PowerPoint ® Presentation Chapter 8 Boiler Operation Procedures Taking Over a Shift • First-Time Boiler Start-up Procedures • Routine Boiler Start-up Procedures • Boiler Maintenance Procedures • Boiler Shutdown Procedures • Boiler Inspection • Hydrostatic Test • Boiler Troubleshooting

Low Pressure Boiler Start-up Procedure

Embed Size (px)

Citation preview

Page 1: Low Pressure Boiler Start-up Procedure

PowerPoint® Presentation

Chapter 8Boiler Operation Procedures

Taking Over a Shift • First-Time Boiler Start-up Procedures • Routine Boiler

Start-up Procedures • Boiler Maintenance Procedures • Boiler Shutdown

Procedures • Boiler Inspection • Hydrostatic Test • Boiler Troubleshooting

Page 2: Low Pressure Boiler Start-up Procedure

Chapter 8 — Boiler Operation Procedures

Boiler operation information is communicated to the boiler operator starting the shift to specify any special procedures required.

Page 3: Low Pressure Boiler Start-up Procedure

Chapter 8 — Boiler Operation Procedures

When blowing down the gauge glass, water should enter the gauge glass quickly when the gauge glass blowdown valve is closed.

Page 4: Low Pressure Boiler Start-up Procedure

Chapter 8 — Boiler Operation Procedures

During a bottom blowdown, the boiler should be under light load and the water level should be at the NOWL.

Page 5: Low Pressure Boiler Start-up Procedure

Chapter 8 — Boiler Operation Procedures

The blowdown valve is opened to evacuate the low water fuel cutoff chamber with the burner firing during blowdown.

Page 6: Low Pressure Boiler Start-up Procedure

Chapter 8 — Boiler Operation Procedures

When testing the flame scanner, the flame scanner sensor is covered to simulate a flame failure.

Page 7: Low Pressure Boiler Start-up Procedure

Chapter 8 — Boiler Operation Procedures

Before starting the boiler for the first time, the boiler should have a minimum water level of approximately 2″ above the bottom of the gauge glass.

Page 8: Low Pressure Boiler Start-up Procedure

Chapter 8 — Boiler Operation Procedures

The burner is started in low fire according to procedures specified by the manufacturer.

Page 9: Low Pressure Boiler Start-up Procedure

Chapter 8 — Boiler Operation Procedures

The boiler vent is closed when pressure in the boiler reaches 10 psi to 15 psi.

Page 10: Low Pressure Boiler Start-up Procedure

Chapter 8 — Boiler Operation Procedures

The main steam stop valve is opened slowly to allow the pressure to equalize when the boiler is a few pounds below the header pressure.

Page 11: Low Pressure Boiler Start-up Procedure

Chapter 8 — Boiler Operation Procedures

A broken or discolored gauge glass is replaced using standard procedures for maximum safety.

Page 12: Low Pressure Boiler Start-up Procedure

Chapter 8 — Boiler Operation Procedures

The low water fuel cutoff controls must be installed vertically for proper performance.

Page 13: Low Pressure Boiler Start-up Procedure

Chapter 8 — Boiler Operation Procedures

The burner is maintained and tested to ensure proper operation and maximum efficiency.

Page 14: Low Pressure Boiler Start-up Procedure

Chapter 8 — Boiler Operation Procedures

Feedwater pumps should be checked periodically to ensure proper bearing temperatures and checked for any unusual vibration.

Page 15: Low Pressure Boiler Start-up Procedure

Chapter 8 — Boiler Operation Procedures

Safety valves are routinely tested to ensure proper operation and must be serviced by an authorized manufacturer representative.

Page 16: Low Pressure Boiler Start-up Procedure

Chapter 8 — Boiler Operation Procedures

Steam traps are checked for proper operation when determining the cause of a steambound feedwater pump.

Page 17: Low Pressure Boiler Start-up Procedure

Chapter 8 — Boiler Operation Procedures

When inspecting a boiler, inspect tube sheets, tubes, and other internal parts for corrosion, overheating, and/or other damage.

Page 18: Low Pressure Boiler Start-up Procedure

Chapter 8 — Boiler Operation Procedures

Handhole covers are removed to provide access to boiler parts during a boiler inspection.

Page 19: Low Pressure Boiler Start-up Procedure

Chapter 8 — Boiler Operation Procedures

All internal surfaces are exposed and cleaned prior to the boiler inspection.

Page 20: Low Pressure Boiler Start-up Procedure

Chapter 8 — Boiler Operation Procedures

Troubleshooting steps from the manufacturer provide a guide to correcting a boiler operation problem.

Page 21: Low Pressure Boiler Start-up Procedure

Chapter 8 — Boiler Operation Procedures

The boiler room log lists boiler operation data that can be used to increase boiler efficiency and identify a potential malfunction.