Hinkley Point Nuclear New Build

Hugh Hutton

Severn Estuary Forum

Gloucester, Friday 11 September 2009

Page 2: 2009 07 EDF Energy - Hugh Hutton

British Energy Public Meeting, Nether Stowey, Monday 20th October 2008Richard Mayson, Nuclear Counsel© Copyright EDF Energy plc. All rights reserved. 2006. 2

About EDF Energy

•UK’s biggest electricity generator

– Nuclear– Coal– Gas– Wind– Combined heat and power

•Largest UK electricity network operator

•Gas and electricity supplier to 5.5 million customers

Page 3: 2009 07 EDF Energy - Hugh Hutton

British Energy Public Meeting, Nether Stowey, Monday 20th October 2008Richard Mayson, Nuclear Counsel© Copyright EDF Energy plc. All rights reserved. 2006. 3 333

Helps combat climate change

Reduces reliance on imported gas

Benefits customers and UK competitiveness

The policy case for nuclear

Low CarbonEmissions

Security of Supply

Stability of Costs

Page 4: 2009 07 EDF Energy - Hugh Hutton

British Energy Public Meeting, Nether Stowey, Monday 20th October 2008Richard Mayson, Nuclear Counsel© Copyright EDF Energy plc. All rights reserved. 2006. 4

EDF is committed to new nuclear in the UK

• EDF Energy intends to build four nuclear units in the UK by 2025 – subject to a robust investment framework

• EDF Energy’s target for completion of first new nuclear power station in the UK is end of 2017

• Technology choice is EPR – 1650 MWe PWR• Preferred sites are in the south of England

• Hinkley Point in Somerset – 2x EPR• Sizewell in Suffolk – 2x EPR• Other sites may also be needed

Page 5: 2009 07 EDF Energy - Hugh Hutton

British Energy Public Meeting, Nether Stowey, Monday 20th October 2008Richard Mayson, Nuclear Counsel© Copyright EDF Energy plc. All rights reserved. 2006. 5

UK nuclear power station sites

EDF/BE nuclear power stations

Site nominated for new build*

Sizewell

Torness

Hartlepool

Dungeness

Hunterston

Heysham

Hinkley Point

Wylfa

Oldbury Bradwell

SellafieldKirksanton

Braystones

*The nomination process for potential new build sites does

not apply in Scotland

Page 6: 2009 07 EDF Energy - Hugh Hutton

British Energy Public Meeting, Nether Stowey, Monday 20th October 2008Richard Mayson, Nuclear Counsel© Copyright EDF Energy plc. All rights reserved. 2006. 6

Hinkley Point – new build nomination area

A BC

A,Boutfall

A,B intake

Page 7: 2009 07 EDF Energy - Hugh Hutton

British Energy Public Meeting, Nether Stowey, Monday 20th October 2008Richard Mayson, Nuclear Counsel© Copyright EDF Energy plc. All rights reserved. 2006. 7

Baseline studies• Flora and fauna

• Breeding birds• Inter-tidal and inshore birds• Wintering birds• Bats• Botanical interest• Badgers, dormice, great crested newts,

water voles, otters, reptiles, invertebrates

• Marine• Fish entrainment• Plankton• Water quality• Subtidal and intertidal habitat mapping • Sediment particle size and distribution• Bathymetry (single beam, sidescan, swathe)• Intertidal topography• Waves – direction, amplitude (Waverider plus shorter term shallow water

installations)• Hydrographic surveys (fixed plus towed doppler current measurement)

Page 8: 2009 07 EDF Energy - Hugh Hutton

British Energy Public Meeting, Nether Stowey, Monday 20th October 2008Richard Mayson, Nuclear Counsel© Copyright EDF Energy plc. All rights reserved. 2006. 8

Cooling water discharge modelling

Page 9: 2009 07 EDF Energy - Hugh Hutton

British Energy Public Meeting, Nether Stowey, Monday 20th October 2008Richard Mayson, Nuclear Counsel© Copyright EDF Energy plc. All rights reserved. 2006. 9

Socio-economic impacts

• Hinkley Point B•Over 550 EDF Energy staff plus 220 from contract partners•Apprenticeship programme – currently 21 apprentices•Around £30million into local economy per year

• Hinkley Point C (current assumptions)•Construction 2012 to 2018 (first unit on line by end 2017)•Construction workforce of several thousand •60 year operational life•600-900 operating staff•20 year decommissioning period