Sector test measurements I• SPS extraction

• MKE waveform scan• Rough aperture check if not yet done

• Establish downstream TL trajectory • Screens matching• Check BPM/corrector polarities (and optics) with kick response• Measure TL dispersion• Trajectory stability• TL aperture – redo TI 2 hor

• Threading through injection region onto closed TDI• Rough setup of TCDI, TDI, TCLI• Aperture in injection region• Orthogonal steering• MKI waveform scan (change of screen conductors, TMR aging)• MKI synchronisation• AGK synchronisation• IQC injection oscillation interlock

Page 3: SECTOR TEST PREPARATION W. Bartmann, C. Bracco, J. Uythoven LIBD Meeting, 10-Feb-2015

Sector test measurements II• Beam dump• Synchronisation• Rough check of extraction channel aperture• BTVD/BTVDD image• Test 14/15 MKD knob• MKB waveform – check with ~5 pilots• MKD waveform – never tested, procedure to be set up

Page 4: SECTOR TEST PREPARATION W. Bartmann, C. Bracco, J. Uythoven LIBD Meeting, 10-Feb-2015

Preparation• Knobs

• for TI 2 horizontal aperture measurement – Francesco• For vertical MSI aperture measurement – Francesco• For TCDI and MKI validation – Francesco• For MKD test - Matthew

• Beam positions • on injection region screens for MKI on/off – Francesco• on dump region screens – Matthew

• List of settings for• MKI max/nom voltage, MSI current - Francesco• MKD max/nom (6.5 TeV), MSE current - Matthew

• MKB/MKD waveform procedure – Matthew• Correctors for orthogonal steering in injection region - Francesco• Check rights for MKI waveform test – Wolfgang, Mike• Settings for TCDI, TDI, TCLI, TCDQ – Chiara, Wolfgang

Page 5: SECTOR TEST PREPARATION W. Bartmann, C. Bracco, J. Uythoven LIBD Meeting, 10-Feb-2015

Planning

Time What Who Duration

Friday 12 Patrol and closure. TT40/TT60 extraction OP 315 Beam down TI2, MKI pulsing OP, ABT 3

18 Beam down TI8, MKI, LHCb shots on TED OP, ABT 119 Beam 1 to TDI, to IP3 OP, ABT 5

Saturday 0 Beam 1 BI commissioning BI 33 Beam 1 kick response OP 25 LHCb TED shots, ALICE Ted shots OP 27 Beam 1 dispersion, linear optics OP, ABP, ABT 29 Beam 2 to TDI, to IP6 OP, ABT 3

12 LBDS synchro, waveform, XPOC ABT 214 Beam 2 BI commisioning BI 317 BLM latency B1 & B2 BI, MPP 219 BLM response collimator splashes B1 OP, ABP 221 Aperture IR2, S23 OP, ABP 6

Sunday 3 Beam 2 kick response OP 25 LHCb TED shots, ALICE Ted shots OP 38 Beam 2 dispersion, linear optics OP, ABP, ABT 2

10 TI2 aperture check, revisit ABT 212 Aperture MSI region Beam 1 ABT 113 Aperture MSI region Beam 2 ABT 114 MKI waveform Beam 1 ABT 115 MKI waveform Beam 2 ABT 116 Screen matching TI2 and/or TI8 ABT 218 BLM response collimator splashes B1 OP, ABP 220 Aperture IR8, S78 & S67 OP, ABP 6

Monday 2 Magnet polarity skew quads etc OP ABP 24 LHCb TED shots, ALICE Ted shots OP 48 The end

• 27th Feb – 1st March

• TI 2 aperture revisit and MKI waveform look a bit tight

• Focus on MKI waveform