Transcript
Page 1: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

69

Time and Cost Overruns in Power Projects in Kenya

Vol. 3 Issue No. 2 June 2013

Time and Cost Overruns in Power Projects in Kenya: A Case

Study of Kenya Electricity Generating Company Limited

David Kagiri

([email protected])

&

Gituro Wainaina

([email protected])

Abstract

Time and cost overruns in infrastructure development projects during

implementation continue to pose great challenges to developing

countries. Research has found that many factors impede the successful

completion of projects on time, within budget and of good quality. This

study sought to investigate the factors that significantly contributed to

time and cost overruns in power projects implemented by KenGen, to

evaluate their relative ranking and to quantify their impacts. The study

was based on a questionnaire survey conducted with persons drawn

from contractors, consultants and KenGen, who are involved in the

implementation of one or more of the four projects in the study. Analysis

of 33 significant variables from the survey revealed eight underlying

factors contributing to overruns, namely, contractors’ inability, improper

project preparation, resource planning, interpretation of requirements,

definition of the work involved, timeliness, government bureaucracy

and risk allocation. As regards ranking, government bureaucracy

topped the list while risk allocation was shown to have been the least

significant. There was also a perception that these factors would recur

in KenGen’s future projects in a similar implementation environment.

By closely relating the factors to the variables, it was observed that

they resulted in overruns in the projects by varying magnitudes. The

projects had time overruns ranging from –4.6% to 53.4 %, while the

Page 2: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

70

David Kagiri & Gituro Wainaina

ORSEA Journal

cost overruns varied between 9.4% and 29%. These revelations should

enable planners to take stock of past performance and incorporate

the lessons learnt in future project planning and implementation.

Because the variables and underlying factors are likely to recur in

future projects, their occurrence needs to be anticipated and

appropriate strategies and mechanisms designed in order to overcome

or minimize their potential impact. Recommendations are given to assist

the Government of Kenya (GoK) and KenGen on how project

management could be improved when future projects are planned and

implemented. The findings of this paper can be used as a reference by

project owners, managers and agencies in developing their own project

management strategies.

Keywords: KenGen; project management; overruns; variables; factors; project

implementation

Background and Introduction

Individuals, private firms or public entities are continually acquiring physical

assets in various forms, such as residential and commercial buildings,

hospitals, schools and institutions, development infrastructure like water,

roads, electricity and telecommunications. These assets represent major

capital investment motivated by market demand or perceived needs

(Hendrickson and Au, 1999). To remain competitive in profit or non-

profit engagements, these entities focus on processes and procedures

that offer value for money and competitive advantage. Understanding

customers’ needs and appropriately deploying the available resources

to meeting them give a competitive edge over competitors in product

and service provision. Thus, efficient and effective resource management

through the appropriate use of tools and techniques for acquiring assets

is critical. Customers are demanding better quality products through

efficient and timely deliveries at low prices. It is therefore important that

Page 3: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

71

Time and Cost Overruns in Power Projects in Kenya

Vol. 3 Issue No. 2 June 2013

the timing, cost and quality of constructed facilities are efficiently managed

in the entire project life cycle for the efficient delivery of services or products.

Delays and cost overruns in public sector investments can raise the capital-

output ratio in the sector and elsewhere, reducing the efficacy of the

investments (Morris, 1990). Thus, successful management of the processes

employed to acquire these assets is to a large extent determined by the

amount of resources expended, the time taken and the quality when

compared to similar projects. Infrastructure includes the capital required

to produce economic services from utilities (electricity, telecommunications

and water) and transport (roads, bridges, seaports and airports) and is

central to promoting economic activity (Chandra, 2002).

The Kenyan power system has a generating capacity of about 1,211 MW,

including 30 MW imported from Uganda on a non-firm basis, with an

effective capacity of 988 MW. The bulk of this capacity is hydro-based

(70 percent), while the rest is supplied from oil-fired and geothermal plants

(GoK, 2003). The 1996 liberalization of power generation, as part of the

power sector reform, saw the entrance of Independent Power Producers

(IPPs), who contribute 173.5 MW to the national grid (KPLC, 2004).

Electricity consumption is relatively low, at about 121KWh per capita.

Overall, only 4 percent of rural and 46 percent of urban households have

access to electricity, equivalent to a national average of 15 percent (GoK,

2003; 2004). This level of national penetration is very low relative to an

average of 32 percent for developing countries (GoK, 2004). Because

many people in Kenya do not have access to this commodity and it is

costly, they depend on indigenous and traditional energy sources like wood

and charcoal (GoK, 2003). This, in turn, has led to the depletion of forest

resources and significant environmental damage. The lack of adequate,

dependable and competitively priced power naturally hampers the

Page 4: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

72

David Kagiri & Gituro Wainaina

ORSEA Journal

productivity and competitiveness of our industries in the region and global

markets.

The current annual growth in demand for electric power stands at 6 percent

(GoK, 2004). This translates into approximately 60 MW of additional

capacity annually. This capacity takes care of retiring units and the aging of

existing ones. The typical installation cost of a 1.0 MW diesel plant is

approximately USD 1.0 million, while that of a geothermal plant is slightly

over USD 2.1 million. The GoK, KPLC and KenGen are not capable of

mobilizing the capital required to meet the growth in demand. Hence, they

will continue to rely on bilateral and multi-lateral agencies for funds to

undertake expansion. Alternatively, with the liberalization of the sector and

the reforms in the economy, the private sector will increasingly have to

play a vital role in meeting the shortfall. Currently, four IPPs are operating

in the country.

In Kenya, public sector projects are identified, planned and implemented

by government ministries or their implementing agencies in state

corporations. The aim of these projects is to improve the country’s

infrastructure like health, communication networks, housing, energy and

water. Hence, expeditious implementation to realize the desired benefits

for their end users is important. However, in Kenya, it is a well-known fact

that time and cost overruns are prevalent in public sector projects (Mwandali

1996, Talukhaba 1988, Karimi 1998, and Musa 1999). Their findings

showed that poor communication, project managers’ lack of experience,

procurement delays, lack of planning, poor infrastructure, inadequate

resources, lack of motivation, tendering methods, variations in the project

environment and poor project definition are some of the major contributors

to time and cost overruns. The time and cost overruns in projects in this

study were limited to those that occurred during the construction or

implementation phase.

Page 5: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

73

Time and Cost Overruns in Power Projects in Kenya

Vol. 3 Issue No. 2 June 2013

Motivation for Research

The Government of Kenya and its development partners continue to

allocate huge financial resources to finance infrastructure development.

However, the intended benefits are partly or never realized due to the

implementation of many unsuccessful projects. Specific research

undertaken to investigate what ails the implementation of some public

sector projects in Kenya provides an insight into what has been the major

causes of project time and cost overruns, and the failure to meet

specifications and stakeholders’ expectations. Musa (1999) conducted

a study on factors influencing delays in water projects in Kenya funded

by the Government. A similar study by Karimi (1998) focused on factors

contributing to cost overruns in projects under the Ministry of Water.

Talukhaba (1988) investigated the time and cost performance of

construction projects. Mwandali (1996) did an analysis of major factors

that affect project management of Kenya Railway projects. Similar

observations have been made in developing countries like Indonesia

(Kaming et al. 1997), Lebanon (Mezher and Tawil, 1998), India

(Morris,1990; Pillai and Kannan, 2001), Nigeria (Mansfield et al. 1994),

Vietnam (Long et al. 2004), Nepal (Manavazhi and Adhikari, 2002)

and Nigeria (Aibinu and Jagboro, 2002). Thailand as a fast growing

economy has not been spared overruns (Ogunlana and Promkuntong,

1996). Various factors contributing to overruns in Saudi Arabia were

identified by Assaf et al. 1995 and in Ghana by Frimpong et al. 2003.

Factors ranging from inflation, project complexity, inaccurate material

estimation, financing, changes in orders, design changes, late submission

of drawings, poor specifications, incorrect site information and poor contract

management among many others were found to be the main causes of

overruns.

Studies conducted in developed economies like Hong Kong

(Kumararswamy and Chan, 1997; 1998), the UK/USA/Australia (Ireland,

Page 6: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

74

David Kagiri & Gituro Wainaina

ORSEA Journal

1987), Florida (Ahmed et al. 2002) and Australia (Ireland, 1985) revealed

a trail of time and cost overruns in building and infrastructure projects in

the public and private sector, attributable to numerous factors that come

into play during project implementation.

No studies have been conducted in Kenya to try and document the success

or failure of public power projects to meet time and cost targets, neither

have there been any studies on the few independent private power plants.

Implementing a power plant project requires huge capital investment, and

poor management of the process leads to huge financial loss in terms of

penalties and revenue of the owner. Time and cost overruns in public power

projects implemented by KenGen are a matter of public interest and concern

for all stakeholders. To be able to respond to internal and external variables

in a project environment that lead to overruns in implementing power

projects, it was thought necessary to find out how and to what extent

these variables contributed to delays and increased costs.

Research Objectives

This research identified and examined the factors that significantly

contributed to time and cost overruns when KenGen implemented the

construction of power projects on behalf of GoK. The research objectives

were to:

(i) Identify the factors that significantly contributed to time and costs

overruns in public power projects;

(ii) Establish the relative importance of these factors; and

(iii) Quantify the time and costs associated with the significant factors.

Research Methodology

The research was a multiple case study design that sought to obtain detailed,

in-depth knowledge of a few power plant development projects. The

Page 7: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

75

Time and Cost Overruns in Power Projects in Kenya

Vol. 3 Issue No. 2 June 2013

projects were procured, implemented and financed through similar processes

but experienced different time and cost performance during implementation.

The study investigated four public sector power projects undertaken by

KenGen in the last 15 years through purposive sampling. Projects prior to

this period were implemented by other government agencies. Their

implementation records, data and information were not easily available.

For the planned survey, it would have been almost impossible to reach

clients, contractors and consultant personnel involved in these projects.

Hence they were left out of the study.

The sample of projects encompassed the generating modes that KenGen

has been developing and operating, namely, hydro-power, thermal and

geothermal. The sample was small due to the nature of projects in this part

of the world. The demand for their development is small and they take a

long time to plan and implement thus limiting the availability of a large

sample that could be subjected to rigorous statistical analysis. Records

and data were also not easily accessible. Reconstructing the total costs of

a public project typically entails long and difficult archival work and complex

accounting (Flyvbjerg et al., 2003). The sample of respondents for the

survey was also purposive to meet the objectives of the study. Fifty-four

respondents were selected.

The research employed both primary and secondary data. The primary

data was collected through a self-administered questionnaire, which was

pilot tested using four experts in the construction and management of

projects. The final form of the questionnaire was e-mailed to the 54

respondents, who included project consultants/specialists, KenGen

personnel (managers and engineers) and contractor personnel involved in

the projects at senior level.

The questionnaire comprised three parts. Part A sought to capture the general

Page 8: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

76

David Kagiri & Gituro Wainaina

ORSEA Journal

particulars of the respondents. Part B focused on the 50 factors (independent

variables) identified from the literature review as the causes of overruns. This

part gave each respondent an opportunity to identify the variables they

perceive to have contributed to overruns by responding on a Likert scale

from 4 (very important) to 1 (not important). The respondents were also to

rate the frequency of the likely occurrence of each variable in a similar KenGen

project on an ordinal scale: high (3), medium (2) or low (1). Part C allowed

the respondent to identify and rank other factors not included in Part B,

which they considered to have been a significant cause of overruns.

The secondary data comprised information obtained from contract

documents, claims documents, monthly, annual and project completion

reports, expenditure spreadsheets, tables capturing data on progress

payments and work progress schedules. The data and information were

recorded on a continuous basis and collated at defined periods for

monitoring, control and reporting purposes. Monitoring, control and

reporting were compared with established baselines.

Data Analysis

Part A of the questionnaire was analyzed using descriptive statistics with a

view to summarizing the general response data in terms of proportions,

frequencies and percentages. Part B, which was the core of the study, was

analyzed in two parts. The responses on the extent of contribution were

analyzed using descriptive statistics and principle component factor analysis,

using the Statistical Package for Social Science (SPSS). Kaming et al.,

(1997) and Musa (1999), in similar studies, used factor analysis. The second

part on the frequency of occurrence was analyzed using the relative

importance index analysis (Frimpong et al., 2003; Kaming et al., 1997;

Kumaraswamy and Chan, 1998).

A total of 54 questionnaires were e-mailed to potential respondents that

participated in the implementation of one or more of the four projects. Of

Page 9: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

77

Time and Cost Overruns in Power Projects in Kenya

Vol. 3 Issue No. 2 June 2013

these, 41 (75.9%) questionnaires were returned. Eleven (26.8%)

questionnaires were received from the employer/client personnel, eighteen

(43.9%) from the contractors’ personnel and thirteen (29.3%) from the

consultants’ personnel. The proportion of respondents in terms of number

of years in similar assignments ranged between 5 and 20.

Approximately 20% of the respondents did not complete part C. The

factors were grouped into categories that appeared to relate to a particular

party within and outside the project. They are many other ways to group

the factors (Ahmed et al., 2002; Chan and Kumaraswamy, 1997, 1998;

and Mezher and Tawil, 1998). The factors were grouped into seven

categories, namely, employer related, contractor, all parties related,

government, financiers, consultant and project location related.

Preliminary Analysis

(i) Analysis of Variables’ Extent of Contribution to Overruns

The calculated mean and standard deviations of responses on the extentof the contribution to the 49 causes of delay and cost are tabulated inAppendix I. The analysis of the mean revealed that “delayed payment tocontractors” had the highest mean of 3.41. “Unpredictable weather” had

the lowest mean of 1.86. Since the response to each statement variedfrom 1 to 4, a mean score of 2.4 (60%) and above was consideredsignificant. From these criteria, key factors among others in table II weredelayed payment to contractors, employer cash flow problems, delay in

disbursement of funds by financiers and bureaucracy of governmentagencies.

(ii)Relative Importance of Variables

This is the analysis of Part B of the questionnaire where the respondentswere required to rate the chances of occurrence of each variable. TheRelative Importance Index (RII) derived to summarize the importance of

each variable was computed as:

Page 10: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

78

David Kagiri & Gituro Wainaina

ORSEA Journal

where:

w = weighting as assigned by each respondent in a range from 1 to 3,

where 1 implied “Low”, 2 implied “Medium” and 3 implied “High;

A= the highest weight (3);

N= the total number in the sample.

The RII is an indicator or measure of the likelihood of recurrence of the

variable from the respondents’ point of view. The indices can, therefore,

be used to determine the rank of each variable. The results are shown in

Table 2 of Appendix II. By applying the criteria of over 60% or an RII

greater than 1.8 the variables that most frequently occurred during the

implementation of similar power projects in Kenya by KenGen were as

follows: the length of implementation of the project, delays in approval by

the engineer, complex interfaces of various work packages, delays in

accessing the site, inadequate planning by employer before commencement

of construction, delays in the procurement of materials and equipment,

bureaucracy of government agencies, delays in the disbursement of funds

by financiers, escalating cost of materials, disputes between parties, poor

handing over, delayed payment to contractors, exchange rate fluctuations,

delays in release of drawings, employer’s cash flow problems, increased

scope of work, inadequate/poor cost control, poor specifications in the

contract, late design changes, poor communication between parties (e.g.

engineer and contractor, engineer and employer), low labour productivity,

underestimation of project duration, environmental issues and government

regulations.

(iii) Comparison between Extent of Contribution and Relative

Importance Index

To elicit the respondents’ rating of the extent of the contribution to the

occurrence of each variable a comparison was made between the mean

NA

wRII

.

�=

Page 11: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

79

Time and Cost Overruns in Power Projects in Kenya

Vol. 3 Issue No. 2 June 2013

rating score of the extent of the contribution and the RII, and the results

are shown in Appendix III. A scatter plot and correlation coefficient were

used to examine the bivariate relationship between the two rankings. Figure

1 displays a plot of the extent of contribution index against RII.

Fig. 1: Scatter Plot for Extent Index and Relative Importance Index

The Pearson product moment coefficient of correlation, r, which is a measure

of the strength of the linear relationship between two variables, was 0.773

and the correlation was significant at the 0.01 level (1-tailed).

Factor Analysis of Time and Cost Overrun Variables

(i) Preliminary Analysis

To capture and reveal any multivariate correlations among the variables

identified as significant contributors to overruns, and to further explore the

structure of the data, the Principal Component Analysis (PCA) technique

Page 12: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

80

David Kagiri & Gituro Wainaina

ORSEA Journal

was employed to explain the relationships among several difficult-to-

interpret correlated variables in terms of a few conceptually meaningful

and relatively independent factors (Kleinbaum et al., 1988). To proceed

with this technique, its appropriateness for factor extraction was examined

through several tests. They included the determinant of correlation matrix,

test of sampling adequacy measured by the Kaiser-Meyer-Olkin (KMO)

statistics, which predicts if data are likely to factor well, based on correlation

and partial correlation, and the Bartlett test of sphericity, which is a statistical

test for the presence of correlations among variables (test of identity matrix).

Thirty-three highly ranked variables based on mean scores (extent of

contribution indices) were selected for factor analysis, since the extent of

their contribution was perceived as “somewhat” to “very” important and

their means approximated to more than 2.4 (60%) on a scale of 1 to 4.

This criterion was consistently chosen with the objectives of the study in

mind. The mean scores of the variables reflect a measure of central tendency

and are construed to indicate or measure the severity of each variable in

the overruns. The normality test plots showed that the data was

approximately normal. The other tests of the determinant of correlation

matrix, KMO and Bartlett’s Test indicated a lack of multicollinearity or

singularity, which confirmed that the data were suitable for proceeding

with factor analysis. Table 1 below shows the extracted factors and their

respective variables that have loadings greater than 0.5.

Page 13: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

81

Time and Cost Overruns in Power Projects in Kenya

Vol. 3 Issue No. 2 June 2013

Table 1: Factor Loading of Contributors to Time and Cost Overruns - Rotated

“CF” stands for component factor; factor loadings with values less than 0.50 are not shown

C auses of Time and C ost Ov erruns

Factors

CF1 C F2 CF 3 CF 4 CF5 CF6 CF7 CF8

C ontrac tors’ lack of e xper ie nce

0.807

P oor construc tion

m ethods

0.750

D elays in proc uring

m ate rials a nd e quipme nt

0.689

C ontrac tor’s ca sh flow

pr oblem s

0.661

U nr ea listic client budge t

0.590

P oor spec if ic ations in the contr act

0 .529

P oor labour

pr oductivity

0 .521

B a d re lations with

f ina ncier s

0 .537

D elaye d pa yme nt to c ontrac tor

0 .841

D elay in gaining a cc ess to site

0 .828

La ck of adeq ua te

pr ofessional skills of pr oject te am

0 .812

P oor sub-contra cting 0 .513

P oor re la tions betwee n e ngine er a nd

c ontrac tor

0.753

G overnm ent r egulations

0.554

I ncre ase d scope of wor k

0.837

C om ple x inter fac es of

va rious wor k pa cka ge s

0.689

L ate de sign chan ge s 0 .812

P oor handing ove r 0 .613

B ure auc rac y of gove rnm ent a genc ie s

0.806

U ne xpec ted ground

c onditions

0.725

P oor com m unic ation be twee n pa rtie s (e.g.

e ngine er a nd. c ontrac tor, enginee r.

a nd. em ployer

0.614

Page 14: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

82

David Kagiri & Gituro Wainaina

ORSEA Journal

Description and Analysis of Factors

The preliminary analysis and principal factor analysis resulted in the

identification of the factors that significantly contributed to time and cost

overruns. The factors identified were contractor’s inability, improper project

preparation, resource planning, interpretation of requirements, definition

of work, timeliness, government bureaucracy and risk allocation.

(i) Contractors’ Inabilities

This factor consisted of inadequate contractor experience, poor construction

methods, delays in procuring materials and equipment, contractor’s cash

flow problems and unrealistic client budget. At the pre-qualification stage,

contractors’ past experience of similar assignments and environments, as

well as the proposed team, were among the parameters used to judge

which contractors would be invited to bid for the work. In the case of

KenGen, the process for selecting contractors for power plant construction

contracts followed the procurement guidelines of financiers such as the

World Bank, EIB, KfW and JBIC. All the contracts were awarded to

international contractors or consortiums on the International Competitive

Bidding (ICB) basis.

Delays in procuring materials and equipment arose in projects due to the

various parties involved. The contractors were responsible for procuring

materials and equipment in all the contracts. For multi-contract projects,

where the engineer had the dual role of designer and supervisor in civil

engineering contracts, many factors were involved, leading to delays. In

some contracts, the contractors delayed the release of drawings, and the

supply contractors delayed giving design information to the engineer’s

designers so that they could prepare the drawings, while the delay in

payment to contractors and the placement of letters of credit exacerbated

the whole process, leading to overruns. Contractor’s cash flow problem

Page 15: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

83

Time and Cost Overruns in Power Projects in Kenya

Vol. 3 Issue No. 2 June 2013

referred to a contractor’s inability to ensure there was sufficient cash to

meet his financial obligations as they fall due in the process of executing

work on the project. Where there were reasonable delays in the release of

due payments to contractors, the contract envisaged that the contractor

had his own cash or access to credit to finance the work and would seek

compensation from the client.

(ii) Improper Project Preparation

This factor consisted of poor specifications in the contract, poor labour

productivity and bad relations with financiers. Due to poor specifications,

there were many instances where the work was delayed while the parties

attempted to find an agreeable interpretation of the specifications. In some

projects, the specifications were prepared early in 1990 but implementation

commenced ten years later. There were many conflicts over drawings and

specifications. For example, a specification in one contract was different

from that in another contract for a similar item, making it very difficult to

harmonize the two. There were cases where the supply of items was

duplicated in two contracts, which was often realized much later when

either the design was advanced or complete. The contract conditions

disallowed the cancellation of a piece of work item being undertaken by

one contractor and awarding it to another. In the four projects, some of

the specifications were inconsistent with local requirements. Poor labour

productivity was one of the main components of contractors’ claims for

loss of productivity, because the labourers involved had engaged in a

slowdown due to failure to pay them on time. There were reported cases

of labour unrest in some contracts due to poor working conditions, like

poor transport for workers and the lack of protective clothing.

The four projects that were studied were financed through various

packages. The financiers included IDA, KfW, GoK, JBIC and EIB. The

Page 16: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

84

David Kagiri & Gituro Wainaina

ORSEA Journal

multilateral financiers had specific requirements for the disbursement of

funds to projects. In the event that GoK and the implementing agency,

KenGen, failed to meet some of the stipulations in the loan agreements,

delays in disbursement would ensue.

(iii) Resource Planning

This factor consisted of delayed payment to contractors, delayed access

to the site, lack of professional skills of project team and poor sub-

contracting. The problems of delayed payments and access to the site

were the responsibility of the client. They were ranked 1st and 2nd, an

indication of the severity of the problem. Delayed payment arose due to

several factors; inadequate funding of the project, complex payment

processes, client cash flow problems and delays in the disbursement

process. Delaying contractors’ or their agents’ access to the site occurred

in various forms in the projects and included delayed release of work site

by the employer or his agents to the contractors involved in interface work,

right of way issues with landowners concerning the power transmission

line trace, and delay in releasing facilities for tests to be used by another

contractor. The failure to provide the contractor with access to the site led

to an extension of the time and additional costs. Disruption of the work

through not giving access to various contractors engaged in projects led to

additional expenditure.

In carrying out the work the contractor was required to deploy enough

qualified manpower in order to deliver the project on time, within budget

and to the specified quality. The repetitive demand for new drawings to be

approved, poor workmanship and the need to rectify mistakes, delays in

procurement and the delivery of insufficient materials due to wrong estimates

were reported. The sub-contracting functions were the sole responsibility

of the main contractor, whether or not he had been nominated. Such sub-

Page 17: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

85

Time and Cost Overruns in Power Projects in Kenya

Vol. 3 Issue No. 2 June 2013

contracts were agreements between the main contractor and sub-

contractor/s and involved no contractual relationship between the sub-

contractors and KenGen. In these projects, power plant design,

manufacture and construction involved many specialized skills. The

contractor accomplished the task through allocating a part or parts of

specialized work outside his core function to these other groups. The client

approved or rejected the selection or nomination of the sub-contractor if

he had reasons to doubt his ability to do a good job.

(iv) Interpretation of Requirements

Included in this factor were poor relations between the engineer and the

contractor and government regulations. As mentioned earlier, the four

projects were awarded to foreign contracting firms and were supervised

by international consulting firms with little or no locally affiliated firms. One

of the conditions for their selection was their familiarity with conditions

pertaining to developing countries, especially in Africa. Poor relations

between the two parties ensued with the result that each party tried to

meet the project requirements independently. The differences in

interpretation of the contract requirements between the engineer and the

contractor appeared to be the major cause of the poor relations. For

example, the contractor applied for compensation because of a perceived

change in the specifications, but it was rejected. When the engineer was

the designer and the contractor’s proposal that the engineering design be

improved was rejected, this appeared to be a source of contention. Many

disagreements over re-measuring quantities under re-measurement contracts

and assessing contractors’ claims led to poor relations. These incidents

generated a lot of correspondence, wasting many man-hours in resolving

disputes.

The contractor was required to be familiar with Kenya’s laws, regulations

Page 18: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

86

David Kagiri & Gituro Wainaina

ORSEA Journal

and by-laws that might affect the project and to comply with the

requirements. These related to tax/tariff requirements like duties, value

added tax, legal entity establishment, and the application of tax laws,

personal income tax, corporate tax and miscellaneous taxes. The legal

requirements related to legal basis and standing, governing laws, contract

type and procedures, environmental issues and corrupt business practices,

among others.

(v) Definition of Work

This factor related to increased scope of work and complex interfaces of

various work packages, which involved all the parties involved in the

project. The engineer’s design changes, the employer’s need to improve

the technology and the contractor’s wrong estimates of the quantity of

materials needed, among many other things, appeared to be the cause of

delays and increased costs. The increased scope of work, due to technical

changes, occurred in all the projects. It was evident that the definition of

work in some of the projects was wanting in terms of scope, specifications

and drawings. The complex interface of various work packages affected

multi-contract projects, due to complications during bidding, such as delays

in awarding contracts, which exacerbated their problems.

(vi) Timeliness

This factor relates to late design changes and poor handing over. During

implementation of a project, the following changes were a common

occurrence: changes in design, materials specifications, the skills needed,

the construction methods or how the work should be done, the sequence

of work, changes in the materials or facilities provided by the owner and

changes in the contract time. For various reasons, the client, engineer or

contractor would make late changes in the design so that, for example, the

design of facilities across various contracts would be uniform. In other

Page 19: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

87

Time and Cost Overruns in Power Projects in Kenya

Vol. 3 Issue No. 2 June 2013

instances, a contractor would demand changes in the materials and design

to ensure the construction would be sound. A project is handed over when

semi-complete or the complete work or facilities are transferred from the

contractor to sub-contractors or from the contractor to the client. For

example, in one project, the client handed over the turbine work to a civil

engineering contractor to construct the pedestals on which to bolt the turbine

for the generation of electricity. Once the turbines were bolted on to the

pedestals, the civil engineering contractor handed it over to the contractor

responsible for the generating facilities, who would install them and then

hand the work over to the civil engineering contractor for final grouting.

He would then hand over the facilities to the same contractor for testing

and commissioning and finally to the owner of the facilities, the client. This

was a complex process in a multi-contract project and was the cause of

claims by contractors. There were many disruptions, leading to poor labour

productivity and equipment utilization, culminating in an extension of the

time and added costs for the affected contractors.

(vii) Government Bureaucracy

This factor related highly to only one original variable, “bureaucracy of

government agencies”. This related to the procedures that various functions

the projects had to follow, such as clearance through customs, payment

procedures, immigration and other permits. The procedures consumed a

lot of time and manpower going through the huge amount of paperwork as

well as the never-ending delays in processing it through various government

agencies. The contractors had to employ additional manpower to expedite

the process. The delay in releasing project equipment and materials through

customs due to the delay in dealing with exemption from duties and taxes

affected all the projects, which incurred added costs for expediting the

process, placing bonds, storing the equipment and for settling various claims

by contractors. Because all these procedures through government agencies

Page 20: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

88

David Kagiri & Gituro Wainaina

ORSEA Journal

took such a long time, payments to contractors were delayed. The

placement of letters of credit by the contractors had to be sanctioned by

the government, which was the lender of the funds. In one supply-and-

install contract, the placement of the foreign component of the letter of

credit was delayed by 24 months, partly due the government’s delay in

issuing the necessary letters to the financier. Consequently, although the

contractor had finished manufacturing the equipment, he could not ship it

and had to store it abroad. The immigration department occasionally

delayed issuing work permits to foreign workers, despite the fact that the

loan agreement between the government and financiers takes cognizance

of the type of people to be employed in the execution of work by contractors

through its appointed agencies like KenGen. Many foreign personnel, both

consultants and contractors, had to spend a lot of time following up on the

issuance or renewal of work permits. Other permits related to local authority

approval for construction, waste disposal, and the drilling of boreholes, as

well as those relating to environmental and safety compliance.

(viii) Risk Allocation

This factor consisted of unexpected ground conditions and poor

communication between parties (for example, between the engineer and

the contractor and vice versa). In the four projects, the risk of unexpected

ground conditions was distributed between three parties. The client (owner)

was responsible for undertaking pre-contract exploratory measures, the

engineer (designer), where applicable, was responsible for designing for

the conditions expected with the larger proportion of risk being transferred

to the contractor. The extent to which this was not feasible determined the

degree to which KenGen retained a portion of the risk under the relevant

clauses in the contracts. The respondents stated that overruns were due to

ineffective risk assessment, changes in the contract conditions without

allowing for a proper review of the consequential impacts and the lack of

Page 21: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

89

Time and Cost Overruns in Power Projects in Kenya

Vol. 3 Issue No. 2 June 2013

thorough risk assessment. Due to “unforeseen conditions” in one of the

projects, the contractor claimed that the boulders/rocks he encountered

had not been revealed by the geotechnical data and information provided

by KenGen.

Relative Importance of these Factors

The second objective of the study was to establish the relative importance

of these factors. The eight “component factors” could explain 77% of the

variance in the thirty-three variables considered significant in contributing

to overruns. To be able to rank these factors, the average of the extent of

the contribution of variables “hanging together” was used. For example,

for “resource planning”, in Table 2, the average of 3.41, 2.68 and 2.61

(Appendix I) was 2.90. From this ranking, government bureaucracy was

ranked first with an index of 3.27 and the second was resource planning

with an index of 2.90. Risk allocation was ranked eighth, with an index of

2.41, as shown in Table 2.

The perception of respondents that these factors in similar, future projects

would reoccur was analyzed using RII of the associated variables, shown

in Table 2. For example, the variables for “resource planning” were delayed

payment to contractor, delay in getting access to site and lack of adequate

professional skills of project team. The respective RII were 0.821, 0.626,

and 0.569 (Appendix III) giving an average of 0.672, shown in Table 2.

Government bureaucracy was ranked first, followed by definition of work.

Risk allocation and improper project preparation were ranked seventh

and eighth, respectively. The Pearson correlation coefficient between the

two rankings was 0.81 and significant at 0.01 (1-tailed).

Page 22: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

90

David Kagiri & Gituro Wainaina

ORSEA Journal

Table 2: Ranking of the Factors

Summary of Research Findings

A survey was conducted with project personnel drawn from KenGen,

and the contractors and consultants involved in the four recent projects in

investigating the factors that made a significant contribution to time and

cost overruns during their implementation by KenGen on behalf of GoK.

The survey was also used to elicit those factors that were likely to recur in

similar projects in the future. The respondents identified additional causes

or variables that contribute to overruns. An analysis of the responses

revealed that some variables significantly contributed to time and cost

overruns and have a chance of recurring in future projects. These included,

among others, delayed payments to contractor, employer’s cash flow

problems, delay in disbursement of funds by financiers, bureaucracy of

government agencies, complex interfaces of various work packages, length

of implementation of the project, delay in procurement of materials and

equipment, inadequate planning by employer before commencement of

construction, late design changes, delays in approval by engineer, delays

in the release of drawings, increased scope of work, disputes between

parties and delay in getting access to site.

Emerged Factor Average

Extent Index

Rank Average

RII

Rank

Contractors’ inability 2.58 6 0.593 6

Improper project preparation 2.59 5 0.558 8

Resource planning 2.90 2 0.672 3

Interpretation of requirements 2.47 7 0.606 5

Definition of work 2.85 3 0.744 2

Timeliness 2.67 4 0.646 4

Government bureaucracy 3.27 1 0.837 1

Risk allocation 2.41 8 0.568 7

Page 23: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

91

Time and Cost Overruns in Power Projects in Kenya

Vol. 3 Issue No. 2 June 2013

From factor analysis, eight latent factors that could to large extent explain

the common variance of these measured variables were identified. These

were deduced as representing contractors’ inability, improper project

preparation, resource planning, interpretation of requirements, definition

of work, timeliness, government bureaucracy and risk allocation.

The ranking of these factors, using the average of the extent of contributions

from their respective cluster of variables showed that government

bureaucracy ranked high as a factor contributing to overruns. This was

followed by resource planning, definition of work, timeliness, improper

project preparation, contractors’ inability, interpretation of requirements

and risk allocation.

The ranking using the relative importance index closely matched the extent

of contribution. Government bureaucracy was ranked highest, followed

by definition of work and resource planning. Timeliness came fourth

followed by interpretation of requirements, contractors’ inability, risk

allocation, and improper project preparation. This order was important

because it revealed the variables that KenGen should emphasise during

the execution of future projects. For example, it is clear that the bureaucracy

of government agencies contributed to overruns in all the projects in the

study. This also highly likely to occur in future projects unless the problems

produced by these agencies are brought under control.

By closely relating the factors to the various variables, it was observed

that they resulted in overruns in the projects by varying magnitudes. The

projects had time overruns ranging from – 4.6% to 53.4 %, while cost

overruns varied between 9.4% and 29%

Page 24: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

92

David Kagiri & Gituro Wainaina

ORSEA Journal

Significant Factors Contributing to Overruns

The significant factors contributing to overruns in the power projects and

identified in the study were contractors’ inability, improper project

preparation, resource planning, interpretation of requirements, definition

of work, timeliness, government bureaucracy and risk allocation. Kaming

et al. (1997), in a similar study on overruns in high-rise projects in Indonesia

found that equipment usage, resource estimates and the shortage of human

resources caused delays, while environmental issues, cost data and inflation

were significant in determining cost overruns. Musa (1999) in a study on

water projects funded by GoK identified the quality of project management,

the operating environment and infrastructure, motivation of workers,

inadequate resources and organization of the project team as factors that

caused delays in the projects. Developing countries lack resources and

managerial skills and have low human capital productivity (Kwak, 2002).

Long et al. (2004) identified incompetent designers/contractors, poor

estimation and cost management, social and technological issues, site-

related issues and improper techniques and tools in the case study of

Vietnam. Therefore, project design standards, specifications and

construction methods must be carefully selected so that they will be

appropriate for the local financial, human and material resources required

during both implementation and subsequent operations (Kwak, 2002). It

is important to appreciate that, for a country like Kenya, with perennial

power shortages, power projects are more often implemented on a “fast

track” basis and certain issues are easily overlooked during project

preparation that often lead to snags when implementing projects like delayed

payment to the contractor with a consequential delay in the schedule.

Contractor’s experience is manifested in how the project is managed and

how the responsibilities and obligations defined in the contract are carried

out. The selection of the project team, supervision, scheduling, coordination

Page 25: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

93

Time and Cost Overruns in Power Projects in Kenya

Vol. 3 Issue No. 2 June 2013

and control of work activities, methodologies, work plans, deployment

and coordination of resources, procurement of materials, knowledge of

the territory of the project and overall site management are indicators of

an experienced contractor. The complexity of the technology and the

financial standing and experience that were pre-qualification criteria for

the four projects eliminated the participation of local contractors, confining

them to minor sub-contracting roles. Poor construction methods by the

contractor could be a reflection of poor specifications, lack of skills and

experience and inappropriate equipment. Poor specifications led to a waste

of resources and time as parties tried to agree on their interpretation.

Turnkey (design-build) projects are easy to implement, but it is much more

difficult to implement projects where the design and construction are done

by different contractors. For example, in two of the projects that were

studied, the consultant was responsible for designing the main civil

engineering work and supervising the construction contractor. This led to

protracted debates and correspondence, which could result in lost time

and additional costs.

Cash flow problems occurred if a contractor was receiving regular

payments from the employer but diverted funds to other activities unrelated

to the project. The main casualties were local sub-contractors, with

consequent effects manifested in the delayed provision of services and

goods and increased costs. Poor specifications arose from the fact that

external consultants were biased to specifying what they were familiar with,

and the client may not have had the time or ability to review them. To

overcome specification problems, some of the requirements had to be

dropped after extended delays in negotiating alternatives.

In the mind of some of the respondents who were stakeholders, the delay

in the disbursement of funds was perceived as being due to bad relations.

Page 26: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

94

David Kagiri & Gituro Wainaina

ORSEA Journal

For example, one financier tied the initial release of funds for one project

to GoK settling an outstanding loan in other sectors unrelated to the project.

Such a situation therefore tended to strain relations between the borrower

and the financier.

The purpose of resource planning is to ensure that enough suitable factors

of production (money, equipment, manpower and land) are obtained and

timely deployed in order to generate a profit. Giving the contractor or his

agents timely access to the site was crucial for ensuring that the contractor

fulfilled his obligations with the allocated resources. Failure to do this led

to poor resource utilization, delays in the schedule and additional costs.

The deployment of competent personnel by contractors called for a

competent team drawn from various professional disciplines and an

appropriate organizational structure that created a cohesive team for

executing and delivering the project. Arising out of the poor relations

between the engineer and the contractor were disagreements that would

often interfere with the work of other contractors on the site.

Having an understanding of government regulations was crucial for the

smooth execution of the projects. However, it appeared that, at the start

of construction, the contractors were unfamiliar with the requirements. The

engineer often found himself in a similar situation and could not make timely

decisions without lengthy consultations. Immigration department delays in

releasing work permits led to the removal of personnel from the projects,

which led to delays and added costs.

The definition of the work to be carried out is derived from the formulation

phase of the project, when the concept is crystallized after technical studies

and consultations have been conducted, requiring considerable effort. Poor

field investigations, incomplete or inadequate information, bad or

Page 27: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

95

Time and Cost Overruns in Power Projects in Kenya

Vol. 3 Issue No. 2 June 2013

deliberately wrong estimation, lack of expertise or experience, inadequate

project analysis, omission of project linkages and poor appraisal and

investment decisions led to wrong project definition and consequently a

wrong definition of the work to be carried out. If the basic parameters of

the project are wrong, the time and cost overruns are built in from the start

and are bound to follow later (Kholi, 2001). The absence of a contract

strategy that was critical for the successful implementation of the project

could be inferred from what was happening in the projects. The number

and size of the contracts, the interface between the different contracts and

the management of the contracts should have been appropriately defined

and planned for at the formulation stage. The problem of complex interfaces

between contracts may have been exacerbated by delays in mobilizing

contractors because of a delay in the mobilization loan. During the entire

implementation period, it was difficult to maintain a coherent project

schedule to work to as a result of inter-contract delays.

The concept and application of risk management in construction projects

have been extensively covered by Kerzner (2001) and Fisk (2000). One

precept to be recognized is that all risks are rightfully the owner’s unless

transferred to or assumed by another party for fair compensation (Fisk,

2000). Risk allocation refers to risk spreading or reaffirmation of the

existing allocation of risk so that the risk stays where it should (Fisk, 2000).

The second guideline for determining whether a risk should be transferred

is whether the receiving party has both the competence to handle the risk

and the expertise necessary to control or minimize it. In all contracts, it

appeared that some of the risks were not well defined and allocated. For

example, the risk of delays associated with customs clearance was ill defined

and was a source of protracted debates. Poor communication between

parties appeared to be a problem when there was inadequate information

and team spirit was lacking. For example, the respondents stated that

Page 28: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

96

David Kagiri & Gituro Wainaina

ORSEA Journal

some of the factors that led to overruns were lack of communication by

the client team at the commencement of the project, hoarding of information

by staff, too many players on the client side, which made it difficult to

know who was responsible for making decisions, and the rigidity of parties,

making it hard for them to assist each other.

Identification of these factors fulfilled the first objective of the study and

was a pointer to solutions to the study problem. The variables associated

with the eight factors were contractors’ lack of experience, poor

construction methods, delays in the procurement of materials and

equipment, contractor’s cash flow problems, unrealistic client budget, poor

specifications in the contract, poor labour productivity, bad relations with

financiers, delayed payments to contractor, delay in getting access to site,

lack of adequate professional skills by project team, poor sub-contracting,

poor relations between the engineer and contractor, relations with the

government, increased scope of work, complex interfaces of various work

packages, late design changes, poor handing over, bureaucracy of

government agencies, unexpected ground conditions and poor

communication between parties. Similar findings were reported by

Mansfield et al. (1994), Pillai and Kannan (2001), Adhikari (2002), and

Frimpong et al. (2003).

Factor labelling was subjective, as some of the variables ‘hanging together’

did not relate to the meaning of the factors. For example, under contractors’

inability, the variable, ‘unrealistic client budget’ did not relate to the meaning

of this factor. However, further analysis of the variables provided clarity

on factor labelling. Government bureaucracy related to one factor only.

This was considered a simple structure. A factor structure is considered

simple if each of the original variables relates highly to one factor and each

factor can be identified as representing what is common to a relatively

small number of variables (Kleinbaum et al., 1998).

Page 29: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

97

Time and Cost Overruns in Power Projects in Kenya

Vol. 3 Issue No. 2 June 2013

Relative Importance of the Factors

The relative importance of these factors in contributing to overruns in future

projects as perceived by the respondents was achieved through ranking,

using the extent of contribution index and the concept of RII. The RII has

been used extensively in research to rank factors from different groups in

a survey. Kumaraswamy and Chan (1998) used RII to rank the factors

perceived by contractors, consultants and clients in building and civil

engineering works. Mansfield et al. (1994) used the severity index, which

was derived from the percentage of respondents giving a certain response.

Long et al. (2004) used mean score, which is the same as the extent of

contribution in the ranking of factors. Adopting this method of ranking

factors, using the average of the mean scores and RII, eight factors were

ranked. The high correlation between the two techniques may be used to

validate the ranking, using either of the methods. One interpretation of the

results was that, in the minds of the respondents, the variables they

considered significant in contributing to overruns were also perceived as

having a high probability of recurring in future projects. The ranking of the

eight factors provides KenGen management and others in similar industries

with a guide to priority areas where more effort should be directed at

curbing overruns in projects during implementation.

Quantitative Impact of Factors

The quantitative assessment of the impact of the variables expressed as a

percentage fulfilled the third objective of the study. The results from the

exercise were aimed at showing the tangible effects of overruns and the

consequences of any of these factors occurring. The absolute values of

overruns associated with some of the factors were identified and expressed

as percentages. However, it was difficult to isolate some of the overruns,

due to the way in which the data was presented Thus, the case study

Page 30: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

98

David Kagiri & Gituro Wainaina

ORSEA Journal

provided a closer analysis of the underlying factors leading to overruns,

from which KenGen, investors or the Government will be in a better position

to provide for appropriate contingencies during planning, having assessed

the potential risks.

Conclusions

Problems associated with the implementation of construction projects by

the private and public sector have been extensively reported in various

literature. The problems are also pervasive in developed economies. They

occur in various forms and magnitude in different types of projects,

economies and environments, leading to time and cost overruns. From the

study findings, the following conclusions are drawn.

(i) There were many variables that contributed to time and cost overruns

in the four recent power projects implemented by KenGen on behalf

of KoG. The variables were delayed payments to contractor, employer

cash flow problems, delay in disbursement of funds by financiers,

bureaucracy of government agencies, complex interfaces of various

work packages, length of implementation of the project, delay in

procurement of materials and equipment, inadequate planning by

employer before commencement of construction, late design changes,

delay in approval by engineer, delay in release of drawings, increased

scope of work, disputes between parties and delay in getting access

to site. This revelation should enable planners to take stock of past

performance and incorporate the lessons learnt.

(ii) These variables are likely to recur in future projects implemented by

KenGen in similar circumstances. There is a need to anticipate their

occurrence and to design appropriate strategies and mechanisms to

overcome or minimize their potential impact.

(iii) Through factors analysis, the 33 significant variables could largely be

explained by eight underlying factors, namely, contractors’ inability,

Page 31: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

99

Time and Cost Overruns in Power Projects in Kenya

Vol. 3 Issue No. 2 June 2013

improper project preparation, resource planning, interpretation of

requirements, definition of work, timeliness, government bureaucracy

and risk allocation. These factors give a general view and could act as

a guide to formulating new policies and strategies for managing projects

in the future.

(iv) Government bureaucracy can be considered to have been the leading

factor in contributing to overruns in these projects. The other factors

in order of significance were resource planning, definition of work,

timeliness, improper project preparation, contractors’ inability,

interpretation of requirements and risk allocation. The occurrence of

any of these factors in a project will largely depend on the environment

at the time of implementing the project. Hence there is a need to

continually scan the environment and identify the actors and factors.

(v) There were time and cost overruns in all four projects, ranging from –

4.6% to 53.4 %, while the cost overruns varied between 9.4% and

29%. The ability to minimize the impact of overruns will largely depend

on having a proper definition of the project scope, adequate planning

of the schedule and resources, commitment of all project teams, and

the application of modern project management techniques through

using qualified and motivated manpower. The risks should continually

be assessed throughout the stages of the project and appropriate

contingencies adopted.

Recommendations

It is evident from the study that implementation of power projects in Kenya,

like any other infrastructure development, will experience problems that

will often lead to time and cost overruns. Based on the finding from this

study, it is recommended that GoK and KenGen undertake the following

when implementing future projects.

Page 32: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

100

David Kagiri & Gituro Wainaina

ORSEA Journal

(i) Contractors’ Performance

In the foreseeable future, the Government and KenGen should continue to

fund power projects through bilateral and multilateral financing agencies.

This will continue to place constraints on the type of contracts or

procurement strategies that can be adopted when selecting contractors to

implement construction. To overcome some of the problems associated

with contractors’ inability, there should be better contract management,

and penalties and incentives should be designed at the implementation

planning stage. Contract planning (both for the work and equipment

suppliers) will have to be linked closely to resource-based planning and

implementation of the projects (Kholi, 2001). Contractors and suppliers

should be bound to integrate their resource, time and project plans (based

on PERT/CPM) and follow them. Enforcing liquidated damages clauses

and enhancing contractors’ incentives for early completion will ensure that

the project is completed on time. Contractors should be paid on time as

per the contract agreement to avoid the situation of timely resource planning

being affected due to cash flow problems. KenGen should ensure that the

engagement of sub-contractors and the delegation of duties by the prime

contractor do not impede the project’s progress. Where delays are

anticipated, those in authority should be able to offload contracts (partially

of fully). Contractors’ ability to manage their finances should be assessed

during the bidding process, by ensuring that the balance sheets are in order

and that there are enough funds to meet immediate obligations. Where

consultants are used for planning, awarding and following up contracts,

the effectiveness of consultants in contract management should be properly

evaluated.

(ii) Project Preparation

During project preparation, enough time and resources should be allocated

to ensure that an adequate field investigation is conducted, appropriate

up-to-date information is gathered, specifications are prepared, the scope

Page 33: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

101

Time and Cost Overruns in Power Projects in Kenya

Vol. 3 Issue No. 2 June 2013

is well defined, good estimates for materials are made, adequate project

analysis is done and linkages in project activities are identified. From this

KenGen will be able to assess the risks involved and formulate adequate

plans and contingencies. On this basis KenGen will be able to sufficiently

translate these plans into a budget that will ensure sufficient funds are

secured. Flyvberg et al. (2004) observed that before a project owner

decides to proceed with construction , every effort should be made to

make preparations, plan and authorize ex ante evaluation so that problems

that may otherwise surface as delays during implementation are identified

and eliminated. If long delays (that is, a year or more) are likely to occur in

project implementation, reviewing and updating the contents of the project

documents should be a prerequisite to ensure that the project will still

produce the deliverables envisaged earlier. KenGen should ensure that

consultants engaged in its projects understand local requirements for

successful implementation. In addition to traditional project management

functions, project managers should set up a process to scan the environment

to identify potential problems, and should seek to establish power

relationships that can help them manage the key actors and factors on

which successful implementation depends (Youker, 1992). There should

also be sufficient manpower in KenGen’s project team, who are qualified

to work alongside the consultant and can provide the knowledge needed

on the project environment. Kwak (2002) observed that international

consultants engaged to assist with project preparation have a different

socio-cultural background from the beneficiaries, they may not be familiar

with local resources and are accustomed to different approaches to

engineering and project management practices. Kenya, like other

developing countries, lacks resources and managerial skills and has low

human capital productivity (Kwak, 2002). Therefore, project design

standards, specifications and construction methods must be carefully

selected so that they will be appropriate for the local financial, human and

material resources required both during implementation and subsequent

operations (Kwak, 2002). Kumaraswamy and Chan (1998) were of the

Page 34: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

102

David Kagiri & Gituro Wainaina

ORSEA Journal

view that the interaction of other factors in the project affected labour

productivity. They further hypothesized that motivation of both management

and labour could be key contributors to productivity.

(ii) Resource Planning

Before actual implementation of the project starts, KenGen should undertake

detailed implementation planning covering aspects such as the physical

work, time plan, input resources, inter-linkages, organizational and

management systems, output generation and cost planning. An adequate

resource plan and its linkage with the time plan is crucial. The implicit

resource requirements (manpower, materials, money, etc.) for each period

may not be available and so the time plan may not be implementable (Kholi,

2001). All the major activities that may impact the timing and cost of the

project should be defined and sufficient time provided for this. For example,

land acquisition, right of way issues, clearances and administrative

procedures should be properly looked into. Sufficient funds to cover the

entire project should be provided to minimize cost overruns that lead to

higher outlays. KenGen should anticipate the need for linkages between

contractors or their agencies and provide for them or it should always

initiate a dialogue with interlinked agencies early in the planning stage so

that realistic time durations are arrived at. The organizational and

management systems needed for successful implementation should be

properly planned. Inadequate project preparation leading to scope changes

during implementation is perhaps the major reason for overruns (Morris,

1990). No efforts should be spared at the initial stage of a project in properly

defining the project’s goals and its deliverables (Dvir et al., 2003).

The tendering process should encourage the participation of local

contractors and consultants as a strategy for improving local skills and

transferring technology. The Government should formulate policies that

Page 35: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

103

Time and Cost Overruns in Power Projects in Kenya

Vol. 3 Issue No. 2 June 2013

will help develop local human capacity through proper training. This will

mean providing incentives, such as offering a tax rebate for money spent

on training, and for authorizing trade unions or other agencies to regulate

and follow up on training and classify trades. Developing human resources

also applies to construction engineers, who usually lack adequate managerial

skills (Odeh and Battaineh, 2002).

(iv) Team Building

The collaborative approach or building a team consisting of KenGen, local

and foreign contractors and consultants in a project will assist in adopting

innovative management techniques in order to be more efficient and

effective. Consultants (project managers) should be taken on board early

on in a project and their continuity ensured throughout the implementation

so that they will provide an effective link between the client and the

contractor. The project manager must appreciate the environment of

development projects, maintain flexibility and be able to analyze the nature

of the associated problems and their diverse effects on the success of the

project and address them promptly (Kwak, 2002). This will also apply to

the KenGen project team, which should be involved in the project at the

planning and formulation stages and throughout implementation. If the

parties involved in planning, designing and drawing up specifications can

work as a team with those who will handle the actual construction and

installation, many loose ends can be tied up, and the seemingly endless

delays and backtracking needed to resolve conflicts can be eliminated

before work even begins (Mezher and Tawil, 1998). The team-building

approach will provide a single interaction with owners and allow more

flexibility because of the wider mix of skills available, and will ensure much

better communication and a quick response to the owner’s needs.

Page 36: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

104

David Kagiri & Gituro Wainaina

ORSEA Journal

(v) Contract Strategy

The contract strategy adopted, i.e. number and size of contracts, and the

link between different contractors and their management, is critical for the

successful performance of the project. KenGen should formulate this at

the planning stage. Complex work interfaces should be avoided and the

work should only be split into packages that can be easily managed. Late

design changes will often complicate the management process of linking

works or contracts.

(vi) Linkage with Government

Linkage with government agencies in executing future projects is inevitable.

To minimize the delays associated with Government agencies, KenGen

should formulate strategies for constructively engaging with the relevant

agencies through its communications department. For example, teams

identified by these agencies could be inducted into projects through, for

example, an invitation to the launch of a project’s charter, occasional site

visit for updates, and continuous dialogue and communication whether or

not a project is ongoing. The key agencies are the Ministry of Energy, the

Ministry of Finance, those dealing with the environment and conservation,

revenue collection, customs clearance and immigration and local authorities.

It will be beneficial to the projects if contractors could be encouraged to

hire local experts in legal, taxation and financial regulations, as well as

environmental issues. This will greatly enhance compliance and reduce

delays when dealing directly with the government agencies.

(vii) Risk Management

The project environment in Kenya comprises diverse risk factors that may

impede the successful performance of projects. KenGen should adopt

modern risk management tools like International Project Risk Management

to identify, assess and analyse the impact and management’s response

(Gibson and Walewski).

Page 37: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

105

Time and Cost Overruns in Power Projects in Kenya

Vol. 3 Issue No. 2 June 2013

Limitations on the Study

One of the main limitations of the study was the size of the sample of

projects available. Of the four selected, only three were completed and in

commercial operation. It would have been more enlightening if a large

sample of completed projects had been available and a large sample of

respondents had been used. The other limitation concerned the secondary

data as regards the difficulty of splitting the discrete time and cost impacts

for each factor due to the close relationship between the variables. Literature

on similar studies in Kenya to collate with that from other countries was

scarce.

Recommendations for Further Research

A lot of research has been done and documented on time and cost overruns

in developing countries in Asia on many areas of infrastructure and

commercial (e.g. high-rise building) development. However, this was lacking

in Kenya, denying many potential investors or developers a source of

information on what factors to consider for ensuring successful

implementation of projects in Kenya. Further research on similar

infrastructure developments is therefore recommended.

Page 38: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

106

David Kagiri & Gituro Wainaina

ORSEA Journal

References

Ahmed, S.M., Azhar, S., Castillo, M. and Kappagantula, P. (2002)

Construction Delays in Florida: An Empirical Study, Final Report

Submitted to State Florida, Department of Community Affairs,

([email protected]) (online).

Assaf, S.A., Al-Khalil, M. and Al-Hazml, M. (1995) ‘Causes of Delay in

Large Building Construction Projects’, Journal of Management in

Engineering, Vol. 11, No. 2.

Chan, D.W.M and Kumaraswamy, M.M. (1997) ‘A Comparative Study of

Causes of Time Overruns in Hong Kong Construction Projects’,

International Journal of Project Management Vol. 15, No. 1, pp.

55-63.

Chandra, P. (2002) Projects Planning, Financing, Implementation and

Review. (5th edition) Publisher, Tata McGraw-Hill Publishing Company.

Chris, H. and Au (1999) Project Management for Construction

Fundamental Concepts for Owners, Engineer, Architects and

Builders. Prentice-Hall, Inc.

Dvir, D., Raz, T. and Shenhar, A.J. (2003) ‘An Empirical Analysis of the

Relationship Between Project Planning and Project Success’,

International Journal of Project Management, 21, pp. 89-95.

Fisk, E.R. (2000) Construction Projects Administration (6th edn), Prentice-

Hall Inc.

Flyvbjerg, B., Holm M.K.S., and Buhl S.L. (2003) ‘How Common and

How Large are Cost Overruns in Transport Infrastructure Projects’.

Department of Development and Planning, Aalborg University, Denmark,

Transport Reviews, 2003, Vol. 23, No. 1, 77-88.

Flyvbjerg, B., Holm M.K.S., and Buhl S.L., (2004) ‘What Causes Cost

Overrun in Transport Infrastructure Projects’. Department of

Development and Planning, Aalborg University, Denmark, Transport

Reviews, Vol. 24 No. 3-18, January 2004.

Page 39: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

107

Time and Cost Overruns in Power Projects in Kenya

Vol. 3 Issue No. 2 June 2013

Frimpong, Y., Oluwoye, J. and Crawford L. (2003) ‘Delay and Cost Overruns

in Construction of Groundwater Projects in a Developing Countries;

Ghana as a Case Study’, International Journal of Project

Management, 21, 321-326.

Gibson, G.E. and Walewski, P. ‘Risks of International Projects: Reward or

Folly’, ([email protected]) (online).

GoK (2003) Kenya Energy Sector Development Strategy, Nairobi, Ministry

of Energy.

GoK (2004) Draft National Energy Policy, Nairobi, Ministry of Energy.

Ireland, V. (1985) ‘The Role of Managerial Actions in the Cost, Time and

Quality Performance of High-Rise Commercial Building Projects’,

Construction Management and Economics, 3, 59-87.

Ireland, V. (1987) ‘A Comparison of U.S., U.K. and Australia Management

Practices with Special Reference to Lost Time’, The Building

Economist, December, pp. 4-10.

Jagboro, G.O. and Aibinu A.A. (2002) ‘The Effects of Construction Delays

on Project Deliver in Nigerian Construction Industry’, International

Journal of Project Management, 20, 593-599.

Kaming, P.F., Olomolaiye, P.O., Holt, G.D. and Harris, F.C. (1997) ‘Factors

Influencing Construction Time and Cost Overruns on High-Rise Projects

in Indonesia’, Construction Management and Economics, 7, 83-94.

Karimi, R.B., “Factors which are Critical in Project Cost Overruns: A Case

Study of Ministry of Water Resources Projects”, Unpublished MBA

Thesis, University of Nairobi, 1998. KPLC (2004), 2003/2004 Annual

Report and Account.

Kerzner, H. (2001) Project Management :A System Approach to Planning,

Scheduling, and Controlling (7th edition), John Wiley & Sons, Inc.

Kleinbaum, D.G., Kupper, L.L. and Muller, K.E. (1988) Applied Regression

Analysis and Other Multivariate Methods (2nd edition), PWS-KENT

Publishing Company, Boston.

Page 40: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

108

David Kagiri & Gituro Wainaina

ORSEA Journal

Kohli U. (2001) “How to Minimize Time and Cost Over-Runs of Projects”,

Available at Http://www.shilpabichitra.com/shilpa2001/v083.htm (Cited

13-August-04).

Kumaraswamy, M.M. and Chan, D.W.M (1998) ‘Contributors to

Construction Delays’, Construction Management and Economist, 16,

17-29.

Kwak, Y.H. (2002) Critical Success Factors in International

Development Project Management. ([email protected]) (online).

Long, N.D., Ogunlana, S., Quang T. and Lam, C.K. (2004) ‘Large

Construction Projects in Developing Countries: a Case Study from

Vietnam’, International Journal of Project Management, 22, 553-

561.

Manavazhi, M.R. and Adhikari, D. K. (2002) ‘Material and EEquipment

Procurement Delays in Highway Projects in Nepal’, International

Journal of Project Management, 20, 627-632.

Mansfield, N.R., Ugwu O.O., and Doran T. (1994) ‘Causes of Delay and

Cost Overruns in Nigeria Construction Projects’, International Journal

of Project Management, 12 (4), 254-260.

Mezher, T.F. and Tawil, W. (1998) ‘Causes of Delays in the Construction

Industry in Labanon’, Engineering, Construction and Architectural

Management, 3, 252-260.

Morris, S. (1990) ‘Cost and Time Overruns in Public Sector Projects’,

Economic and Political Weekly, Nov. 24, Vol. XXV, No. 47, pp. M154

-168.

Musa, G. H., “Determination of Factors Influencing Projects Delays in Water

Projects in Kenya: The Case of Government Funded Projects”,

Unpublished MBA Thesis University Of Nairobi, 1999.

Mwandali, D., “Analysis of Major Factors that Affect Projects Management:

A Case of Kenya Railways Projects”, Unpublished MBA Thesis,

University of Nairobi, 1996.

Page 41: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

109

Time and Cost Overruns in Power Projects in Kenya

Vol. 3 Issue No. 2 June 2013

Odeh, A.M., and Battaineh, H.T. (2002) ‘Causes of Construction Delay:

Traditional Contracts’, International Journal of Project Management,

20, 67-73.

Ogunlana, S.O., Promkuntong, K and Jearkjirm, V. (1996) ‘Construction

Delays in a Fast-Growing Economy: Comparing Thailand with Other

Economies’, International Journal of Project Management. Vol. 14,

No. 1, pp. 37-45.

Pillai, N.V and Kannan, K.P. (2001) ‘Time and Cost Over-runs of the Power

Projects in Kerala’, Centre for Development Studies,

Thiruvananthapuram, Working Paper No. 320 (available: www.cds.edu).

Talukhaba, A.A., “Time and Cost Performance of Construction Projects”,

Unpublished M.A. Thesis, University of Nairobi, 1988.

Youker, R. (1992) ‘Managing the International Project Environment’,

International Journal of Project Management 10, No. 4; Butterworth-

Heinemann; pp 219-226.

Page 42: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

110

David Kagiri & Gituro Wainaina

ORSEA Journal

Appendices

Appendix I: Descriptive Statistics - Variables’ Extent of Contribution

Causes of Time and

Cost Overruns N Mean

Stand ard

Deviation

Delayed payment to contractor 41 3.414634 0.805469

Employer cash flow problems 41 3.390244 0.891012

Delays in disbursement of fu nds by financiers 41 3.365854 0.968403

Bureaucracy of government agencies 41 3.268293 0.742442

Delay in getting access to site 41 2.975610 1.060373

The length of implementation of the

project 41 2.951220 1.094331

Delay in procurement of materia ls and

equipment 41 2.878049 0.927230

Inadequate planning by employer b efore commencemen t of construction 41 2.829268 0.972174

Late design changes 41 2.804878 1.054028

Delays in approval by engineer 41 2.756098 0.969033

Delays in release of d raw ings 41 2.731707 1.000610

Increased scope of work 41 2.707317 1.006079

Disputes between parties 41 2.707317 0.980915

Delay in getting access to site 41 2.682927 0.985876

Poor specifica tions in the contract 41 2.634146 1.042979

Bad re la tions with financiers 40 2.625000 1.169867

Lack of adequate professional skills of

project teams 41 2.609756 0.891012

Inadequate supervision of work 41 2.609756 1.021715

Environmenta l issues 41 2.560976 1.049971

Poor sub-contracting 41 2.560976 0.97593

Contrac tors’ lack of exper ience 41 2.560976 1.141245

Government regulations 41 2.536585 1.185276

Poor handing over 41 2.512195 0.977802

Low labour productivity 41 2.512195 0.897829

Underestimation of project duration 41 2.487805 1.164516

Poor construction methods 41 2.463415 1.097669

Page 43: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

111

Time and Cost Overruns in Power Projects in Kenya

Vol. 3 Issue No. 2 June 2013

Causes of Time and

Cost Overruns N Mean

Standard

Deviation

Unrealistic client budget 41 2.439024 1.025885

Poor communication between parties. 41 2.414634 1.094888

Complex payment process 41 2.414634 0.948040

Unexpected ground conditions 41 2.414634 0.974054

Client failure to supply information and materials 41 2.390244 0.971546

Lack of involvement by client team 41 2.390244 1.115304

Poor relations between engineer and contractor 41 2.365854 1.042979

Contractor short of equipment for work 41 2.341463 0.964618

Inadequate / Poor cost control 41 2.317073 1.010916

Escalation in cost of materials 41 2.317073 1.010916

Contractor's cash-flow problems 41 2.292683 1.167131

Exchange rate fluctuations 41 2.268293 0.949326

Inappropriate organizational structure 41 2.268293 0.895109

Project contract terms 41 2.219512 1.084255

Poor relations between engineer and contractor 41 2.195122 0.954450

Lack of motivation in all teams 41 2.170732 0.891696

Inadequate safety measures 41 2.146341 0.963353

Political interference 41 2.121951 1.029445

Lack of client top management support 40 2.100000 1.127739

Inadequate inspection of work 41 2.073171 0.932476

Labour disputes 41 2.024390 0.907959

Corruption or rent seeking 41 1.951220 1.071243

Unpredictable weather 41 1.878049 0.812254

Valid N (list-wise) 40

Page 44: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

112

David Kagiri & Gituro Wainaina

ORSEA Journal

Appendix II: Relative Importance Indices for the Variables

Variable N Sum Mean RII

Bureaucracy of government agencies 41 103 2.512195 0.837398

Delayed payment to contractor 41 101 2.463415 0.821138

Employer cash flow problems 41 99 2.414634 0.804878

Increased scope of work 41 94 2.292683 0.764228

The length of the implementation of the project 41 93 2.268293 0.756098

Delay in disbursement of funds by financiers 41 91 2.219512 0.739837

Complex interfaces of various works

packages 41 89 2.170732 0.723577

Delay in procurement of materials and

equipment 41 88 2.146341 0.715447

Inadequate planning by employer before commencement of construction 40 83 2.075000 0.691667

Escalation in cost of materials 41 85 2.073171 0.691057

Exchange rate fluctuations 40 82 2.050000 0.683333

Delay in release of drawings 41 84 2.048780 0.682927

Late design changes 41 82 2.000000 0.666667

Disputes between parties 41 81 1.975610 0.658537

Poor handing over 41 79 1.926829 0.642276

Government regulations 41 79 1.926829 0.642276

Delays in approval by engineer 41 77 1.878049 0.626016

Delays in getting access to site 41 77 1.878049 0.626016

Underestimation of project duration 41 76 1.853659 0.617886

Inadequate/poor cost control 41 74 1.804878 0.601626

Complex payment process 41 74 1.804878 0.601626

Poor sub-contracting 41 73 1.780488 0.593496

Inadequate supervision of work 41 72 1.756098 0.585366

Poor specifications in the contract 41 72 1.756098 0.585366

Poor communication between parties (e.g. engineer and contractor) 41 72 1.756098 0.585366

Page 45: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

113

Time and Cost Overruns in Power Projects in Kenya

Vol. 3 Issue No. 2 June 2013

Variable N Sum Mean RII

Contractor’s cash flow problems 41 72 1.756098 0.585366

Low labour productivity 40 70 1.750000 0.583333

Contractor’s lack of experience 41 71 1.731707 0.577236

Lack of adequate professional skills of

project teams 41 70 1.707317 0.569106

Unrealistic client budget 41 70 1.707317 0.569106

Corruption or rent seeking 41 70 1.707317 0.569106

Poor relations between engineer and

contractor 41 70 1.707317 0.569106

Poor infrastructure e.g. roads, telecommunication 41 70 1.707317 0.569106

Inadequate safety measures 41 70 1.707317 0.569106

Environmental issues 41 70 1.707317 0.569106

Inappropriate organizational structure 41 69 1.682927 0.560976

Lack of involvement by client team 41 69 1.682927 0.560976

Political interference 41 69 1.682927 0.560976

Unexpected ground conditions 40 66 1.650000 0.550000

Client failure to supply information and materials 40 65 1.625000 0.541667

Poor construction methods 41 66 1.609756 0.536585

Contractor short of equipment for work 41 66 1.609756 0.536585

Inadequate inspection of work 41 64 1.560976 0.520325

Bad relations with financiers 40 61 1.525000 0.508333

Labour disputes 41 62 1.512195 0.504065

Poor contract terms 40 58 1.450000 0.483333

Unpredictable weather 41 58 1.414634 0.471545

Lack of motivation in all teams 41 57 1.390244 0.463415

Lack of client top management support 40 54 1.350000 0.450000

Page 46: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

114

David Kagiri & Gituro Wainaina

ORSEA Journal

Appendix III: Comparison of Extent of Contribution to Frequency of

Occurrence of Variables

V ariables/Causes of

O verruns

Extent

Index

Rank RII Rank

D elayed payment to contracto r 3.41 1 0.821 2

E mployer cash flow problems 3.39 2 0.805 3

D elays in disb ursement of funds by

f inanciers

3.37 3 0.739 6

Bureaucracy of government agencies 3.27 4 0.837 1

Complex interfaces of various works

p ackages

2.98 5 0.724 7

T he length of implementation of the

p roject

2.95 6 0.756 5

D elay in procurement of materials and equipment

2.88 7 0.715 8

Inadequate planning by employer

b efore commissioning construction

2.83 8 0.691 9

Late design changes 2.80 9 0.667 13

D elays in approval b y engineer 2.76 10 0.626 17

D elays in release of drawings 2.73 11 0.683 12

Increased sco pe of work 2.71 12 0.764 4

D isputes between parties 2.71 13 0.659 14

D elay in getting access to site 2.68 14 0.626 18

Poor specif ications in the contract 2.63 15 0.585 24

Bad relations with financiers 2.63 16 0.508 44

Lack of adequate professional skills of

p roject teams

2.61 17 0.569 29

Inadequate sup ervision of work 2.61 18 0.585 23

E nvironmental issues 2.56 19 0.642 16

Poor sub-contracting 2.56 20 0.593 22

Contractor’s lack of experience 2.56 21 0.577 28

G overnment regulations 2.54 22 0.569 35

Poor handing over 2.51 23 0.624 15

Lo w labour productivity 2.51 24 0.583 27

U nderestimation o f project duration 2.49 25 0.618 19

Poor construction methods 2.46 26 0.537 41

Page 47: T ime and Cost Overruns in Power Pr ojects in Kenya: A Case … · 2019-07-16 · 69 Time and Cost Overruns in Power Projects in Kenya Vol. 3 Issue No. 2 June 2013 T ime and Cost

115

Time and Cost Overruns in Power Projects in Kenya

Vol. 3 Issue No. 2 June 2013

Variables/Causes of

Overruns

Extent

Index

Rank RII Rank

Unrealistic client budget 2.44 27 0.569 30

Poor communication between parties 2.41 28 0.585 25

Complex payment process 2.41 29 0.602 21

Unexpected ground conditions 2.41 30 0.550 39

Client failure to supply information and materials

2.39 31 0.542 40

Lack of involvement by client team 2.39 32 0.561 37

Poor relations between engineer and contractor

2.37 33 0.569 32

Contractor short of equipment for work

2.34 34 0.537 42

Inadequate/poor cost control 2.32 35 0.602 20

Escalation in cost of materials 2.32 36 0.691 10

Contractor’s cash flow problems 2.29 37 0.585 26

Exchange rate fluctuations 2.27 38 0.683 11

Inappropriate organizational structure 2.27 39 0.561 36

Project contract terms 2.22 40 0.483 46

Poor infrastructure eg. roads, telecom 2.20 41 0.569 33

Lack of motivation in all teams 2.17 42 0.463 48

Inadequate safety measures 2.15 43 0.569 34

Political interference 2.12 44 0.569 38

Lack of client top management support

2.10 45 0.450 49

Inadequate inspection of work 2.07 46 0.520 43

Labour disputes 2.02 47 0.504 45

Corruption or rent seeking 1.95 48 0.569 31

Unpredictable weather 1.88 49 0.471 47


Recommended