Implementing “the basics” as a change programme
Ewan Glen, 2 March 2016
+44 (0)1225 820980 www.bmt-hqs.com [email protected] ©BMT Hi-Q Sigma Ltd
The project control “basics”
Why a change programme?
Change programme Programme phase overview
Some key lessons and experiences
Summary
Presentation Agenda
+44 (0)1225 820980 www.bmt-hqs.com [email protected] ©BMT Hi-Q Sigma Ltd
“…a temporary, flexible organisation created to co-ordinate, direct and oversee the implementation of a set of related projects and activities in order to deliver outcomes and benefits related to the organisation’s strategic objectives”
Managing Successful Programmes, Axelos
Change programme definition
Outputs Outputs Outputs Outcomes Benefits
Projects Programme Organisation Programme
+44 (0)1225 820980 www.bmt-hqs.com [email protected] ©BMT Hi-Q Sigma Ltd
High level overview of a change programme
Identify
Deliver
Define Close Governance
Monitoring & control
Governance Monitoring &
control
+44 (0)1225 820980 www.bmt-hqs.com [email protected] ©BMT Hi-Q Sigma Ltd
Active SRO and dedicated Programme Manager
Senior Responsible
Owner
Change Programme
Manager
• Accountable for the delivery of the programme
• Strategic direction and guidance
• Obtain and maintain buy-in from the wider organisational management
• Responsible for the delivery of the programme
• Tactical direction, cognisant of business drivers
• Focus on overall programme
+44 (0)1225 820980 www.bmt-hqs.com [email protected] ©BMT Hi-Q Sigma Ltd
Governance structure in place and resource secured
to implement the programme
Governance Organisation Wider Engagement
As required
Sponsoring Layer Steering Board
Chair: SRO Members: Senior managers from each Business Unit / Function, Project Sponsors Attendees: Programme Manager Frequency: Monthly
Senior Responsible
Owner
Programme Board Chair: Programme Manager Members: Business Change Managers, Functions, Project Leads, Programme Core Team Frequency: Monthly
Programme Manager
Business Change
Managers
Programme Core Team
Programme Layer
Project Reviews Chair: Project lead Members: Business Change Managers, Project Team members. Frequency: As required
Project Lead Project Lead Project lead
• Key stakeholders • Sponsors of related change
programmes • Customers
Example from DE&S Ships OC
Project Layer
+44 (0)1225 820980 www.bmt-hqs.com [email protected] ©BMT Hi-Q Sigma Ltd
High level overview of a change programme
Identify
Deliver
Define Close
Programme mandate
Case for change (business need)
Vision & mission Scope boundaries
Governance Monitoring &
control
Benefits Current State
Future State B
luep
rin
t
+44 (0)1225 820980 www.bmt-hqs.com [email protected] ©BMT Hi-Q Sigma Ltd
Develop understanding of the Case for Change
In January 2014 it was recognised that the [organisation] did not have a coherent view of the resource used (money and people), levels of performance and risk, and relative priority of each of the organisations programmes and projects. This made it difficult to have informed Board level discussions on how we could optimise output delivery and balance risk (for example, through the allocation of resource).
There was a lack of commonality of approach across key programme & project management disciplines and in some areas a lack of rigour. The links between the Ships Portfolio Office (SPfO) and team level Programme Support Offices was weak. We did not have a clearly defined system of governance.
Combined these issues hampered effective strategic decision making, the delivery of core outputs, and the confidence the Customer and key stakeholders had with our organisation.
High level initial view (symptom driven)
+44 (0)1225 820980 www.bmt-hqs.com [email protected] ©BMT Hi-Q Sigma Ltd
Establish Definition Projects
Programme Context | Benefits | Definition | Governance | Success Factors
2. Performance Management Ensure a coherent and integrated performance management system exists that supports internal, customer and industry performance management requirements. The
system should include a comprehensive set of agreed metrics and targets, systems to generate trusted performance outturn management information, and a robust system of governance to ensure proper Holding to Account for delivery
1. Portfolio Management Information Develop a single living Management Information picture that provides a coherent view of Ships OC activity (the Portfolio). This MI picture should identify the required resource
(money and people), risk and performance profile, and strategic priority of each element of the Portfolio, to enable effective strategic decision making
Management Information
Performance Summary
3. Approvals & Assurance
Ensure approvals and assurance
activity is conducted iaw OC,
DE&S and Departmental
process as efficiency as
possible through sharing of experience
4. Assumptions Management
Ensure that an optimised assumptions management process is
used that drives coherence between all
stakeholders in the enterprise and exposes and manages both the
inter and intra dependencies of Ships
programmes and projects
5. Commercial Management
Ensure that the commercial legal
and process requirements are understood and
planned for by all those involved in programmes and projects. Ensure more effective
contracts management
6. Planning & Scheduling
Implement an Integrated planning & scheduling
Methodology in the Ships OC that drives a consistent
approach to planning into the heart of the business, allowing a Portfolio level view to be automatically
generated showing peak load periods, resource constraints
and dependencies.
7. Risk Management Design, document and implement an
optimised Enterprise level risk
management system that drives effective collective decision making on
key risk issues
8. Financial Management
Take the Corporate Finance Systems and
processes and the local methodologies
and refocus them into a single set of
systems and processes which are focused on providing support and control
within the P3M management system
9. Resource Management
Develop a workforce planning system that enables all Ships OC
manpower resources to be matched to a
prioritised set of programmes and
projects
10. Programme Office Constructs Define optimal organisational arrangements for central programming function in the Ships OC including how to optimise the relationship between the Ships Programme
Office and team level Programme Support Offices
Organisation & Roles
Example from DE&S Ships OC
+44 (0)1225 820980 www.bmt-hqs.com [email protected] ©BMT Hi-Q Sigma Ltd
Develop understanding of the Case for Change
In January 2014 it was recognised that the [organisation] did not have a coherent view of the resource used (money and people), levels of performance and risk, and relative priority of each of the organisations programmes and projects. This made it difficult to have informed Board level discussions on how we could optimise output delivery and balance risk (for example, through the allocation of resource).
There was a lack of commonality of approach across key programme & project management disciplines and in some areas a lack of rigour. The links between the Ships Portfolio Office (SPfO) and team level Programme Support Offices was weak. We did not have a clearly defined system of governance.
Combined these issues hampered effective strategic decision making, the delivery of core outputs, and the confidence the Customer and key stakeholders had with our organisation.
High level initial view (symptom driven)
then Detailed assessment
(cause driven)
Performance Management
• Subjective data (internal & external)
• Lack of analysis
• Significantly different report formats between similar teams
• Insufficient holding to account (H2A)
Planning & Scheduling
• Front door doesn’t work
• Lack of (integrated) baseline describing work
• Schedule and budget not always aligned
• Very little programme schedule analysis
Risk Management
• Risks not routinely captured, reviewed and approved
• Unrealistic assessments, not linked to finance process
• Mitigation strategies not turned into actions
• No clear escalation routes
• No list describing the projects and programmes it was delivering
• In almost every team, where management reports were generated they were bespoke for the team
• There was no senior management H2A around a performance dashboard
Specific Examples from 2014
• Open door policy for changes from the customer
• Some business units had one schedule and lots of projects others had lots more schedules than projects
• There were no integrated schedules outside
• No structure to organisations risk management
• Inconsistent use of risk toolset• Use of corporate risk tool to
manage project risks, confusing corporate reporting of risk with risk management
+44 (0)1225 820980 www.bmt-hqs.com [email protected] ©BMT Hi-Q Sigma Ltd
Establish clear view of programme outputs & benefits
Optimise Processes
& Tools Improve Structures
Develop Skills Generate Portfolio
Management Information
Higher level policy and process
CONOPs
Project Control Framework
Detailed process/procedures
Organisation
PfO
PROG PROG PROG PROG PROG
PgO PgO PgO PgO PgO
Programme Benefits
• More effective use of
resources
• Increased stakeholder
confidence and greater
standing
• More efficient use of
industrial capacity
• Right decisions made at
the right time
• Professional and
confidence people
working as one
• Enhanced effectiveness
year on year
Example from DE&S Ships OC
+44 (0)1225 820980 www.bmt-hqs.com [email protected] ©BMT Hi-Q Sigma Ltd
High level overview of a change programme
Identify
Deliver
Define Close
Current State
Future State
Governance Monitoring &
control
Blu
epri
nt
Controls framework, policy & processes
Organisation
Tools & Information
Implementation strategy & plans (projects in tranches)
Programme mandate
Case for change (business need)
Vision & mission Scope boundaries
Benefits
+44 (0)1225 820980 www.bmt-hqs.com [email protected] ©BMT Hi-Q Sigma Ltd
BLUEPRINT
Future State
Clear direction of travel
Current state
Maximise re-use of existing good process
Be realistic on how much there is to do, the resource available to make the change
and the capability to deliver the future process
+44 (0)1225 820980 www.bmt-hqs.com [email protected] ©BMT Hi-Q Sigma Ltd
Involvement the delivery community in developing
the process framework
Delivery team involvement in developing process framework
Ensure staff act as owners of the projects developing the improved processes, ensuring buy-in across
business units
Provides a consistent message of what you’re doing, what staff need to
do and why
Process Framework
Method-ology
Process & Tools
Cycle
Management involvement in approving process framework
Achieve via briefings and face-to-face communication (at various levels)
+44 (0)1225 820980 www.bmt-hqs.com [email protected] ©BMT Hi-Q Sigma Ltd
• Clarity around what responsibilities exist at each level within the project controls framework
• Build information from the bottom up to underpin the top-down strategy
Recognise differences between projects,
programmes and the portfolio
Customer / stakeholder
Organisation Portfolio
Programme
Project
Enablers
Portfolio Management
Programme Management
Project Management
Recognise
that these
are each
doing a
different
job!
Requirements & budget
Business plan
“Front door”
Programme plan
Baseline project schedules
KSE resource Process Tools
Programme Information
Project Information
Portfolio Information
Programme Reviews
Project Reviews
Portfolio Reviews
Customer / External Reviews
+44 (0)1225 820980 www.bmt-hqs.com [email protected] ©BMT Hi-Q Sigma Ltd
Planning implementation –
Understand the business & culture
Consistency
Build consistency & rigour in P3 management and controls from the project level
Consider “key principles based approach” to allow flexibility
Embedded support
Embed the change programme staff within the definition project teams, providing upskilling, mentoring and training
Culture awareness
Overcome resistance to change through an understanding of the culture, with real-time feedback
+44 (0)1225 820980 www.bmt-hqs.com [email protected] ©BMT Hi-Q Sigma Ltd
High level overview of a change programme
Identify
Deliver
Define Close Governance
Monitoring & control
Issue policy & process
Training, briefing, coaching
Communications
Establish enablers
Progressive implementation (within tranches)
Feedback and learning
Programme mandate
Case for change (business need)
Vision & mission
Current State
Future State
Scope boundaries
Blu
epri
nt
Benefits
Controls framework, policy & processes
Organisation
Tools & Information
Implementation strategy & plans (projects in tranches)
+44 (0)1225 820980 www.bmt-hqs.com [email protected] ©BMT Hi-Q Sigma Ltd
Implementation Approach – Communicate!
Key Implementation Themes: ‒ Introducing a standardised project control
approach and toolset
‒ Bringing all schedules into a single environment
‒ Educating & training staff
‒ Using the resulting information to support performance management and decision making
Example from DE&S Ships OC
Establish a simple briefing message to ensure programme intent is clearly understood
BOSS
+44 (0)1225 820980 www.bmt-hqs.com [email protected] ©BMT Hi-Q Sigma Ltd
Establish Maturity Progressively
Enablers
Management Plans, Policy, Process
Guidance / Templates (ASG)
Training / Coaching / Briefing
Programme Office Constructs (PfO and PgO Established)
Financial Management (Funding – project alignment)
Planning & Scheduling (Project schedules established)
Performance Reviews (OF5/B1 to 2* reviews updated)
Portfolio Management Information (fed progressively as projects deliver)
Resource Mgt (data & schedules)
Commercial Mgt (data & schedules)
Risk & Opportunity (Risks captured & managed)
Approval & Assurance (best practice & action tracking)
Incre
asin
g M
atu
rity
Example from DE&S Ships OC
+44 (0)1225 820980 www.bmt-hqs.com [email protected] ©BMT Hi-Q Sigma Ltd
Communicate Implementation Plan
Ongoing P3M Programme Management & Stakeholder Engagement / Communications tasks
Process Definition
Establishing Enablers
Establishing Foundations (Project level)
Executing Using Project Controls (Programme & Portfolio level)
Initial Operating
Capability
PHASE 1 PHASE 2
Managing
Example from DE&S Ships OC
+44 (0)1225 820980 www.bmt-hqs.com [email protected] ©BMT Hi-Q Sigma Ltd
Create and maintain the demand
It is necessary to create and maintain the demand for good project controls data.
If this is not the case, then good practice will wither at a rapid rate and maintaining configuration control of scope, schedule and cost will become increasingly difficult.
Performance Management
A performance reporting framework which demands and demonstrates use of the performance measurement output, up through the management organisation, should be created to drive the cultural change.
Create the demand
Deliver Projects
Project Information
Decisions
Programme Information
Decisions
Portfolio Information
+44 (0)1225 820980 www.bmt-hqs.com [email protected] ©BMT Hi-Q Sigma Ltd
High level overview of a change programme
Identify
Deliver
Define Close
Steady state process
Recognised benefits
Governance Monitoring &
control
Lessons learned
Assurance & compliance established
Programme mandate
Case for change (business need)
Vision & mission
Current State
Future State
Scope boundaries
Blu
epri
nt
Benefits
Controls framework, policy & processes
Organisation
Tools & Information
Implementation strategy & plans (projects in tranches)
Issue policy & process
Training, briefing, coaching
Communications
Establish enablers
Progressive implementation (within tranches)
Feedback and learning
+44 (0)1225 820980 www.bmt-hqs.com [email protected] ©BMT Hi-Q Sigma Ltd
1. Document & communicate the Control Environment Assess the risks to its use
2. Assign appropriate compliance management oversight
3. Give delivery responsibility to staff equipped to deliver
4. Implement regular monitoring and auditing of PCF application
5. Enforce the process consistently
6. Learn from non-compliance issues and improve PCF as a result
Get the balance right!
Ensure sustainability, continued compliance and
learning
+44 (0)1225 820980 www.bmt-hqs.com [email protected] ©BMT Hi-Q Sigma Ltd
High level overview of a change programme
Identify
Deliver
Define Close
Programme mandate
Case for change (business need)
Vision & mission
Current State
Future State
Steady state process
Recognised benefits
Scope boundaries
Governance Monitoring &
control
Blu
epri
nt
Controls framework, policy & processes
Organisation
Tools & Information
Implementation strategy & plans (projects in tranches)
Benefits
Lessons learned
Issue policy & process
Training, briefing, coaching
Communications
Establish enablers
Progressive implementation (within tranches)
Feedback and learning
Assurance & compliance established
+44 (0)1225 820980 www.bmt-hqs.com [email protected] ©BMT Hi-Q Sigma Ltd
The project control “basics”
Why a change programme?
Change programme Programme phase overview
Some key lessons and experiences
Summary
Clear Roles & Responsibilities
Control Over Scope
Agreed Plans & Targets
Performance Information
Management Decisions
Satisfied Customer
Thank you
+44 (0)1225 820980 www.bmt-hqs.com [email protected] ©BMT Hi-Q Sigma Ltd