Transmission Line Abstract of RFD 2020-21
Q1 Q1 Q2 Q2 Q3 Q3 Q4 Q4
CENTRAL SECTOR T A T A T A T A T A
DAMODAR VALLEY CORPORATION (DVC) 13 0 95 0 435 0 0 0 543 0
POWER GRID CORPORATION OF INDIA LIMITED (PGCIL) 268 380 3844 4448 910 0 324 0 5346 4828
TOTAL 281 380 3939 4448 1345 0 324 0 5889 4828
STATE SECTOR
TRANSMISSION CORPORATION OF ANDHRA PRADESH LIMITED. (APTRANSCO) 0 0 67 127 70 0 0 0 137 127ASSAM ELECTRICITY GRID CORP. LIMITED (AEGCL) 0 0 0 0 0 0 40 0 40 0
BIHAR STATE POWER TRANSMISSION COMPANY LIMITED (BSPTCL) 0 0 52 0 0 0 0 0 52
CHHATTISGARH STATE POWER TRANSMISSION CO. LTD. (CSPTCL) 0 0 43 0 0 0 74 0 117
DELHI TRANSCO LIMITED (DTL) 0 0 0 11 13 0 0 0 13 11
GUJARAT ENERGY TRANSMISSION CORP. LIMITED (GETCO) 0 0 48 161 48 200 0 296 161
HARYANA VIDYUT PRASARAN NIGAM LIMITED (HVPNL) 12 13 66 76 64 0 100 0 242 89
HIMACHAL PRADESH POWER TRANSMISSION CORP. LTD. (HPPTCL) 0 0 36 2 0 3 110 0 146 5
J&K POWER DEVELOPMENT DEPARTMENT (JKPDD) 0 0 21 0 24 0 0 0 45
JHARKHAND URJA SANCHARAN NIGAM LIMITED (JUSNL) 0 0 290 672 547 0 0 0 837 672
KARNATAKA POWER TRANSMISSION CORP. LIMITED (KPTCL) 20 225 125 100 113 0 0 0 258 325
KERALA STATE ELECTRICITY BOARD (KSEB) 91 0 30 97 23 0 0 0 144 97
M.P. POWER TRANSMISSION CORPORATION LIMITED (MPPTCL) 40 144 53 259 494 63 816 0 1403 466
MAHARASHTRA STATE ELEC. TRANSMISSION COMPANY LTD. (MSETCL) 14 0 0 85 225 0 247 0 486 85
ELECTRICITY DEPARTMENT, GOVT. OF MANIPUR(ED, MANIPUR) 0 0 90 0 0 0 0 0 90
ORISSA POWER TRANSMISSION CORPORATION LTD. (OPTCL) 0 12 82 3 0 0 170 0 252 15
POWER TRANSMISSION CORP. OF UTTARAKHAND LTD. (PTCUL) 30 150 0 0 0 0 71 0 101 150
PUNJAB STATE TRANSMISSION CORPORATION LIMITED (PSTCL) 12 1 101 0 67 0 0 0 180 1
RAJASTHAN VIDYUT PRASARAN NIGAM LIMITED (RVPNL) 10 0 0 85 517 112 264 0 791 197
TAMILNADU TRANSMISSION CORPORATION LTD. (TANTRANSCO) 94 77 15 74 929 113 0 0 1038 264
TRANSMISSIPN CORPORATION OF TELANGANA (TSTRANSCO) 53 1 70 28 168 0 340 0 631 29
U.P. POWER TRANSMISSION CORPORATION LTD. (UPPTCL) 51 88 54 159 388 0 108 0 601 247
WEST BENGAL STATE ELECTRICITY TRANSMISSION CO. LIMITED (WBSETCL) 0 0 0 0 64 89 0 0 64 89
TOTAL 427 711 1243 1939 3754 380 2540 0 7964 3030
PRIVATE SECTOR
ADANI TRANSMISSION LTD. 102 0 389 0 43 0 292 0 826 0
ESSEL INFRAPROJECTS LIMITED 221 0 0 0 0 0 0 0 221
STERLITE GRID LTD. (SGL) 534 0 357 0 0 0 0 0 891
KALPATARU POWER TRANSMISSION LTD (KPTL) 0 0 0 236 0 0 0 0 0 236
TOTAL 857 0 746 236 43 0 292 0 1938 236
Grand Total 1565 1091 5928 6623 5142 380 3156 0 15791 8094
Total
Substation Abstract of RFD 2020-21
Q1 Q1 Q2 Q2 Q3 Q3 Q4 Q4T A T A T A T A T A
CENTRAL SECTOR
DAMODAR VALLEY CORPORATION (DVC) 315 0 480 0 0 0 0 0 795 0
POWER GRID CORPORATION OF INDIA LIMITED (PGCIL) 5315 4010 10260 3500 1500 500 6000 0 23075 8010
TOTAL 5630 4010 10740 3500 1500 500 6000 0 23870 8010STATE SECTOR
TRANSMISSION CORPORATION OF ANDHRA PRADESH LIMITED. (APTRANSCO) 1315 0 1565 0 0 0 0 0 2880 0
BIHAR STATE POWER TRANSMISSION COMPANY LIMITED (BSPTCL) 0 0 900 0 0 0 0 0 900 0
CHHATTISGARH STATE POWER TRANSMISSION CO. LTD. (CSPTCL) 630 0 0 0 0 0 0 0 630 0
DELHI TRANSCO LIMITED (DTL) 0 60 420 0 0 0 0 0 420 60
GUJARAT ENERGY TRANSMISSION CORP. LIMITED (GETCO) 0 0 980 780 0 160 0 0 980 940
HIMACHAL PRADESH POWER TRANSMISSION CORP. LTD. (HPPTCL) 0 0 0 0 600 0 0 0 600 0
HARYANA VIDYUT PRASARAN NIGAM LIMITED (HVPNL) 1360 200 0 700 620 0 0 0 1980 900
J&K POWER DEVELOPMENT DEPARTMENT (JKPDD) 0 0 0 0 480 0 0 0 480 0
JHARKHAND URJA SANCHARAN NIGAM LIMITED (JUSNL) 2260 0 0 1200 0 0 0 0 2260 1200
KERALA STATE ELECTRICITY BOARD (KSEB) 800 0 200 200 0 100 0 0 1000 300
KARNATAKA POWER TRANSMISSION CORP. LIMITED (KPTCL) 0 200 800 1300 1900 50 0 0 2700 1550
M.P. POWER TRANSMISSION CORPORATION LIMITED (MPPTCL) 640 370 260 320 2055 320 0 0 2955 1010
MAHARASHTRA STATE ELEC. TRANSMISSION COMPANY LTD. (MSETCL) 200 30 0 200 725 0 0 0 925 230
ELECTRICITY DEPARTMENT, GOVT. OF MANIPUR(ED, Manipur) 315 0 0 0 0 0 0 0 315 0
ODISHA POWER TRANSMISSION CORPORATION LTD. (OPTCL) 0 320 875 320 660 0 0 0 1535 640
PUNJAB STATE TRANSMISSION CORPORATION LIMITED (PSTCL) 260 420 100 0 500 0 0 0 860 420
POWER TRANSMISSION CORP. OF UTTARAKHAND LTD. (PTCUL) 50 0 0 0 0 0 0 0 50 0
RAJASTHAN VIDYUT PRASARAN NIGAM LIMITED (RVPNL) 0 0 480 160 160 0 0 0 640 160
TAMILNADU TRANSMISSION CORPORATION LTD. (TANTRANSCO) 400 100 3000 200 3000 200 0 0 6400 500
TRANSMISSIPN CORPORATION OF TELANGANA (TSTRANSCO) 1000 0 200 0 520 0 0 0 1720 0
U.P. POWER TRANSMISSION CORPORATION LTD. (UPPTCL) 640 680 2700 1480 1680 500 0 0 5020 2660
WEST BENGAL STATE ELECTRICITY TRANSMISSION CO. LIMITED (WBSETCL) 0 0 0 0 320 0 400 0 720 0
TOTAL 9870 2380 12480 6860 13220 1330 400 0 35970 10570PRIVATE SECTOR
ADANI TRANSMISSION LIMITED 0 0 0 0 1950 0 0 0 1950 0
STERLITE POWER TRANSMISSION LTD. 1260 1000 0 0 0 0 0 0 1260 1000
KALPATARU POWER TRANSMISSION LTD (KPTL) 0 0 0 1000 0 0 0 0 0 1000
TOTAL 1260 1000 0 1000 1950 0 0 0 3210 2000
GRAND TOTAL 16760 7390 23220 11360 16670 1830 6400 0 63050 20580
Total
REPORT INDICATING STATUS OF CONSTRUCTION OF TRANSMISSION LINES (220 kV & ABOVE)IN RFD PROGRAMME DURING- 2020-21
As on 31-OCT-2020
7. 8. 9. 10. 13.
Revised/Anticipated
11.
Progress Status of Transmission Target Date
RemarksTotalLocations
(Nos)
Foundationcompleted
(Nos)
TotalLength(cKm)
1.
Stringingcompleted
(CKm)Schedule
5. 6. 2. 3. 4.
SlNo
Name ofTransmission
Lines
Ckts(S/C)
&(D/C)
VoltageLevel(kV)
TowerErected
(Nos)
Tag Names
12.
CENTRAL SECTOR
DAMODAR VALLEY CORPORATION ( DVC )
LILO of Parulia - Dtps at Durgapursteel TPS
D/C 220 13 17 17 16 13 MAY-20 JAN-21 Initially contract for Electrical workissued to M/s R.K. Electric AutomationLtd which had been terminated on17.04.18, matter is under subjudice.Fresh order placed on 13.02.19 to M/sAvartanah Infrastructure Pvt. Ltd. toexecute the leftover work. However,completion time is being revised in theevent of situation arisen due to COVID-19.
1 RFD
MTPS - Ramgarh (Bypassing Gola SS) S/C 220 207 682 678 673 191 OCT-20 MAR-21 It was planned to construct a 220KVS.Stn at Gola having it's three xdouble Circuit connectivity with MTPS,Ranchi-PGCIL & Ramgarh. Later,construction of Gola S.stn. wasdropped. In the 19th StandingCommittee Meeting on Power SystemPlanning of ER, a revised plan videletter no. EDCON/SPEICEA-07 Dated.05.01.17, was proposed forconversion of said 3 X DC line intothree Single Circuit lines such as i)MTPS-Ranchi ii) MTPS-Ramgarh & iii)Ranchi- Ramgarh. bypassing the GolaS/S. From Ramgarh S.Stn. to Gola ,37km of the line is charged since22.04.2014. Further 138.85KM/170KM of Gola -MTPS portion ofthe line is charged also. Due todiversion, total locations increasedfrom 681 to 682. However, completiontime is being revised in the event ofsituation arisen due to COVID -19.
2 RFD
17Page 1 ofReport generated through NPP 9.05.58 PMSunday 08
7. 8. 9. 10. 13.
Revised/Anticipated
11.
Progress Status of Transmission Target Date
RemarksTotalLocations
(Nos)
Foundationcompleted
(Nos)
TotalLength(cKm)
1.
Stringingcompleted
(CKm)Schedule
5. 6. 2. 3. 4.
SlNo
Name ofTransmission
Lines
Ckts(S/C)
&(D/C)
VoltageLevel(kV)
TowerErected
(Nos)
Tag Names
12.
MTPS- Ranchi (PG) (Bypassing GolaSS)
S/C 220 228 779 775 761 172 OCT-20 MAR-21 It was planned to construct a 220KVS.Stn at Gola having it's three xdouble Circuit connectivity with MTPS,Ranchi- PGCIL & Ramgarh. Later,construction of Gola S.stn. wasdropped. In the 19th StandingCommittee Meeting on Power SystemPlanning of ER, a revised plan videletter no. EDCON/SPEICEA-07 Dated.05.01.17, was proposed forconversion of said 3 X DC line intothree Single Circuit lines such as i)MTPS-Ranchi ii) MTPS-Ramgarh & ill)Ranchi- Ramgarh. bypassing the GolaS/S. From Ramgarh S.Stn. to Gola ,37km of the line is charged since22.04.2014. Further 138.85KM/170KM of Gola -MTPS portion & 4KM/58 KM of Gola-Ranchi portion ofthe line is also charged . Due todiversion total location increased from778 to 779 . However, completion timeis being revised in the event ofsituation arisen due to COVID -19.
3 RFD
Ramgarh - Ranchi (PG) (BypassingGola SS) (Balance portion)
S/C 220 95 355 355 348 69 AUG-20 MAR-21 It was planned to construct a 220KVS.Stn at Gola having it's three xdouble Circuit connectivity with MTPS,Ranchi, PGCIL & Ramgarh. Later,construction of Gola S.stn. wasdropped. In the 19th StandingCommittee Meeting on Power SystemPlanning of ER, a revised plan videletter no. EDCON/SPEICEA-07 Dated.05.01.17, was proposed forconversion of said 3 X DC line intothree Single Circuit lines such as i)MTPS-Ranchi ii) MTPS-Ramgarh & ill)Ranchi- Ramgarh. bypassing the GolaS/S. From Ramgarh S.Stn. to Gola ,37km of the line is charged since22.04.2014 and 4 KM/58 KM of Gola-Ranchi portion of the line is alsocharged. However, completion time isbeing revised in the event of situationarisen due to COVID -19.
4 RFD
17Page 2 ofReport generated through NPP 9.05.58 PMSunday 08
7. 8. 9. 10. 13.
Revised/Anticipated
11.
Progress Status of Transmission Target Date
RemarksTotalLocations
(Nos)
Foundationcompleted
(Nos)
TotalLength(cKm)
1.
Stringingcompleted
(CKm)Schedule
5. 6. 2. 3. 4.
SlNo
Name ofTransmission
Lines
Ckts(S/C)
&(D/C)
VoltageLevel(kV)
TowerErected
(Nos)
Tag Names
12.
POWER GRID CORPORATION OF INDIA LIMITED ( PGCIL )
Disconnection of LILO arrangement ofDhauliganga - Bareilly at Pithoragarhand connecting it to Jauljive
D/C 220 50 75 68 56 14 JUN-20 DEC-20 Stage-I forest clearance received on31.10.19. Working permissionreceived on 23.12.19. Civil Aviationclearance for 5 locs. yet to bereceived. Work has also been affecteddue to lockdown of the entire countrybecause of Corona Pandemic. Worksrestarted again.
1 RFD
Jigmeling - Alipurdauar line (Q) (IndiaSide)
D/C 400 324 466 435 420 230 JAN-21 MAR-21 Working permission in forest in Assamreceived in Feb'19. Alternatearrangements made for evacuation ofpower (contigency throughPunatsangchu ATS). Work affecteddue to COVID-19. Work has restartedafter lockdown. However, progress isslow due to corona pandemicsituation. Work in Assam area alsoaffected due to heavy rain. 6 kms inWest Bengal in ROW.
2 RFD
LILO of both ckts of Bawana - Mandolaat Maharanibagh
D/C 400 104 89 79 79 93 DEC-20 MAR-21 Forest proposal under DPTA & FCAsubmitted. Land allocated by DDA forCA. Approval & tree cuttingpermission awaited. Forest clearanceproposal (FCA) processed by Delhiforest deptt. and forwarded toRMOEF, Lucknow, which is clearedby REC on 25.09.20. MoM awaited.
3 RFD
LILO of both ckts. of Chandithala -Kharagpur at Medinipur (PM-JTL-TBCB)
D/C 400 146 199 199 199 148 NOV-20 NOV-20 Physical work of the line completed.However, final connection to theCharged 400kV D/C Chandithala-Kharagpur WBSETCL line shall bedone after availing shutdown andreadiness of the Medinipur substation.
4 RFD
LILO of North Trichur - Cochin line atNorth Trichur HDVC Station (Q)
D/C 400 1 4 4 4 1 SEP-20 DEC-205 RFD
Mohindergarh - Bhiwani line D/C 400 122 181 163 139 20 OCT-20 MAR-21 Executing agency has undergoneNCLT and now contract terminated.Balance work awarded in Nov'19. 17nos. foundation under ROW.
6 RFD
Pugalur HVDC - Arasur line (Q) D/C 400 118 162 162 162 118 JUN-20 SEP-20 Commissioned 09/20.7 RFD
Pugalur HVDC - Pugalur line (Q) D/C 400 100 138 138 138 100 JUN-20 SEP-20 Commissioned 09.20.8 RFD
Raigarh (HVDC stn) - Pugalur (HVDCstn) HVDC Bipole Link
BIPOLE 800 3531 4773 4773 4773 3531 AUG-20 SEP-20 Commissioned 09/20.9 RFD
17Page 3 ofReport generated through NPP 9.05.58 PMSunday 08
7. 8. 9. 10. 13.
Revised/Anticipated
11.
Progress Status of Transmission Target Date
RemarksTotalLocations
(Nos)
Foundationcompleted
(Nos)
TotalLength(cKm)
1.
Stringingcompleted
(CKm)Schedule
5. 6. 2. 3. 4.
SlNo
Name ofTransmission
Lines
Ckts(S/C)
&(D/C)
VoltageLevel(kV)
TowerErected
(Nos)
Tag Names
12.
Ranchi - Medinipur line (PM-JTL-TBCB) D/C 765 538 718 718 718 534 OCT-20 NOV-20 Work affected due to cycloneAMPHAN on 20.05.20. Route diverteddue to non felling of 3 Sarna (Puja)trees in Jharkhand portion of the line.Three new towers placed. Work hasalso been affected due to lockdown ofthe entire country because of CoronaPandemic. Works restarted again afterlockdown. Line work expected to becompleted by Oct'20. However,commissioning matching withreadiness of Medinipur S/S (ant. byNov'20).
10 RFD
Tumkur (Pavagada) PS - Devanahally(KPTCL) line - (Q)
D/C 400 312 428 427 417 273 SEP-20 NOV-20 Progress affected due to ROW issueespecially in Bangalore area andCOVID-19 pandemic.
11 RFD
17Page 4 ofReport generated through NPP 9.05.58 PMSunday 08
7. 8. 9. 10. 13.
Revised/Anticipated
11.
Progress Status of Transmission Target Date
RemarksTotalLocations
(Nos)
Foundationcompleted
(Nos)
TotalLength(cKm)
1.
Stringingcompleted
(CKm)Schedule
5. 6. 2. 3. 4.
SlNo
Name ofTransmission
Lines
Ckts(S/C)
&(D/C)
VoltageLevel(kV)
TowerErected
(Nos)
Tag Names
12.
STATE SECTOR
ASSAM ELECTRICITY GRID CORP. LIMITED ( AEGCL )
Sonabil - Biswanath Chariali S/C 220 40 136 133 62 0 MAR-21 MAR-21 RoW issues at many locations.1 RFD
BIHAR STATE POWER TRANSMISSION COMPANY LIMITED ( BSPTCL )
LILO of both Purnea (PG) - Begusaraiat Khagaria (New)
D/C 220 14 0 0 0 JUL-20 Completed1 RFD
LILO of (Quad) Barh - Patna atBakhtiyarpur (New)
D/C 400 10 61 49 43 JUL-20 AUG-20 Related to BGCL2 RFD
LILO of Sasaram - Sahupuri atKarmnasa (New)
D/C 220 8 5 0 0 0 JUL-20 Completed3 RFD
Muzaffarpur (PG) - Gouraul line D/C 220 20 70 55 55 3 JUL-20 NOA issued on 21.01.2019 and workunder progress.
4 RFD
CHHATTISGARH STATE POWER TRANSMISSION CO. LTD. ( CSPTCL )
Bemetara - Mungeli line 2nd circuit S/C 220 40 0 0 0 33 JUL-20 MAR-20 line charged on dtd 04.03.20201 RFD
Gurur - Kurud (Bangoli) D/C 220 74 118 118 118 72 JAN-21 JAN-21 line charged on dtd 17.02.20202 RFD
LILO of Korba (E) - Siltara at DSPM D/C 220 3 7 6 6 1 JUL-20 Work in progress, railway approval ispending
3 RFD
DELHI TRANSCO LIMITED ( DTL )
IP-Park Street-Electric Lane (Cable) S/C 220 5 0 0 0 DEC-20 Two section of approx. 1 KM lengthlaid.
1 RFD
Shalimarbagh - Sanjay GandhiTransport Nagar
M/C 220 8 21 21 21 8 DEC-20 SEP-20 Commissioned 04/20 (Late Reported).2 RFD
ELECTRICITY DEPARTMENT, GOVT. OF MANIPUR ( ED, Manipur )
Yurembam - Thoubal via Nambol D/C 400 90 137 116 106 40 JUL-201 RFD
GUJARAT ENERGY TRANSMISSION CORP. LIMITED ( GETCO )
Bhatia - Bhogat line (AL-59) D/C 220 26 53 29 25 0 SEP-20 SEP-20 WIP.1 RFD
Hadala - Shapar line (Twin AL-59) D/C 400 124 198 121 102 0 FEB-21 FEB-21 WIP.2 RFD
Halvad - Sadla line with AL-59conductor
D/C 220 76 124 101 101 59 FEB-21 FEB-21 Tender on website and last date is17.12.2018. (Risk & cost for Balancework).
3 RFD
LILO of both ckt. Otha - Sagapara lineat Talaja
D/C 220 21 0 0 0 DEC-20 DEC-204 RFD
LILO of Jetpur - Sardargadh line atShapur s/s
D/C 220 12 0 0 0 SEP-20 SEP-205 RFD
LILO of one Ckt. of Ukai - Achhaliyaline no.3 at Virpor (Package -2)
D/C 220 27 128 0 0 0 DEC-20 DEC-20 LoA issues on 26.10.20186 RFD
LILO of Vallabhipur - Vartej line atMaglana S/s
D/C 220 10 0 0 0 SEP-20 SEP-207 RFD
HARYANA VIDYUT PRASARAN NIGAM LIMITED ( HVPNL )
17Page 5 ofReport generated through NPP 9.05.58 PMSunday 08
7. 8. 9. 10. 13.
Revised/Anticipated
11.
Progress Status of Transmission Target Date
RemarksTotalLocations
(Nos)
Foundationcompleted
(Nos)
TotalLength(cKm)
1.
Stringingcompleted
(CKm)Schedule
5. 6. 2. 3. 4.
SlNo
Name ofTransmission
Lines
Ckts(S/C)
&(D/C)
VoltageLevel(kV)
TowerErected
(Nos)
Tag Names
12.
Bhiwani - Isharwal line D/C 220 100 218 64 58 0 FEB-21 NOV-20 The contract has been terminatedWork is awarded to M/s Skipper ondated 09.07.2019 but allotment/PO isyet to be issued
1 RFD
Deroli Ahir - Narnaul D/C 220 26 54 54 52 0 SEP-20 NOV-20 work awarded to M/s K. RamaChandra Rao Limited.
2 RFD
Dhanonda- Deroli Ahir D/C 220 56 114 83 67 0 DEC-20 OCT-20 work awarded to M/s K. RamaChandra Rao Limited
3 RFD
LILO of Sector-72- Rangla Raipur atRoj-Ka-Meo
D/C 220 7 0 0 0 NOV-20 JUN-21 work awarded to M/s. Skipper Ltd.4 RFD
Panchgaon 400 kV - Panchgaon 220kV
D/C 220 1 0 0 0 0 NOV-20 NOV-20 Re-tendering is in process. Tenderopened on 30.10.18 and bid underevaluation.
5 RFD
Panchkula (PGCIL)- Panchkula Sector32
D/C 220 40 72 53 43 14 JUL-20 NOV-20 Work in progress.6 RFD
PGCIL Bhadson - Salempur D/C 220 13 0 0 0 13 APR-20 JUN-20 Commissioned 07/20.7 RFD
HIMACHAL PRADESH POWER TRANSMISSION CORP. LTD. ( HPPTCL )
Bajoli Holi HEP - Lahal GISS D/C 220 36 59 37 18 0 JUL-20 JUN-20 Work in Progress1 RFD
Dehan - Hamirpur(PG) (GEC-I) D/C 220 110 197 68 16 FEB-21 DEC-20 Delay in FC.2 RFD
JHARKHAND URJA SANCHAR NIGAM LTD. ( JUSNL )
Chaibasa - Gua TL D/C 220 168 278 127 110 0 OCT-20 DEC-20 Working permission awaited.1 RFD
Chatra - PBCMP (Barkagaon) D/C 220 117 185 158 125 20 DEC-20 DEC-202 RFD
Essar (Latehar) - Latehar D/C 400 81 122 121 115 43 DEC-20 DEC-20 Tree cutting permission awaited fromDFO, Latehar.
3 RFD
Latehar (JSUNL) - PTPS D/C 400 220 304 275 260 82 JUL-20 DEC-20 Forest Clearance - Stage-I Clearanceawaited.
4 RFD
LILO of Govindpur - TTPS TL atJainamore
D/C 220 70 92 82 67 24 JUL-20 DEC-20 Stage-I forest clearance awaited.Revised FRA to be issued from DC,Bokaro.
5 RFD
TTPS - Govindpur TL D/C 220 181 300 298 296 152 NOV-20 NOV-20 ROW issue in 2 Nos. Locations inBokaro Dist.
6 RFD
J&K POWER DEVELOPMENT DEPARTMENT ( JKPDD )
LILO of Thein-Hiranagar at Kathua-II(Ghatti)
D/C 220 24 DEC-201 RFD
(PMDP - Kashmir) LILO of Wagoora -Mirbazar line at Lassipora
D/C 220 11 22 13 0 0 SEP-20 NOV-20 Works under progress.2 RFD
(PMDP - Kashmir) New Wanpoh - MirBazar line
D/C 220 10 14 12 0 SEP-20 JAN-21 Works under progress.3 RFD
KARNATAKA POWER TRANSMISSION CORP. LIMITED ( KPTCL )
Devanhalli -(Hardware Park 2nd ckt)and Doddaballapura (2nd ckt)
M/C 220 113 0 0 0 NOV-20 NOV-20 Check survey approved on 05-Jan-2019.
1 RFD
17Page 6 ofReport generated through NPP 9.05.58 PMSunday 08
7. 8. 9. 10. 13.
Revised/Anticipated
11.
Progress Status of Transmission Target Date
RemarksTotalLocations
(Nos)
Foundationcompleted
(Nos)
TotalLength(cKm)
1.
Stringingcompleted
(CKm)Schedule
5. 6. 2. 3. 4.
SlNo
Name ofTransmission
Lines
Ckts(S/C)
&(D/C)
VoltageLevel(kV)
TowerErected
(Nos)
Tag Names
12.
HDVC Kolar - T. Gollahali(Thimmasandra) line
D/C 220 54 162 143 84 13 AUG-20 AUG-20 Work under progress. (Note: As perrevised check survey approved on23.03.2019 from SEE, Tr. (W) circle,the total no of towers is 162.)
2 RFD
Jagalur (Hiremallanahole) -Chitradurga
D/C 220 71 154 82 52 1 SEP-20 SEP-20 ROW ossies at Gonuru, Mutiur, H.M.hole village limits, demanding forhigher compensation. Reqiostopmsin,otted tp DC Chitrafurga to issuethe order for compensation. TB @Chitrafurga Station completed excepttesting and commissioning.
3 RFD
LILO of Somanahalli - Kolar SC line toMylasandra (New Electric City)
S/C 400 1 6 0 0 JUN-20 JUN-20 Check survey approved on 23.07.19.The design documents of 40kV towershas been approved. Foundationdrawings submitted on to CEE, P&Cby agency.
4 RFD
Melasandra (New elctronic city) -Yerandanahalli and concersion ofexisting Peeny - Singarpeta S/C line toM/C line up to Yerandanahalli
M/C 220 19 35 35 6 JUN-20 JUN-20 220kV SC line from Somanahalli-Yerrandanahalli LC is required for aperiod of 90 days to complete line (a)work. During the above shut downperiod, Yerrandanahalli R/s has to befed from Hosur end. Pending with theCEE, Hosur Tamilnadu (issue isdiscussed in OCC)
5 RFD
KERALA STATE ELECTRICITY BOARD ( KSEB )
Brahmapuram - Kaloor line D/C 220 23 16 15 13 4 APR-20 JUN-201 RFD
Kattakkada-Vizhinjam D/C 220 44 0 0 0 APR-202 RFD
LILO of 220kV Kaniampetta -Areakode at Kunnamangalam line
D/C 220 15 0 0 0 JUL-203 RFD
LILO of 220kV Lower Periyar -Madakathara at Chalakundy line
D/C 220 24 0 0 0 APR-204 RFD
LILO of Arekode-Kaniyambetta -Kunnamngalam
D/C 220 15 JUL-205 RFD
Mylatti-Vidyanagar D/C 220 23 0 0 0 DEC-206 RFD
MAHARASHTRA STATE ELEC. TRANSMISSION COMPANY LTD. ( MSETCL )
2nd Ckt. Stringing of Gangapur -Valve at Jamde (GEC-I)
S/C onD/C
220 13 0 0 0 JUN-201 RFD
Koradi-II - Uppalwadi UG and O/Hline D/C 220 15 13 5 0 0 DEC-20 FEB-21 Work of CTT1 at MSPGCL Koradipremises in progress. Koradi S/s to JB- Excavation of cable trench is inprogress. Also Excavation of cabletrench is in progress. for section JB4to JB5, JB4 to JB3 & JB3 to CTT-II.
2 RFD
17Page 7 ofReport generated through NPP 9.05.58 PMSunday 08
7. 8. 9. 10. 13.
Revised/Anticipated
11.
Progress Status of Transmission Target Date
RemarksTotalLocations
(Nos)
Foundationcompleted
(Nos)
TotalLength(cKm)
1.
Stringingcompleted
(CKm)Schedule
5. 6. 2. 3. 4.
SlNo
Name ofTransmission
Lines
Ckts(S/C)
&(D/C)
VoltageLevel(kV)
TowerErected
(Nos)
Tag Names
12.
Kumbhargaon (Nanded) - Kurunda D/C 220 121 224 157 143 2 FEB-21 DEC-20 ROW : ROW Issue at Loc. No.124,125,126. RailwayCrossing:Railway involved inLoc.No.112-113.Proposal submitted toSenior Divisional Elect. Engineer(South Central Railway Nanded
3 RFD
LILO of 400KV Bhusawal - Aurangabadckt-II at Aurangabad (Thaptitanda)
D/C 400 126 273 248 229 124 FEB-21 MAR-21 Work in progress.4 RFD
LILO of Kolshet-Wada and Padghe-Wada line at Kudus S/s
D/C 400 32 46 15 8 0 DEC-20 JUN-21 Huge ROW Forest : 10.345Hec., 11locations,2.95km length, Revisedproposal submitted on 05.08.20.
5 RFD
LILO of one Ckt. of 220kV Kolshet-Wada line and Padghe-Wada line onM/C towers at 400 kV Kudus S/S
D/C 220 31 46 15 8 0 DEC-20 JUN-21 Area involved 10.35 ha (Appr)Revised proposal submitted on05.08.2020.
6 RFD
LILO on 220kV Mhaisal - Jath at 400kVAlkud
D/C 400 45 77 33 0 0 DEC-20 MAR-21 ROW issues. Case submitted for Sec.16.
7 RFD
LILO on both ckts. of Uran-KhargharUlwe Node
D/C 220 18 DEC-208 RFD
LILO on Nalasopara- Boisar line atPalghar
D/C 220 1 3 2 2 0 JUN-20 DEC-20 1) Involvement of Defence observed.Requested to provide an NOC. Effortshave been under progress for takingNOC. 2) Parallel resurvey was carriedout to avoid Defence and requiredchanges will be accommodated inforest proposal which is underprogress.
9 RFD
Vishwind- Bhenda D/C 220 84 DEC-2010 RFD
M.P. POWER TRANSMISSION CORPORATION LIMITED ( MPPTCL )
Ashta - Ujjian (GEC-I) DCDS 400 179 258 198 176 38 FEB-21 FEB-211 RFD
Badod - Nalkheda (Susner ) (GEC) DCDS 220 104 169 169 156 72 DEC-20 DEC-202 RFD
Chhatarpur - Tikamgarh 220 KV Line DCDS 220 90 297 234 178 16 DEC-203 RFD
Indore (PGCIL) - Ujjian (GEC-I) DCDS 400 91 130 125 121 79 NOV-20 NOV-204 RFD
Julwaniya - Kukshi line DCDS 220 126 214 169 111 17 MAR-21 DEC-205 RFD
Kanwan - Dhar line (GEC-I) DCDS 220 63 106 106 106 63 JAN-21 NOV-20 Commissioned 09/20 (Late Reported).6 RFD
LILO of both ckt. Nagda - Neemuch atMandsaur (LILO from loc.No. 211) S/s(GEC-I)
DCDS 220 56 159 159 159 56 DEC-20 JUN-20 Commissioned 07/20.7 RFD
LILO of both ckt of Nagda - Neemuch220 KV line at Mandsore(Sitamau)400 kV S/s (Ckt II)
DCDS 220 47 0 0 0 Commissioned 08/208 RFD
LILO of both ckts. Nagda - Ujjain atUjjain
DCDS 220 40 38 38 38 34 APR-20 DEC-209 RFD
17Page 8 ofReport generated through NPP 9.05.58 PMSunday 08
7. 8. 9. 10. 13.
Revised/Anticipated
11.
Progress Status of Transmission Target Date
RemarksTotalLocations
(Nos)
Foundationcompleted
(Nos)
TotalLength(cKm)
1.
Stringingcompleted
(CKm)Schedule
5. 6. 2. 3. 4.
SlNo
Name ofTransmission
Lines
Ckts(S/C)
&(D/C)
VoltageLevel(kV)
TowerErected
(Nos)
Tag Names
12.
LILO of one ckt of Khandwa (PGCIL) -Rajgarh (PGCIL) at Chhegaon
DCDS 400 20 8 8 8 1 DEC-2010 RFD
Mandsaur (Sitamau) - Marut ShaktiPool (GEC-I)
DCDS 220 93 147 147 147 93 OCT-20 DEC-20 Commissioned 08/2011 RFD
Nagda - Mandsaur (GEC-I) DCDS 400 137 197 197 197 131 MAR-21 MAR-2112 RFD
Nagda - Ujjain line (GEC-I) D/C 400 53 152 152 152 107 SEP-20 DEC-2013 RFD
Rewa UMSP- Sidhi line DCDS 220 100 199 95 74 FEB-2114 RFD
Shujalpur - Narsinghgarh Line DCDS 220 51 170 170 170 51 JAN-21 SEP-20 Commissioned 04/20 (Late Reported).15 RFD
Ujjain - Nalkheda (GEC) DCDS 220 160 252 206 149 50 FEB-21 JAN-2116 RFD
ORISSA POWER TRANSMISSION CORPORATION LTD. ( OPTCL )
Bolangir - Kesinga line D/C 220 170 327 316 302 13 JAN-21 MAR-21 Delayed due to forest clearance issue.The total line length in ckm may becorrected to 179.78 in place of 170ckm. The portion from Bolangir toBolangir PG charged on 30.07.20.The ckm is 2.734 ckm
1 RFD
LILO of one ckt of Rengali - Tarkera atDeogarh
S/C 220 24 JUL-20 My be deleted as the project is yet tobe awarded
2 RFD
Pandiabili PGCIL - Pratapsasan line D/C 220 58 114 99 95 44 SEP-20 MAR-21 Total line length may be revised to62.838 ckms
3 RFD
POWER TRANSMISSION CORP. OF UTTARAKHAND LTD. ( PTCUL )
LILO of Dhauliganga - Pithoragarh(PGCIL) line
D/C 220 11 0 0 0 MAY-20 MAY-20 Work is under progress. PhysicalProgress is 36%. Excavation done for6 nos. tower locations out of 39 towerlocations.
1 RFD
LILO of Kashipur - Pantnagar line atJaffarpur
D/C 220 8 17 15 MAY-20 MAR-20 Physical Progress Is 40 % , Contractof M/s Vijay Rai & Company, Biharhas been terminated by SE(C&P) videits office letter no. 645 date31.08.2019 due to non performingover project.
2 RFD
LILO of Lakhwar- Dehradun at Vyasi D/C 220 71 110 56 52 0 FEB-21 JUN-20 Foundation Completed : 56 Nos.Tower erection : 52 Nos. Stringing:0.000 Kms
3 RFD
PUNJAB STATE TRANSMISSION CORPORATION LIMITED ( PSTCL )
Gaunsgarh - Ladhowal D/C 220 34 0 0 0 DEC-201 RFD
LILO of 2nd Ckt. of PGCIL Jalandhar -Kotla Jangan (nakodar) line atKartarpur
D/C 220 1 4 4 4 1 JUN-20 JUN-20 Commissioned 07/20.2 RFD
LILO of Himmatpura - jagraon atAjitwal
D/C 220 3 10 7 3 0 DEC-20 DEC-20 Work is held up due to right of wayproblems at TL No.4, 5 and 6.
3 RFD
17Page 9 ofReport generated through NPP 9.05.58 PMSunday 08
7. 8. 9. 10. 13.
Revised/Anticipated
11.
Progress Status of Transmission Target Date
RemarksTotalLocations
(Nos)
Foundationcompleted
(Nos)
TotalLength(cKm)
1.
Stringingcompleted
(CKm)Schedule
5. 6. 2. 3. 4.
SlNo
Name ofTransmission
Lines
Ckts(S/C)
&(D/C)
VoltageLevel(kV)
TowerErected
(Nos)
Tag Names
12.
LILO of Jadla - Jamsher at 220 KV S/SBanga
D/C 220 11 JUN-204 RFD
Makhu - Algaon D/C 220 101 162 161 159 96 JUL-19 JUN-20 W.O issued to Mahesh Kohli for PileFoundation & work in progress.
5 RFD
Malout - Abohar S/C onD/C
220 30 102 101 95 20 DEC-20 DEC-20 Work help up due to non availability oflabour
6 RFD
RAJASTHAN VIDYUT PRASARAN NIGAM LIMITED ( RVPNL )
Akal- Jaisalmer-2 line (GEC-I) D/C 220 112 195 195 193 88 NOV-20 NOV-20 NOA issued in favor of M/s Skipper ondated 01.06.2018. Forest involved : InPrinciple approval issued on 23.12.19.DN deposited by RVPN on11.05.2020 . PTW awaited.
1 RFD
Gajner - Chhatargarh line (GEC-I) D/C 220 167 298 295 293 151 JAN-21 DEC-20 NOA issued on dated 05.06.18 infavor of M/s Man structural. Courtcase at 3 nos. Loc.. Hearing on23.11.20.
2 RFD
GSS Basni (Jodhpur) - GSS NPH (U/C)Jodhpur
D/C 220 3 18 18 18 3 JUN-20 DEC-20 W/O awarded to M/s Transrail on26.12.17. Stringing completed cablejoint termination pending.
3 RFD
LILO of Jhalawar - Chhabra line at 220KV GSS Aklera
D/C 220 98 98 MAR-21 NOV-20 Commissioned 10/20.4 RFD
LILO of one circuit of Akal - Jodhpur(new) line at Jaisalmer-2 (GEC-I)
D/C 400 14 21 21 21 14 JUN-20 NOV-20 Commissioned 10/20.5 RFD
LILO of one Ckt of existing STPS -Ratangarh line at 220kV GSSRawatsar
D/C 220 85 145 145 145 85 OCT-20 JUL-20 Commissioned 08/206 RFD
Ramgarh -Bhadla D/C 400 320 446 446 446 320 OCT-20 OCT-20 W/O awarded to M/S SEW Hydrabad.Anti theft charged.Inspector fees forcharging has been deposited on29.10.20 & charging permission isawaited.
7 RFD
TAMILNADU TRANSMISSION CORPORATION LTD. ( TANTRANSCO )
Ariyalur - Thiruvalam PGCIL D/C 765 347 500 500 500 347 DEC-20 MAR-21 All works completed. Will beenergised on commissioning ofAriyalur 765KV ss
1 RFD
Basin Bridge - TNEB HQ (UG Cable) S/C 230 7 0 0 0 0 JUN-20 DEC-20 Work awarded to M/s.Energy PowerCables.Laying 8/15 completed. Joints15/42 completed. Road cut permissionawaited for 4 sections. Paymentmade.
2 RFD
LILO in the existing 230 kV Pasumalai- Alagarkoil at the proposedSamayanallur 230 kV SS
D/C 230 9 11 11 11 9 JUN-20 NOV-20 Commissioned 10/20.3 RFD
17Page 10 ofReport generated through NPP 9.05.58 PMSunday 08
7. 8. 9. 10. 13.
Revised/Anticipated
11.
Progress Status of Transmission Target Date
RemarksTotalLocations
(Nos)
Foundationcompleted
(Nos)
TotalLength(cKm)
1.
Stringingcompleted
(CKm)Schedule
5. 6. 2. 3. 4.
SlNo
Name ofTransmission
Lines
Ckts(S/C)
&(D/C)
VoltageLevel(kV)
TowerErected
(Nos)
Tag Names
12.
LILO of one ckt of Thappagundu -Anaikadavu 400 line at Udumalpet(PGCIL) S/S
D/C 400 40 60 60 60 20 DEC-20 DEC-20 Stringing work pending as landowners are demanding compensationamount. Enter upon permissionobtained.Court case disposed infavour of TANTRANSCO.
4 RFD
LILO of Pugalur - Kalivanthapattu lineat Ariyalur
2xD/C 400 15 15 15 15 14 SEP-20 Work completed.5 RFD
North Chennai PS - Ariyalur D/C 765 542 799 799 797 516 NOV-20 DEC-20 Work under progress.6 RFD
Palavady - Thirupathur line D/C 230 75 299 289 248 51 JUN-20 DEC-20 Work under progress.7 RFD
TRANSMISSION CORPORATION OF ANDHRA PRADESH LIMITED ( APTRANSCO )
Hindupur (400) - Pampanur Tanda(220)(GEC-I)
D/C 220 70 239 98 41 DEC-20 DEC-20 25% Work Completed.1 RFD
Maradam (from 400kV Maradam) -Pydibhimavaram line
D/C 220 46 46 169 168 16 JUL-20 JUL-20 Tower foundations are completed,erection and stringing are underprogress.
2 RFD
Mylavaram-Jammalamdugu QMDCLine
D/C 400 21 0 0 0 JUL-20 JUL-20 The scheme is modified by laying220kV lines from pooling stations atMylavaram Ultra Mega Solar Park(1000MW ) at kadapa dist. of AP tothe existing 400kVJammamalamadugu in a Costeffective manner instead ofconstructing separate 400kVSubstation at Mylavaram.
3 RFD
Transmission Corporation of Telangana Limited ( TSTRANSCO )
Dichpally 400kV - Banswada 220kV D/C 220 168 OCT-201 RFD
Dindi -Existing Kondamallepally line D/C 220 70 JUL-202 RFD
Kethiredypally - AP-41 line (Twin HTLSQuad Conventional Towers)
D/C 400 53 78 75 73 0 JUN-203 RFD
Narsapur- Proposed Bowrampet line D/C 220 136 MAR-214 RFD
Nirmal - Indravelly (Utnoor) proposedline at Adilabad District
D/C 220 204 JAN-215 RFD
U.P. POWER TRANSMISSION CORPORATION LTD. ( UPPTCL )
Badhaikalan (Muzaffarnagar) - Shamliline
D/C 220 66 113 56 35 0 NOV-20 Work in progress.1 RFD
Greater Noida(765) - Integratedtownship Gr. Noida line
S/C 220 36 134 115 94 3 JUN-20 JAN-21 Work in progress.2 RFD
Jeheta (400)- Hardoi Rd (220)Interconnector
D/C 220 19 39 19 0 0 NOV-20 Work in progress. RoW & Revision ofprofile is in progress for Multicurcuit.
3 RFD
LILO of 220 kV C.B. Ganj (220)-Budaun (220) line
D/C 220 2 4 4 0 0 NOV-20 Work in progress.4 RFD
LILO of 220 kV Pura Chandausi (220) -Budaun (220) line at Budaun
D/C 220 36 57 57 47 0 NOV-20 Work in progress.5 RFD
17Page 11 ofReport generated through NPP 9.05.58 PMSunday 08
7. 8. 9. 10. 13.
Revised/Anticipated
11.
Progress Status of Transmission Target Date
RemarksTotalLocations
(Nos)
Foundationcompleted
(Nos)
TotalLength(cKm)
1.
Stringingcompleted
(CKm)Schedule
5. 6. 2. 3. 4.
SlNo
Name ofTransmission
Lines
Ckts(S/C)
&(D/C)
VoltageLevel(kV)
TowerErected
(Nos)
Tag Names
12.
LILO of Baraut (220)- Shamli atNirpura line
D/C 220 30 56 45 16 0 DEC-20 Work in progress. PTCC RailwayCrossing Power line Crossing & NHAIcase submitted.
6 RFD
LILO of ckt-II of Kursi Rd PG- Unnaoline at Hardoi Rd(Jehata)
D/C 400 25 45 45 44 25 NOV-20 NOV-20 1) Lines are Complete in all respectexcept erection of one tower &stringing for dead end tower to gantryas gantry at 400 kV S/s .Jehata notready. 2) Both lines have beencharged on 132kV as an anti-theftmeasure on dated 26.02.20.
7 RFD
LILO of ckt-I of 400 kV DC Kursi RdPG- Unnao line at Hardoi Rd(Jehata)
D/C 400 34 57 57 57 33 NOV-20 NOV-20 1) Lines are Complete in all respectexcept erection of one tower &stringing for dead end tower to gantryas gantry at 400 kV S/s .Jehata notready. 2) Both lines have beencharged on 132kV as an anti-theftmeasure on dated 26.02.20.
8 RFD
LILO of Ibrahim Patti (PGCIL) -Kasaramau (Mau) at Rasra
D/C 400 74 115 114 112 68 DEC-20 Work in progress.9 RFD
LILO of Muzaffarnagar - Nanauta lineat Badhaikalan
D/C 220 8 21 21 21 10 SEP-20 NOV-20 Work completed.10 RFD
LILO of One ckt 220 kV Sohawal (PG) -New Tanda line at Ayodhya (220)
D/C 220 27 56 43 11 0 NOV-20 NOV-20 PTCC case applied on 30.11.2020.11 RFD
LILO of One ckt Laitpur TPS -Dunaraline at Babina
D/C 220 15 25 25 25 15 JUN-20 Line energised on 23.08.2019.12 RFD
LILO of one Ckt. of Chhata (Mathura) -Manth (400) at Vrindawan
D/C 220 46 74 74 74 44 SEP-20 Line energised on 21.08.202013 RFD
LILO of Rasra (220)- Gazipur at Rasra D/C 220 26 49 49 42 2 DEC-20 Foundations work completed, Erectionwork in progress.
14 RFD
Rasra (400) - Bhadaura (Gazipur) line D/C 220 108 184 108 0 0 MAR-21 Foundation work in progress.15 RFD
Shahjahanpur PG (400)- Azizpur line D/C 220 49 95 95 95 48 DEC-20 Work in progress.16 RFD
WEST BENGAL STATE ELECTRICITY TRANSMISSION CO. LIMITED ( WBSETCL )
Subashgram (PG) - Baruipur D/C 220 64 126 125 123 49 NOV-20 NOV-20 Work under progress at slow rate dueto acute ROW problem.
1 RFD
17Page 12 ofReport generated through NPP 9.05.58 PMSunday 08
7. 8. 9. 10. 13.
Revised/Anticipated
11.
Progress Status of Transmission Target Date
RemarksTotalLocations
(Nos)
Foundationcompleted
(Nos)
TotalLength(cKm)
1.
Stringingcompleted
(CKm)Schedule
5. 6. 2. 3. 4.
SlNo
Name ofTransmission
Lines
Ckts(S/C)
&(D/C)
VoltageLevel(kV)
TowerErected
(Nos)
Tag Names
12.
PRIVATE SECTOR
ADANI POWER LTD. ( APL )
Agra (UP)-Greater Noida (WUPPTCL)(GTL-TBCB)
S/C 765 160 411 405 397 112 SEP-20 NOV-20 a) Covid-19: Project progressincluding Statutory approvals affecteddue to COVID-19. b) RoW: 4Locations under Jewar area havingsevere ROW, Severe RoW in AP89(due to ordinance factory) & AP90
1 RFD
Fatehgarh PS/S - Bhadla (PG) (initiallyto be operated at 400 kV) (F-BTL-TBCB)
D/C 765 292 405 400 370 231 JAN-21 DEC-20 a) Covid-19: Project progressincluding Statutory approvals affecteddue to COVID-19. b) Severe RoW. c)High Court Status quo Order:Substation Work affected due toHon'ble High Court Rajasthan Statusquo order dated 08.09.2020.
2 RFD
Ghatampur TPS-Agra (UP) (GTL-TBCB) S/C 765 229 579 575 534 165 SEP-20 NOV-20 a) Covid-19: Project progressincluding Statutory approvals affecteddue to COVID-19. b) RoW c) Workingpermission: WP in Forest Areaswithheld for Lease issue. Only 4 nos.Foundation in Forest areas balance.D) Lease issue in Reserve Forest:DFO Agra & Nodal officer have askedLease premium & Annual Lease Rentfor Reserve Forest.This practice is notprevalent in any other State.
3 RFD
LILO of both ckt. of Ranchi - Maithon-RB line at Dhanbad (NKTL-TBCB)
D/C 400 4 10 0 0 0 OCT-20 MAR-21 a) Covid-19: Project progress affecteddue to COVID-19.
4 RFD
LlLO of C.B.Ganj - Badaun at Badaun(OBTL-TBCB)
S/C 220 2 6 3 0 0 NOV-20 NOV-20 a) Covid-19: Project progressincluding Statutory proposals affecteddue to COVID-19.
5 RFD
LlLO of Chandausi - Badaun atBadaun (OBTL-TBCB)
S/C 220 37 58 57 46 0 NOV-20 MAR-21 a) Covid-19: Project progressincluding Statutory proposals affecteddue to COVID-19.
6 RFD
17Page 13 ofReport generated through NPP 9.05.58 PMSunday 08
7. 8. 9. 10. 13.
Revised/Anticipated
11.
Progress Status of Transmission Target Date
RemarksTotalLocations
(Nos)
Foundationcompleted
(Nos)
TotalLength(cKm)
1.
Stringingcompleted
(CKm)Schedule
5. 6. 2. 3. 4.
SlNo
Name ofTransmission
Lines
Ckts(S/C)
&(D/C)
VoltageLevel(kV)
TowerErected
(Nos)
Tag Names
12.
North Karanpura - Chandwa(Jharkhand) NKSTPP line (NKTL -TBCB)
M/C 400 52 42 22 20 0 JUN-20 JUL-21 a) Covid-19: Project progressincluding Statutory proposals affecteddue to COVID-19. b) ForestClearance: Delay in receipt of Forestclearance, around 450 days (Since01-07-19) passed against 200 daysand delayed for reasons beyondcontrol of NKTL. Proposal is pendingat Nodal Officer for recommendationto State Govt. In meeting called byCEA on 16.03.20, NKTL had statedthat NKTL will be able to complete theNK-C line in 9 months from the date offorest clearance. Anticipating theForest Clearance in Oct-20,Completion expected by Jul-20. CEA /MOP support is requested. c) GM-JJLand NOC from Latehar DC office andFRA certificate from both Latehar andChatra DC offices are still awaited. d)Approval from DVC is on hold asNTPC has asked DVC to shift theirline for NTPC's coal conveyor belt ofexternal CHP. DVC's Line Diversionproposal technically cleared andbased on joint site inspectionconducted on 09.07.20. demandcharges paid
7 RFD
17Page 14 ofReport generated through NPP 9.05.58 PMSunday 08
7. 8. 9. 10. 13.
Revised/Anticipated
11.
Progress Status of Transmission Target Date
RemarksTotalLocations
(Nos)
Foundationcompleted
(Nos)
TotalLength(cKm)
1.
Stringingcompleted
(CKm)Schedule
5. 6. 2. 3. 4.
SlNo
Name ofTransmission
Lines
Ckts(S/C)
&(D/C)
VoltageLevel(kV)
TowerErected
(Nos)
Tag Names
12.
North Karanpura - Chandwa(Jharkhand) PS line (NKTL -TBCB)
D/C 400 50 73 52 44 0 JUN-20 JUL-21 a) Covid-19: Project progressincluding Statutory proposals affecteddue to COVID-19. b) ForestClearance: Delay in receipt of Forestclearance, around 450 days (Since01-07-19) passed against 200 daysand delayed for reasons beyondcontrol of NKTL. Proposal is pendingat Nodal Officer for recommendationto State Govt. In meeting called byCEA on 16.03.20, NKTL had statedthat NKTL will be able to complete theNK-C line in 9 months from the date offorest clearance. Anticipating theForest Clearance in Oct-20,Completion expected by Jul-20. CEA /MOP support is requested. c) GM-JJLand NOC & FRA Certificate from DCoffice: GM-JJ Land NOC from LateharDC office and FRA certificate fromboth Latehar and Chatra DC officesare still awaited.
8 RFD
Essel Infraprojects Ltd. ( ESSEL )
Babai (RRVPNL)- Bhiwani (PG) (NRSS-XXXVITL-TBCB)
D/C 400 221 299 265 215 1 JUN-20 Details of Tr. Line Falling underForest: 3.37 Km ,Forest area: 12.90Ha (2.80 Kms) of Rajsthan + 3.46 Ha(0.57 Kms) of Haryana. Forestproposals submitted on : 15.05.2017for Haryana and on 11.08.2017 forRajasthan. Stage I approval fromHaryana Forest Deptt. received on27.03.2018 and Stage I approval fromRajasthan Forest Deptt. received on06.07.2018. Wildlife Clearance :Wildlife area(ha) : 7.452 Ha (2.80Kms) Khetri Bansyal ConversionReserve Wildlife proposals submittedon : 16.02.2018 and at present,Proposal recommended by NBWL andcurrently recommendations forwardedto State Govt. (Rajasthan). SevereRoW issues: 52/1, 52/3, 53/0, 54/0,54/1, 54/2 & 54A/0 of Tehsil Dadri andloc. No. 17/0 & 18/0 of Tehsil Khetri.
1 RFD
STERLITE GRID LTD. ( SGL )
17Page 15 ofReport generated through NPP 9.05.58 PMSunday 08
7. 8. 9. 10. 13.
Revised/Anticipated
11.
Progress Status of Transmission Target Date
RemarksTotalLocations
(Nos)
Foundationcompleted
(Nos)
TotalLength(cKm)
1.
Stringingcompleted
(CKm)Schedule
5. 6. 2. 3. 4.
SlNo
Name ofTransmission
Lines
Ckts(S/C)
&(D/C)
VoltageLevel(kV)
TowerErected
(Nos)
Tag Names
12.
Khandwa Pool - Dhule (KTL - TBCB) D/C 765 379 492 476 474 350 MAY-20 MAR-21 1. Objection has been raised by D.C,Dhule for traversing of line throughsubmergence area of proposedJamphal Dam in Maharastra anddiversion of line is requested. Work isstopped now and this force majeureevent has been intimated to theconcerned LTTCs. 2. In the meetingheld in CEA dated 29-07-2019, it hasbeen finaised that KTL has to re-routethe line so as to divert the Dam areaand the construction work of KD linehas to be completed by May20 subjectto the timely grant of Forest Clearanceand Sec-164 approval 3. Forestclearance proposal for diverted routeis pending with Government ofMaharashtra from last 7 months 4.Delay due to occurrence of ForceMajeure (FM) event i.e. outbreak ofCOVID-19 and this FM event hasbeen intimated to all LTTCs. 5. NOCfrom Irrigation department, Dhule isawaited. 6. Approval for Sec-164(diverted route) from CEA is awaited
1 RFD
Silchar (PG) - Misa (PG) (Q) line (NER-II TL-TBCB)
D/C 400 357 487 483 434 238 JUL-20 DEC-20 1. PGCIL bays at Silchar and Misaend has to be expedite so as to matchwith the transmission line schedule 2.The proposal for PLCC Carrierfrequency has been submitted toMinistry of Commnication (WPC Wing)on 08-07-2019 and the approval is stillawaited 3. RoW issue at Location No.AP 29 in village - Barjatrapur, Teshil Katigorah, District Cachar as the landowners are asking for unduecompensation. 4. Delay due tooccurrence of Force Majeure (FM)event i.e. outbreak of COVID-19 andthis FM event has been intimated toall LTTCs
2 RFD
17Page 16 ofReport generated through NPP 9.05.58 PMSunday 08
7. 8. 9. 10. 13.
Revised/Anticipated
11.
Progress Status of Transmission Target Date
RemarksTotalLocations
(Nos)
Foundationcompleted
(Nos)
TotalLength(cKm)
1.
Stringingcompleted
(CKm)Schedule
5. 6. 2. 3. 4.
SlNo
Name ofTransmission
Lines
Ckts(S/C)
&(D/C)
VoltageLevel(kV)
TowerErected
(Nos)
Tag Names
12.
Surajmaninagar - P. K. Bari line (NER-II TL-TBCB)
D/C 400 155 209 208 202 118 APR-20 OCT-20 1. The proposal for PLCC Carrierfrequency has been submitted toMinistry of Communication (WPCWing) on 08-07-2019 and theapproval is still awaited 2. Delay dueto occurrence of Force Majeure (FM)event i.e. outbreak of COVID-19 andthis FM event has been intimated toall LTTCs
3 RFD
17Page 17 ofReport generated through NPP 9.05.58 PMSunday 08
REPORT INDICATING STATUS OF CONSTRUCTION OF SUB STATIONS (220 kV & ABOVE) IN RFD PROGRAMMEDURING 2020-21
As on 31-OCT-2020
6.3.
Materials /Equipments
erected(%)
1. 7. 8.
LandAcquired
(%)
Cummulative progress till date
Materials /Equipments
Received(%)
10.
Commissioning
2.
Remarks
11.
VoltageRatio
(kV/kV)
Name ofSub Stations
Capacity(No.xMV
A)
Civilworks
completed(%)
SlNo
9. 14.4. 12.
CapacityTested/
Commissioned
(MVA)
Revised/AnticipatedOriginal
5.
Date ofAward Tag Type
13.
CENTRAL SECTOR
DAMODAR VALLEY CORPORATION ( DVC )
Order for execution placed on06.11.18. Supply of materials,Engineering activities, civilwork , Electrical Erection workunder process.However orderfor supply of Transformerplaced on 04.06.19 andexpected to be commissionedby August'21. However,completion time is beingrevised in the event of situationarisen due to COVID -19.
AUG-2130 0100 AUG-202x160Burdwan GIS along withassociated line bays at Parulia S/s
220/132 201 RFD
The Transformer has beensuccessfully commissioned on19.12.2019 and put on load on21.12.2019. For 2nd Autotransformer order placed on04.06.19 and expected to becommissioned by August' 21.However, completion time isbeing revised in the event ofsituation arisen due to COVID-19.
AUG-2140 40100 AUG-202x160Dhanbad (2 Auto-Xmer) 220/132 802 RFD
400KV infrastructure is readyand its 220KV infrastructure isunder construction. ICTcharged from 400KV side on23.05.18. Order for balancework placed on 13.02.19 andexpected to be completed by31st Jan'21. However,completion time is beingrevised in the event of situationarisen due to COVID -19.
JAN-2190 60100 APR-201x315DSTPS ICT-II S/s 400/220 1003 RFD
POWER GRID CORPORATION OF INDIA LIMITED ( PGCIL )
Award placed in Oct'19. Civilwork & erection started.
DEC-2020 10100 JAN-211000Bhadla S/S 400/220 451 RFD
Page 1 of 12Report generated through NPP 08/11/2020 21.04.15
6.3.
Materials /Equipments
erected(%)
1. 7. 8.
LandAcquired
(%)
Cummulative progress till date
Materials /Equipments
Received(%)
10.
Commissioning
2.
Remarks
11.
VoltageRatio
(kV/kV)
Name ofSub Stations
Capacity(No.xMV
A)
Civilworks
completed(%)
SlNo
9. 14.4. 12.
CapacityTested/
Commissioned
(MVA)
Revised/AnticipatedOriginal
5.
Date ofAward Tag Type
13.
2 nos. 765 kV ICT banks areexpected to commission byMar'21 progressively. Workhas also been affected due tolockdown of the entire countrybecause of Corona Pandemic.Heavy rain fall in Bhuj area ofGujarat in the month ofAug/Sep'20 hampered theworks at site and also damagesome imported component ofGIS Material. Assessment ofdamages is in progress.
MAR-2180 60100 OCT-201x1500Bhuj S/S 765/400 902 RFD
2 nos. 500MVA 400/220 kVICT commissioned in Oct'19.3rd 400 kV ICT alsocommisisoned in Sep'20. Restof the ICTs (3 nos. 400 kV ICTare expected to commission byMar'21 progressively. Workhas also been affected due tolockdown of the entire countrybecause of Corona Pandemic.Heavy rain fall in Bhuj area ofGujarat in the month ofAug/Sep'20 hampered theworks at site and also damagesome imported component ofGIS Material. Assessment ofdamages is in progress.
MAR-2180 60100 MAR-211x1500Bhuj Substaion 400/220 903 RFD
220 KV GIS charged inMarch'20. 400 kV GIS is readybut charging will be donematching with LILO line gettingdelayed due to forestclearance issue in Delhi.
MAR-2198 95100 JUN-202000Dwarka -I (GIS) S/S 400/220 994 RFD
Commissioned 07/20.AUG-20100 100100 MAY-20500Extan. at Maithon 400/220 1005 RFD
Award placed in Mar'17. Workhas been affected due tolockdown of the entire countrybecause of Corona Pandemic.Now, work has been resumedwith limited manpower.
DEC-2080 60100 JUN-202x315Extn at Jeypore s/s 400/220 806 RFD
Commissioned 07/20.JUN-20100 100100 MAY-201x1500Extn at Meerut substation 765/400 1007 RFD
Page 2 of 12Report generated through NPP 08/11/2020 21.04.15
6.3.
Materials /Equipments
erected(%)
1. 7. 8.
LandAcquired
(%)
Cummulative progress till date
Materials /Equipments
Received(%)
10.
Commissioning
2.
Remarks
11.
VoltageRatio
(kV/kV)
Name ofSub Stations
Capacity(No.xMV
A)
Civilworks
completed(%)
SlNo
9. 14.4. 12.
CapacityTested/
Commissioned
(MVA)
Revised/AnticipatedOriginal
5.
Date ofAward Tag Type
13.
Award placed in Jun'17. Workhas been affected due tolockdown of the entire countrybecause of Corona Pandemic.Now, work has been resumedwith limited manpower.
DEC-20100 90100 MAY-201x315Extn at New Siliguri s/s (3rd ICT) 400/220 978 RFD
Award placed in Aug'19. Engg.& civil work under progress.Work has also been affecteddue to lockdown of the entirecountry because of CoronaPandemic. Now, work hasbeen resumed & work is underprogress.
DEC-2035 20100 JAN-21500Fatehpur S/S 400/220 459 RFD
Supply of Transformer &Reactor was affected due topoor road conditions. Recently,road widening/ strengtheningwork has been completed byNHAI. Accordingly,transportation of reactorscompleted & of transformers isunder progress. Work has alsobeen affected due to lockdownof the entire country becauseof Corona Pandemic. Now,work has been resumed withlimited manpower.
DEC-2090 72100 JUL-202x315Jauljivi (GIS) s/s 400/220 8910 RFD
Award placed in Sep'17. Workhas been affected due tolockdown of the entire countrybecause of Corona Pandemic.Now, work has been resumedwith limited manpower. Workalso affected due to cycloneAMPHAN on 20.05.20.Commissioning matching withassociated TBCB line,expected completion byDec'20.
DEC-2090 19100 FEB-211x1500Jeerat (New) S/s (PM-JTL -TBCB) 765/400 6311 RFD
Page 3 of 12Report generated through NPP 08/11/2020 21.04.15
6.3.
Materials /Equipments
erected(%)
1. 7. 8.
LandAcquired
(%)
Cummulative progress till date
Materials /Equipments
Received(%)
10.
Commissioning
2.
Remarks
11.
VoltageRatio
(kV/kV)
Name ofSub Stations
Capacity(No.xMV
A)
Civilworks
completed(%)
SlNo
9. 14.4. 12.
CapacityTested/
Commissioned
(MVA)
Revised/AnticipatedOriginal
5.
Date ofAward Tag Type
13.
Work was stopped fromNov'19 - Dec'19 due toagitation by local tribals.Restarted slowly from10.12.19. Work has beenaffected due to lockdown ofthe entire country because ofCorona Pandemic. Now, workhas been resumed with limitedmanpower. Work also affecteddue to cyclone AMPHAN on20.05.20. Commissioningprogressively by Dec'20,matching with associated line.
DEC-2092 74100 JUL-202x1500Medinipur S/s (PM-JTL -TBCB) 765/400 8812 RFD
Work progress affected due tolockdown of the entire countrydue to Corona Pandemic.
OCT-2048 35100 MAR-212x500New Mariani S/S 400/220 6813 RFD
Progress affected due toCOVID-19 pandemic.
FEB-2193 79100 SEP-202x315North Trichur Substation 400/220 8014 RFD
Progress affected due toCOVID-19 pandemic. Pole-Icommissioned in Sep'20.
FEB-2193 88100 AUG-206000Raigarh and Pugalur HVDC Station 800 9615 RFD
Commissioned 09/20.SEP-20100 1001001x1500Raigarh and Pugalur Station with6000 MW HVDC Terminal (Pole-I)
800 10016 RFD
Award placed in Mar'17. Workhas been affected due tolockdown of the entire countrybecause of Corona Pandemic.Now, work has been resumedwith limited manpower.
NOV-2090 60100 JUN-20370Repl of 400/220kV Malda S/s(3x315-2x500)
400/220 8017 RFD
Award placed in Oct'19. Civilwork started.
DEC-2010 0100 JAN-21500Saharanpur S/S 400/220 3018 RFD
STATE SECTOR
BIHAR STATE POWER TRANSMISSION COMPANY LIMITED ( BSPTCL )
M/s BGCL0 00 AUG-20480Dumraon (GIS) s/s 220/132 01 RFD
M/s BGCL0 00 AUG-20420Mokama S/S 220/132 02 RFD
CHHATTISGARH STATE POWER TRANSMISSION CO. LTD. ( CSPTCL )
Work completed .S/s & 1 No.315 MVA ICT charged on dtd.31.01.2020
JUL-20100 100100 MAY-202x315Kurud (Dhamtari) S/S 400/220 1001 RFD
DELHI TRANSCO LIMITED ( DTL )
JUL-200 00 JUL-201x100Patparganj (Addl.) 220/33 01 RFD
Page 4 of 12Report generated through NPP 08/11/2020 21.04.15
6.3.
Materials /Equipments
erected(%)
1. 7. 8.
LandAcquired
(%)
Cummulative progress till date
Materials /Equipments
Received(%)
10.
Commissioning
2.
Remarks
11.
VoltageRatio
(kV/kV)
Name ofSub Stations
Capacity(No.xMV
A)
Civilworks
completed(%)
SlNo
9. 14.4. 12.
CapacityTested/
Commissioned
(MVA)
Revised/AnticipatedOriginal
5.
Date ofAward Tag Type
13.
JUL-2090 90100 JUL-202x160Sanjay Gandhi Transport Nagar(SGTN) GIS
220/66 902 RFD
ELECTRICITY DEPARTMENT, GOVT. OF MANIPUR ( ED, Manipur )
Completed and equipmenttesting in progress
0 00 MAY-201x315Thoubal S/S 400/132 01 RFD
GUJARAT ENERGY TRANSMISSION CORP. LIMITED ( GETCO )
NIT done on 23.10.17; PriceBid Opened; Under approval
JUL-200 0100 JUL-20320Babara (Dist. Amreli) S/S 220/66 01 RFD
Initial Stage.JUL-200 0100 JUL-20500Bhachunda GIS (Dist. Kutch) 400/220 02 RFD
WIPJUL-200 0100 JUL-201x160Kalawad 220/66 03 RFD
HARYANA VIDYUT PRASARAN NIGAM LIMITED ( HVPNL )
Work awarded to M/s HPL JVSalasar. Work under Process.
OCT-2083 77100 MAY-202x160Bakana S/s 220/66 911 RFD
Work Awarded to M/s TBEAEnergy India Limited.Contouring is in progress.
MAR-2120 16100 MAY-202x160Faridabad Sector-58 GIS 220/66 692 RFD
work awarded to M/s TBEAEnergy India Limited, NH-8,Village MiyagamKarjan,Vadodara, Gujrat
MAR-2123 14100 JUN-202x100Faridabad Sector-78 GIS 220/33 643 RFD
Contract has been awarded toM/s Skippers Seil Ltd.
MAY-2196 20100 MAY-202x100Gurgaon Sector-69 GIS 220/33 634 RFD
Work awarded to M/SKalpataru.
MAR-215 4100 NOV-202x100Gurgoan Sector-107 GIS 220/33 355 RFD
The work has been awarded toM/s IKE Electric Pvt. Ltd.Maharashtra JV M/s DeesanAgro-Tech Pvt. Ltd, Mumbaion dt-17.07.18. Site handedover to the firm on 14.09.2018and the civil work is inprogress
OCT-20100 89100 APR-202x160Rajokheri S/s 220/66 916 RFD
Contract Awarded on20.02.2019 to IKE Electric Pvt.Ltd. Maharashtra.
JUN-2126 15100 OCT-202x160Roj-Ka-Meo 220/66 347 RFD
Contract Awarded on20.02.2019 to IKE Electric Pvt.Ltd. Maharashtra.
JUN-2149 15100 OCT-201x100Roj-Ka-Meo 220/33 548 RFD
HIMACHAL PRADESH POWER TRANSMISSION CORP. LTD. ( HPPTCL )
Design and Drawings approvalare under process.
OCT-200 00 DEC-201x100Charor GIS (GEC-I) 220/33 01 RFD
OCT-200100 DEC-202x100Dehan s/s (GEC-I) 220/132 02 RFD
Page 5 of 12Report generated through NPP 08/11/2020 21.04.15
6.3.
Materials /Equipments
erected(%)
1. 7. 8.
LandAcquired
(%)
Cummulative progress till date
Materials /Equipments
Received(%)
10.
Commissioning
2.
Remarks
11.
VoltageRatio
(kV/kV)
Name ofSub Stations
Capacity(No.xMV
A)
Civilworks
completed(%)
SlNo
9. 14.4. 12.
CapacityTested/
Commissioned
(MVA)
Revised/AnticipatedOriginal
5.
Date ofAward Tag Type
13.
DEC-200 00 DEC-201x100Sunda (Addl. T/F) (GEC-I) 220/66 03 RFD
Substation is beingconstructed with funds sourcedfrom ADB.
DEC-200 00 DEC-202x100Sunda S/S 220/132 04 RFD
JHARKHAND URJA SANCHAR NIGAM LTD. ( JUSNL )
All supply & 90% erection workcompleted. Cable laying work ,Earthmat & Stringing workunder progress
DEC-20100 90100 JUN-204x100Jainamore (Bokaro) S/S 220/132 901 RFD
Work Status: 400kV, 220kV &132 kV Tower & equipmentfoundation switchyard panelroom completed. 400kV,220kV & 132 kV equipmenterection & Boundary wall brickwork & precast boundary wallwork under progress.
DEC-2070 60100 JUN-206x105+3x100
Latehar GSS (PGCIL) 400/220/132
952 RFD
220kV & 132 kV Tower &equipment foundation,switchyard panel room, CableTrench ,store shed, Fire wallcompleted. Erection Work:220kV & 132 kV tower erectioncompleted. Equipment erection& Boundary wall brick work &precast boundary wall workunder progress.
DEC-2090 90100 APR-202x150Lohardaga GSS (PGCIL) 220/132 953 RFD
Erection Status:- Boundarywall, control Room Building &FFPH building work -80%.400/220 Structure &equipment foundation work 70%
DEC-2070 70100 APR-202x315Patratu GSS (PGCIL) 400/220 804 RFD
J&K POWER DEVELOPMENT DEPARTMENT ( JKPDD )
Works under progress.MAR-2160 0100 DEC-201x160Delina (Augmentation ) 220/132 701 RFD
DEC-201x160Kathua-II (Ghatti) 220/662 RFD
Work included in the draftTransmission Plan. fundingagency to be identified.
0 00 DEC-201x160Lassipora (GIS) 220/33 03 RFD
KARNATAKA POWER TRANSMISSION CORP. LIMITED ( KPTCL )
Page 6 of 12Report generated through NPP 08/11/2020 21.04.16
6.3.
Materials /Equipments
erected(%)
1. 7. 8.
LandAcquired
(%)
Cummulative progress till date
Materials /Equipments
Received(%)
10.
Commissioning
2.
Remarks
11.
VoltageRatio
(kV/kV)
Name ofSub Stations
Capacity(No.xMV
A)
Civilworks
completed(%)
SlNo
9. 14.4. 12.
CapacityTested/
Commissioned
(MVA)
Revised/AnticipatedOriginal
5.
Date ofAward Tag Type
13.
90% work completed, Informedagency to take up the balancecable Laying and termination,Battery charging, testing andcommissioning . Minor civilworks under progress. Due toCOVID-19 Work is under slowprogress.
SEP-20100 100100 SEP-202x100Channagiri (Nallur/Benkikere) 220/66 901 RFD
Oil Sump plastering, Controlroom building pedestalconcrete and plinth beamcompleted. 10MVATransformer foundationexcavation & PCC workcompleted. Welding & backfilling work, 11kV SWG shedwork, retaining wall SSM work,control room building wallconstruction, and cable ductinside control room are underprogress.
SEP-200 0100 SEP-202x100Heggunje (Mandarthi) S/S 220/110 202 RFD
SEP-202x100Hosdurga (Madure) 220/663 RFD
LOI issued on 03-Aug-19.Land is handed over to theagency on 14.08.2019. Activitychart approved on 30-Aug-2019.
AUG-200 0100 DEC-202x100Mughalkod S/S (GEC-I) 220/110 04 RFD
400kV GIS hall and Controlroom building completed Allother civil works are nearingcompletion. 400kV side : GISModule equipment testing, HVtesting completed and C&RPanel testing completed.220kV Side: 220kV moduleequipments and HV testingcompleted and C&R Paneltesting under progress. TBs atYaraandanahalli: minor workslike dismantling of CTs andPTs from old Hosur bay to betaken up.
DEC-20100 100100 OCT-201x1500Mylasandra GIS (Near Electroniccity)
400/220 945 RFD
Page 7 of 12Report generated through NPP 08/11/2020 21.04.16
6.3.
Materials /Equipments
erected(%)
1. 7. 8.
LandAcquired
(%)
Cummulative progress till date
Materials /Equipments
Received(%)
10.
Commissioning
2.
Remarks
11.
VoltageRatio
(kV/kV)
Name ofSub Stations
Capacity(No.xMV
A)
Civilworks
completed(%)
SlNo
9. 14.4. 12.
CapacityTested/
Commissioned
(MVA)
Revised/AnticipatedOriginal
5.
Date ofAward Tag Type
13.
Control Room foundationmarking and excavationcompleted. Bay equipentEarthmat work is underprogress. Equipmentfoundation and erection work,cable duct work underprogress. Divertion OM issuedon 28.08.2020 form SEE, P&Mfor divertion of released100MVA Transformer whichwill be released atSomanahalli.
DEC-2030 20100 DEC-202x100Sira s/s 220/66 756 RFD
Control room finishing work &other minor works underprogress. All equipmenterection completed and PCtesting under progress.
SEP-20100 100100 SEP-202x100T. Gollahalli (Thimmansandra) S/S 220/66 987 RFD
KERALA STATE ELECTRICITY BOARD ( KSEB )
Work awarded to M/s. GET&DIndia Ltd. and work is inprogress.
JUL-2086 79100 APR-204x100Aluva 220/110 861 RFD
Work awarded to M/s.Seimens India Ltd and work isin progress .
JUL-2080 60100 APR-202x100Chalakudy S/S 220/110 792 RFD
Site levelling completing; workawarded to M/s. Seimens IndiaLtd.
JUL-2025 0100 SEP-202x100Chithirapuram S/S 220/66 23 RFD
Work awarded to M/s. GET&DIndia Ltd. and work is inprogress.
JUL-2085 45100 MAY-202x100Kunnamangalam S/S 220/110 594 RFD
MAHARASHTRA STATE ELEC. TRANSMISSION COMPANY LTD. ( MSETCL )
ICT-I and II back charged on04-07-2020.
JUL-20100 96100 JUN-202x100Amrapur (Pathardi) S/S 220/132 1001 RFD
1) Work resumed.2)Excavation for compoundwall started in last week. 3)Applied for LT connection.Payment made to MSEDCL.
0 0100 DEC-201x100GIS Ulwe Node 220/22 02 RFD
1 x 100 MVA, 220/132kV ICT Iand 1 x 25 MVA, 220/33 KvT/F back charged on26/07/2020.
SEP-20100 99100 DEC-20125Naghbid S/S 220/33 843 RFD
Page 8 of 12Report generated through NPP 08/11/2020 21.04.16
6.3.
Materials /Equipments
erected(%)
1. 7. 8.
LandAcquired
(%)
Cummulative progress till date
Materials /Equipments
Received(%)
10.
Commissioning
2.
Remarks
11.
VoltageRatio
(kV/kV)
Name ofSub Stations
Capacity(No.xMV
A)
Civilworks
completed(%)
SlNo
9. 14.4. 12.
CapacityTested/
Commissioned
(MVA)
Revised/AnticipatedOriginal
5.
Date ofAward Tag Type
13.
100 MVA 220/33 kV ICT-I backcharged on 29.03.19. ICT-IIand 25 MVA,220/33 kV T/F-I&II back charged on 30.07.19.
NOV-19100 100100 DEC-20250Narangwadi s/s 220/132 1004 RFD
ICT-I and ICT-II along with220kV bus & PT backchargedon 18-03-2019 & 220KV bays(6 Nos) charged ondt.28.03.2019.The 220/33 kv50 MVA T/F is successfullytest charged ondtd.15.05.2019. T/F-II backcharged on 06/12/19.
SEP-1998 96100 DEC-20250Uppalwadi Sub-Station 220/33 1005 RFD
M.P. POWER TRANSMISSION CORPORATION LIMITED ( MPPTCL )
Additional X-mer work50 50100 JUN-201x160Barwaha S/S 220/132 901 RFD
Commissioned 09/20 (LateReported).
NOV-20100 100100 APR-201x160Gorabazar S/S 220/132 1002 RFD
40 40100 APR-201x160Katni 400 kV S/S ( Addl. X-mer) 220/132 903 RFD
Work under progress.78 60100 DEC-201x160Kukshi S/S 220/132 1004 RFD
DEC-2065 65100 DEC-202x315Mandsaur (Sitamau) (GEC-I) 400/220 1005 RFD
47 47100 DEC-202x160Nalkheda (Susner) (GEC) 220/132 886 RFD
60 60100 OCT-201x315Pithampur 400kV S/S (Addl. X-mer) 400/220 1007 RFD
Additional X-mer52 52100 SEP-201x100Sukha (Jabalpur) (Addl. T/F) 220/33 978 RFD
62 62100 SEP-201x160Udaipura S/S (Upgradation) 220/132 989 RFD
OCT-2066 66100 OCT-202x315Ujjain (GEC-I) 400/220 10010 RFD
66 66100 APR-201x160Vidisha (Addl. X-mer) 220/132 9511 RFD
ORISSA POWER TRANSMISSION CORPORATION LTD. ( OPTCL )
MAR-2190 80100 JUL-201x40Deogarh 220/33 901 RFD
MAR-2190 80100 SEP-201x315Duburi (ICT-III) 400/220 802 RFD
Commissioned 05/20.JUN-20100 100100 JUL-202x160Goda S/S 220/132/33 1003 RFD
80 600 DEC-201x160Gunupur 220/132 704 RFD
Commissioned 07/20.AUG-20100 100100 JUL-201x160Joda S/S 220/132/33 1005 RFD
Delayed due to forestclearance issue
MAR-2190 80100 JUL-202x20Laphripara 220/33 856 RFD
Voltage Ratio should be400/220kV and capacityshould be 2X500MVA=1000MVA
MAR-2185 80100 DEC-20500Meramundali B 400/220 857 RFD
Page 9 of 12Report generated through NPP 08/11/2020 21.04.16
6.3.
Materials /Equipments
erected(%)
1. 7. 8.
LandAcquired
(%)
Cummulative progress till date
Materials /Equipments
Received(%)
10.
Commissioning
2.
Remarks
11.
VoltageRatio
(kV/kV)
Name ofSub Stations
Capacity(No.xMV
A)
Civilworks
completed(%)
SlNo
9. 14.4. 12.
CapacityTested/
Commissioned
(MVA)
Revised/AnticipatedOriginal
5.
Date ofAward Tag Type
13.
POWER TRANSMISSION CORP. OF UTTARAKHAND LTD. ( PTCUL )
WIPJUL-2073 25100 MAY-202x25Baram (GIS) s/s 220/33 751 RFD
PUNJAB STATE TRANSMISSION CORPORATION LIMITED ( PSTCL )
Commissioned 05/20.JUN-20100 100100 APR-2060Baja Khanna (Aug. of 100 MVA T/Fwith 160 MVA T/F)
220/66 1001 RFD
APR-201x100Banga (Upgradation of 132 KVS/Stn. to 220 KV S/Stn. )
220/1322 RFD
NOV-20500Makhu (Addl. T/F) 400/2203 RFD
Commissioned 05/20.JUN-20100 100100 APR-201x100Maur (Addl. T/F) 220/66 1004 RFD
AUG-201x100Tibber (Addl. T/F) 220/665 RFD
RAJASTHAN VIDYUT PRASARAN NIGAM LIMITED ( RVPNL )
Electrical works: Work orderIssued to M/s Kay Cee Energyand Infra Private limited, Kotaon Dated:-10.05.2018.Earthing work is underprogress.
DEC-20100 100100 OCT-201x160Aklera (Dist. Jhalawar) 220/132 1001 RFD
NOA issued in favor of M/sKanohar. Wiring work underprogress.
DEC-20100 100100 SEP-201x160Chhatargarh GSS (Upgradation)(GEC-I)
220/132 972 RFD
Work completed. Trf. Erectedand test charged from LV sideon dt 08.03.2020. Associatedline work under progress.
DEC-20100 100100 JUL-202x160NPH Jodhpur S/S 220/132/33 1003 RFD
TAMILNADU TRANSMISSION CORPORATION LTD. ( TANTRANSCO )
Work under progress.MAR-2190 80100 SEP-202x1500Ariyalur S/S 765/400 901 RFD
Work under progress.MAR-2190 75100 NOV-202x1500North Chennai PS (GIS) 765/400 902 RFD
Commissioned 10/20.NOV-20100 100100 JUN-202x100Samayanallur S/S 230/110 1003 RFD
All works nearing completion.GIS testing in progress.
NOV-20100 95100 JUN-202x100TNEB HQ (GIS) (JICA) S/S 230/33 1004 RFD
TRANSMISSION CORPORATION OF ANDHRA PRADESH LIMITED ( APTRANSCO )
i) All PTR Bay Extension workscompleted ii)ICT will be allotedas per the load requirementduly matching with thecommissioning schedule of220kV downstream network
JUN-2090 90100 MAY-201x315Aug. at Hindupur 400/220 1001 RFD
68 out 68 Nos Foundationscompleted . Remaining worksunder progress.
NOV-200 0100 MAY-20500Aug.at Kalpaka -4th (500MVA) 400/220 502 RFD
Page 10 of 12Report generated through NPP 08/11/2020 21.04.16
6.3.
Materials /Equipments
erected(%)
1. 7. 8.
LandAcquired
(%)
Cummulative progress till date
Materials /Equipments
Received(%)
10.
Commissioning
2.
Remarks
11.
VoltageRatio
(kV/kV)
Name ofSub Stations
Capacity(No.xMV
A)
Civilworks
completed(%)
SlNo
9. 14.4. 12.
CapacityTested/
Commissioned
(MVA)
Revised/AnticipatedOriginal
5.
Date ofAward Tag Type
13.
Equipment foundation worksunder progress.48 Nos out of52 Nos Equipment foundationscompleted.
NOV-200 0100 MAY-20500Aug. at Manubolu (Nellore) 400/220 203 RFD
Works are under progress.JUL-2080 80100 JUL-202x160Betamcherla (GEC-I) 220/132/33 854 RFD
instead of constructingseparate 400kV Substation atMylavaram, the scheme ismodified by laying 220kV linesfrom pooling stations atMylavaram Ultra Mega SolarPark (1000MW ) at kadapadist. of AP to the existing400kV Jammamalamadugu ina Cost effective manner.
0 0100 JUL-203x315Mylavaram (GEC-II) 400/220 05 RFD
90% of work completed.JUL-2090 90100 JUL-203x100Pydibhimavaram S/S 220/132 856 RFD
Transmission Corporation of Telangana Limited ( TSTRANSCO )
0 00 JUL-202x100Banswada 220 001 RFD
0 00 DEC-202x160Bowrampet S/S 220/132 002 RFD
OCT-202x100Indravelly (Utnoor) S/S withAutomation System
220/1323 RFD
JUN-2085 30100 JUN-201000Rayadurg (GIS) 400/220/132
904 RFD
U.P. POWER TRANSMISSION CORPORATION LTD. ( UPPTCL )
work in progress.JUN-2165 21100 OCT-202x160Azizpur S/s Shahjahanpur 220/132 601 RFD
work in progress.DEC-2087 71100 JUN-202x160Babina S/s (Jhansi) 220/132 722 RFD
Work in progress.APR-2189 84100 OCT-202x160Badaikala S/s Muzaffarnagar 220/132 773 RFD
Work in progress.FEB-2170 29100 SEP-202x500+2x200
Basti GIS 400/220 674 RFD
work in progress.JAN-2173 42100 AUG-20240Integrated Township Noida S/s 220/33 685 RFD
Work in progress.FEB-2191 70100 SEP-202x500Jehta (Hardoi Road) S/s Lucknow 400/220 706 RFD
work in progress.91 71100 OCT-204x100Jehta (Hardoi Road) S/s (Lucknow) 220/132 707 RFD
Work in progress.MAR-2172 461002x160Nirpura S/s Baghpat 220/132 608 RFD
T/F-I 60 MVA charged on15.11.2019
95 90100 SEP-2060Phoolbagh S/s Kanpur 220/33 959 RFD
Work in progress. 40MVA T/F- I likely to be energised inJuly' 2020.
JAN-2190 72100 JUN-202x160Sangipur S/s (Pratapgarh) 220/132 7010 RFD
T/F-160 MVA charged on24.08.2020
100 95100 OCT-202x160Vrindawan S/s 220/132 9511 RFD
WEST BENGAL STATE ELECTRICITY TRANSMISSION CO. LIMITED ( WBSETCL )
Page 11 of 12Report generated through NPP 08/11/2020 21.04.16
6.3.
Materials /Equipments
erected(%)
1. 7. 8.
LandAcquired
(%)
Cummulative progress till date
Materials /Equipments
Received(%)
10.
Commissioning
2.
Remarks
11.
VoltageRatio
(kV/kV)
Name ofSub Stations
Capacity(No.xMV
A)
Civilworks
completed(%)
SlNo
9. 14.4. 12.
CapacityTested/
Commissioned
(MVA)
Revised/AnticipatedOriginal
5.
Date ofAward Tag Type
13.
Work under progress.AUG-2010 0100 NOV-202x160Baruipur GIS 220/132 221 RFD
FEB-212x160Belmuri GIS 220/1322 RFD
JAN-211x80KLC (Augmentation) 220/1323 RFD
PRIVATE SECTOR
ADANI POWER LTD. ( APL )
a) Covid-19: Project progressincluding Statutory proposalsaffected due to COVID-19.
FEB-2180 65100 NOV-202X315+2X160
Badaun GIS (OBTL) 400/220/132
701 RFD
a) Covid-19: Project progressincluding Statutory proposalsaffected due to COVID-19.
MAR-2118 0100 OCT-202x500Dhanbad s/s (NKTL-TBCB) 400/220 332 RFD
STERLITE GRID LTD. ( SGL )
1. 132kV transmission line hasto be constructed by TSECLfrom P.K. Bari (TBCB) to P.K.Bari (TSECL) to utilize thesystem. 2. Allotment of 1.16acres of Government land is inprocess 3. Delay due tooccurrence of Force Majeure(FM) event i.e. outbreak ofCOVID-19 and this FM eventhas been intimated to allLTTCs
OCT-20100 10095 APR-202x315P.K. Bari S/S (NER-II TL- TBCB) 400/132 1001 RFD
1. 132kV transmission line hasto be constructed by TSECLfrom Surajmaninagar (TBCB)to Surajmaninagar (TSECL) toutilize the system. 2. Allotmentof 0.69 acres of Governmentland is in process. 3. Delaydue to occurrence of ForceMajeure (FM) event i.e.outbreak of COVID-19 and thisFM event has been intimatedto all LTTCs
OCT-20100 10095 APR-202x315Surajmaninagar (NER-II TL -TBCB) 400/132 1002 RFD
Page 12 of 12Report generated through NPP 08/11/2020 21.04.16