Page 1: Standard costing presentation

1

Standard costing

Page 2: Standard costing presentation

Standard

The word standard means a criterion (principle, measure).

A standard figure is one against which one can measure an actual figure to see the deviation.

2

Page 3: Standard costing presentation

Standard Rate

The word Standard Rate is the numerical proportion prevailing between two sets of things.

A firm has three ‘standard of things’ available on which to base standard rates: Money, Physical inputs and Physical outputs.

3

Money

Physical Inputs

Physical Outputs

Money/output, e.g. Re./unit of materials

Money/output, e.g. Re./unit of product

Input/output, e.g. labour/machine hrs./unit of product

Page 4: Standard costing presentation

Standard Cost

Standard cost is ‘a predetermined cost which is compared in advance of production on the basis of specifications of all the factors affecting costs and used in standard costing.’

In other words, standard cost is a predetermined cost that should be attained under a given set of operating conditions.

4

Page 5: Standard costing presentation

Standard Costing

Standard costing is a technique which is used in many industries, where production is of repetitive nature.

Standard costing is developed due to the shortcomings of historical costing.

CIMA, London, defines standard costing ‘as the predetermined cost based on technical estimates of materials, labour and overheads for selected period of time and for the prescribed set of working conditions’.

Standard costing is that technique in which the standard cost is determined before starting the production.

5

Page 6: Standard costing presentation

6

Standard costing system

The management evaluates the performance of a company by comparing it with some predetermined measures

Therefore, it can be used as a process of measuring and correcting actual performance to ensure that the plans are properly set and implemented

Page 7: Standard costing presentation

Objectives Of Standard Costing

To establish control To set standards for various elements of cost To fix responsibility To make budgetary control more effective

7

Page 8: Standard costing presentation

8

Procedures of standard costing system

Set the predetermined standards for sales margin and production costs

Collect the information about the actual performance Compare the actual performance with the standards to

arrive at the variance Analyze the variances and ascertaining the causes of

variance Take corrective action to avoid adverse variance Adjust the budget in order to make the standards more

realistic

Page 9: Standard costing presentation

9

Functions of standard costing system

Valuation– Assigning the standard cost to the actual output

Planning – Use the current standards to estimate future sales

volume and future costs Controlling

– Evaluating performance by determining how efficiently the current operations are being carried out

Page 10: Standard costing presentation

10

Motivation– Notify the staff of the management’s expectations

Setting of selling price

Page 11: Standard costing presentation

11

Variance

Page 12: Standard costing presentation

12

Variance analysis

A variance is the difference between the standards and the actual performance

When the actual results are better than the expected results, there will be a favourable variance (F)

If the actual results are worse than the expected results, there will be an adverse variance (A)

Page 13: Standard costing presentation

Classification Of Variances

Functional Basis Measurement Basis Result Basis Controllability Basis

13

Page 14: Standard costing presentation

Functional Basis

14

Page 15: Standard costing presentation

Measurement Basis

15

Page 16: Standard costing presentation

Absolute variance: Difference between the standard cost and the actual cost in terms of money is known as absolute variance.

Relative variance: difference is expressed as a percentage of the standard cost, it is known as relative variance.

16

Page 17: Standard costing presentation

Result basis

17

Page 18: Standard costing presentation

18

Cost variance

Page 19: Standard costing presentation

19

Cost variance

•Cost variance = Price variance + Quantity varianceCost variance is the difference between the standard cost and the Actual cost

•Price variance = (standard price – actual price)*Actual quantity A price variance reflects the extent of the profit change resulting from the change in activity level

•Quantity variance = (standard quantity – actual quantity)* standard cost

A quantity variance reflects the extent of the profit change resulting from the change in activity level

Page 20: Standard costing presentation

20

Three types of cost variance

Material cost variance Labour cost variance Variable overheads variance

Page 21: Standard costing presentation

21

Material and labour variance

Page 22: Standard costing presentation

22

Page 23: Standard costing presentation

23

Page 24: Standard costing presentation

Material cost variance

It is the difference between the standard direct material cost of the actual production volume and the actual cost of direct materials.

Material cost variance = (Standard quantity of input for actual production × SP) – (Actual quantity of input × AP)

Material cost variance = Material price variance + Material usage variance

24

Page 25: Standard costing presentation

25

Material cost variance

Material price variance

= (standard price – actual price)*actual quantity

= ($3 - $3.2)*2400

= $480 (A) Material usage variance

= (Standard quantity – actual quantity)* standard price

= (Standard quantity for actual production – actual quantity production) * standard price

= (4*800 – 2400)*$3

= $2400 (F)

4000 units1000 units

Page 26: Standard costing presentation

26

Material cost variance

Material price variance $480 (A) Material usage variance $2400 (F) Total Material cost variance $1920 (F)

Page 27: Standard costing presentation

27

Material price variance

This is that portion of the material cost variance which is due to the difference between the standard price specified and the actual price paid.

If the actual price is higher than the standard price, it would result in adverse price variance and if the actual price is lower than standard price, the result is favorable price variance.

Material price variance = (standard price – actual price) x actual quantity of materials

Page 28: Standard costing presentation

Material Usage Variance

This is that portion of material cost variance which is due to the difference between the standard quantity of actual production and the actual quantity used.

Material usage variance

= (Standard quantity – actual quantity) x standard price

= (Standard quantity for actual production – actual quantity production) x standard price

28

Page 29: Standard costing presentation

Material Mix Variance

This is that portion of usage variance which is due to the difference between the standard and actual composition of mixture.

Material Mixture Variance = Standard price [Actual quantity in standard mix (i.e. RSQ) – Actual quantity]

Revised Standard quantity = Total actual quantity consumed ×

29

Page 30: Standard costing presentation

Material Yield Variance

This variance arises due to the difference between the standard yield specified and actual yield obtained.

Material yield variance = [(Standard loss in terms of actual input) – (Actual loss on actual input)] × (Average standard price)

Material yield variance = Material usage variance – Material mix variance

30

Page 31: Standard costing presentation

Material Sub-usage Variance

When a product is produced from a mixture of two or more kinds of material, there may arise material sub-usage variance.

Material sub-usage variance = (Standard Quantity – Revised Standard Quantity) × Standard Price

It can be seen from this formula that material sub-usage variance is the analysis of variance in basic standard quantity of each material.

31

Page 32: Standard costing presentation

Labour Variances

32

Page 33: Standard costing presentation

33

Formulas Of Labour Variances

Labour rate variance = (standard price – actual price) x actual hours

Labour Idle Time Variance = [(actual hrs.- idle time) x standard price] – (actual hrs. x standard price)

Labour Gang variance = [revised(actual hrs.- idle time) x standard price] – [(actual hrs.- idle time) x standard price]

Labour Yield variance = [revised(actual hrs.- idle time) x standard price x (actual output/standard output)] - [revised(actual hrs.- idle time) x standard price]

Labour sub-efficiency variance = (standard hrs. x standard price) - [revised(actual hrs.- idle time) x standard price x (actual output/standard output)]

Page 34: Standard costing presentation

Labour Cost Variance = (standard hrs. x standard price) – (actual hrs. x actual price)

Labour Usage variance = standard price x (standard hrs. – actual hrs.)

Labour efficiency variance = (standard hrs. x standard price) - [revised(actual hrs.- idle time) x standard price]

34

Page 35: Standard costing presentation

Labour Rate Variance

This is that portion of the labour cost variance which is caused by the use of actual wage rate other than predetermined.

Labour rate variance = Actual labour time (Standard wage rate – Actual wage rate)

35

Page 36: Standard costing presentation

Labour Efficiency Variance

It is the difference between the standard time and the actual time spent multiplied by standard wage rate.

Labour efficiency variance = Standard wage rate (Standard labour time – Actual labour time)

36

Page 37: Standard costing presentation

Labour Idle Time Variance

It is that portion of labour cost variance which is due to the abnormal idle time of workers.

While calculating labour efficiency variance, abnormal idle time is deducted from the actual time spent to determine the real efficiency of the workers.

Idle time variance = Abnormal idle time × Standard wage rate

37

Page 38: Standard costing presentation

Labour Gang Variance

This variance arises due to the change in the composition or mix of a group of workers as compared to the standard composition or mix.

Labour gang variance = (Revised standard time – Idle time) × Standard rate per hour

Here, RST= Total actual time x

38

Page 39: Standard costing presentation

Labour Yield Variance

It is computed on the basis of the increase or decrease in the actual yield or output when compared to the standard.

Labour Yield Variance = [Actual yield – Standard yield in units expected from the actual hours worked] × Standard labour cost per unit

39

Page 40: Standard costing presentation

Labour Usage Variance

Labour Usage Variance is the measure of difference between standard hours and actual hours,multiplied by the standard rate.

Labour Usage variance = (standard hrs. – actual hrs.) x standard price

40

Page 41: Standard costing presentation

Labour Cost Variance

Labor cost variance can be defined as the deviation of the actual direct wages paid from the direct wages specified for the standard output.

Labour Cost Variance= (Standard time x Standard price)-(Actual time x Actual price)

41

Page 42: Standard costing presentation

42

Overheads variance

Page 43: Standard costing presentation

I. Variable Production Overhead Variance

Standard Variable Overheads= Actual Production * Standard Rate

Standard Rate = Budgeted Variable Overheads/Budgeted Production

43

Page 44: Standard costing presentation

II. Fixed Production Overhead Variances

44

Page 45: Standard costing presentation

Fixed Production Overhead Cost or Total Variance

Total Variance =( Actual Production * Standard Recovery Rate)- Actual Overheads

Fixed Production Overhead Expenditure Variance

Expenditure Variance=( Standard Recovery rate * Budgeted Production)- Actual Overhead

45

Page 46: Standard costing presentation

Fixed Production Overhead Volume Variance

Volume Variance = Standard Fixed Overhead- Budgeted fixed Overhead

46

Page 47: Standard costing presentation

SALES

Sales variances an b calculated in two ways:

A. The turnover or the volume method

B. The profit or the margin method

47

Page 48: Standard costing presentation

A. The Turnover or The Value Method

48

Page 49: Standard costing presentation

Value Variance= Actual Sales- Budgeted Sales Price Variance= Actual Sales – Standard Sales Volume Variance= Standard Sales- Budgeted

Sales Quantity Variance= Revised Standard Sales –

Budgeted Sales Mixed Variance= Standard Sales – Revised

Standard Sales

49

Page 50: Standard costing presentation

B. Profit Method

50

Page 51: Standard costing presentation

Application Of Standard Costing

Process industries Service industries Engineering industries Textile industries Extraction industries

51

Page 52: Standard costing presentation

Advantages Of Standard Costing

• Formulation of price and production policies• Comparison and analysis of data• Management by exception• Delegation of authority and responsibility• Cost consciousness• Better capacity to anticipate• Better economy, efficiency, and productivity• Preparation of periodical financial statements• Facilities budgeting

52

Page 53: Standard costing presentation

Limitations Of Standard Costing

High degree of technical skill Segregation of variances into controllable and non-

controllable factors Duplication in recording, Either too strict or too liberal.

53

Page 54: Standard costing presentation

“THANK YOU”

54