Page 1: YOUR IKEA KITCHEN PROJECT...YOUR IKEA KITCHEN PROJECT Congratulations on kicking off your IKEA kitchen project. With a little help from Traemand*, you’ll have the kitchen of your

YOUR IKEA KITCHEN PROJECT

Congratulations on kicking off your IKEA kitchen project. With a little help from Traemand*, you’ll have the kitchen of your dreams! We are IKEA’s nationwide kitchen planning and installation partner. Our experienced teams can measure, plan, assemble and install your dream IKEA kitchen. We offer a five-year warranty on all of our IKEA installations in conjunction with IKEA’s 25-year product warranty.

1. Order the Measurement & Planning (M&P) Service from IKEASelect a date and two-hour time window for Traemand to come to your home and measureyour existing space. The Measurement appointment will take between 30 and 45 minutes. Besure to complete your Kitchen Planning Checklist on the customer portal beforehand. A KitchenPlanning Consultant will be assigned to your project, and will call you to review your kitchenmeasurements and wants and desires from your completed checklist. You'll receive a KitchenPlan Package by email within 5 business days of your measurement appointment. Need extratime? Don't worry, you can make revisions for up to 45 days!

2. Purchase your new kitchen from IKEAOrder and schedule the delivery of your parts at your local IKEA store based on the parts listincluded in your Kitchen Plan Package. Our plans and your vision make this step easier for theIKEA kitchen coworker who will assist you!

3. Book your kitchen installation with TraemandWe're here when you need us. Let your Kitchen Planning Consultant know your delivery datesand your preferred installation dates. This allows us to get in on time while you stay on budget.

4. Take inventory of your delivered partsIt’s important to make sure the items delivered match the items on your receipt. If something isdamaged or missing, let IKEA know within 48 hours of your delivery. Any parts that were out ofstock when you placed your order will need to be ordered and paid for at the store prior toinstallation.

5. Schedule and complete prep work for your new kitchenPrep work ensures your space is ready for cabinet installation! It includes disassembly ofexisting kitchen, drywall, flooring (except floating floors), electrical and plumbing. If you're on abudget you can DIY prep work and have electric and plumbing completed by licensedtradespeople. If you prefer to have your prep work done for you, you can also hire a contractor.Don't know a General Contractor? Traemand can refer one to you! Be sure to let us know ifyour prep work changes your installation date.

6. Successful Traemand assembly and installationTraemand has installed tens of thousands of IKEA kitchens since our start in 2005. Traemand’sexperienced installation teams are licensed, trained, drug-screened and background checked.We offer the best warranty in the industry.

7. Finishing touches and trimoutFinal plumbing and electrical (also known as trimout), countertop templating and installation,as well as backsplash, paint touch-ups, appliance installation and new accessories round out theend of your kitchen remodeling project! We can refer you to contractors who can do this work.

8. Enjoy your new kitchen, fill out our survey!You did it! With a little help from Traemand, your vision and preparation kept your IKEA kitchenproject on track. We'd love to know how we did, so don't forget to fill out your survey, as well!

We are here for you! If you have questions, email [email protected] or call us at (720) 214-4064. You can also visit us at www.traemand.com for more information.

*Measurement, Measurement & Planning, and Installation are performed by Traemand, an independent third party service provider.

Page 2: YOUR IKEA KITCHEN PROJECT...YOUR IKEA KITCHEN PROJECT Congratulations on kicking off your IKEA kitchen project. With a little help from Traemand*, you’ll have the kitchen of your

Wall construction, rough plumbing,

electrical & sheetrock

Paint & Patch

NewFlooring

Traemand Installation

Countertop,Tile, Final

Plumbing & Electrical

Final Steps

ONE to TWO

WEEKS

TWO to THREE DAYS

TWO to FOUR WEEKS

KITCHEN REMODEL TIMELINE

Time frame from countertop template to

install depends on vendor

chosen & time of year. After installed, complete

backsplash, final plumbing & electrical.

This is when paint touch-ups are completed,

remaining debris is

removed, and your kitchen is deep cleaned.

Installation depends on

scope of work, number of cabinets &

existing wall materials in the

home.

Most flooring (tile,

nail down, glue down, vinyl)

can be installed before

cabinets. All floating floors should be done after cabinets.

TWO DAYS

After sheetrock it's time to mud,

sand, texture, prime & paint

your walls. Minor touch-ups will need to be

done after cabinets and

countertops are installed.

This is the time to open walls for

rough electrical &

plumbing work. Sheetrock is last.

Disassembly

Timing depends on who

you choose to complete the

disassembly of your existing

kitchen. Hiring a professional often ensures

your old kitchen is gone

in one day!

ONE DAY

ONE WEEK

Put the date you’d like to be living in your new

kitchen below.

DAY 1 DAY 14 DAY 21 DAY 23 DAY 25 DAY 53 DAY 60

/ /Simple cabinet replacement with stock counter tops can be done in less than a week. Extensive remodeling could take up to 60 days. See time-line below to plan how long your project might take.

ONE WEEK


Recommended