 8-1/2" PDC

23:00 0:00 1:00 1 1 356.75$ N/D BOP S 11-5/8" x 5K psi

0:00 7:00 7:00 7 7 2,497.25$ Continue N/D BOP S 11-5/8" x 5K psi

7:00 14:30 7:30 7.5 7.5 2,675.63$ Prepare and RIH 5-1/2" caing (# 17 ppf, L-80, BTC-R3) f/surface

to bottom casing at shoe 447 Mkb , FC at 436.42 m .

14:30 15:00 0:30 0.5 0.5 178.38$ P/up kelly for circulate clean hole

15:00 16:00 1:00 1 1 356.75$

R/U cementing line and pressure test to 2000 psi, hold 5 min -

OK '- Hold safety meeting prior cementing job '- Pump preflush

as water ahead 0.5 m3/min @ rate 0.8 m3/min '- Displace

w/water 1.16 m3 @ rate 0.8 m3/min. Bumped to 500 psi no

cement return to surface. CIP (cement In Place) @ 16:00 Hrs

16:00 0:00 8:00 8 8 1,712.40$ WOC

10 ABC 0:00 0:00 0:00 24 24 5,137.20$ Continue WOC for 48 hrs '- Lay down 40 jts 5" DP and Kelly, '-

Clean up mud tank, '- prepare to Rig down

0:00 18:00 18:00 18 18 3,852.90$ - Continue WOC for 48 hrs - Lower mast

18:00 0:00 6:00 6 6 1,712.40$ - Clean up subtruckture, '- 40 % Rig Down

6:00 18:00 12:00 18 18 3,852.90$

- Continue Rig Down to 70 %, '- Modify mouse Hole pipe to

make longer in progress, '- While waiting on road condition to

move out Rig equipment

18:00 0:00 6:00 6 6 1,712.40$ Wait on day

148.00 7.00 18.00 109.00 282

52,799.00 1,997.80 5,137.20 23,331.45 11.75

Total Hours83,265.45$

4 ABC

5 ABC

8 ABC

ABC

7 ABC

2 ABC

3 ABC

1 ABC

STAND BY

W/O CREW

TOTAL

HOURSTOTAL COST OPERATIONDAY WELL

TIMEOPERATING MOVING

STAND BY

W/CREW

12 ABC

6

9 ABC

11 ABC

Example in Well ABC Drilling

Page 7: Monitor drilling performance

From To Elapsed

6:00 7:00 1:00 1 1 214.05$ Prepare to Spud-In and Pree Job Safety Meeting

7:00 15:00 8:00 8.00 8 2,854.00$ SPUD-IN WEEL ABC At 07:00 hours on 07 november 20xx Drill out

form 12 1/4" Hole to 58 M. stop drill Doe To problem on shale shaker

15:00 17:00 2:00 2 2 570.80$ Repair shale shaker

17:00 0:00 7:00 7.00 7 2,497.25$ Cont'd drill out formation from 58 M to 122 M

0:00 2:30 2:30 2.5 2.5 891.88$ Continued drill out formation from 122 M to 135 M

2:30 3:00 0:30 0.5 0.5 178.38$ Circulated for cleaning hole (GPM: 400, SPP: 240 psi

3:00 6:00 3:00 3.0 3 1,070.25$ POOH 12-1/4" TCB + BHA Assembly from 135 M to surface (found

balling on 12-1/4" bit and 6-1/2" DC

6:00 8:00 2:00 2.0 2 713.50$ RIH back 12-1/4" TCB + BHA Assembly from surface to 135 M

8:00 8:30 0:30 0.5 0.5 178.38$ Circulated for cleaning hole (GPM: 390, SPP: 210 psi

8:30 11:00 2:30 2.5 2.5 891.88$ POOH 12-1/4" TCB + BHA Assembly from 135 M to surface

11:00 15:00 4:00 4 4 1,141.60$ Prepared for RIH csg 9-5/8". PJSM prior to run 9-5/8 "csg

15:00 16:30 1:30 1.5 1.5 535.13$ RIH 9-5/8" casing (11 jts # 40 ppf, K-55, BTC-R3) to 132 M (set shoe 9-

5/8" csg)

16:30 19:30 3:00 3.0 3 1,070.25$ RIH stinger + DP 5" to 132 M for Cementing 9-5/8" csg

19:30 20:00 0:30 0.5 0.5 178.38$ Circulated prior to cementing job. No Cementing engineer stand by at

location ABC

20:00 0:00 4:00 4 4 856.20$ Wait on cementing engineer while break circulated (GPM: 425, SPP:

180 psi)

0:00 7:00 7:00 7 7 1,498.35$ Cont'd wait on cementing engineer while break circulated (GPM: 425,

SPP: 180 psi)

7:00 8:30 1:30 1.5 1.5 535.13$

R/U Cementing line and presure test to 2000 psi, Hold 5 min - ok, '-

Hold safety meeting prior cementing job, Pump preplush as water

ahead, 0,5 m3 @ rate 0.8 m3/min, Mix and pump slurry 15.8 ppg, 6.62

m3 @ rate 0.8 m3/min, Displace w/ water 1.16 m3 @ rate 0.8 m3/min.

Cip (cement in place) @ 08:25 hours.

8:30 15:00 6:30 6.5 6.5 2,318.88$ Pull Out out DP 5" + stringer and L/D same

15:00 0:00 9:00 9 9 1,926.45$ WOC

0:00 9:00 9:00 9 9 1,926.45$ Cont'd WOC

9:00 0:00 15:00 15.0 15 5,351.25$

Break off landing joint and L/D same '- Instaled 9-5/8" x 2000 well head

and prepare to N/U 11" x 5 K BOPS, Moved 44 jts 5-1/2 casing F/Yard to

ABC location (RIG SITE), Moved 10 big saxs of bentonite F/Yard to ABC

6 location

0:00 7:00 7:00 7 7 1,997.80$ Continue rolling crane from ABC base camp to XJ-450 rig site.

7:00 18:00 11:00 11 11 3,924.25$

N/U BOP 11-5/8" X 5 K & relate, fungtion test BOPS "OK". Press

test annular, pipe rams and blind rams to 1000 psi each for 5

minutes "OK".

18:00 20:30 2:30 2.5 2.5 891.88$ RIH W/8-1/2 PDC BIT TO TAC SHOE (132).

20:30 21:30 1:00 1 1 356.75$ Drill out shoe and CMT to 134 M.

21:30 0:00 2:30 2.5 2.5 891.88$ Continue Drill formation 8-1/2" Hole F/134 M to 175 M.

0:00 5:00 5:00 5 5 1,783.75$

Continue drill out formation with 8-1/2" PDC + BHA from 175 m

to 222 m (WOB/RPM/SPP/GPM/Last ROP/ROP Ave.= 1-

klbs/58/480 psi/404 GPM/10.2 mph/19.6 mph), Founded mud

loss 12 bbls/mnt @ interval 220 m - 222 m with lithologi: coal

5:00 6:00 1:00 1 1 356.75$ Circulate while mixing mud in active tank

6:00 23:00 17:00 17 17 6,064.75$

Continue drill out formation with 8-1/2" PDC + BHA from 222 m

to 378 (WOB/RPM/SPP/GPM/Last ROP/ROP Ave.= 1-5

klbs/58/500 psi/448 GPM/47,20 mph/17.9 mph). Stop drilling

formation due to founded loss total @ interval 374 m - 378 m.

total mud loss = 280 bbls. Last lithologi: sandstone (80%),

Claystone(20%)

23:00 23:30 0:30 0.5 0.5 178.38$ POOH 8-1/2" PDC + BHA from 378 m to 250 m while mixing mud

to active tank

23:30 0:00 0:30 0.5 0.5 107.03$ Mixing mud to active tank

0:00 2:30 2:30 2.5 2.5 535.13$ Continue mixing mud to active tank

2:30 3:30 1:00 1 1 356.75$ RIH Back 8-1/2" PDC +BHA from 250 m to 378 m

3:30 4:00 0:30 0.5 0.5 178.38$

Circulate (GPM: 444, SPP: 400 psi). Blind drill with 8-1/2" PDC +

BHA from 378 m to 380 m. founded loss totally. Total mud loss:

390 bbls

4:00 5:00 1:00 1 1 356.75$ POOH 8-1/2" PDC + BHA FROM 378 M TO 318 M while mixing

mud to active tank

5:00 10:00 5:00 5 5 1,070.25$ wait on water for fill active tank and mixing mud

10:00 11:00 1:00 1 1 356.75$ circulate f/check annulus and still founded loss

11:00 13:00 2:00 2 2 713.50$ pull out bit 8-1/2" PDC + BHA from 318 m to 125 m (casing shoe)

while mixing mud + LCM to active tank

13:00 13:30 0:30 0.5 0.5 178.38$ Break circulate (GPM: 444, SPP: 400 psi). At shoe no loss (OK)

13:30 15:00 1:30 1.5 1.5 535.13$ run back from 132 m (casing shoe) to 241 m (6 stand)

15:00 15:30 0:30 0.5 0.5 178.38$ Break circulate (GPM: 444, SPP: 400 psi). Good return

15:30 17:30 2:00 2 2 713.50$ run back from 241 m to 378 m (botton)

17:30 0:00 6:30 6.5 6.5 2,318.88$

drill out formation f/378 to 436 m (WOB/RPM/MFI/SPP/Last

ROP/ROP Ave = 1-9 klbs/40-60/430 GPM/480 psi/25,76

mph/25,21 mph). Founded partial loss 2 - 4 bpm

0:00 1:30 1:30 1.5 1.5 535.13$ Continue drill out formation f/ 436 m to 456 m (Total Depth)

1:30 3:00 1:30 1.5 1.5 535.13$ Circulate for clening hole (GPM: 391, SPP: 460 psi)

3:00 7:00 4:00 4 4 1,427.00$ POOH 8-1/2" PDC + BHA from 456 m to surface for run electrical

logging

7:00 10:00 3:00 3 3 642.15$ R/u DQWL and prepare Tools

10:00 15:30 5:30 5.5 5.5 1,962.13$ Run wireline logging 1. MSFL - DLL - DT - GR - SP - CAL 2. HRL -

GR, R/D DQWL Unit

15:30 18:30 3:00 3 3 1,070.25$ RIH 8-1/2" Bit PDC + BHA to botton (456)

18:30 19:00 0:30 0.5 0.5 178.38$ Circulate for cleaning hole (GPM: 391, SPP: 460 psi)

19:00 23:00 4:00 4 4 1,427.00$ POOH 8-1/2" PDC + BHA from 456 m to surface for running

casing 5-1/2". LTD 5 jts DC 6-1/2", 1 jts DC7", Bit Sub, 8-1/2" PDC

23:00 0:00 1:00 1 1 356.75$ N/D BOP S 11-5/8" x 5K psi

0:00 7:00 7:00 7 7 2,497.25$ Continue N/D BOP S 11-5/8" x 5K psi

7:00 14:30 7:30 7.5 7.5 2,675.63$ Prepare and RIH 5-1/2" caing (# 17 ppf, L-80, BTC-R3) f/surface

to bottom casing at shoe 447 Mkb , FC at 436.42 m .

14:30 15:00 0:30 0.5 0.5 178.38$ P/up kelly for circulate clean hole

15:00 16:00 1:00 1 1 356.75$

R/U cementing line and pressure test to 2000 psi, hold 5 min -

OK '- Hold safety meeting prior cementing job '- Pump preflush

as water ahead 0.5 m3/min @ rate 0.8 m3/min '- Displace

w/water 1.16 m3 @ rate 0.8 m3/min. Bumped to 500 psi no

cement return to surface. CIP (cement In Place) @ 16:00 Hrs

16:00 0:00 8:00 8 8 1,712.40$ WOC

10 ABC 0:00 0:00 0:00 24 24 5,137.20$ Continue WOC for 48 hrs '- Lay down 40 jts 5" DP and Kelly, '-

Clean up mud tank, '- prepare to Rig down

0:00 18:00 18:00 18 18 3,852.90$ - Continue WOC for 48 hrs - Lower mast

18:00 0:00 6:00 6 6 1,712.40$ - Clean up subtruckture, '- 40 % Rig Down

6:00 18:00 12:00 18 18 3,852.90$

- Continue Rig Down to 70 %, '- Modify mouse Hole pipe to

make longer in progress, '- While waiting on road condition to

move out Rig equipment

18:00 0:00 6:00 6 6 1,712.40$ Wait on day

148.00 7.00 18.00 109.00 282

52,799.00 1,997.80 5,137.20 23,331.45 11.75

Total Hours83,265.45$

4 ABC

5 ABC

8 ABC

ABC

7 ABC

2 ABC

3 ABC

1 ABC

STAND BY

W/O CREW

TOTAL

HOURSTOTAL COST OPERATIONDAY WELL

TIMEOPERATING MOVING

STAND BY

W/CREW

12 ABC

6

9 ABC

11 ABC

COST CONTROLER

Example in Well ABC Drilling

Page 8: Monitor drilling performance

From To Elapsed

6:00 7:00 1:00 1 1 214.05$ Prepare to Spud-In and Pree Job Safety Meeting

7:00 15:00 8:00 8.00 8 2,854.00$ SPUD-IN WEEL ABC At 07:00 hours on 07 november 20xx Drill out

form 12 1/4" Hole to 58 M. stop drill Doe To problem on shale shaker

15:00 17:00 2:00 2 2 570.80$ Repair shale shaker

17:00 0:00 7:00 7.00 7 2,497.25$ Cont'd drill out formation from 58 M to 122 M

0:00 2:30 2:30 2.5 2.5 891.88$ Continued drill out formation from 122 M to 135 M

2:30 3:00 0:30 0.5 0.5 178.38$ Circulated for cleaning hole (GPM: 400, SPP: 240 psi

3:00 6:00 3:00 3.0 3 1,070.25$ POOH 12-1/4" TCB + BHA Assembly from 135 M to surface (found

balling on 12-1/4" bit and 6-1/2" DC

6:00 8:00 2:00 2.0 2 713.50$ RIH back 12-1/4" TCB + BHA Assembly from surface to 135 M

8:00 8:30 0:30 0.5 0.5 178.38$ Circulated for cleaning hole (GPM: 390, SPP: 210 psi

8:30 11:00 2:30 2.5 2.5 891.88$ POOH 12-1/4" TCB + BHA Assembly from 135 M to surface

11:00 15:00 4:00 4 4 1,141.60$ Prepared for RIH csg 9-5/8". PJSM prior to run 9-5/8 "csg

15:00 16:30 1:30 1.5 1.5 535.13$ RIH 9-5/8" casing (11 jts # 40 ppf, K-55, BTC-R3) to 132 M (set shoe 9-

5/8" csg)

16:30 19:30 3:00 3.0 3 1,070.25$ RIH stinger + DP 5" to 132 M for Cementing 9-5/8" csg

19:30 20:00 0:30 0.5 0.5 178.38$ Circulated prior to cementing job. No Cementing engineer stand by at

location ABC

20:00 0:00 4:00 4 4 856.20$ Wait on cementing engineer while break circulated (GPM: 425, SPP:

180 psi)

0:00 7:00 7:00 7 7 1,498.35$ Cont'd wait on cementing engineer while break circulated (GPM: 425,

SPP: 180 psi)

7:00 8:30 1:30 1.5 1.5 535.13$

R/U Cementing line and presure test to 2000 psi, Hold 5 min - ok, '-

Hold safety meeting prior cementing job, Pump preplush as water

ahead, 0,5 m3 @ rate 0.8 m3/min, Mix and pump slurry 15.8 ppg, 6.62

m3 @ rate 0.8 m3/min, Displace w/ water 1.16 m3 @ rate 0.8 m3/min.

Cip (cement in place) @ 08:25 hours.

8:30 15:00 6:30 6.5 6.5 2,318.88$ Pull Out out DP 5" + stringer and L/D same

15:00 0:00 9:00 9 9 1,926.45$ WOC

0:00 9:00 9:00 9 9 1,926.45$ Cont'd WOC

9:00 0:00 15:00 15.0 15 5,351.25$

Break off landing joint and L/D same '- Instaled 9-5/8" x 2000 well head

and prepare to N/U 11" x 5 K BOPS, Moved 44 jts 5-1/2 casing F/Yard to

ABC location (RIG SITE), Moved 10 big saxs of bentonite F/Yard to ABC

6 location

0:00 7:00 7:00 7 7 1,997.80$ Continue rolling crane from ABC base camp to XJ-450 rig site.

7:00 18:00 11:00 11 11 3,924.25$

N/U BOP 11-5/8" X 5 K & relate, fungtion test BOPS "OK". Press

test annular, pipe rams and blind rams to 1000 psi each for 5

minutes "OK".

18:00 20:30 2:30 2.5 2.5 891.88$ RIH W/8-1/2 PDC BIT TO TAC SHOE (132).

20:30 21:30 1:00 1 1 356.75$ Drill out shoe and CMT to 134 M.

21:30 0:00 2:30 2.5 2.5 891.88$ Continue Drill formation 8-1/2" Hole F/134 M to 175 M.

0:00 5:00 5:00 5 5 1,783.75$

Continue drill out formation with 8-1/2" PDC + BHA from 175 m

to 222 m (WOB/RPM/SPP/GPM/Last ROP/ROP Ave.= 1-

klbs/58/480 psi/404 GPM/10.2 mph/19.6 mph), Founded mud

loss 12 bbls/mnt @ interval 220 m - 222 m with lithologi: coal

5:00 6:00 1:00 1 1 356.75$ Circulate while mixing mud in active tank

6:00 23:00 17:00 17 17 6,064.75$

Continue drill out formation with 8-1/2" PDC + BHA from 222 m

to 378 (WOB/RPM/SPP/GPM/Last ROP/ROP Ave.= 1-5

klbs/58/500 psi/448 GPM/47,20 mph/17.9 mph). Stop drilling

formation due to founded loss total @ interval 374 m - 378 m.

total mud loss = 280 bbls. Last lithologi: sandstone (80%),

Claystone(20%)

23:00 23:30 0:30 0.5 0.5 178.38$ POOH 8-1/2" PDC + BHA from 378 m to 250 m while mixing mud

to active tank

23:30 0:00 0:30 0.5 0.5 107.03$ Mixing mud to active tank

0:00 2:30 2:30 2.5 2.5 535.13$ Continue mixing mud to active tank

2:30 3:30 1:00 1 1 356.75$ RIH Back 8-1/2" PDC +BHA from 250 m to 378 m

3:30 4:00 0:30 0.5 0.5 178.38$

Circulate (GPM: 444, SPP: 400 psi). Blind drill with 8-1/2" PDC +

BHA from 378 m to 380 m. founded loss totally. Total mud loss:

390 bbls

4:00 5:00 1:00 1 1 356.75$ POOH 8-1/2" PDC + BHA FROM 378 M TO 318 M while mixing

mud to active tank

5:00 10:00 5:00 5 5 1,070.25$ wait on water for fill active tank and mixing mud

10:00 11:00 1:00 1 1 356.75$ circulate f/check annulus and still founded loss

11:00 13:00 2:00 2 2 713.50$ pull out bit 8-1/2" PDC + BHA from 318 m to 125 m (casing shoe)

while mixing mud + LCM to active tank

13:00 13:30 0:30 0.5 0.5 178.38$ Break circulate (GPM: 444, SPP: 400 psi). At shoe no loss (OK)

13:30 15:00 1:30 1.5 1.5 535.13$ run back from 132 m (casing shoe) to 241 m (6 stand)

15:00 15:30 0:30 0.5 0.5 178.38$ Break circulate (GPM: 444, SPP: 400 psi). Good return

15:30 17:30 2:00 2 2 713.50$ run back from 241 m to 378 m (botton)

17:30 0:00 6:30 6.5 6.5 2,318.88$

drill out formation f/378 to 436 m (WOB/RPM/MFI/SPP/Last

ROP/ROP Ave = 1-9 klbs/40-60/430 GPM/480 psi/25,76

mph/25,21 mph). Founded partial loss 2 - 4 bpm

0:00 1:30 1:30 1.5 1.5 535.13$ Continue drill out formation f/ 436 m to 456 m (Total Depth)

1:30 3:00 1:30 1.5 1.5 535.13$ Circulate for clening hole (GPM: 391, SPP: 460 psi)

3:00 7:00 4:00 4 4 1,427.00$ POOH 8-1/2" PDC + BHA from 456 m to surface for run electrical

logging

7:00 10:00 3:00 3 3 642.15$ R/u DQWL and prepare Tools

10:00 15:30 5:30 5.5 5.5 1,962.13$ Run wireline logging 1. MSFL - DLL - DT - GR - SP - CAL 2. HRL -

GR, R/D DQWL Unit

15:30 18:30 3:00 3 3 1,070.25$ RIH 8-1/2" Bit PDC + BHA to botton (456)

18:30 19:00 0:30 0.5 0.5 178.38$ Circulate for cleaning hole (GPM: 391, SPP: 460 psi)

19:00 23:00 4:00 4 4 1,427.00$ POOH 8-1/2" PDC + BHA from 456 m to surface for running

casing 5-1/2". LTD 5 jts DC 6-1/2", 1 jts DC7", Bit Sub, 8-1/2" PDC

23:00 0:00 1:00 1 1 356.75$ N/D BOP S 11-5/8" x 5K psi

0:00 7:00 7:00 7 7 2,497.25$ Continue N/D BOP S 11-5/8" x 5K psi

7:00 14:30 7:30 7.5 7.5 2,675.63$ Prepare and RIH 5-1/2" caing (# 17 ppf, L-80, BTC-R3) f/surface

to bottom casing at shoe 447 Mkb , FC at 436.42 m .

14:30 15:00 0:30 0.5 0.5 178.38$ P/up kelly for circulate clean hole

15:00 16:00 1:00 1 1 356.75$

R/U cementing line and pressure test to 2000 psi, hold 5 min -

OK '- Hold safety meeting prior cementing job '- Pump preflush

as water ahead 0.5 m3/min @ rate 0.8 m3/min '- Displace

w/water 1.16 m3 @ rate 0.8 m3/min. Bumped to 500 psi no

cement return to surface. CIP (cement In Place) @ 16:00 Hrs

16:00 0:00 8:00 8 8 1,712.40$ WOC

10 ABC 0:00 0:00 0:00 24 24 5,137.20$ Continue WOC for 48 hrs '- Lay down 40 jts 5" DP and Kelly, '-

Clean up mud tank, '- prepare to Rig down

0:00 18:00 18:00 18 18 3,852.90$ - Continue WOC for 48 hrs - Lower mast

18:00 0:00 6:00 6 6 1,712.40$ - Clean up subtruckture, '- 40 % Rig Down

6:00 18:00 12:00 18 18 3,852.90$

- Continue Rig Down to 70 %, '- Modify mouse Hole pipe to

make longer in progress, '- While waiting on road condition to

move out Rig equipment

18:00 0:00 6:00 6 6 1,712.40$ Wait on day

148.00 7.00 18.00 109.00 282

52,799.00 1,997.80 5,137.20 23,331.45 11.75

Total Hours83,265.45$

4 ABC

5 ABC

8 ABC

ABC

7 ABC

2 ABC

3 ABC

1 ABC

STAND BY

W/O CREW

TOTAL

HOURSTOTAL COST OPERATIONDAY WELL

TIMEOPERATING MOVING

STAND BY

W/CREW

12 ABC

6

9 ABC

11 ABC

COST CONTROLER

Example in Well ABC Drilling

Page 9: Monitor drilling performance

Plan Vs. Actual

• Multi engineers, geosciences, & finance together discuss scenario for the completion of the well.

• Finally the (Time –Depth – Cost) curve been generated to monitor Drilling performance.

• TDC curve usually used to presenting Drilling performance

WELL SCHEMATIC PAGE 1 of 1 Job CODE

FIELD : SE Asia WELL NO: ABC CHARGE TO : AFE 12-1234 DATE : 8/8/20xx

RECOMMENDATION : Swab Test & Isolate High WC Zone(s) Well Kill Fluid Density : 8.4 ppg

CURRENT STATUS : Production Est. Pump : 415

LATEST TEST : 5 BOPD %WC (7/31/14) SFL / WFL / FAP : - m/ - m/ - m

RIG DAYS : 11.0 ( all cash ) EST. GAIN : 30 BOPD

RT - GL - KB : 4.7 / 79 / 86.7 PBTD/TD : 455m / 455m WELL TYPE : SOW LOG DATE : 7/11/2012

Important Note:

* Do not kill, equalize well w/FFW as necessary

PROCEDURE:

11 JTS 9 5/8" K-55, 1 Spud in Drill formation to 122 m with 12-1/4” RB, (Nov.7, 2012)

40PPF, R-3 2 Cont’ drilling from 122 m to 134 m, with 12-1/4” RB, Circulate, POOH

BTC CASING, 12¼" TCB + BHA 134 m to surface. RIH back 12¼" TCB + BHA from

SHOE @132m surface to 134 m. Circulate. POOH 12¼" TCB + BHA from 134 m to

surface. RIH 9-5/8" casing (# 40 ppf, K-55, BTC-R3) to 132 M (set shoe

9-5/8" csg). RIH stinger + DP 5" to 132. Circulated. (Nov.8, 2012)

3 Cont’ R/U cementing line and pressure test to 2000 psi, pump flush,

mix and pump slurry 15.8 ppg, 6.62 m3 @ rate 0.8 m3/min, displace

with water. CIP (cement in place) @ 08:25 hrs. Pull out DP 5" + stringer

and L/D same. WOC (Nov.9, 2012)

4 Cont’ WOC. Break out L/D joint and same. Install Well Head 9-

5/8" X 5K psi and Prepare to N/U BOP 11" X 5K psi. (Nov.10, 2012)

S4 5 BOP S 11-5/8" X 5K. M/U and RIH 8-1/2" PDC + BHA to 132 m (Top of

Cement) Drilling & FS w/ 8-1/2" PDC + BHA from 132 m to 134 m with

284.0 - 285.0 m 8-1/2" PDC + BHA from 134 m to 175 m WOB/RPM/SPP/GPM/Last

S5 (05 Jul 20xx) ROP/ROP) (Nov.11, 2012)

6 Cont’ drilling with 8-1/2" PDC + BHA from 175 m to 222 m. Circulate

304.4 - 305.4 m Continue drilling out formation with 8-1/2" PDC + BHA from 222 m to

S6 (12-19 Sep 20xx) 378 m. mud loss = 280 bbls. POOH 8-1/2" PDC + BHA from 378 m to

250 m Nov.(12, 2012)

324.4 - 326.0 m 7 RIH back 8-1/2" PDC + BHA from 250 m to 378 m. Circulate. Pull out bit

8-1/2" PDC + BHA from 318 m to 125 m( casing shoe). Circulate Run

327.0 - 327.6 m back from 132 m ( casing shoe ) to 241 m (6 stand). Circulate . Run

back from 241 m to 378 m (bottom). Drilling formation from378 m to

Pump set (PSN) @340m 329.0 - 329.6 m 436 m (Nov.13, 2012)

S7B 8 Cont’ drill out formation f/ 436 m to 455 m. Circulate. POOH 8-1/2"

PDC + BHA from 455 m to surface for run logging. Run logging 1. MSFL

375.0 - 376.0 m - DLL - DT -GR - SP – CAL 2. HRL – GR RIH 8 1/2" Bit PDC + BHA to

Bottom (455 m). Circulate POOH 8-1/2" PDC + BHA from 455 m to

379.0 - 381.0 m surface for running casing 5 1/2". (Nov.14, 2012)

S7C 9 RIH 5-1/2" casing (# 17 ppf, L-80, BTC-R3) from surface to 447 m (set

csg shoe). Circulate clean hole Cementing job 5-1/2" csg. Pump

392.6 - 393.6 m preflush. CIP (cement in place) at 16:00 WIB hrs. WOC, MLU released

R/D all equipments (Nov.15, 2012)

395.0 - 396.0 m

PBTD @425m (CBL)

Shoe @ 447m

Surface Casing 11 JTS 9-5/8", 40.00ppf, K-55, R3, BTC Casing, shoe @132m

Prod Casing 38 JTS 5-1/2", 17.00 PPF, L-80, R-3,BTC CASING. FLOAT SHOE @447.0m & F.C @436.42m.

PLAN ACTUAL

70.9 BFPD 93

COST US$ : 771,219

TD @ 455m TD @ 455m

RECOMENDATION:The well was drilled to TD @455m on (07-15 Nov 20xx). The well was IC on (02-07 Jul 20xx) by perforating S4 sand (284.0-285.0m). The well was POP on 07 Jul 20xx at 11:00am. Recompletion was done on (12-19 Sep 20xx) to perforate S5 sand (304.4-305.4m), S6 sand (324.4-326.0m, 327.0-327.6m, 329.0-329.6m), S7B sand (375.0-376.0m, 379-381m) and S7C (392.6-393.6m, 395.0-396.0m). After lowering the pump and set PSN @375m on 27 Sep 2013, the well was POP with initial production at 122BFPD/36BOPD/70% WC.

Current production: 70.88BFPD/5.25BOPD/93%WC

Example in Well ABC Drilling

Page 10: Monitor drilling performance

20m 12m

100m 134m

440m 447m

TD @440m TD @455m

TECHNICAL DATA

WELL NAME ABC

LOCATION SE ASIA A -> B Drill hole 12 1/4" until 100 m 0.1 1.0

TARGET X: 123456 B -> C Put & cemen the casing 9 5/8", Prepare to dril l hole 8 1/2" 2.4 2.0

Y: 7654321 C -> D Drill hole 8-1/2" until + 440m 2.3 4.0

Elevation 74 D -> E Put & cement the casing 5 1/2" and put wellhead 1.2 1.2

Dri l l ing type Vertical E -> F perforation and POP 2.5 3.5

Well Class Development

TD 440 meter

Rig 450 hp A -> F Total 8.5 11.7

Rig Floor 4.8m

AFE 12-1234

TIME - DEPTH - COST CURVE

CODE DESCRIPTIONPLAN & ACTUAL

PLAN & ACTUAL

DAYS

$-

$10,000

$20,000

$30,000

$40,000

$50,000

$60,000

$70,000

$80,000

$90,000

-750

-650

-550

-450

-350

-250

-150

-50

0.00 2.00 4.00 6.00 8.00 10.00 12.00 14.00

De

pth

(M

)

Days

PLAN & ACTUAL DRILLING WELL-ABC(DRILLING DESIGN)

C

A

B

C

B

D

E F

Rolling crane from ABCbase camp & Drill out shoe

POOH Due to losses

C

B

D

E F