18
BUILDING A GARAGE 24 X24

Building a garage

Embed Size (px)

Citation preview

Page 1: Building a garage

BUILDING A GARAGE

24 X24

Page 2: Building a garage

SCOPE STATEMENT

I would like to build your garage at your standards. That will include being built in a timely manner. Your recommendations will be taken serious. We will try to accommodate your request of changes to the best of our ability, without changing the time line. We will base the cost of the project to be set at around 12,000 dollars and take about 3 months to build giving the weather is good .

Page 3: Building a garage

Building a Garage step by stepPLANNING

Planning1. Area

• look for flooding• sloping of the land• surveyed

2.Get permits3.Order material4.Hire workers5.Get tools Development6.Layout the area with chalk7.Dig holes (10)

Execution8.Set poles with concrete

• Smooth put area• Frame up the footer• Lay wire mess• Deliver concert• Poor concrete

9. Put up trusses • deliver trusses • hang trusses• lay plywood• lay sheath• lay felt• put shingles on 10. Frame up the side

11. Put ply wood on outside walls Final

12. Install window13. Install electric 14. Install garage door and man door

Page 4: Building a garage

Prints

Page 5: Building a garage

COMMUNICATION PLAN

Communication Method Meduim Facilitator Participants Purpose Frequency

Weekly status report E-mail Project manager RB and BT

to update the status of all activities,reports on

those activities expected to be

accomplished in the next week

Weekly

Project Meeting Conference call /face to face Project manager PM/RB

Supervisor/ET

to initiate the eprojectand the

progress and resolve any issues

Daily

Notification/Communications E-mail Anyone Anyone

To maintain the progress of the

implemention and coordinate project

issues

As Required

End of day Meeting Face to Face/Phone call Project manager Supervisor/ET

to discusse the issues of the day

and where to start tomorrow

Daily

Page 6: Building a garage

RESOURCESUnit of Cost

(hour,day,week, month Fixed)

Level of Risk High, Medium, or Low

Resourceskill level

or Material Quality

Associated Tasks Duration Required

Available Time

RequiredCost

HOURS

MIKE 15 yrs.SUPERVISOR/WORKER 2 month 52.00 $20.00 $1,040.00 LOW

DAN 10yrs LEAD MAN 2 month 50.75 $18.00 $913.50 LOW

JOE 1yr LABOR 2 month 50.75 $15.00 $761.25 MEDIUM

JIM 1yr LABOR 2 month 50.75 $15.00 $761.25 MEDIUM

DOUG 1yr LABOR 2 month 50.75 $15.00 $761.25 MEDIUM

Total Labor 255.00 $83.00 $4,237.25

HOMDEPOT 30 yrs. Materials 1 Day $3,892.00 MEDIUM

Grays Electrical 10 yrs. Installation 1 Day 8 $55.00 $440.00 MEDIUM

Garage Doors/Windo

w's R US

15 yrs. Installation 1 Day 8 $1,369.00 MEDIUM

twin city concret Delivery/Materials 1 Day 2

$1,050.00MEDIUM

stark trusses Delivery/Materials 1 Day 1 $300.00 MEDIUM

Total $11,288.25

Page 7: Building a garage

RISK ANALYSISRisk Analysis

1 funding

2 weather

3 labor

4 on time delivery

likely hood

low med high

effectlow

med 3

high 1 4 2

I am excepting the risk.the highest one is the weather so I will keep my eye on the weather and

purchase a tarp just in case.

Page 8: Building a garage

WBS PHASE 1FLOORING             PHASE 1

WIRE MESS 6X6 W1.4XW1.4 576.00 sf $10.30 $206.00 576/SF7.25/42*84

POST 4X4 8’ 2.00 ea. $7.77 $15.54  

POST 4X4 8’ 2.00 ea. $7.77 $15.54 2/EA7.77

POST 4X4 4’ 1.00 ea. $7.77 $7.77 1/EA7.77

 POST 4X4 9’ 1.00 ea. $12.70 $12.70 1/EA12.70

POST 4X4 11’ 1.00 ea. $14.20 $14.20 1/EA

 CONCRETE (FOOTING) 12”X6”   1.78 cy $90.00 $160.20  

CONCRETE (STEM) 6”X 20”   2.96 cy $90.00 $266.40  

CONC. FTING(DOORWAY SLAB)(1) 48”X48”X4” DP   0.20 cy $90.00 $18.00  

2*4 2*4 12' 100.00 ft $0.89 $89.00  

CONC. FTING (RIDGE SUPPORT)(1) 26”X 26” X 12” DP   0.17 cy $75.00 $12.75  

CONC. FTING (GARAGE DOOR)(2) 20”X20”X10” DP   0.17 cy $75.00 $12.75  

CONCRETE (FLOOR) 4”   7.11 cy $75.00 $533.25  

TOTAL MATERIAL           $1,364.10 TOTAL

TOTAL LABOR HOUR 5.00 DAYS 16.00 2DAYS $83.00 $1,577.00 $2,941.10

Page 9: Building a garage

WBS PHASE 2

ITEM: SIZE: LENGTH: NEEDED DESCRIPT PRICE TOTAL  

ROOF             PHASE 2

 H2.5 RAFTER TIE   16’ 38.00 ea. $0.84 $31.92

 ROOF SHEATH 1/2” CDX   956.00 sf $0.11 $154.00 700sf roll

ROOF FELT 30# FELT   956.00 sf $0.11 $118.80 216 sf roll

2*4 2*4 12' 50.00 ft $0.89 $44.50  

ROOFING shingles     956.00 sf $10.26 $307.80 956/SF/27.0 21/bundle 3bundle per 100sf

BARGE RAFTERS 2X6 19’ 4.00 ea. $6.97 $27.88  

HEADER (INT MAIN DOOR) 4X8   1.00 ea. $45.00 $45.00  

 HEADER (MAIN WINDOW) 4X10 7’ 1.00 ea. $55.00 $55.00  

TRUSSES     38.00 ea. $4.50 $171.00  

TOTAL MATERIALS           $955.90 TOTAL

TOTAL LABOR HOUR 5.00 DAYS 14.00 HRS $83.00 $1,162.00 $2,117.90

Page 10: Building a garage

WBS PHASE 3 &4ITEM: SIZE: LENGTH: NEEDED DESCRIPT PRICE TOTAL PHASE 3

FRAMING PHASE 3 EXT WALL SHEATH ½” CDX 981.00 sf $0.11 $154.00 981/SF.11/700sf EXT WALL VAPOR 15# FELT 981.00 sf $0.12 $155.52 981/SF15.15 432sf MAIN EXT STUDS 2X6 95.13 57.00 ea. $2.49 $141.93 UPPER INT PLATES 2X4 144.00 lf $0.15 $21.60Cement 60lb 10.00 bg $3.99 $39.90 UPPER INT WALL STUDS 2X4 5’ 37.00 EA $4.05 $149.85PLYWOOD 4*8 150.00 EA $1.25 $187.50 HEADER(MAIN GAR DOOR) 5-1/8X15 GLB 17’ 1.00 EA $54.56 $54.562*4 2*4 12' 75.00 ft $0.89 $66.75 JOISTS 16 TJI 360 24’ 19.00 ea. $3.00 $57.00 RIM JOIST 96.00 lf $0.86 $82.56 96/LF19.0TOTAL MATERIALS $1,111.17 TOTALTO TAL LABO R HOUR 5.00 DAYS 19.00 HR $83.00 $1,577.00 $2,688.17

ELECTRICIAN PHASE 4install electricity and run power 8.00 hr. $55.00 $440.00

install electricity out lets TOTALTOTAL LABOR HOUR 8.00 hr. $55.00 $440.00 440.00

Page 11: Building a garage

WBS 4.5INSTALLATION/WORKERS

Installation PHASE 4.5Garage door installation $1,030.00

window installation $495.00 TOTALMan door $590.00 $2,115.00

  WO RKERS RATE/HR T/H T/CSPONSER BTPM RBSUPERVISOR/WORKER MIKE $20.00 52.00 $1,040.00LEAD MAN DAN $18.00 50.75 $913.50LABOR JOE $15.00 50.75 $761.25LABOR JIM $15.00 50.75 $761.25LABOR DOUG $15.00 50.75 $761.25TOTAL $83.00 255.00 $4,237.25

Page 12: Building a garage

COSTS BREAKDOWN CHART

Task Labor cost Cost of materials Total price Share of cost (%)

Roof (asphalt shingles) $1,162.00 $955.90 $2,117.90 19%Framing $1,577.00 $1,111.17 $2,688.17 24%

Electricity $440.00 $440.00 4%Delivery $525.00 5%Other $461.44 $461.44 4%

TOTAL $6,871.00 $3,892.61 $11,288.61 100%

Garage construction costs breakdown chart1

Concrete and foundation $1,577.00 $1,364.10 $2,941.10 26%

Garage door (1) window(1) Man Door (1) $2,115.00 $2,115.00 19%

Page 13: Building a garage

TASK USAGE

Page 14: Building a garage

TASK USAGE

Page 15: Building a garage

TASK USAGE

Page 16: Building a garage

TASK SHEET

Page 17: Building a garage

GANTT CHART

Page 18: Building a garage

Finished Product