32
NZBC Clause H1 Overview Robert Campion Architectural Profiles Ltd (APL) October 2007

NZBC-H1_Overview-Oct07

Tags:

Embed Size (px)

DESCRIPTION

Rob Campion of APL gives an overview of the NZBC Clause H1 - Energy Efficiency

Citation preview

Page 1: NZBC-H1_Overview-Oct07

NZBC Clause H1Overview

Robert CampionArchitectural Profiles Ltd (APL)

October 2007

Page 2: NZBC-H1_Overview-Oct07

energy efficiency

“Biggest energy efficiency steps

in 30 years”

Page 3: NZBC-H1_Overview-Oct07

nzbc clause H1

Page 4: NZBC-H1_Overview-Oct07

energy efficiency

The changes;

tougher insulation requirements

domestic hot water systems

commercial lighting

commercial HVAC systems

Page 5: NZBC-H1_Overview-Oct07

heat loss

un-insulated house

windows =12%walls =24%

roof = 42%

floor =10%

Page 6: NZBC-H1_Overview-Oct07

nzbc clause H1

Generally based on NZS 4218:2004

but…with increased R-values

Tables shown within H1 replace those used in NZS 4218

Page 7: NZBC-H1_Overview-Oct07

climate zones

Zone1 Auckland, North

Zone 2 Balance North

Island, except Central Plateau

Zone 3South Island & Central Plateau

Page 8: NZBC-H1_Overview-Oct07

new R values

Page 9: NZBC-H1_Overview-Oct07

new R values

non-solid constructionroof; z1 = R2.9

z2 = R2.9

z3 = R3.3

floor; z1 = R1.3

z2 = R1.3

z3 = R1.3

window; z1 = 0.26

z2 = R0.26

z3 = R0.26

wall; z1 = R1.9

z2 = R1.9

z3 = R2.0

Page 10: NZBC-H1_Overview-Oct07

nzbc clause H1

3 Methods of Compliance…

ScheduleUsed when <30% of wall area is glazed

CalculationUsed when <50% of wall area is glazed

ModelingUsed when >50% of wall area is glazedand complex design

Page 11: NZBC-H1_Overview-Oct07

schedule method

Page 12: NZBC-H1_Overview-Oct07

floor

un-insulated house

floor = 10% z1 = R1.3

z2 = R1.3

z3 = R1.3

Page 13: NZBC-H1_Overview-Oct07

floor

insulated timber floordraped foil100mm sagcarpet

= R1.5

no carpet

= R1.1Pic Courtesy of BRANZ - BRANZ House Insulation Guide

Page 14: NZBC-H1_Overview-Oct07

floor

concrete floorslab/perim. ratio

= 1.5

insulated / no TB

= R1.3

insulated with TB

= R1.5

Pic Courtesy of BRANZ - Build Magazine

Page 15: NZBC-H1_Overview-Oct07

roof

un-insulated house

roof = 42%

z1 = R2.9

z2 = R2.9

z3 = R3.3

Page 16: NZBC-H1_Overview-Oct07

roof

concrete tile - trussblanket typetimber battensz2 requirement

= R2.9

insulation mustmeet R2.65

Pic Courtesy of BRANZ - BRANZ House Insulation Guide

Page 17: NZBC-H1_Overview-Oct07

walls

un-insulated house

walls = 24%z1 = R1.9

z2 = R1.9

z3 = R2.0

Page 18: NZBC-H1_Overview-Oct07

walls

brick veneerblanket type100 x 50studs @ 600z2 requirement =

R1.9

insulation mustmeet R2.05

Pic Courtesy of BRANZ - BRANZ House Insulation Guide

Page 19: NZBC-H1_Overview-Oct07

walls

stucco on cavityblanket type100 x 50studs @ 600z2 requirement

= R1.9

insulation mustmeet R2.15

Pic Courtesy of BRANZ - BRANZ House Insulation Guide

Page 20: NZBC-H1_Overview-Oct07

walls

stucco on cavityblanket type100 x 50studs @ 400z2 requirement

= R1.9

insulation mustmeet R2.3

Pic Courtesy of BRANZ - BRANZ House Insulation Guide

Page 21: NZBC-H1_Overview-Oct07

windows

un-insulated house

windows =12% z1 = R0.26

z2 = R0.26

z3 = R0.26

Page 22: NZBC-H1_Overview-Oct07

schedule method

Page 23: NZBC-H1_Overview-Oct07

wers table

Page 24: NZBC-H1_Overview-Oct07

calculation method

Page 25: NZBC-H1_Overview-Oct07

calculation method

Zone 2, 34.7% (45m2) Glazed Area

HLRef = 38.9m2/0.26 + 6.1/0.31

= 149.6 + 19.7

= 169.3 m2 oC/W

Page 26: NZBC-H1_Overview-Oct07

calculation method

If window target = 169.3…

Aluminium frame / single clear glass R(Total) = 0.15

45m2 @ 0.15 = 300 (130.7130.7 must be made up elsewhere)

equates to doubling all other values

Page 27: NZBC-H1_Overview-Oct07

calculation method

If window target = 169.3…

Aluminium frame / clear IGU R(Total) = 0.26

45m2 @ 0.26 = 173.1 (3.83.8 must be made up elsewhere)

Page 28: NZBC-H1_Overview-Oct07

calculation method

If window target = 169.3…

Thermally broken frame/clear IGU R(Total) = 0.31

45m2 @ 0.31 = 145.2 (24.124.1 can be reduced elsewhere)

Page 29: NZBC-H1_Overview-Oct07

modeling method

Modeling Method

Designer contacts a specialist with the appropriate software to calculate the building requirements

Page 30: NZBC-H1_Overview-Oct07

modeling method

Page 31: NZBC-H1_Overview-Oct07

status

Zone 3 31 October 2007

Zone 2 30 June 2008

Zone 1 30 Sept 2008

Page 32: NZBC-H1_Overview-Oct07

thank you

Refer to the Third Edition of NZBC Clause H1 – Energy Efficiency in conjunction with NZS 4218:2004 – Energy Efficiency, Small Building Envelope, for a full understanding of the changes.