Page 1: RARAF Accelerator Replacement

RARAF Accelerator Replacement

• History of RARAF Van de Graaff

• Removal of Van de Graaff

• Placement and assembly of Singletron

• Comparison of accelerators

• Timeline for installation

Page 2: RARAF Accelerator Replacement

RARAF Accelerator Replacement

Van de Graaff at Brookhaven National Laboratory 1949

Page 3: RARAF Accelerator Replacement

RARAF Accelerator Replacement

Cosmotron Cosmotron injector

Page 4: RARAF Accelerator Replacement

RARAF Accelerator ReplacementVan de Graaff at BNL before move to Nevis

Page 5: RARAF Accelerator Replacement

RARAF Accelerator ReplacementVan de Graaff stored at Nevis and being positioned

Page 6: RARAF Accelerator Replacement

RARAF Accelerator ReplacementNevis 200 MeV cyclotron partially disassembled and being entombed

Page 7: RARAF Accelerator Replacement

RARAF Accelerator ReplacementVan de Graaff before removal

Page 8: RARAF Accelerator Replacement

RARAF Accelerator ReplacementRemoving charging belt (June 13)

Page 9: RARAF Accelerator Replacement

RARAF Accelerator Replacement

Page 10: RARAF Accelerator Replacement

RARAF Accelerator ReplacementRemoval of acceleration tube

Page 11: RARAF Accelerator Replacement

RARAF Accelerator Replacement

Terminal, acceleration tube and column removed

Page 12: RARAF Accelerator Replacement

RARAF Accelerator ReplacementBaseplate with column and drive motor removed

Page 13: RARAF Accelerator Replacement

RARAF Accelerator ReplacementMaking opening in rear wall

Page 14: RARAF Accelerator Replacement

RARAF Accelerator ReplacementVan de Graaff tank being removed from building

(August 2)

Page 15: RARAF Accelerator Replacement

RARAF Accelerator Replacement

Page 16: RARAF Accelerator Replacement

RARAF Accelerator Replacement

Page 17: RARAF Accelerator Replacement

RARAF Accelerator ReplacementRemoval of baseplate

Page 18: RARAF Accelerator Replacement

RARAF Accelerator Replacement

Page 19: RARAF Accelerator Replacement

RARAF Accelerator ReplacementAccelerator tank leaving Nevis

Page 20: RARAF Accelerator Replacement

RARAF Accelerator Replacement

Interior parts of the Van de Graaff being taken away by Robert Krawchuk

Page 21: RARAF Accelerator Replacement

RARAF Accelerator Replacement

Arrival of Singletron at RARAF (August 10)

Page 22: RARAF Accelerator Replacement

RARAF Accelerator Replacement

Page 23: RARAF Accelerator Replacement

RARAF Accelerator Replacement

Installation of baseplate and resonant coil tank

Page 24: RARAF Accelerator Replacement

RARAF Accelerator ReplacementHV power supply & resonator coil

Singletron, baseplate & quadrupole

Page 25: RARAF Accelerator Replacement

RARAF Accelerator Replacement

Interior of Singletron Terminal with shell removed

Page 26: RARAF Accelerator Replacement

RARAF Accelerator Replacement

Parameter Van de Graaff Singletron

Terminal Voltage (MV) 0.8 - 4.2 0.2 - 5.0

Ripple (V) ~1200 200

Proton current (μA) >150 200 (100)

He current (μA) ? 125

Charging system Belt Induction

Note: Lower x-ray radiation in Singletron due to spiral acceleration tube design

Accelerator comparison

Page 27: RARAF Accelerator Replacement

RARAF Accelerator ReplacementPrinciple of operation of a Pelletron or Van de Graaff

Page 28: RARAF Accelerator Replacement

RARAF Accelerator Replacement

Singletron resonant coil interior Interior of tank with “Dees”

Page 29: RARAF Accelerator Replacement

RARAF Accelerator Replacement

Electrodes & diode stacks with spark gaps

Page 30: RARAF Accelerator Replacement

RARAF Accelerator ReplacementRF ion source

Page 31: RARAF Accelerator Replacement

RARAF Accelerator Replacement

TASK From To

Mechanical installation (positioning, anchoring rails, etc.) 9/20 10/4

Wiring, water, ion source, function tests 10/5 10/7

Accelerator checks (open air) 10/10 10/14

INSTALLATION BREAK (1st 4 weeks over) 10/17 10/24

Tank filling and conditioning for voltage 10/25 11/2

HV test/ radiation check 11/3 11/4

Beam tests 11/7 11/11

Specification: voltage, stability, beam current 11/14 11/18

INSTALLATION BREAK (2nd 4 weeks over) 11/21 11/28

Return if necessary 11/29

Timeline for Singletron installation

Page 32: RARAF Accelerator Replacement

RARAF Accelerator Replacement

RARAF Staff

Gerhard Randers-PehrsonAlan BigelowGuy GartyGreg RossGiusseppe Schettino

HVEE staff

Arnoud TerpstraRobert Honee