Report pursuant to s 42A Resource Management Act 1991
In the matter of: A Notice of Requirement to
construct, operate, use,
maintain and improve
approximately 11.5km of new
State Highway connection
between Ashhurst and
Woodville
And: A hearing by Manawatu District
Council, Palmerston North City
Council and Tararua District
Council pursuant to s 102
Requiring Authority: New Zealand Transport Agency
Hearing date: 25 March 2019
NJ-015652-992-521-V1:KZ-e
Section 42A Technical Evidence: Construction and Earthworks
By: Gregor Mclean
SJ-015652-992-521-V1:KZ-e
Page 3 of 19
Contents
1 Introduction ................................................................................................................................. 4
1.1 Expert Witnesses – Code Of Conduct ................................................................................ 5
2 Background and Scope of Evidence .......................................................................................... 5
2.1 Background ......................................................................................................................... 5
2.2 Scope of evidence ............................................................................................................... 6
2.3 Reports and material considered ....................................................................................... 7
2.4 Site visit ............................................................................................................................... 7
2.5 Statutory Context ................................................................................................................. 7
3 Existing Environment .................................................................................................................. 8
4 Project Effects ............................................................................................................................. 9
4.1 Construction Phase Effects ................................................................................................ 9
5 Management of Effects .......................................................................................................... 15
6 Designation .............................................................................................................................. 16
7 Review of submissions ........................................................................................................... 17
8 Draft Requirement conditions ................................................................................................. 18
9 Conclusions .............................................................................................................................. 18
SJ-015652-992-521-V1:KZ-e
Page 4 of 19
1 Introduction
1. My full name is Gregor John McLean. I hold a Bachelor of Arts (Geography/Environmental
Planning) from Massey University and a Post Graduate Diploma in Natural Resource
Management from Lincoln University. I have the status of a Certified Professional in
Erosion and Sediment Control (CPESC Number 7628).
2. I am a Director and Environmental Consultant at SouthernSkies Environmental Limited. I
have been in that position since 2003. My role involves erosion and sediment control
design, consenting and implementation, project environmental management plans,
monitoring and site auditing and development and delivery of erosion and sediment
control training.
3. I have 23 years experience in the above areas including:
a) Environmental auditing for Greater Wellington Regional Council and Auckland
Council;
b) Development and delivery of Erosion and Sediment Control training;
c) Preparation of chemical Flocculation Management Plans including soil bench
testing;
d) Independent Erosion and Sediment Control expert for the Board of Inquiry –
Transmission Gully Project and Erosion and Sediment Control expert for Mill Creek
Windfarm; and
e) Co-Author of the Erosion and Sediment Control Standard for the New Zealand
Transport Agency (August 2010) and Auckland Council Erosion and Sediment
Control Guideline (2015).
4. I have prepared this evidence on behalf of the Territorial Authorities, Palmerston North
City Council, Manawatu District Council and Tararua District Council (the “Territorial
Authorities”) in relation to the Notices of Requirement (“NOR”) for Te Ahu a Turanga –
Manawatū Tararua Highway Project (“the Project”) lodged by the New Zealand Transport
Agency (“NZTA”). I understand that my evidence will accompany the planning report being
prepared by the Territorial Authorities under s 42A of the Resource Management Act
1991 (“RMA”).
SJ-015652-992-521-V1:KZ-e
Page 5 of 19
1.1 Expert Witnesses – Code Of Conduct
5. I confirm that I have read the Code of Conduct for Expert Witnesses in the Environment
Court Practice Note 2014 and that I agree to comply with it. I confirm that I have
considered all the material facts that I am aware of that might alter or detract from the
opinions that I express, and that except where I state I am relying on information provided
by another party, the content of this evidence is within my area of expertise.
6. During the writing of this evidence I became aware that a colleague from the
SouthernSkies Auckland office was involved with a tender for the Project. I have
considered my obligations under the Code of Conduct and am satisfied that I am able to
comply. I have not had any discussions with that individual regarding the NOR and the
content of my review. For the avoidance of doubt, I reiterate that the opinions set out in
this report are my own as an independent expert witness.
2 Background and Scope of Evidence
2.1 Background
7. The Project is defined as the construction, operation, use, maintenance and improvement
of approximately 11.5km of new State Highway connection between Ashhurst and
Woodville under the RMA. This proposed new section of State Highway will replace the
indefinitely closed State Highway 3 route through the Manawatu Gorge. A detailed
description of the Project is set out in Part C of the Assessment of Environmental Effects
(“AEE”) submitted by NZTA and a summary description is set out in the s 42A Planning
Assessment.
8. The construction of the Project will generate approximately 6,000,000m3 of excavated
(cut) material (excluding topsoil). Approximately 3,800,000m3 of this cut material will be
placed as structural fill for embankments along the proposed route. The remainder of the
excess cut material (2,200,000m3) will be disposed of within the designation boundaries
either in spoil disposal sites or in landscape areas adjacent to structural embankments to
avoid the need to export material off site for disposal.
SJ-015652-992-521-V1:KZ-e
Page 6 of 19
2.2 Scope of evidence
9. I have been asked to assess the construction management elements of the NOR. My
assessment considers the following matters:
a) Key issues in contention;
b) The statutory context;
c) An overview of the existing environment in terms of the NOR corridor soils,
topography and watercourses;
d) Adequacy of NZTA’s investigations and interpretation of the findings of those
investigations;
e) Likely key effects (positive and adverse) on the environment of allowing the
Project;
f) Appropriateness of any proposed mitigation measures or monitoring;
g) Submissions relating to construction management, including erosion and
sediment control; and
h) Any other matters.
10. My evidence is focussed on construction management, specifically erosion and sediment
control, including stream works. It is acknowledged that this will be largely addressed
through the regional council consenting process. In this regard my evidence has focussed
on the effects of construction and the management of those effects within the NOR
corridor.
11. My evidence should be read in conjunction with expert evidence of the other experts that
have contributed to the s 42A Planning Assessment. In particular, the evidence of Mr
Logan Brown (Freshwater) and Mr James Lambie (Ecology) is relevant in varying ways to
the consideration of the matters that I address.
SJ-015652-992-521-V1:KZ-e
Page 7 of 19
2.3 Reports and material considered
12. As part of preparing this statement of evidence, I have read the following reports and
documents:
a) Te Ahu a Turanga; Manawatū Tararua Highway Project, Notices of
Requirement for Designations - Volume 2: Assessment of Effects on the
Environment and Supporting Material, dated 31 October 2018;
b) AEE Part J Appendix 2 – ECDF;
c) AEE Part J Appendix 3 - Preliminary Road Design Philosophy Report;
d) Technical Assessment 4 - Landscape and Natural Character;
e) Technical Assessment 4 Appendix 4.A - Natural Character Assessment;
f) Technical Assessment 6 - Terrestrial Ecology;
g) Technical Assessment 6 Appendix 6.A - Terrestrial Vegetation and Habitats;
h) Technical Assessment 6 Appendix 6.C - Freshwater report; and
i) Appendices Manawatu Gorge Alternatives Detailed Business Case Appendix I
– Preliminary Geotechnical Appraisal.
2.4 Site visit
13. I undertook a site visit on 23 November 2018 with the s 42A Reporting Team and NZTA
representatives and I am familiar with the surrounding environment.
2.5 Statutory Context
14. The relevant statutory documents and provisions relevant to the evaluation of the NOR
are set out in the s 42A Planning Assessment.
15. The statutory framework provides some guidance to managing the effects of earthworks
and management approaches in protected areas or landforms. When considering these
statutory matters, it is NZTA’s position in relation to the management of earthworks
(Section 44.11 AEE page 203) that:
SJ-015652-992-521-V1:KZ-e
Page 8 of 19
To the extent that the Project is able to respond to these provisions as part of the NORs, the
proposed designation provides:
a corridor within which a road can be constructed with acceptable effects;
adequate area to accommodate earthworks and the erosion and sediment control
measures that may be necessary to manage them;
clear design outcomes in the ECDF in relation to earthworks, slope treatments and
topsoil management; and
a management plan framework that foreshadows the implementation of an appropriate
regime for the management of effects on water resources and water bodies.
3 Existing Environment
16. Section 7.1 of the AEE (page 21) describes the topography of the NOR corridor as:
The landscape traversed by the proposed designations comprises steep hill country ranging
from 200 metres above sea level to the south and 400 metres above sea level to the north,
with deeply incised gullies that contain remnant or regenerating native vegetation and areas of
exotic scrub.
17. Section 7.2 of the AEE (page 26) describes the Landform, Geology and Natural Hazards of
the proposed designation. In particular:
The wider Project area has a complex geology, with a number of geological formations showing
contrasting geological behaviours. It is a seismically active area due to the presence of a
number of active and inactive fault lines, including the Wellington and Mohaka Faults. The
proposed designation crosses two active faults and, therefore, there is a risk of rockfall,
landslides and ground rupture as a result of a seismic event.
River flooding as a result of sustained or high intensity rainfall is the most frequent and
widespread hazard throughout the Manawatu – Whanganui Region. Significant flood events
occurred in 2004 and 2015 that impacted wide parts of the region, including the Project area.
The primary flood risk areas in the lower river system of the Manawatu River are Palmerston
North, Feilding, Foxton and Foxton Beach, while Pahi ̄atua is the primary risk area in the upper
catchment.
SJ-015652-992-521-V1:KZ-e
Page 9 of 19
The geology and terrain traversed by the proposed designation means that there is also some
risk of slips in significant storm events.
18. The Manawatu Gorge Alternatives Detailed Business Case – Appendix I - Preliminary
Geotechnical Appraisal describes Route Option 3 (Short List Option 3) as:
…most favourable when considering geotechnically risk and resilience. While it still presents
significant geotechnical complexity and risk, it is shorter and has relatively smaller exposure to
the general geotechnical risks across the site compared with the other routes.
19. The general geotechnical risks in terms of earthworks (cut faces, fill embankments,
bridges and site drainage) are described in Section 8 of that report.
20. There are eight catchments across the NOR corridor with 24 watercourses (ephemeral
and perennial) that are impacted by the construction of the road. In addition, a bridge will
traverse the Manawatu River. Technical Assessment 6 – Appendix 6C Freshwater –
Ecological Impact Assessment, provides a description of the freshwater ecological
condition and values of the sites watercourses. In some instances there are streams with
significant identified ecological values.
21. Essentially the description of the site, geotechnical condition and watercourses highlight
the complexity of the NOR corridor in terms of management of environmental effects
(temporary, short and longer term). While this will influence the detailed design and the
construction of the Project over time, they are also relevant considerations for designation
of the road corridor, and I discuss this below.
4 Project Effects
4.1 Construction Phase Effects
22. NZTA at Section 10 (page 37) of the AEE describes a broad overview of the construction
methodology and a description of the key elements of construction. At the next phase of
the Project, being the detailed design and resource consenting phase, a detailed
construction methodology will be developed by NZTA.
23. At Section 10.4 (page 40) of the AEE, NZTA outlines “Early Construction Activities -
Enabling Works” for which management plans are not considered necessary. The suite of
enabling works is quite extensive and includes “preliminary activities” like:
SJ-015652-992-521-V1:KZ-e
Page 10 of 19
a) Pre-construction site surveys;
b) Site establishment;
c) Site compounds;
d) Site access and haul roads;
e) Protection and relocation of utilities;
f) Property access;
g) Ecological surveys and relocations;
h) Te Apiti wind farm reconfiguration;
i) Vegetation clearance and protection; and
j) Erosion and sediment control.
24. In its s 92 response dated 15 January 2019 NZTA stated that:
“It is still developing the scope of enabling works that are necessary to ensure the broader
construction programme and projected opening date can be achieved, and limited in scale and
anticipated effects on the environment.”
25. NZTA anticipates that enabling works will either be authorised by separate regional
resource consents, permitted activities under relevant district planning documents, or
authorised by reference to an Outline Plan of Works.
26. I am concerned at the broad scale of the enabling works as defined by NZTA. The
potential scale of enabling works in terms of land and stream disturbance could be
extensive. I am of the opinion that any enabling works should form part of a management
plan process or at the very least, be included within conditions that require regulatory
review and certification to ensure that the effects are adequately managed within the
NOR corridor.
27. Some aspects of the works listed in the enabling works definition could also pre-
determine the outcome of other management plans, which may not be certified at this
stage. For example, the establishment of erosion and sediment control measures should
SJ-015652-992-521-V1:KZ-e
Page 11 of 19
not occur until the overarching ESCP and Site Specific/ Activity Specific ESCP’s have been
prepared and certified. For that reason I have recommended that the NOR conditions
reflect a management structure which results in oversight of the enabling works from a
construction effects perspective. The s 42A Planning Report sets out these matters
further.
28. A range of erosion and sediment control measures will need to be installed prior to
earthworks and stream works being undertaken. I expect these to be installed in
accordance with best practice. It is proposed that the contractor will prepare an Erosion
and Sediment Control Plan (“ESCP”) as part of the suite of management plans offered up
by NZTA. The ESCP is normally an overarching plan, which relies on site or activity specific
ESCPs being submitted at a later date, and prior to any earthworks taking place. This
enables specific construction activities or site areas to be addressed in detail, with
regional council and stakeholder, including contractor, input following (or at the time of)
detailed design being finalised.
29. I recommend that the overarching ESCP be provided as part of the NOR process. This
also addresses the issues with enabling works, as already detailed in this evidence. A
detailed activity or site specific ESCP can then be provided and approved prior to works
commencing, as part of the regional council consents. This should ensure adequate
erosion and sediment controls for the duration of the construction of the road, including
suitable protection for the many watercourses.
30. It is unclear from the AEE what best practice Erosion and Sediment Control Guideline /
Standard will be utilised in preparing the various management plans, however this will
form part of the regional consenting phase. It is noted that the One Plan, rule 13-6
contains an advice note with reference to the Erosion and Sediment Control Guidelines
for the Wellington Region (“Wellington Guidelines”) when referring to methods to avoid,
remedy or mitigate sediment runoff.
31. The One Plan also acknowledges that depending on where the earthwork site is located
and the extent of the earthworks, higher standards may need to be met than those set out
in the Wellington Guidelines. These could apply, for example, in construction locations
near a sensitive water body or soils with high clay content.
32. The NOR corridor environment (geology, topography and watercourses), the values of
receiving environments, and the expected duration of what will be extensive construction
SJ-015652-992-521-V1:KZ-e
Page 12 of 19
works will, in my opinion, require industry best practice erosion and sediment control to
be implemented, as secured through conditions of consent.
33. The Project requires considerable earthworks with an estimated 2,200,000m3 of excess
cut to be disposed of within the NOR corridor. This volume could however, change
(increase or decrease) as a result of detailed design, geotechnical investigations and
when responding to ground conditions during construction, requiring revised design. In
this regard the footprint of the works may also change (increase or decrease). The NOR
corridor therefore needs to be large enough to accommodate these potential changes to
design and construction methodology.
34. NZTA has indicated a number of spoil sites within the NOR corridor. I am comfortable that
there is adequate room within the designation to accommodate the excess cut material.
NZTA has indicated that the ‘proposed spoil sites’ shown on the indicative plans illustrate
areas of land for disposal considerably in excess of the area required. In particular, I note
the NZTA s 92 response (dated 15 January 2019) which states that the proposed spoil
site located at chainage 4400 to 5300 could by itself accommodate the current
estimated excess fill. The same can also be said of the spoil sites located between
chainage 11500 and 12900.
35. I do have concerns with the location of some of the spoil sites within the NOR corridor and
in particular, where they are shown to be located on the headwaters of streams. At this
stage, I have relied on the design outcomes indicated in the Environmental and Cultural
Design Framework (“ECDF”) which stipulate that the spoil sites should be designed to
minimise impacts on waterbodies.
36. However, it is important that the spoil sites are located carefully as part of detailed design
to ensure management of effects on stream systems, and specifically reclamation. In
particular, the location of the spoil sites needs to be managed to ensure that additional
streams are not reclaimed. I do not consider that the ECDF has sufficient robustness to
solely rely on that document, and I have therefore recommended a change to the
Construction Environmental Management Plan (“CEMP”) condition. This condition now
explicitly requires the location of spoil sites and the avoidance of reclamation to be
addressed as part of the CEMP.
37. The impact on vegetation, streams and wetlands from the spoil sites and temporary
works, such as construction access, could result in additional environmental effects that
SJ-015652-992-521-V1:KZ-e
Page 13 of 19
have not been considered or assessed by NZTA. I note that these concerns are shared by
Mr Brown and Mr Lambie for the Territorial Authorities.
38. NZTA have advised the Territorial Authorities in its s 92 response (dated 15 January
2019) that the impact on vegetation or wetlands does not differ depending on whether
the construction activities are temporary or permanent. For that reason NZTA do not see
a need to assess the effects of temporary or permanent works separately.
39. NZTA is correct provided that all works (including temporary works) are located within the
permanent footprint of the indicative design shown within the NOR corridor (i.e. the extent
of cut and fill shown on indicative design drawings) and avoid spoil sites being located on
the headwaters of streams.
40. For example, approximately 450 metres of stream would be covered by the earthworks
footprint in the QEII east covenant.1 In this same area its is also proposed that the
clearance of indigenous vegetation should be limited to 20 metres beyond the extent of
fill and 5 metres beyond the extent of cut.2 However, it is unclear if these extents have
considered the required space for erosion and sediment control devices.
41. To install a sediment retention pond (“SRP”) or a number of decanting earth bunds for
these works you may require up to 75 metres from the toe of fill, whereas a silt fence
(“SF”) would only require a small area of clearance. If there is not a sufficiently cleared
area below the extent of fill, less efficient devices would need to be implemented to
control the physical works.
42. In terms of efficiency a SRP can be 90% efficient3 compared to 50% for a SF. In terms of
the sediment loss and subsequent impact on the receiving environment this could
increase the potential sediment discharge to the receiving environment by 40% for the
duration of those works. This increase would have a subsequent environmental effect on
the receiving environment particularly when dealing with areas of high natural character,
such as in the case of the Eastern QEII. In those areas it is very unlikely that use of a SF,
instead of a SRP, would be best practice. Therefore the NOR corridor needs to provide
sufficient room for a SRP to be installed and maintained in these sensitive areas.
1 Technical assessment 4 - Landscape and Natural Character – Paragraph 237. 2 Technical assessment 6 Appendix 6.A - Terrestrial Vegetation and Habitats – Section 5.3.3 page 49. 3 Landcare Research July 2016, Scientific basis for erosion and sediment control practices in New Zealand.
SJ-015652-992-521-V1:KZ-e
Page 14 of 19
43. To ensure the workability of the NOR corridor in delivering a road with acceptable effects,
the effects envelope defined for vegetation clearance and stream disturbance needs to
account for these additional mitigation works. As far as I understand, for the likes of the
example above, it has not been taken account of.
44. In terms of the effects of sediment on streams, NZTA has confirmed that these have not
been assessed at this stage and that the assessment will be undertaken prior to the
lodgement of regional consents. Instead, the Freshwater Report relies on an indicative
design detail, with an envelope of scale of effect (Table 6.C.9) which excludes
construction effects.
45. Technical Assessment 6 Appendix 6.C - concludes that: “the magnitude of effect on
aquatic ecological values from erosion and sedimentation, in our experience from other
large-scale roading projects, is likely to be low against the background, even though a
substantial amount of sediment may be discharged. This is provided by a robust and
enforced erosion and sediment control plan designed and implemented to the permitted
standards outlined in section 8 of the “Erosion and Sediment Control Guidelines for the
Wellington Region” dated September 2002, as described under the Horizons One Plan”.
Section 8 of the ESC Guidelines is Forestry Operations and is an incorrect reference.
46. In the absence of any detailed freshwater ecology assessment and detail regarding works
methodologies and erosion and sediment control at this stage, I agree it is difficult to
assess the likely impacts of sediment on freshwater values. NZTA itself has recognised
however that there are a number of sites with high ecological effects (see Table 6.C.9).
These will require careful management.
47. As a matter of general principle, so long as there is adequate detail adhering to best
practice guidelines/standards within the ESCP and Site Specific ESCP’s, and all
construction works, including enabling works, are addressed, implemented and managed
through management plans, I am of the opinion that the effects of construction,
specifically sediment and dust, can be appropriately managed.
48. However, at this stage of the process it is still necessary, in my opinion, for NZTA to
establish that the NOR corridor can provide sufficient room for any best practice
mitigation to be put in place, including in difficult or vulnerable (high value) sites.
SJ-015652-992-521-V1:KZ-e
Page 15 of 19
5 Management of Effects
49. NZTA has proposed a suite of management plans to establish the environmental
requirements for the Project. The plans also provide a mechanism by which performance-
based consent conditions for the entire Project can be implemented (refer Figure 32 from
the AEE).
50. The use of management plans for large projects is common practice. There are many
examples of management plan conditions that have been imposed on large scale
infrastructure projects throughout New Zealand.
51. The CEMP provides an overarching management framework that will manage
environmental effects, which arise from the construction of the Project. The CEMP is
intended to cover all anticipated construction elements and provide details of a wide
range of matters including environmental policy, objectives and performance standards.
52. The CEMP will have a number of supporting plans including those set out in (page 164)
Table 35 of the AEE. None of those relate specifically to earthworks, sediment discharge
or stormwater run off at this stage. Instead, when referring to Figure 32 (above) these
matters / potential effects are to be addressed at the resource consenting phase through
ESCPs and (to a lesser extent) potentially the Freshwater Ecology Management Plan.
53. The CEMP and any supporting plans will require review and amendment during the life of
the Project (including as detailed design progresses) to reflect changes to activities, risks,
mitigation measures, responsibilities and management processes. The ability to make
SJ-015652-992-521-V1:KZ-e
Page 16 of 19
changes to management plans is critical to continually improving the effectiveness of the
plans and the mitigation measures that they provide. The CEMP does provide for the
ability to make changes to the CEMP, but does not give the Territorial Authorities any
visibility of this. This has been partly addressed by NZTA at condition 5(d) and condition
10(xii). The proposed amendments to this condition within the s 42A Planning Report
provide for that visibility.
54. In addition to the management plans, NZTA has prepared an ECDF. The preliminary ECDF
provides a design framework within which the design of the proposed Project will be
developed. It identifies design principles, constraints and opportunities that guide the
design of the Project. The intention of NZTA is that the ECDF will be further developed, in
consultation with stakeholders, to include design solutions that respond to designation
(and future resource consent) conditions and ultimately inform the design of the Project,
including the management plans.
55. I note that the updated ECDF (condition 11) may not derogate from the principles in the
preliminary ECDF. This means that the principles as set out in the ECDF must address all
key points (albeit on a preliminary basis) at this stage.
56. The ECDF at Section 3 Emerging Design Outcomes contains specific matters in relation to
Ecologically Sensitive areas, Earthworks / Spoil Disposal (including cut / fill batters and
topsoil), Water Bodies (Culverts / Stormwater Treatment Wetlands and Revegetation).
These will be incorporated into detailed design.
57. In my experience during the detailed design and construction phase other disciplines,
such as geotechnical design may override some of the ECDF design outcomes. For
example, during construction unexpected ground conditions may be experienced and the
design of the batter, including stabilisation would need to respond to these conditions. To
ensure resilience of the road this may result in the least preferred stabilisation techniques
such as shotcrete being used. As far as possible key environmental outcomes should be
recorded in conditions.
6 Designation
58. I have considered whether there is adequate area within the NOR corridor to
accommodate earthworks and the erosion and sediment control measures that may be
necessary to manage them. I am generally comfortable, although (as already indicated
SJ-015652-992-521-V1:KZ-e
Page 17 of 19
through one example earlier in my evidence) I have concerns about the NOR corridor
width in some areas of the proposed designation.
59. When having regard to the Indicative Alignment Plans (A01 – 09) within the AEE, the
designation width in some areas would be problematic in terms of implementing industry
best practice erosion sediment control and response to any design or construction
changes. For example at Chainage 3850 the Manawatu River Bridge is in close proximity
to the boundary; at Chainage 6650 and at Chainage 7350 the fill batter extends beyond
the southern designation boundary; and at Chainage 8050 the Te Apiti Wind Farm road
reconfiguration sits on the southern designation boundary.
60. It is understood that detailed design of the road is yet to be completed, however to enable
a design and construction response to ground condition changes, ensuring sufficient
width in the designation beyond the extent of the cuts and fills is imperative to ensure
that the earthworks and stream works can be appropriately managed. I have addressed
this point earlier in my evidence, however, I recommend these matters be addressed at
an early stage to provide certainty that the NOR corridor can accommodate necessary
erosion and sediment control measures.
7 Review of submissions
61. S295 - Royal Forest & Bird Protection Society Incorporated at paragraph 24 disagrees
with the 'Freshwater - Ecological Impact Assessment' which states that "the downstream
reaches [of the Manawatu River and its tributaries] are unlikely to be directly affected by
the Project (i.e. the activity is unlikely to diminish the natural state of the waterways".
Forest and Bird consider that works associated with the construction of the Highway (in
particular earthworks, temporary water takes, vegetation clearance, sediment and
contaminant runoff, etc.) can create a substantial direct impact on the state of these
waterways if not managed correctly and can create a lasting long-term impact, particularly
in the case of sedimentation.
62. I agree that construction works, including the proposed enabling works, can have an
adverse environmental effect on watercourses if not managed appropriately. However, I
am comfortable that industry best practice erosion and sediment controls if implemented,
coupled with appropriate monitoring, will enable likely sediment related environmental
effects to be appropriately managed. This issue would need to be further addressed
SJ-015652-992-521-V1:KZ-e
Page 18 of 19
through the management plans and through the ESCP’s. I provide comment on the
proposed conditions later in this evidence.
63. S312 – Ag Research Limited – At Section 3 Effect of proposed designation, the submitter
comments that: “in addition to the loss of the long-term phosphorus fertiliser and sheep
grazing experiment, there will also be construction effects and long-term environmental
impacts on the wider Research Station. The key concerns during construction are fugitive
dust, sediment and water runoff, emissions from construction vehicles and noise effects
on stock. These effects could alter the physical soil conditions, impact the pasture and
change the way stock graze the research blocks”.
64. As discussed above, I reiterate that provided industry best practice erosion and sediment
controls are implemented, coupled with appropriate monitoring, then the likely sediment
related environmental effects can be appropriately managed. In relation to dust, NZTA
will prepare a Construction Air Quality Management Plan, which will address dust
management from construction activities. This plan will be prepared at the resource
consent stage of the Project.
8 Draft Requirement conditions
65. The relevant conditions I have considered and made recommendations (as detailed in my
report) in respect of are:
a) Condition 5 Outline Plan or Outline Plans (Permanent Works);
b) Condition 5A – Outline Plan or Outline Plans (Enabling Works);
c) Condition 10 – Construction Environmental Management Plan; and
d) Condition 11 - Environmental and Cultural Design Framework.
9 Conclusions
66. I am concerned at the broad scale of the enabling works definition. Given the extent of
these potential works, I am of the opinion that any enabling works should form part of a
management plan process or at the very least, be included within conditions that require
regulatory review and certification to ensure that the effects are adequately managed.
SJ-015652-992-521-V1:KZ-e
Page 19 of 19
67. The location of the spoil sites needs to be managed to ensure that additional streams are
not reclaimed.
68. I consider that there is generally adequate area within the NOR corridor to accommodate
the earthworks and the erosion and sediment control measures that may be necessary to
manage them. There are some areas of specific concern regarding the corridor width
when accounting for additional mitigation works (over the effects envelope) for vegetation
clearance and stream disturbance. It is unclear whether the extent of vegetation
clearance and impact on streams have considered the required space for erosion and
sediment control devices. There needs to be sufficient width in the NOR corridor beyond
the extent of the cuts and fills to accommodate necessary mitigation measures and I
recommend this matter is addressed at an early stage.
69. Provided adequate detail adhering to best practice guidelines / standards is provided
within the ESCP and Site Specific ESCP’s, and all construction works, including enabling
works are addressed, implemented and monitored through management plans, I consider
that the effects of construction, specifically sediment and dust, can be appropriately
managed.
Gregor McLean