Project Engineer knowledge test

HERVE BARON

© 2015 – Hervé Baron

Hazard area classification is defined in the Engineering design basis.

Right or Wrong?

Project Engineer knowledge test

HERVE BARON

© 2015 – Hervé Baron

Hazard area classification is defined in the Engineering design basis.

Wrong. Only the code to be applied, e.g., API, to calculate the extent of the hazardous area, is defined in the Engineering design basis. The zone area determined as part of the HSE design.

Project Engineer knowledge test

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

On which revision of the P&IDs is based the first purchase of Piping materials?

1st issue

2nd issue

3rd issue

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

On which revision of the P&IDs is based the first purchase of Piping materials?

1st issue

2nd issue (IFD)

3rd issue

Extract from The Oil & Gas Engineering Guide, Editions Technip, 2nd Edition, page 120

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

Which documents are needed to elaborate the plot plan:

Equipment data sheets

P&IDs

PFDs

Equipment list

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

Which documents are needed to elaborate the plot plan:

Equipment data sheets

P&IDs

PFDs

Equipment list

Extract from The Oil & Gas Engineering Guide, Editions Technip, 2nd Edition, page 206

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

Which document(s) show(s) the capacity of Process equipment:

the Equipment list

the PFD/HMB

the Mechanical data sheet

the Process data sheet

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

Which document(s) show(s) the capacity of Process equipment:

the Equipment list

the PFD/HMB

the Mechanical data sheet

the Process data sheet

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

What % of Isometrics are required to effectively start Piping pre-fabrication?

10%

30%

50%

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

What % of Isometrics are required to effectively start Piping pre-fabrication?

10%

30%

50%

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

What % of Piping materials must be delivered for Piping pre-fabrication to effectively start?

25%

50%

70%

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

What % of Piping materials must be delivered for Piping pre-fabrication to effectively start?

25%

50%

70%, all diameters, grades and types (pipes, fittings, o-lets, etc.)

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

The HAZOP looks at the consequence of failures of:

equipment

safeguards

operator

control devices

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

The HAZOP looks at the consequence of failures of:

equipment

safeguards

operator

control devices

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

Which of the following is true of a Pre-FEED

Is sometimes called “Select phase”

Considers options in the basic configuration

Focuses on a single design

Is also called “Basic Engineering”

Consists of Process engineering only

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

Which of the following is true of a Pre-FEED

Is sometimes called “Select phase”

Considers options in the basic configuration

Focuses on a single design

Is also called “Basic Engineering”

Consists of Process engineering only

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

In which document do you find the flash point and auto-ignition temperature of a product?

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

In which document do you find the flash point and auto-ignition temperature of a product?

The MSDS (Material Safety Data Sheet)

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

What type of check is called "squad check"

the cold eye review

the inter-disciplinary check

the Company review

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

What type of check is called "squad check"

the cold eye review

the inter-disciplinary check

the Company review

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

Civil guide drawings are issued at FEED stage.

Right or Wrong?

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

Civil guide drawings are issued at FEED stage.

Wrong. They are issued as part of detail design. They show all input data (loads, dimensions, position of anchor bolts) for civil detail design.

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

Which load is taken into account in the consumers list for pumps?

absorbed power at normal flow

absorbed power at design flow

motor nameplate (rated) power

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

Which load is taken into account in the consumers list for pumps?

absorbed power at normal flow

absorbed power at design flow

motor nameplate (rated) power

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

What is the number of manhours required for the first issue of each P&ID?

30

100

200

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

What is the number of manhours required for the first issue of each P&ID?

30, indeed, P&IDs are more or less the same from one job to the other

100

200

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

Which is the pre-requisite to issue the Plot Plan for design (IFD revision)

First 3D model review completed

Equipment size confirmed by Vendors

HAZOP review completed,

P&ID issued for design,

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

Which is the pre-requisite to issue the Plot Plan for design (IFD revision)

First 3D model review completed

Equipment size confirmed by Vendors

HAZOP review completed,

P&ID issued for design,

Extract from “The Oil & Gas Engineering Guide”, Editions Technip, 2nd Edition, page 149

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

On which revision of the Civil Area drawings are the following items Approved For Construction (AFC)?

IFC1 (first) IFC2 IFC3 IFC4 (final)

Secondary sewers

Paving

Pipe supports

Secondary cable routing

Foundations

Pressurized Piping

Gravity piping

Main cable routing

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

On which revision of the Civil Area drawings are the following items Approved For Construction (AFC)?

IFC1 (first) IFC2 IFC3 IFC4 (final)

Secondary sewers x

Paving x

Pipe supports x

Secondary cable routing x

Foundations x

Pressurized Piping x

Gravity piping x

Main cable routing x

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

Ref.: The Oil & Gas Engineering Guide, Editions Technip, 2nd Edition, page 102

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

Where goes each drain?

HERVE BARON

© 2015 – Hervé Baron

Project Engineer knowledge test

Where goes each drain?

Ref.: The Oil & Gas Engineering Guide, Editions Technip, 2nd Edition, page 100

© 2015 – Hervé Baron

HERVE BARON

The Oil & Gas Engineering Guide - 2nd edition

A unique synthesis for the busy Project professional 270 pages 300 illustrations

Interested and wanting to know more on Engineering?

© 2015 – Hervé Baron

HERVE BARON

The Oil & Gas Engineering Guide 2nd edition

Please note that it will take weeks before the book is on Amazon... but you can already purchase it from the publisher.

Up to March 30th there is a 25% discount

Please go to:

http://www.editionstechnip.com/en/catalogue-detail/1111/oil-gas-engineering-guide-the.html