Upload
miner-generalao
View
363
Download
3
Embed Size (px)
Citation preview
PPP can be broadly defined as contractual agreement between the Government and a private firm to:
• Finance• Design • Implement and • Operate
Infrastructure facilities and services that were traditionally provided by the public sector.
What is unique with PPP
• Balancing act: Embodies optimal risk allocation between the parties – minimizing cost while realizing project developmental objectives.
• Needs to structure a project in such a way that the private sector gets a reasonable rate of return on its investment
Elements of PPP
• A contractual agreement between the public sector and the private sector
• Strategic mode of procurement• Shared risks and resources• Value for Money• Outcome orientation• Acceleration of infrastructure provision
and faster implementation
July 1990 – Republic Act No. 6957, also called the BOT Law. It presented two project schemes: build-operate-and-transfer (BOT) and build-and- transfer (BT).
9 Contractual agreements under the BOT Law as amended
• Build-operate-and-transfer (BOT) • Build-and-transfer (BT)• Build-lease-and-transfer (BLT) • Build-own-and-operate (BOO) • Build-transfer-and-operate (BTO) • Contract-add-and-operate (CAO) • Develop-operate-and-transfer (DOT) • Rehabilitate-operate-and-transfer (ROT) • Rehabilitate-own-and-operate (ROO)
2010 – President Aquino reorganizes the BOT Center and renames it as the Public-Private Partnership of the Philippines and transfers it from the Department of Trade and Industry to the National Economic Development Authority
The story so far
• 34 completed PPP projects with a total cost of P3.9B
• 38 operational projects with a total cost of P16.6B
• 28 just awarded projects for around P10B.
The story so far
• 34 completed PPP projects with a total cost of P3.9B
• 38 operational projects with a total cost of P16.6B
• 28 just awarded projects for around P10B.
• Complicated process, delay in government review and approval,
• Bidding failure, no bidders• Issue on direct guarantees and sharing
of risks • How to strike a balance between
commercial viability and public interest• Improving the quality of project pipelines with sufficient
project preparation, including economic, financial, technical
and environmental feasibility studies, is critical to clearing
the way for private sector participation. Limited flow of bankable projects because of underinvestment in project preparation represents a major obstacle to public-private partnerships for infrastructure.
Blended finance is combining the public sector’s social return objectives and private sector’s financial return objectives through risk mitigation by the public sector in a manner that induces the private sector to participate.
Notes on blended finance• Blended finance is defined as the complementary use of grants (or
grant-equivalent instruments) and non-grant financing from private and/or public sources to provide financing on terms that would make projects financially viable and/or financially sustainable.
• Given that certain infrastructure investments may not be commercially viable, innovative instruments have been sought to close this ‘viability gap’ and make a larger number of projects bankable.
• By blending grants with loans, this innovative approach to development finance aims to achieve a number of objectives – from increasing the volume of development finance in a context of constrained resources, to increasing the viability of investments, to enhancing the overall effectiveness of aid.