Gresham-BarlowSchoolDistrictBondProjectStatusReport

SAMBARLOWHIGHSCHOOL

ProjectTitle:SamBarlowHighSchoolReconstruction/Modernization ProjectManager:JohnAbelReportingStatusDate:August15,2017 ProjectManagerPhone:503-705-4640ProjectDescription:SelectiveDemolition,NewStandardClassrooms,ScienceClassroomsandCTEClassrooms,RenovationstoExistingClassrooms,MediaCenter,Auditorium,BandandChoirClassrooms,NewBleachersandFieldsandRequiredSiteImprovements.StatusataGlance

StatusItem AsPlanned Caution Requires

Resolution

LEGEND:

Budget X Movingalongwell,nosignificantconcernsatthistime.

Schedule X Resolutionmayimpactcostorschedule.

Construction X Requiresattentionandresolution.

DesignandConstructionSchedule

DesignPhase ConstructionPhase ORIGINALESTIMATE

APPROVEDBUDGET

COSTTODATE

ESTIMATEDBUDGETVARIANCESTART FINISH START FINISH

12/2016 4/2018 4/2018 7/2020 60,900,069 CriticalIssues

1. ObtainingapprovalfromtheMultnomahCountyLandUseDepartment.2. Managementteammustbalanceprojectbudgetandscopeofwork.

SummaryStatusMilestones/deliverables/informationitemsforthisreportingperiod:

1. RevisedscheduleforDesignPhasefromOpsisArchitects2. ValueEngineeringLogfromLeaseCrutcherLewisConstruction3. RevisedConstructionSchedulefromLeaseCrutcherLewisConstruction