Activity types & RelationshipsBy Er.Nikil Raj…Creating logic in your project
CRITICAL PATH SCHEDULE EARLY
START ORACLE LATE START
PLANNING EARLY START ORACLE
Primavera SLACK FORWARD PASS
EPS PASS
Copyright © all rights reserved to www.tutomaash.com | any queries can be mailed to [email protected]
05/01/2023
2
Activity types
START MILESTONEFINISH MILESTONE
TASK DEPENDENT RESOURCE
DEPENDENT
LEVEL OF EFFORTWBS SUMMARY
05/01/2023
3
START MILESTONE
FINISH MILESTONE
Start milestone activities displays start date
Finish milestone activities displays finish date0DURATION
ACTIVITIES
05/01/2023
4
TASK DEPENDENT RESOURCE
DEPENDENTTASK DEPENDENT
ACTIVITYRESOURCE DEPENDENT
ACTIVITY
RESOURCE CALENDAR
PROJECT CALENDAR
05/01/2023
5
LEVEL OF EFFORT
FOUNDATION
SUPER STRUCTURE
FINISH WORK
PROJECT MANAGEMENT (LOE)
SSFF
30d30d
30d
90dDuration is calculated from its
relationships• Level of effort activities cannot have constraints assigned to them.
• Level of effort activities are not included when leveling resources.
NOTE
05/01/2023
6
WBS SUMMARY
4TH Floor Roof Slab – 10 day• Marking - 1day• Wall reinforcement - 3day• wall shuttering - 2 day• Roof slab shuttering - 1 day• Slab reinforcement - 2 day• Slab concreting - 1 day• Total slab duration (WBS summary) –
10 day
WBS Summary Activities will follow its
WBS Summary duration
05/01/2023
7
RelationshipsACTIVIT
Y AACTIVIT
Y B
ACTIVITY A
ACTIVITY B
ACTIVITY A
ACTIVITY B
ACTIVITY B
ACTIVITY A
ACTIVITY B
ACTIVITY A
ACTIVITY B
ACTIVITY A
FSSF
SSFF
FS-1D
FS+1D
LEAD
LAG
1D
1D
FINISH TO START
START TO FINISH
START TO START
FINISH TO FINISH