High Pressure Process Critical Instrument Autorodder installation CLEARGUARD Page 1

High Pressure, Critical Service Instrument - Autorodder Installation

Embed Size (px)

Citation preview

Page 1: High Pressure, Critical Service Instrument - Autorodder Installation

High Pressure ProcessCritical Instrument

Autorodder installation

CLEARGUARD

Page 1

Page 2: High Pressure, Critical Service Instrument - Autorodder Installation

Before

50 Bar (725 PSI) Process Pressure Manual rod-out frequency = once per 6 weeks (Preventative maintenance schedule)

CLEARGUARD

Page 2

Page 3: High Pressure, Critical Service Instrument - Autorodder Installation

BeforeCLEARGUARD

Page 3

Associated costs = Temporary access platform, staff (x2), Production loss Risks = Working at height, in the line of fire

Page 4: High Pressure, Critical Service Instrument - Autorodder Installation

1st InstallationCLEARGUARD

Page 4

2” ANSI 300# Autorodder80mm (3 1/4”) dia. Cylinder, 500mm (19 2/3”) Stroke

Page 5: High Pressure, Critical Service Instrument - Autorodder Installation

3rd InstallationCLEARGUARD

Page 5

2” ANSI 300# Double Block & Bleed Plug ValveAutorodder

80mm (3 1/4”) dia. Cylinder, 640mm (25 1/5”) Stroke

Page 6: High Pressure, Critical Service Instrument - Autorodder Installation

4th InstallationCLEARGUARD

Page 6

2” ANSI 300# Autorodder80mm (3 1/4”) dia. Cylinder, 500mm (19 2/3”) Stroke

Page 7: High Pressure, Critical Service Instrument - Autorodder Installation

Result

Happy Customer

CLEARGUARD

Page 7

Page 8: High Pressure, Critical Service Instrument - Autorodder Installation

Benefits

No more manual rod outs

Increased safety

Consistent, reliable, accurate Pv measurement

Cost effective

CLEARGUARD

Page 8

Page 9: High Pressure, Critical Service Instrument - Autorodder Installation

www.clearguard.com