UPGRADING OF NAIROBI URBAN ROAD
NETWORK
Meeting at NAIROBI CLUB ON 8TH FEBRUARY, 2017
1
Presented by: Eng. S. M. Kinoti
Ag. DG -KURA
OUTLINE
1.INTRODUCTION
2.NAIROBI PLANS (ROADS COMPONENT)
3.UPPERHILL PROJECT HIGHLIGHTS
4.CHALLENGES
5.EXPECTATIONS
6.Q AND A
2
INTRODUCTION3
KURA is a State Corporation under the Ministry of
Transport, Infrastructure, Housing and Urban
Development mandated to manage, develop,
rehabilitate and maintain all national urban trunk
roads.
INTRODUCTION4
Vision
To be a global leader in the provision and
management of urban roads network
Mission
To professionally provide quality, safe and
adequate urban road network that satisfies
stakeholder needs
URBAN TRANSPORT SITUATION IN
NAIROBI 5
Since inception 7 years ago KURA has been able to upgrade,
construct and maintain over 12,000km of roads in the country
most of them in Nairobi City County.
Nairobi population is over 4m and the day’s population is about
7m (Includes people from the nearby towns e.g Kajiado,
Machakos, Kiambu)
This leads to: -
1. Heavy traffic flows during peak hours
2. Traffic management demands outstripping the
resources
3. Inadequate infrastructure facilities
MEASURES BEING TAKEN BY KURA TO ADDRESS
TRAFFIC CONGESTION IN NAIROBI6
Nairobi Urban Transport Master Plan 2006 and the Nairobi
Integrated Urban Development Plan’ (NIUPLAN), 2014 were
developed through funding from Japan International Cooperation
Agency ( JICA)
KURA is implementing the road infrastructure components of
these Plans
Some of the completed projects under these master plans include:
1. Dualling of Langata Road from Kenya Wildlife Service to
Bomas of Kenya
2. Improvement of Eastleigh Roads Phase 1
3. Improvement of Upperhill Roads Phase 1
4. Construction of Northern Bypass
5. Construction of Eastern Bypass
6. Construction of Nairobi Western Ring Roads
MAP OF ROADS PROJECTS WITHIN NAIROBI7
MAP FOR NAIROBI MISSING LINKS8
ON-GOING PROJECTS:1. Construction of Eastern Missing Link Roads and
Non-Motorized Transport Facilities (NMT) in
Nairobi – Kenya
2. Nairobi Outer Ring Road (C59) Improvement
Project
3. Dualling of Ngong road(Phase 1) from Kenya
National Library Services to Junction Ring Road
Kilimani
4. Construction of Waiyaki Way – Red Hill Project
5. Upgrading of Industrial Area Roads Phase 1
9
ON-GOING PROJECTS CONT’D…..
6. Construction of Baraka link Road (Kangundo Rd –
Komarock Road)
7. Upgrading of Lenana – Muchugia –Dagoreti Link Rd
8. Improvement of Eastleigh Roads Phase 11
9. Piloting of Intelligent Transportation System(ITS) on
Western Ring Roads
10.Upgrading of Upperhill – Mabagathi Link Rd
11.Rehabilitation and Upgrading of Upper Hill Rds
Phase 11
9
UP-COMING PROJECTS:
1. Ngong Road Phase 2 (Prestige – Dagoreti Corner) – JICA
2. Ngong Rd Phase 3 (Dagoreti Corner – Karen Roundabout)
- GoK
3. Upgrading of Industrial Area Roads Phase 2
4. Design and construction of Missing Links in Nairobi
Eastern Region
5. Design and construction of Upperhill Overpasses and
Missing Links in Nairobi Western Region
6. Design for implementation of Intelligent Transportation
System on various junctions within Nairobi CBD
10
ELEVATED SECTION ON OUTERING RD11
WAIYAKI WAY – RED HILL STRUCTURES 12
EXPANSION OF NGONG ROAD PHASE 113
LIKONI/ENTERPRISE RD INTERCHANGE 14
UPGRADING OF UPPERHILL ROADS
PHASE II
AND
UPPERHILL – MBAGATHI LINK ROAD
15
INTRODUCTION
Under Vision 2030, Upperhill is designed to
be the Regional Financial hub (East, Central
and the horn of Africa).
Eastleigh and City Centre are designed to be
commercial hubs of the city
KONZA is the Technocity.
KURA is fulfilling the dream of Vision 2030
and we are all witnessing this transformation
today.
16
18
UPPERHILL PROJECT ROADS
Road Name Length
(KM)
Existing
Rd width
Design Rd
Width
Upper Hill Road 1.0 18 21.6
Lower Hill Road 1.4 30 21.6
Masaba Road 1.3 18 21.6
Matumbato Road 1.0 18 21.6
Chyulu Road 0.5 9-12 21.6
Menengai Road 0.4 18-30 21.6
Mara Road 0.4 18-30 21.6
Link Road between Chyulu and Mara Road 0.5 9-12 21.6
Upperhill – Mbagathi Link Road 2.1 30 21.6
Mawenzi Road 0.6 15-18 12
Improvement of roads within KNH and Mbagathi Way 5.0 12 - 18 12
TOTAL 14.2
18
REHABILITATION AND UPGRADING
OF UPPER HILL ROADS (PHASE 11)19
Project Title Rehabilitation and Upgrading of Upper Hill Roads (Phase 11)
Financier Government of Kenya
Employer Director General, Kenya Urban Roads Authority (KURA)
Engineer General Manager (Design and Construction), KURA
Contractor Tosha Holdings Ltd
Contract Sum 2.25 Billion
Date of Award 19th September, 2016
Commencement date 6th December, 2016
Contract period 24 months
Date of completion 7th December, 2018
Period of time elapsed 2 months
CONSTRUCTION OF UPPER HILL -
MBAGATHI LINK ROADS20Project Title Construction Of Upper Hill -Mbagathi Link Roads
Financier Government of Kenya
Employer Director General, Kenya Urban Roads Authority (KURA)
Engineer General Manager (Design and Construction), KURA
Contractor INTERWAYS WORKS LTD
Contract Sum 1.25 Billion
Date of Award 19th September, 2016
Commencement date 6th December, 2016
Contract period 18 months
Date of completion 7th June, 2018
Period of time elapsed 2 months
EXTENT OF CONTRACT21
Construction of the roads to dual carriageways
Construction of walkways and cycle lanes
Construction of drainage structures.
Protection works including stone pitching and gabions as
necessary
Installation of road furniture and road markings
Relocation of services Rehabilitation of roads within
KNH and Mawensi Road
Construction of a footbridge over Mbagathi way
UPPERHILL PHASE 222
PROJECT MAP23
TYPICAL CROSSECTION24
UPPER HILL – MBAGATHI LINK RD25
UPPER HILL – MBAGATHI LINK RD26
CHALLENGES27
Service relocation i.e Sewer and water lines,
Power lines and Data cables.
Unavailability of adequate space for roads
expansion
Unknown details of land already surrendered
Access to land for areas not surrendered
EXPECTATIONS28
Property owners who have surrendered for
expansion of the Road corridor to avail the details
of surrender.
Property owners who have not surrendered to do
as per Structure plan.
Cooperation from all the stakeholders during
construction period