R/V SIKULIAQUNOLS Annual Meeting 23-24 Oct 2012
R/V SIKULIAQ Anticipated Schedule
Design Verification and Transfer January to September 2010Start Fabrication October 2010Keel Laying 11 April 2011Z-drives Delivered to Shipyard December 2011Launch 13 October 2012Builder’s Trials April 2013Acceptance Trials May 2013Delivery 26 July 2013Post Delivery Dockside/Training August/September 2013Transit and Science Trials October to December 2013Ice Trials April 2014Inport and Dry-dock May 2014
Transit/science trials schedule will be entered into UNOLS ship schedule
Seward
1
3
2
Shipyard
1 Multi-beam testing off Eastern Seaboard
2 Science testing out of Puerto Rico
3 West Coast ice testing in the Bering Sea
SEAFAC