Production -how ships are built

  The objective is to provide a broad overview of the production process for ship construction.

  Before production there are a number of essential pre-production activities

• Market analysis, product mix selection

• Design development, specification, strategic planing

• Estimating, tendering, contract negotiation

• Detailed design, product work breakdown

• Tactical planning, purchasing

• Detailed planning, scheduling, production information

• packaging of materials and information to work stations

Page 3: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/3

MAR807

Shipyard Facilities (1)

  The facilities which are found in a shipyard depend on the manufacturing strategy which is adopted. It may in some cases be more cost-effective to sub-contract certain activities. A comprehensive list is:

  For Hull Production

• Steel Stockyard

• Steel Treatment (levelling, shotblasting, painting)

• Plate and profile cutting

• Plate and profile forming

• Workshops for sub-assembly, assembly and unit assembly

• Block assembly, outfitting and painting workshops

• Block storage area

Page 4: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/4

MAR807

Shipyard Facilities (2)

  Outfitting facilities are also required. It is more common to sub-contract outfitting than hull work, but some shipyards retain a full range of facilities.

  Outfitting

• Pipe storage, cutting and welding

• Machine Shop

• Accommodation work (woodwork, metal furniture, linings)

• Electrical and electronic workshop

• Sheet metal workshop (ventilation trunks, metal fittings)

• Riggers workshop

• Outfit unit assembly

• Material and equipment storage

  Post-launch facilities for outfitting and trials are also required

Page 5: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/5

MAR807

Shipyard Facilities (3)

  Ship Construction is the major facility in most cases. There are a number of methods for transfer of the completed ship to the water

• Inclined Slipway (for dynamic launch - traditional)

• Side launch slipway

• Graving Dock

• Shiplift

• Load-out (to floating dock)

  There are other methods used occasionally

  All the alternatives can be enclosed in a building for environmental protection.

  All require large capacity cranes for lifting and manipulating blocks.

Page 6: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/6

MAR807

Shipyard facilities (4)

  A number of supporting facilities are also required. These can form a substantial part of the cost of a new facility.

• Electrical sub-stations

• Bulk gas storage facilities

• Compressed air plant

• Water storage tanks

• Associated services distribution systems

• Offices

• Amenities (changing rooms, canteens, et.)

• Training facilities

• Car and bus parking

Page 7: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/7

MAR807

Which facilities are required for a shipyard?

  For a new or re-developed site, the selection is on the basis of

• cost - can the requirement be met more cost-effectively by sub-contract?

• importance - is it essential to have control of the requirement?

  Other factors could include

• space available

• funds available

• future changes in product mix

Page 8: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/8

MAR807

Steel Storage

  The first stage in the process is the stockyard for steel.

  The need for this is dictated by the ability to match supply of steel to the facilities with the demand. If the steel mill is close, and can provide steel with a very short lead time, then storage is not a problem.

  Most shipyards have a steel stock for one to three months.

  Plates are generally stored horizontally and handled individually by magnet beam crane.

  Profiles are usually handled in batches using slings.

Page 9: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/9

MAR807

Page 10: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/10

MAR807

Page 11: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/11

MAR807

Page 12: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/12

MAR807

Steel Treatment

  Assuming the shipyard does not but steel ready primed.

  The treatment process includes

• pre-heating, usually water wash or gas

• levelling

• shot-blasting

• paint application

• drying

  The processes are linked by a roller conveyor, and the operation is largely automated

Page 13: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/13

MAR807

Page 14: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/14

MAR807

Page 15: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/15

MAR807

Page 16: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/16

MAR807

Page 17: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/17

MAR807

Steel Cutting

  Plates are generally cut using Numerical Control (NC) machines.

  Older shipyards use optically controlled machines.

  The cutting process can be

• oxy-gas (smaller shipyards and where welding preparation is required)

• plasma (large production volumes but cutting is underwater)

• laser (rare to date and only for thinner plate)

• mechanical plane (straight edges only, but very accurate)

• edge milling (also only straight edges)

• guillotine (for small, straight-sided parts)

  Profiles are cut using oxy-gas or mechanically

• robots are used for high volumes of throughput

• mechanised conveyors may be used to move the profiles

• hand or portable equipment is still used in small shipyards

Page 18: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/18

MAR807

Page 19: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/19

MAR807

Page 20: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/20

MAR807

Page 21: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/21

MAR807

Page 22: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/22

MAR807

Page 23: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/23

MAR807

Plate Forming

  Plates are formed using a number of machine types.

  For small volumes of production, machines can be used for other purposes.

  Heat-line bending is an alternative, but slower and labour-intensive.

  Machines are

• Plate Rolls (for shell plates, best for single curvature)

• Gap Press (for most forming, including double curvature, but slow)

• Portal Press (for most forming)

• Press Brake (for flanging and corrugated stiffening)

  Accurate bending is difficult because of “spring-back”.

  Heat line bending can be used for final adjustment of formed plates

  Templates can be produced used CAD-generated information.

Page 24: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/24

MAR807

Page 25: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/25

MAR807

Page 26: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/26

MAR807

Profile Forming

  Profile forming is primarily for transverse frames and uses a cold bender.

  Templates are defined by CAD

  The final shape of the frame is checked using

• templates

• wire sets

• inverse-curve bending

  Other processes can be used for flanges and small stiffeners

• Press brakes

• Mast rolls

Page 27: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/27

MAR807

Page 28: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/28

MAR807

Assembly

  Shipbuilding is primarily an assembly industry, using the parts created in previous processes. Steelwork Assembly is usually in several stages and many definitions exist for these. The simplest are

• Assembly - all stages where interim products are joined together

• minor assembly - joining two or more individual pieces

• sub-assembly - joining parts and minor assemblies

• unit assembly - joining interim products to create a unit which could be taken to the final construction site

• block assembly - joining units to create larger products before they are taken to the construction site

  Outfit Assemblies are also created, in similar stages between

• minor assemblies - e.g. pipes and supports

• engine room modules - complete sections with all equipment

Page 29: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/29

MAR807

Page 30: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/30

MAR807

Page 31: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/31

MAR807

Page 32: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/32

MAR807

Page 33: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/33

MAR807

Page 34: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/34

MAR807

Specialist Steelwork Assembly Equipment and Processes

  Curved Panel Assembly

• provides an accurately shaped jig for panel assembly– telescopic pins of adjustable height– magnetic or other faring equipment– single-sided welding

  Flat Panel Assembly

• is frequently a flow line with work stations linked by conveyor

• provides specialised equipment for each stage of assembly– plate alignment and fairing using magnets– plate welding (single side or with a turnover crane included)– stiffener marking, location and fairing– stiffener welding– secondary stiffener location and welding

• generally automated welding systems

Page 35: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/35

MAR807

Page 36: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/36

MAR807

Page 37: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/37

MAR807

Page 38: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/38

MAR807

Page 39: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/39

MAR807

Outfitting (1)

  In many shipyards, outfitting organisation is less advanced than steelwork.

  There may be automated or semi-automated processes at early stages.

  Assembly is limited and manual.

  Pipe Shop

• automated storage and retrieval where production volume is high

• automatic pipe cutting to length

• automatic flange welding can be used

• NC pipe benders are in use

• other specialised equipment is used for branches

• assembly is a manual operation

Page 40: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/40

MAR807

Page 41: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/41

MAR807

Page 42: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/42

MAR807

Page 43: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/43

MAR807

Page 44: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/44

MAR807

Page 45: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/45

MAR807

Outfitting (2)

  Other outfitting workshops generally provide basic facilities.

  Sheet metal

• small mechanical cutting and forming equipment

• lock forming and other specialist equipment

• manual assembly

  Machine Shop

• general purpose machine tools

• specialist equipment (e.g. shaft lathe)

  Woodwork Shop

• frequently use bought-in items rather than manufacture at the shipyard

• general purpose equipment is used

Page 46: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/46

MAR807

Further Block stages

  Advanced shipyards are able to combine steel and outfitting at an early stage of production. It is more usual to install equipment and other outfitting at the block stage.

  Typical activities carried out on completed hull blocks are

• shotblasting

• painting

• outfit installation

  Specialised facilities may be provided for these activities.

• paint cells - (temperature and humidity control, access equipment)

• outfitting halls - (access equipment and cranes)

Page 47: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/47

MAR807

Page 48: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/48

MAR807

Page 49: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/49

MAR807

Page 50: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/50

MAR807

Page 51: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/51

MAR807

Page 52: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/52

MAR807

Ship Construction

  The choice of facility is wide.

• inclined slipway for end launch

• flat construction area – for load-out– for side launch

• graving dock

• flat area combined with a lift

  Any of the above may be arranged to allow two vessels to be produced simultaneously

  Any of which may be open, partly or completely to provide for weather protection

  The final erection area is typically the area of highest capital cost

Page 53: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/53

MAR807

Page 54: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/54

MAR807

Page 55: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/55

MAR807

Page 56: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/56

MAR807

Page 57: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/57

MAR807

Page 58: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/58

MAR807

Page 59: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/59

MAR807

Page 60: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/60

MAR807

Lifting and Handling

  The method used to move final assemblies to the erection area is a major cost element

  Alternatives include:

• level luffing jib cranes

• goliath cranes

• overhead cranes in buildings

• self-elevating transporters, in association with cranes

• ground level systems– wheeled systems– sliding or “walking” systems

Page 61: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/61

MAR807

Page 62: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/62

MAR807

Page 63: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/63

MAR807

Post launch

  Launching is traditionally a major milestone in ship production.

  It is often of less significance, where the outfitting of the ship is substantially complete before launch. In some cases, standard cargo ships may be delivered within four weeks of launch.

  A quay is required to moor the ship for the final outfitting period.

  This period may still be extended in the case of a military vessel, a large cruise ship or other vessel with complex internal or deck outfitting.

  The quay requires cranes and services to match the volume of work to be done. Separate stores and workshops may be needed.

  Support for testing and trails is also provided at the quay.

Page 64: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/64

MAR807

Post delivery

  The production process is completed with delivery of the ship.

  However, to complete the cycle from marketing, feedback from the customer should be sought.

  As a minimum there will be a guarantee docking after twelve months.

  Some advanced shipyards place a guarantee engineer on board the ship to monitor all aspects of operation and feedback to the design and production process.

  The level of post delivery support will vary both wit the attitude of the shipyard and the technical and operational requirements.

Page 65: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/65

MAR807

Page 66: Marine Production Technology

MTM1a/300GJB/PRODN/09.96/66

MAR807

References

  Ship Production, Storch, Hammon, Bunch, Moore

  Creating a production facility for standard ships, Kimber, Hargroves

  Shipbuilding Technology International Annual publication

  Shipyard Technology Occasional publication

  “Naval Architect” regular features on shipyards and technology

  Marine Log, Maritime Reporter, Fairplay regular articles