CONSTRUCTION UPDATE – January 2015 Dr. Prem Reddy Health & Science

January 2015 Construction Update - Victor Valley Community College District - Dr. Prem Reddy Health Sciences Building

Embed Size (px)

Citation preview

CONSTRUCTION UPDATE – January 2015Dr. Prem Reddy Health & Science

Metal decking installed at digital

nurses lab

Metal Decking being set

Metal roof deck installed

At science labs

Perimeter walls being framed in medical supplies & equipment

Boring for columns

for shade structure

Metal deck installed at restrooms.

Perimeter wall framing and structural steel set in faculty office area.

Perimeter wall framing in nursing fundamentals lab.

Also overhead piping installed.

Metal decking, perimeter wall framing in nursing

fundamentals and corridor 127

Plywood covers holes bored for shade

structure posts in new courtyard area

Steel set in admin & workroom areas.

Metal Decking installed at faculty offices

Metal Decking at nursing fundamentals lab.

Overhead piping installed.

Rear view of rotunda.

Looking towards faculty offices from corridor 127

Overhead piping, perimeter framing, and metal decking installed at beds &

equipment

Interior view of main entrance

Perimeter framing at workroom and admin areas

More perimeter framing at anatomy labs.

Preparation for footings at new trash enclosure

New doorway cut into existing science bldg.

(Temporary Door)

Metal decking installed at anatomy labs

SIM Lab area perimeter wall framing installed. Decking in process of

install.

Perimeter wall framing and metal decking installed at

deans office / meeting rooms

Holes bored for covered walkway

pilasters.

Framing for walls along corridor 127

Progress on metal decking at nursing fundamentals

Top view of metal decking installation

Another top view of metal decking. Looking towards the second floor

mezzanine and rotunda

Stored duct waiting for install is covered to

prevent dirt and debris from accumulating inside.

Stored duct waiting for install is covered to

prevent dirt and debris from accumulating inside.

Duct being installed in chemistry lab

Decking installed over corridor 127

Installing in wall conduits for power and piping for

roof drains.

Electrical room 132

Rebar laid out on metal decking in mezzanine for

concrete topping and equipment pad.

Looking down into courtyard area

Opening for duct from HVAC unit in mezzanine.

Signed steel beam set into place

Temporary jacks set in place in preparation of

concrete being poured on deck above

Concrete being poured on mezzanine deck

Footing poured for trash enclosure

Interior walls being framed for faculty offices

Framing of interior walls in the admin, workroom,

deans office areas

Concrete poured out for revolving door at main

entry

Mezzanine concrete and equipment pad- North

side

Mezzanine concrete and equipment pad- South

side