BUILDING A GARAGE
24 X24
SCOPE STATEMENT
I would like to build your garage at your standards. That will include being built in a timely manner. Your recommendations will be taken serious. We will try to accommodate your request of changes to the best of our ability, without changing the time line. We will base the cost of the project to be set at around 12,000 dollars and take about 3 months to build giving the weather is good .
Building a Garage step by stepPLANNING
Planning1. Area
• look for flooding• sloping of the land• surveyed
2.Get permits3.Order material4.Hire workers5.Get tools Development6.Layout the area with chalk7.Dig holes (10)
Execution8.Set poles with concrete
• Smooth put area• Frame up the footer• Lay wire mess• Deliver concert• Poor concrete
9. Put up trusses • deliver trusses • hang trusses• lay plywood• lay sheath• lay felt• put shingles on 10. Frame up the side
11. Put ply wood on outside walls Final
12. Install window13. Install electric 14. Install garage door and man door
Prints
COMMUNICATION PLAN
Communication Method Meduim Facilitator Participants Purpose Frequency
Weekly status report E-mail Project manager RB and BT
to update the status of all activities,reports on
those activities expected to be
accomplished in the next week
Weekly
Project Meeting Conference call /face to face Project manager PM/RB
Supervisor/ET
to initiate the eprojectand the
progress and resolve any issues
Daily
Notification/Communications E-mail Anyone Anyone
To maintain the progress of the
implemention and coordinate project
issues
As Required
End of day Meeting Face to Face/Phone call Project manager Supervisor/ET
to discusse the issues of the day
and where to start tomorrow
Daily
RESOURCESUnit of Cost
(hour,day,week, month Fixed)
Level of Risk High, Medium, or Low
Resourceskill level
or Material Quality
Associated Tasks Duration Required
Available Time
RequiredCost
HOURS
MIKE 15 yrs.SUPERVISOR/WORKER 2 month 52.00 $20.00 $1,040.00 LOW
DAN 10yrs LEAD MAN 2 month 50.75 $18.00 $913.50 LOW
JOE 1yr LABOR 2 month 50.75 $15.00 $761.25 MEDIUM
JIM 1yr LABOR 2 month 50.75 $15.00 $761.25 MEDIUM
DOUG 1yr LABOR 2 month 50.75 $15.00 $761.25 MEDIUM
Total Labor 255.00 $83.00 $4,237.25
HOMDEPOT 30 yrs. Materials 1 Day $3,892.00 MEDIUM
Grays Electrical 10 yrs. Installation 1 Day 8 $55.00 $440.00 MEDIUM
Garage Doors/Windo
w's R US
15 yrs. Installation 1 Day 8 $1,369.00 MEDIUM
twin city concret Delivery/Materials 1 Day 2
$1,050.00MEDIUM
stark trusses Delivery/Materials 1 Day 1 $300.00 MEDIUM
Total $11,288.25
RISK ANALYSISRisk Analysis
1 funding
2 weather
3 labor
4 on time delivery
likely hood
low med high
effectlow
med 3
high 1 4 2
I am excepting the risk.the highest one is the weather so I will keep my eye on the weather and
purchase a tarp just in case.
WBS PHASE 1FLOORING PHASE 1
WIRE MESS 6X6 W1.4XW1.4 576.00 sf $10.30 $206.00 576/SF7.25/42*84
POST 4X4 8’ 2.00 ea. $7.77 $15.54
POST 4X4 8’ 2.00 ea. $7.77 $15.54 2/EA7.77
POST 4X4 4’ 1.00 ea. $7.77 $7.77 1/EA7.77
POST 4X4 9’ 1.00 ea. $12.70 $12.70 1/EA12.70
POST 4X4 11’ 1.00 ea. $14.20 $14.20 1/EA
CONCRETE (FOOTING) 12”X6” 1.78 cy $90.00 $160.20
CONCRETE (STEM) 6”X 20” 2.96 cy $90.00 $266.40
CONC. FTING(DOORWAY SLAB)(1) 48”X48”X4” DP 0.20 cy $90.00 $18.00
2*4 2*4 12' 100.00 ft $0.89 $89.00
CONC. FTING (RIDGE SUPPORT)(1) 26”X 26” X 12” DP 0.17 cy $75.00 $12.75
CONC. FTING (GARAGE DOOR)(2) 20”X20”X10” DP 0.17 cy $75.00 $12.75
CONCRETE (FLOOR) 4” 7.11 cy $75.00 $533.25
TOTAL MATERIAL $1,364.10 TOTAL
TOTAL LABOR HOUR 5.00 DAYS 16.00 2DAYS $83.00 $1,577.00 $2,941.10
WBS PHASE 2
ITEM: SIZE: LENGTH: NEEDED DESCRIPT PRICE TOTAL
ROOF PHASE 2
H2.5 RAFTER TIE 16’ 38.00 ea. $0.84 $31.92
ROOF SHEATH 1/2” CDX 956.00 sf $0.11 $154.00 700sf roll
ROOF FELT 30# FELT 956.00 sf $0.11 $118.80 216 sf roll
2*4 2*4 12' 50.00 ft $0.89 $44.50
ROOFING shingles 956.00 sf $10.26 $307.80 956/SF/27.0 21/bundle 3bundle per 100sf
BARGE RAFTERS 2X6 19’ 4.00 ea. $6.97 $27.88
HEADER (INT MAIN DOOR) 4X8 1.00 ea. $45.00 $45.00
HEADER (MAIN WINDOW) 4X10 7’ 1.00 ea. $55.00 $55.00
TRUSSES 38.00 ea. $4.50 $171.00
TOTAL MATERIALS $955.90 TOTAL
TOTAL LABOR HOUR 5.00 DAYS 14.00 HRS $83.00 $1,162.00 $2,117.90
WBS PHASE 3 &4ITEM: SIZE: LENGTH: NEEDED DESCRIPT PRICE TOTAL PHASE 3
FRAMING PHASE 3 EXT WALL SHEATH ½” CDX 981.00 sf $0.11 $154.00 981/SF.11/700sf EXT WALL VAPOR 15# FELT 981.00 sf $0.12 $155.52 981/SF15.15 432sf MAIN EXT STUDS 2X6 95.13 57.00 ea. $2.49 $141.93 UPPER INT PLATES 2X4 144.00 lf $0.15 $21.60Cement 60lb 10.00 bg $3.99 $39.90 UPPER INT WALL STUDS 2X4 5’ 37.00 EA $4.05 $149.85PLYWOOD 4*8 150.00 EA $1.25 $187.50 HEADER(MAIN GAR DOOR) 5-1/8X15 GLB 17’ 1.00 EA $54.56 $54.562*4 2*4 12' 75.00 ft $0.89 $66.75 JOISTS 16 TJI 360 24’ 19.00 ea. $3.00 $57.00 RIM JOIST 96.00 lf $0.86 $82.56 96/LF19.0TOTAL MATERIALS $1,111.17 TOTALTO TAL LABO R HOUR 5.00 DAYS 19.00 HR $83.00 $1,577.00 $2,688.17
ELECTRICIAN PHASE 4install electricity and run power 8.00 hr. $55.00 $440.00
install electricity out lets TOTALTOTAL LABOR HOUR 8.00 hr. $55.00 $440.00 440.00
WBS 4.5INSTALLATION/WORKERS
Installation PHASE 4.5Garage door installation $1,030.00
window installation $495.00 TOTALMan door $590.00 $2,115.00
WO RKERS RATE/HR T/H T/CSPONSER BTPM RBSUPERVISOR/WORKER MIKE $20.00 52.00 $1,040.00LEAD MAN DAN $18.00 50.75 $913.50LABOR JOE $15.00 50.75 $761.25LABOR JIM $15.00 50.75 $761.25LABOR DOUG $15.00 50.75 $761.25TOTAL $83.00 255.00 $4,237.25
COSTS BREAKDOWN CHART
Task Labor cost Cost of materials Total price Share of cost (%)
Roof (asphalt shingles) $1,162.00 $955.90 $2,117.90 19%Framing $1,577.00 $1,111.17 $2,688.17 24%
Electricity $440.00 $440.00 4%Delivery $525.00 5%Other $461.44 $461.44 4%
TOTAL $6,871.00 $3,892.61 $11,288.61 100%
Garage construction costs breakdown chart1
Concrete and foundation $1,577.00 $1,364.10 $2,941.10 26%
Garage door (1) window(1) Man Door (1) $2,115.00 $2,115.00 19%
TASK USAGE
TASK USAGE
TASK USAGE
TASK SHEET
GANTT CHART
Finished Product