Date Task to be completed Timings Notes 8 th January Meeting with actors 1pm Meeting will include me showing actors floorplans, shot list and a schedule for the filming day as well as outlining the costumes they will need and what they will need to bring. 9 th January Travel to London to film on location as well as completing interviews with actors whilst filming and taking photos of actors in locations. 7:00 – Traveling to London 9:00 – Filming in Tube station 11:00 – Filming in Oxford street (shopping location) 13:00 – Filming in Green park 14:00 – Break for Lunch 15:00 – Filming at London Bridge 16:00 – Looking over footage 17:00 – Re-filming any shots needed 18:00 – Travel home All filming will have to take place on this day due to cost of travel to and from London and availability of actors

Production schedule

  • Upload
    ylrice

  • View
    102

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Production schedule

Date Task to be completed Timings Notes8th January Meeting with actors 1pm Meeting will include me showing

actors floorplans, shot list and a schedule for the filming day as well as outlining the costumes they will need and what they will need to bring.

9th January Travel to London to film on location as well as completing interviews with actors whilst filming and taking photos of actors in locations.

7:00 – Traveling to London9:00 – Filming in Tube station11:00 – Filming in Oxford street (shopping location)13:00 – Filming in Green park14:00 – Break for Lunch 15:00 – Filming at London Bridge 16:00 – Looking over footage 17:00 – Re-filming any shots needed 18:00 – Travel home

All filming will have to take place on this day due to cost of travel to and from London and availability of actors

11th January Collecting together all the footage that I have gathered reviewing it and deleting anything that is not needed

11:15 – 12:55

18th January Start editing all the footage that I have gathered

11:15 – 12:55

22nd January Editing footage 9:15 – 10:05

25th January Editing footage 11:15 – 12:55

29th January Finish editing and start to edit interviews with actors

9:15 – 10:05 Will put together a short behind the scenes video including interviews

Page 2: Production schedule

with actors, films and photos from locations. I will also create another separate video that includes outtakes from filming.

1st February Consolidation of production/putting everything onto blog and checking everything that I need to do has been completed

11:15 – 12:55

22nd February Design Digipak and poster for my song and video

11:15 – 12:55

25th February Design Digipak and poster for my song and video

9:15 – 10:05

29th February Design Digipak and poster for my song and video

11:15 – 12:55

1st March Evaluation Question 1 9:15 – 10:05

4th March Evaluation Question 2 9:15 – 10:05

7th March Evaluation Question 3 11:15 – 12:55

11th March Evaluation Question 4 9:15 – 10:05

14th March Upload all evaluation questions to blog 11:15 – 12:55