32
Lord Howe Island Hybrid Renewable Energy Project

David Pollington - Lord Howe Island Board & Andrew Logan - UPC Renewables

Embed Size (px)

Citation preview

Lord Howe IslandHybrid Renewable Energy Project

Introductions

Andrew Logan

Manager Infrastructure & Engineering Services, Lord Howe Island Board

David Pollington

COO UPC Renewables Australia

(previously project OE PM with Jacobs)

3

Agenda

1. About the Island

2. Why the Project is Needed

3. Project Objectives

4. The Community

5. Site Constraints

6. Moving towards a Solution

4

Lord Howe Island Overview

• 700 kilometres north-east of

Sydney

• Settled in 1834

• No indigenous population

• World Heritage listed in 1982

Lord Howe Island

5

Lord Howe Island Overview

• 11 km long

• 300m to 2 km wide

• 2/3 of the Island is Permanent Park Preserve

• 360 residents

• Tourism is main industry

• Maximum 400 tourists

• Administered by the Lord Howe Island Board

Why the Project is Needed?

• Currently consume ~ 540,000L of diesel for power generation p.a.

• Power Saving Measures have largely been exhausted

– Diesel engines upgraded units in 2008

– 120kW of private solar panels installed since 2011

– Energy efficiency programs

– Fridge replacement programs

– Electricity use is controlled

• Potential winding back of NSW Government funding

6

7

Project Objectives

• Sustainable electricity generation for the Island at current high level quality of supply

• Improve community’s self-sufficiency

• Protecting the Island’s World Heritage and tourism values

• Lowest long term cost of energy production and reduce the impact of diesel price escalation

• Provide a pathway for other technologies such as electrical vehicles to be introduced

• A system that can be maintained and operated by the LHIB electricity generation team

• Provide a show case of what is possible in a remote community

Community Engagement

8

Community Engagement

9

Island Constraints and Challenges

10

11

Island Constraints and Challenges

Island Constraints - Solar Land Area

Wind, Solar and Battery Option

Equivalent Solar and Battery Option

450kW

T01

400kWh

battery

T02

2000kWh

battery

450kW

250kW

551kW

507kW 441kW

801kW

Island Constraints - Solar Site Terrain

15

Island Constraints - Wind Site Terrain

16

17

500m to largest lodge on Island

280m to nearest residence

Home to 8,000 breeding pairs of the EPBC listed migratory bird – flesh-footed shearwater

200m to Airservices Australia aviation navigation equipment

Island Constraints - Air Services Australia Navigation Equipment

18

19

Island Constraints – Close Proximity to Neighbours

Island Challenges - Noise

20

Site Constraints and Challenges

21

Existing Electricity System

• Existing Generation– Main Powerhouse 3 x 300kW

– Manual Back Up Generator 1 x 424kW

– 120kW of Private Roof Top Solar approved – most connected

• All underground reticulation 6.6kV and 415V

22

Existing Electricity System

• System Load

– Average 260kW

– Min 160kW

– Max 460kW

– No significant motor loads

– Minimal seasonal variation

– Typical Diurnal pattern

– Load profile consistent across the week

23

Proposed Solution

• Option 1, consisting of:

– 2 x 200kW of Wind Generation

– 450kWac of Solar PV

– 400kW/400kWh of battery storage

• Option 2 consisting of:

– 550kWac of Solar PV

– 400kW/400kWh of battery storage

• In both cases– Sizing to be further optimised during detail design

– Overall Control System including existing diesel gensets

24

Projected Fuel Savings

Option 1Diesel Fuel Consumption (litres) 180,000

Reduction in Fuel Consumption (%) 67

Option 2Diesel Fuel Consumption (litres) 350,000

Reduction in Fuel Consumption (%) 35

25

Modelling

• Calculations performed using Homer

• Solar and wind potential outputs calculated by Homer checked with PVSyst and WAsP

• More than 15 months of onsite wind and solar data recorded at a minimum of 10min average with many months of 1min average data

• Actual Load data recorded for a number of years on 1 minute average basis

• Private solar actual performance over 12 months monitored and compared with solar record.

26

Private Solar PV - Performance

27

Current Project Status

• Solar PV and Battery Installation DA approved

• WTG approval not yet obtained

– LHIB as the consent authority has approved the project subject to undertaking some additional work to be done to support the DA application

– ASA has requested some additional modelling

– Commonwealth Government is currently assessing the EPBC referral

• Solar PV, Battery and Control System has been tendered

29

Timing

• Project is currently targeting completion in late 2018

• Commence construction of the Solar PV and Battery – August 2017

• Installation of over all control system late 2017

• Commence construction of the wind turbines mid 2018

• Staged commissioning commencing late 2017

30

Further Enhancement

• Predictive Technologies for Wind and Solar

• Smart Meter Installation on the Island

• Electric Cars and Charging Stations

• Increased renewables penetration

• Distributed storage options

31