42
Critical power: Transfer switches and switchgear Sponsored by:

Critical power: Transfer switches and switchgear

Embed Size (px)

DESCRIPTION

When an interruption of electrical power occurs, an automatic transfer switch shifts loads between utility and generator power. During these transitions, transfer switch timing and sequence is critical to ensure proper system operation. Consulting engineers must understand transfer switch types, timing requirements, ratings, and the effects that the characteristic of each emergency load has on generator operation. They must also understand how a facility’s electrical system (available fault current, number of generators, paralleling configuration) affects transfer switch choices.

Citation preview

Page 1: Critical power: Transfer switches and switchgear

Critical power: Transfer switches and switchgear

Sponsored by:

Page 2: Critical power: Transfer switches and switchgear

Today’s Webcast Sponsors:

Page 3: Critical power: Transfer switches and switchgear

Danna Jensen, PE, LEED AP BD+C,ccrd partners,Dallas, TX.

Ken Lovorn, PE, Lovorn Engineering Associates,Pittsburgh, PA.

Moderator: Jack Smith, Consulting-Specifying Engineer and Pure Power, CFE Media, LLC

Presenters:

Page 4: Critical power: Transfer switches and switchgear

Danna Jensen, PE, LEED AP BD+C,ccrd partners,Dallas, TX.

Ken Lovorn, PE, Lovorn Engineering Associates,

Pittsburgh, PA.

Understanding the code requirements for transfer switches and properly applying them in an emergency power design

Critical power: Transfer switches and switchgear

Page 5: Critical power: Transfer switches and switchgear

Topics

• Applicable codes and requirements• Open and closed transition switches• Applying transfer switches and switchgear in

emergency power system design

• Transfer switch timing and sequencing.

Page 6: Critical power: Transfer switches and switchgear

Applicable codes

• NFPA 70:National Electrical Code (2014)

• NFPA 110: Standard for Emergency and Standby Power Systems (2013)

• NFPA 99:Health Care Facilities Code (2012).

Page 7: Critical power: Transfer switches and switchgear

Applicable codes

• NFPA 70 Articles:– 517, 695, 700, 701, 702, and 708– 700: Emergency systems

• NFPA 110, chapter 6– Transfer switch equipment

• NFPA 99, chapter 6– Electrical systems.

Page 8: Critical power: Transfer switches and switchgear

Transfer switch requirements

• Prevent interconnection of two sources• Electrically operated/mechanically held• Listed for emergency system use • Supply only emergency loads• Suitable for operation of all functions intended to

supply.

Page 9: Critical power: Transfer switches and switchgear

Transfer switch requirements

• Generator exercising timers• Protection (selective coordination)• Motor load transfer provisions• Isolation of neutral conductor provisions• Include source monitoring and time delays.

Page 10: Critical power: Transfer switches and switchgear

Signaling/monitoring requirements

• Source monitoring:– Undervoltage sensing – Frequency sensing.

• Audible and visual annunciation – Switch position– When “not-in-automatic” mode– Not functioning– Ground fault.

Page 11: Critical power: Transfer switches and switchgear

Required time delays

• Engine start• Transfer to EPS• Retransfer to utility• Bypass delay• Engine shutdown.

Page 12: Critical power: Transfer switches and switchgear

Additional (optional) time delays

• Load priorities• Programmed transition• Elevator pre-transfer.

Page 13: Critical power: Transfer switches and switchgear

Switch types

• Automatic• Nonautomatic• Open or delayed

transition• Closed transition• Bypass isolation.

Page 14: Critical power: Transfer switches and switchgear

Open transition transfer switches

• Open transition means the load is disconnected from source one prior to being connected to source two

• Maximum isolation of the two sources• Power interruption to the load.

Page 15: Critical power: Transfer switches and switchgear

Closed transition transfer switches

• Closed transition means that the load is connected to source two prior to being disconnected from source one

• The two sources must be synchronized to be able to use closed transition

• As long as both sources are available, there is no power interruption to the load

• May have control issues if source one is dead, because source two cannot synchronize with a dead source.

Page 16: Critical power: Transfer switches and switchgear

Bypass transfer switches

• In the bypass mode, the transfer switch is isolated from both the normal and emergency sources so its mechanism may be maintained without a power interruption

• Applications• Drawbacks.

Page 17: Critical power: Transfer switches and switchgear

Switchgear mounted transfer switches

• Locating transfer switches in the switchgear lineup can:– Save installation time– Cause problems with adequate isolation between

switches and other components– Simplify control wiring when a number of switches

need to be coordinated– Potentially reduce electrical space requirements.

Page 18: Critical power: Transfer switches and switchgear

Transfer switch timing

• All loads at the same time• Separate loads into two or more steps• Delayed operation of transfer switches.

Page 19: Critical power: Transfer switches and switchgear

Single-step load assumption

• Worst-case starting condition• Possible generator failure• Severe voltage and frequency dip• Voltage may dip so low that control relays

could drop out.

Page 20: Critical power: Transfer switches and switchgear

Multiple-step load transfer

• May allow a reduced generator size• Mitigates major voltage dips• Allows more load without increasing

the generator size.

Page 21: Critical power: Transfer switches and switchgear

Delayed transfer applications

• High inertia loads• Elevator drive motors• Refrigeration compressors• Sources that are not in phase.

Page 22: Critical power: Transfer switches and switchgear

Sponsored by:

Applying transfer switches in emergency power system design

Page 23: Critical power: Transfer switches and switchgear

Design considerations

• The specifics of a facility’s electrical system affects the transfer switch choice

• Available fault current, number of generators, paralleling configuration, etc.

Page 24: Critical power: Transfer switches and switchgear

Application considerations• Location

– Available space– Minimize damage– Separate from utility

service equipment– Qualified personnel– Electrical point of

interconnection.

MAIN SERVICEENTRANCE

ATS

Page 25: Critical power: Transfer switches and switchgear

Application considerations

• Load analysis– Critical loads – Inductive loads– Nonlinear loads– Solid state loads

(VFD).

Page 26: Critical power: Transfer switches and switchgear

Application considerations

• Priority selection– Automatic– Nonautomatic– Bypass-isolation– Open or delayed transition– Closed transition.

Page 27: Critical power: Transfer switches and switchgear

Application considerations

• 3-pole versus 4-pole

Page 28: Critical power: Transfer switches and switchgear

Equipment rating

• Current rating to support total load• Withstand and closing rating (UL 1008)

– Any breaker– Specific breaker– Short time– 3-cycle versus 30-cycle.

Page 30: Critical power: Transfer switches and switchgear

Sponsored by:

Transfer switch timing application

Page 31: Critical power: Transfer switches and switchgear

Sample load list

• 50-kW lighting load• 30-ton air conditioning • 40-hp air handling unit• 40-hp air handling unit• 100-hp fire pump• 250-kW UPS• 60-hp elevator.

Page 32: Critical power: Transfer switches and switchgear

Single-step load transfer

• Lighting load• Air conditioning • Air handling unit• Air handling unit• Fire pump• UPS• Elevator.

Page 33: Critical power: Transfer switches and switchgear

Two-step load transfer, alt 1

• Step 1: UPS

• Step 2:– Lighting load– Air conditioning – Air handling unit– Air handling unit– Fire pump– Elevator.

Page 34: Critical power: Transfer switches and switchgear

Two-step load transfer, alt 2

• Step 1:– Lighting load– Air conditioning – Air handling unit– Air handling unit– Fire pump– Elevator.

• Step 2: UPS

Page 35: Critical power: Transfer switches and switchgear

Three-step load transfer, alt 1

• Step 1: UPS• Step 2:

– Lighting load– Air conditioning – Air handling unit

• Step 3: – Air handling unit– Fire pump– Elevator.

Page 36: Critical power: Transfer switches and switchgear

Three-step load transfer, alt 2• Step 1:

– Lighting load– Air conditioning – Air handling unit

• Step 2:– Air handling unit– Fire pump– Elevator

• Step 3: UPS.

Page 37: Critical power: Transfer switches and switchgear

Timing comparison

With 6-pulse UPS• Single step: 1,750 kW• Two step, alt 1: 1,750 kW• Two step, alt 2: 1,750 kW• Three step, alt 1: 1,750 kW• Three step, alt 2: 1,750 kW.

With 12-pulse UPS• Single step: 1,750 kW• Two step, alt 1: 1,250 kW• Two step, alt 2: 1,250 kW• Three step, alt 1: 800 kW• Three step, alt 2: 800 kW.

Page 38: Critical power: Transfer switches and switchgear

Conclusions

• Unfiltered 6-pulse UPS systems can dictate the size of the generator regardless of timing

• Sequential timing of transfer switches can permit smaller generator sizes

• Dividing the load into more steps can reduce the generator size.

Page 39: Critical power: Transfer switches and switchgear

Danna Jensen, PE, LEED AP BD+C,ccrd partners,Dallas, TX.

Ken Lovorn, PE, Lovorn Engineering Associates,Pittsburgh, PA.

Moderator: Jack Smith, Consulting-Specifying Engineer and Pure Power, CFE Media, LLC

Presenters:

Page 40: Critical power: Transfer switches and switchgear

Thanks to Today’s Webcast Sponsors:

Page 42: Critical power: Transfer switches and switchgear

Critical power: Transfer switches and switchgear

Sponsored by: