Update on Hangar One by Bryce Bartelma at the August 9, 2012, meeting of the Moffett Restoration Advisory Board.
Citation preview
1
Former NAS Moffett Field
Hangar 1 Removal Action Update
Bryce Bartelma, PG
Navy BRAC PMO West
August 9, 2012
RAB Meeting
2
• Control release of PCBs from Hangar 1 in accordancewith EE/CA (July 2008) and Action Memorandum(December 2008)
Demolition of interior structures
Removal of contaminated siding
Application of weather-resistant coating to steel frame
Project Objective
3
Continued Monitoring andProtection Measures
• Continued biological activity andnesting deterrents
• Maintain storm water and groundsurface protection
• Navy and NASA air monitoring datademonstrates control of air emissions
4
April 2012
5
July 2012
6
Final Material Removed – July 19, 2012
7
Fixing the Holiday Star
• Replacement ofelectrical components
8
Remaining Tasks
• Scaffolding deconstruction
• Mezzanine prep and coat
• Final touch ups, cleaningand surface soil removal
9
Schedule
• Complete Fieldwork andDeconstruct Scaffolding
October 2012
• Final Cleaning andDemobilize
November 2012
• Submit After ActionCompletion Report
Winter/Spring 2013
10
Hangar 1 Interactive CD
CLICK HERE FOR DEMO
11
Questions?