Gresham-BarlowSchoolDistrictBondProjectStatusReport
SAMBARLOWHIGHSCHOOL
ProjectTitle:SamBarlowHighSchoolReconstruction/Modernization ProjectManager:JohnAbelReportingStatusDate:August15,2017 ProjectManagerPhone:503-705-4640ProjectDescription:SelectiveDemolition,NewStandardClassrooms,ScienceClassroomsandCTEClassrooms,RenovationstoExistingClassrooms,MediaCenter,Auditorium,BandandChoirClassrooms,NewBleachersandFieldsandRequiredSiteImprovements.StatusataGlance
StatusItem AsPlanned Caution Requires
Resolution
LEGEND:
Budget X Movingalongwell,nosignificantconcernsatthistime.
Schedule X Resolutionmayimpactcostorschedule.
Construction X Requiresattentionandresolution.
DesignandConstructionSchedule
DesignPhase ConstructionPhase ORIGINALESTIMATE
APPROVEDBUDGET
COSTTODATE
ESTIMATEDBUDGETVARIANCESTART FINISH START FINISH
12/2016 4/2018 4/2018 7/2020 60,900,069 CriticalIssues
1. ObtainingapprovalfromtheMultnomahCountyLandUseDepartment.2. Managementteammustbalanceprojectbudgetandscopeofwork.
SummaryStatusMilestones/deliverables/informationitemsforthisreportingperiod:
1. RevisedscheduleforDesignPhasefromOpsisArchitects2. ValueEngineeringLogfromLeaseCrutcherLewisConstruction3. RevisedConstructionSchedulefromLeaseCrutcherLewisConstruction