Upload
informa-australia
View
78
Download
0
Embed Size (px)
Citation preview
Introductions
Andrew Logan
Manager Infrastructure & Engineering Services, Lord Howe Island Board
David Pollington
COO UPC Renewables Australia
(previously project OE PM with Jacobs)
3
Agenda
1. About the Island
2. Why the Project is Needed
3. Project Objectives
4. The Community
5. Site Constraints
6. Moving towards a Solution
4
Lord Howe Island Overview
• 700 kilometres north-east of
Sydney
• Settled in 1834
• No indigenous population
• World Heritage listed in 1982
Lord Howe Island
5
Lord Howe Island Overview
• 11 km long
• 300m to 2 km wide
• 2/3 of the Island is Permanent Park Preserve
• 360 residents
• Tourism is main industry
• Maximum 400 tourists
• Administered by the Lord Howe Island Board
Why the Project is Needed?
• Currently consume ~ 540,000L of diesel for power generation p.a.
• Power Saving Measures have largely been exhausted
– Diesel engines upgraded units in 2008
– 120kW of private solar panels installed since 2011
– Energy efficiency programs
– Fridge replacement programs
– Electricity use is controlled
• Potential winding back of NSW Government funding
6
7
Project Objectives
• Sustainable electricity generation for the Island at current high level quality of supply
• Improve community’s self-sufficiency
• Protecting the Island’s World Heritage and tourism values
• Lowest long term cost of energy production and reduce the impact of diesel price escalation
• Provide a pathway for other technologies such as electrical vehicles to be introduced
• A system that can be maintained and operated by the LHIB electricity generation team
• Provide a show case of what is possible in a remote community
Island Constraints - Solar Land Area
Wind, Solar and Battery Option
Equivalent Solar and Battery Option
450kW
T01
400kWh
battery
T02
2000kWh
battery
450kW
250kW
551kW
507kW 441kW
801kW
17
500m to largest lodge on Island
280m to nearest residence
Home to 8,000 breeding pairs of the EPBC listed migratory bird – flesh-footed shearwater
200m to Airservices Australia aviation navigation equipment
Island Constraints - Air Services Australia Navigation Equipment
18
Existing Electricity System
• Existing Generation– Main Powerhouse 3 x 300kW
– Manual Back Up Generator 1 x 424kW
– 120kW of Private Roof Top Solar approved – most connected
• All underground reticulation 6.6kV and 415V
22
Existing Electricity System
• System Load
– Average 260kW
– Min 160kW
– Max 460kW
– No significant motor loads
– Minimal seasonal variation
– Typical Diurnal pattern
– Load profile consistent across the week
23
Proposed Solution
• Option 1, consisting of:
– 2 x 200kW of Wind Generation
– 450kWac of Solar PV
– 400kW/400kWh of battery storage
• Option 2 consisting of:
– 550kWac of Solar PV
– 400kW/400kWh of battery storage
• In both cases– Sizing to be further optimised during detail design
– Overall Control System including existing diesel gensets
24
Projected Fuel Savings
Option 1Diesel Fuel Consumption (litres) 180,000
Reduction in Fuel Consumption (%) 67
Option 2Diesel Fuel Consumption (litres) 350,000
Reduction in Fuel Consumption (%) 35
25
Modelling
• Calculations performed using Homer
• Solar and wind potential outputs calculated by Homer checked with PVSyst and WAsP
• More than 15 months of onsite wind and solar data recorded at a minimum of 10min average with many months of 1min average data
• Actual Load data recorded for a number of years on 1 minute average basis
• Private solar actual performance over 12 months monitored and compared with solar record.
26
Current Project Status
• Solar PV and Battery Installation DA approved
• WTG approval not yet obtained
– LHIB as the consent authority has approved the project subject to undertaking some additional work to be done to support the DA application
– ASA has requested some additional modelling
– Commonwealth Government is currently assessing the EPBC referral
• Solar PV, Battery and Control System has been tendered
29
Timing
• Project is currently targeting completion in late 2018
• Commence construction of the Solar PV and Battery – August 2017
• Installation of over all control system late 2017
• Commence construction of the wind turbines mid 2018
• Staged commissioning commencing late 2017
30
Further Enhancement
• Predictive Technologies for Wind and Solar
• Smart Meter Installation on the Island
• Electric Cars and Charging Stations
• Increased renewables penetration
• Distributed storage options
31