Rajasurya Engineering Enterprises, a proprietary, one of the leading concern, in the field of Engineering, Detail Engineering, Mechanical, Electrical, Civil works and Erection & Commissioning of Power Plant Equipments.
Rajasurya was established in the year 1999 and today, it has grown up to a level of undertaking any challenge in to Engineering.
Rajasurya is a well knit Organization aspiring to do a cost effective, efficient and reliable business.
“Time and Quality” are the principles and this alone has been the ‘Mantra’ of our development.
Rajasurya has got its head quarters at Chennai, equipped with latest technological background, infrastructure and a healthy financial resource.
A well-trained and experienced team of engineers is the asset of Rajasurya.
Power, Petroleum and Process are the key areas in developing a nation and Rajasurya is marching firmly and successfully towards these major sectors in a remarkable way.
Our strength and facilities:
The core group consists of talented engineers supported by a panel of specialists in various disciplines.
Familiarity with ISO 9000 requirements
RAJASURYA has link-ups in to manufacturing of components and to design products.
Spacious office located in Chennai with all modern office equipment and Machinery.
Advantages working with RAJASURYA :
All our professionals have,
solid work experience with leading MNC’s in the areas of boilers and auxiliaries.
Full familiarity with ASME, BS, DIN and other international codes and standards.
Excellent contacts with Indian customers and state / central government agencies.
OUR CAPABILITIES
We offer the following Services
CONSULTANCY IN POWER PLANTS & PROCESS INDUSTRIES
Detail Engineering
Piping Layout Drawings
Piping Isometric Fabrication drawings
Structural Drawings
Platforms ,Duct Supports
Platforms, Stringer, Gangway, Railings for all platforms
Preparation of Schematic Drawings,
Instrumentation Drawings, etc.,
IN CONTRACTS:
Annual Maintenance Contracts
Heavy Pumps Erection
Electrical Works
Control Panel Erection
Control Boxes Erection, Stand Fabrication
Painting Works
Oil Guns Servicing
Hot Well Erection
Condenser Tube Renewal
Hydrogen Cooler Cleaning and Erection
Baffle Plate Fabrication
Piping System Erection
Coal and Vapour Piping Erection
Dampers Erection
Erection of WIND BOX Assembly
Erection of Fans
Erection Fuel Firing system
Erection HFO System
Main steam Supports Erection
Overhauling of Pumps
Erection of Air Pre Heater Tubes
Sea Water Pipes Re Routing
Erection of Steam Blowing Piping
HP Heater, LP Heater , Ejector, M.O. Cooler Tube Renewal and Erection
MANUFACTURING & SUPPLY
Guillotine Gates
Oil Guns for 110 MW
Tilting Spares
Coupling Bolts
Raw Coal Run back System
Oil Filters
Oil Strainer For Turbine
Semi Circular Doors for Ball Mills
Universal Coupling for Main Steam Stop valve Actuator
Water Box for 110MW Units
Water Box doors for 110MW Units
Oil Nozzle Tip
Supply of HT Studs and Nuts for control vale inter connection Pipes
Stringer Steps for Conveyor System
SS Mesh Oil Strainer
Thrust Block and Cap Nuts for Boiler Drum Man Hole Doors
Bearing Cooling Coils for 110MW Units
Modified Re Circulation Dampers for Mill Plants
Bearing Cooling Coils for M.C. Pumps
Plat form Grills for CWS System
MAJOR RESOURCES AVAILABLE WITH RAJASURYA
Sl.No.
Category No. of Persons
1. Project Managers 1
2. Deputy Project Managers 2
3. Engineers 2
4. Supervisors 4
5. Material Controller 2
6. Formen 2
7. Fitters 3
8. Qualified Welders 5
9. Grinders & Gas Cutters 5
10. Riggers 10
11. Helpers (Semi-skilled) 10
12. Khalasis 15
13. Unskilled Labours 20
Note: Additional requirement of manpower in any Category shall be arranged as per work content either locally or from other areas.
OUR MACHINERY
Sl.N
o
DESCRIPTION
QTY. IN
Nos.
1. Center Lathe 8 feet 01 No.
2. Center Lathe 12 feet 01 No.
3. Center Lathe 6 feet 01 No.
4. Radial Drilling Machine 01 No.
5. Portable Drilling Machine 01 No.
6. Metal cutting machine 01 No.
7. Shaping machine 01 No.
8. Table grinding machine 01 No.
9. Welding machine 03 Nos
10. Bug Cutting machine 01 No
11. Magnetic drilling Machine 02 Nos
Sl.No. Name of Work Work order / Letter Ref. Duration Clients Name
DESIGN ORDERS
1. Rate contract for OFF LOADING of Engineering Drawings
BHEL:PC:PUR:RC:001 Dt:16.08.2003
1 year BHEL-CHENNAI
2. Rate contract for OFF LOADING of Engineering Drawings
BHEL:PC:PUR:RC:3012 Dt:27.01.2004
1 year BHEL-CHENNAI
3. Rate contract for OFF LOADING of Engineering Drawings
PC-450-7100019295 Dt:27.07.2006
1 year BHEL-CHENNAI
4. Preparation of Isometric Drawings with Details
CNT 7386/MG-16/2799 Dt:26.06.2006
6 Months FICHTNER Consulting Engineers
( India ) P LTD.
5. Preparation of Isometric Drawings with Details
CNT 7486/MG-16/601A Dt:26.04.2007
6 Months FICHTNER Consulting Engineers
( India ) P LTD.
6. Preparation of Isometric Drawings with Details
CNT 7996/MG-16/1698 Dt:12.06.2007
6 Months FICHTNER Consulting Engineers
( India ) P LTD.
7. Preparation of Isometric Drawings with Details
327/06
Dt:14.10.2006
6 Months ANDRITZ Separation ( India ) P LTD.
8. As built drawings for Fuel firing system in unit II 60 MW at ETPS
PO/UTE/234P/UNIT-I Dt:11.11.2006 2 Months
SKODA / U-TECH
9. As built drawings for HFO Pumping Station system in unit II 60 MW at ETPS
PO/UTE/248 Dt08.05.2006 2 Months
SKODA / U-TECH
WORK ORDERS
1. Dismantling & erection of HP FLUSH Pumps
PO/ETPS/S/028 Dt:14.11.2000
1 Month SKODA EXPORT
2. Dismantling & Erection of control boxes
PO/ETPS/S/043 Dt:23.04.2001
2 Months SKODA EXPORT
3. Rectification of Baffle plates R&M K1&K2 Condenser in Unit I 60 MW at ETPS
PO/R&M/EN-1/002 Dt:20.01.2003
2 Months L&T LTD.
IN YEAR 2004
1. HOT WELL painting work at ETPS
PO/ETPS/S/215/VJ/04 Dt:26.07.2004
15 days SKODA EXPORT
2. Refurbishment of Ennore Thermal Power Station – Dismantling, Erection of Condenser K1 & K2 – Unit II 60MW at ETPS.
PO / ETPS/ 215C/02 Date :15.05.2004
2 Months SKODA / U-TECH
IN YEAR 2005
Sl.No. Name of Work Work order / Letter Ref. Duration Clients Name
1. R&M Works in condenser at Unit – IV 110MW at ETPS
PO/UTE/4346/01 Dt:18.01.2005
3 Months TNEB / U-TECH
2. Fabrication & Erection of HFO Pumping station works
PO/UTE/220/HFO/UNIT-II/01 Dt:15.04.2005
1 Month SKODA / U-TECH
3. Air Pre Heater Re Tubing Work at Unit II 60MW at ETPS
PO/UTE/223/01 Dt:14.05.2005
2 Months SKODA / U-TECH
4. Dismantling of Old Vapour Piping and Extra work at HFO Pumping station at Unit II – 60MW at ETPS
PO/UTE/226/01 Dt:21.10.2005
1 Month SKODA / U-TECH
5. Erection of COAL & VAPOUR Pipe Lines of Boiler in Unit II -60 MW at ETPS
PO/UTE/226/ERE/01 Dt:07.10.2005
1 Month SKODA / U-TECH
6. Extra Rectification works in HFO Pumping station in Unit II 60MW at ETPS
PO/UTE/220/HFO/REC/ UNIT-II/01 Dt:29.11.2005
1 Month SKODA / U-TECH
7. Fabrication & erection of Steam Blowing line in Unit II 60MW at ETPS
PO/UTE/220/SB/UNIT-II/01 Dt:25.11.2005
1 Month SKODA / U-TECH
8. Fabrication Supply of COAL & VAPOUR Pipe line of Boiler at Unit II 60 MW at ETPS
PO/UTE/226CA/01 Dt:02.12.2005
1 Month SKODA / U-TECH
9. Modification of Pipe lines at Unit II 60 MW at ETPS
PO/UTE/226CB/01 Dt:02.12.2005
1 Month SKODA / U-TECH
10. Overhauling of GUILLOTINE GATES in Unit I 60 MW at ETPS
PO/UTE/220/GU/UNIT-I/01 Dt:24.12.2005
1 Month SKODA / U-TECH
11. Overhauling of HFO PUMPING Station in Unit I 60 MW at ETSP
PO/UTE/220/HFO/OH/UNIT-I/01 Dt:24.12.2005
1 Month SKODA / U-TECH
IN YEAR 2006
Sl.No. Name of Work Work order / Letter Ref. Duration Clients Name
1. Fabrication & Erection of HFO PUMPING station Skid in Unit I 60 MW at ETPS
PO/UTE/220/HFO/UNIT-1/01 Dt:02.01.2006
1 Month SKODA / U-TECH
2. Fabrication of MS VAPOUR Pipes, MS VAPOUR Bends, & Reducers in Unit II 60 MW at ETPS
PO/UTE/4445-52/01 Dt:02.02.2006
1 Month SKODA / U-TECH
3. Dismantling work in COAL & VAPOUR Pipe lines in Unit I 60 MW at ETPS
PO/UTE/233/P/01 Dt:11.02.2006
1 Month SKODA / U-TECH
4. Fabrication & Erection of MAIN OIL COOLER Pipes, Flushing line Pipes and bend in Unit II 60 MW at ETPS
PO/UTE/236/01 Dt:08.03.2006
1 Month SKODA / U-TECH
5. Dismantling and devolution of STEAM BLOWING line in Unit II 60 MW at ETPS
PO/UTE/235SB/01 Dt:18.03.2006
1 Month SKODA / U-TECH
6. Rectification of HFO Heating Station platform & fabrication & Erection of HFO Pumping station, Return / Suction / Steam lines
PO/UTE/226/02 Dt:19.05.2006
1 Month SKODA / U-TECH
7. Fabrication of ATYP Flange for GUILLOTINE GATES of Unit I 60 MW at ETPS
PO/UTE/240/01 Dt:20.05.2006
1 Month SKODA / U-TECH
8. Air Pre Heater Re Tubing Work at Unit I 60 MW at ETPS
PO/UTE/223/02 Dt:31.05.2006
2 Months SKODA / U-TECH
9. Renewal of CONDENSER TUBES, Partition plates, condenser tubes at ETPS
PO/UTE/241 Dt:06.06.2006
1 Month SKODA / U-TECH
10. Erection of WIND BOX BURNER and Fabrication and erection of Coal and Oil Pipes of BURNER,LDO PIPES, HFO Heating station Piping
PO/UTE/245
Dt :16.06.2006
1 Month SKODA / U-TECH
11. Fabrication and erection of MS VAPOUR pipes in Unit I 60 MW at ETPS
PO/UTE/247
Dt:20.07.2006
1 Month SKODA / U-TECH
12 Fabrication of wind box BURNER Frame at Unit I 60 MW at ETPS
PO/UTE/252
Dt:25.08.2006
1 Month SKODA / U-TECH
13. Fabrication and erection of COAL & VAPOUR pipes in Unit I 60 MW at ETPS
PO/UTE/226/ERE/UNIT I
Dt:11.11.2006
1 Month SKODA / U-TECH
14.
Fabrication & erection of Steam Blowing line in Unit I 60MW at ETPS
PO/UTE/220/SB/UNIT-I
Dt:11.11.2006
1 Month SKODA / U-TECH
15. Dismantling and devolution of Steam Blowing line in
Unit I 60MW at ETPS
PO/UTE/235 SB/UNIT-IDt:11.11.2006
1 Month SKODA / U-TECH
16. Fabrication & Erection of MAIN OIL COOLER pipe flushing line pipe and bend including dismantling and normalizing
PO/UTE/236/UNIT-I Dt:11.11.2006
1 Month SKODA / U-TECH
17. Design, Fabrication & supply of Vapour pipe lines in Unit I 60 MW at ETPS
PO/UTE/215
Dt:22.11.2006
1 Month SKODA / U-TECH
18. Maching of PLATE HEAT EXCHANGERS Stay bolts
PO/UTE/250 Dt:10.10.2006
1 Month SKODA / U-TECH
IN THE YEAR 2007
1. Fabrication and erection of Coal and Vapour Piping in Unit – III 110 MW
at ETPS
PO/UTE/256
Dt:24.01.2007
1 Month TNEB/U-TECH
2. Maching of PLATE HEAT EXCHANGERS Stay bolts
1 Month TNEB/U-TECH
3. Erection of Economiser Beam cooling liles
Drum interval Exhaust piping
Feed manifold at 8.0 M Elevation
Furnace Bottom sealing Piping
Erection of HDPE Piping
Cyclone separator
Ash drain lines Membrane water wall drain and vent
PO/UTE/256A
Dt:02.02.2007
1 Month SKODA / U-TECH
4. ETPS – MM II Circle – conveyor division Attending modification works in heavy oil pipe lines of the OIL HANDLING plant
WCT.605/D.286 Dt:21.05.2007
1 Month TNEB
5. ETPS-MMI Circle – Mill plant division – Unit II Modification of vapour line – fabrication of new vapour bend removal of insulation
CE/MM-I / LT-697 Dt:14.04.2007
1 Month TNEB
IN THE YEAR 2008
1. ETPS MM II Circle –Conveyor Dn. OHP – Attending breakdown works in heavy oil & light oil systems of oil handling plant
WCT-753/D1828 Dt:01.03.2008
1 Month TNEB
2. ETPS – Mechanical maintenance – I Circle – turbine Maintenance division – 110 MW Unit V Cleaning of PLATE HEAT EXCHANGER plates with soap and acid solution re fixing the gasket with special adhesive & assembling the plates.
WCT No.1904/D.251/08 Dt:27.02.2008
1 Month TNEB
3. ETPS – Mechanical Maintenance – I Circle – Turbine Maintenance division – Fabrication of Man hole doors for Debris filters with SS Plates for unit I to V
WCT No.1896/d.225/08
Dt:15.02.2008
1 Month TNEB
4. ETPS – Mechanical Maintenance - I Circle – Turbine Maintenance division – fabrication and supply of Main steam stop valve actuator connecting link mechanism with universal coupling and erection in Unit III
WCT No.1847/D.126/08 Dt:22.01.2008
1 Month TNEB
5. ETPS – Mechanical Maintenance - I Circle – Turbine Maintenance division – Dewatering pump house 30HP Diesel engine pump – dismantling, Inspection, Reconditioning of worn out parts testing and commissioning of the 30 HP Diesel engine
WCT No.1843/D.122/08
Dt:22.01.2008
20 days TNEB
6. ETPS – Mechanical Maintenance - I Circle – Turbine Maintenance division – 110 MW Unit IV - Machining of gland box oil guard bolts and Nuts, MP Inner casing studs and nuts and LP HEATER studs and OIL SERVO lock nuts
WCT No.1829/D.82/08 Dt:14.01.2008
20 days TNEB
7. ETPS – Mechanical Maintenance - I Circle – Turbine Maintenance division – 110 MW Unit IV - TG Set machining of 60 nos seal oil pump coupling bolt 2 nos, Flanges with adapter, 5 nos, Casting studs, dummy flanges pins inner thread pins 35 nos Bolt machining etc.
WCT NO. 1828/ D. 86, Dt 14.01.08
20 days TNEB
8. ETPS – Mechanical Maintenance - I Circle – Turbine Maintenance division – 110 MW Unit IV - Reconditioning of lub oil filters machining of iylam sheet, bolt machining and coupling bolt machining.
WCT NO. 1827/ D. 85, Dt. 14.01.08
20 days TNEB
9.
ETPS – Mechanical Maintenance - I Circle –Mill Plant division – 110 MW Unit IV - Renewal/ Recondiioning of coal and vapour lines and bends providing additional strenthening plates in coal and vapour line and bends renewal of insulation work during shut down period
WCT NO 1961/ D. 435 Dt 18.04.08
20 days TNEB
10. ETPS - CWS Division - Removing, Reconditioning and Refixing of Pinion gear Shaft and assembling of gear box of cws pump No 6
WCT No-2024/D 586/08/Dt 24.06.08
20 days TNEB
11. ETPS – Mechanical maintenance – I Circle – turbine Maintenance division – 110 MW Unit V Cleaning of PLATE HEAT EXCHANGER plates with soap and acid solution re fixing the gasket with special adhesive & assembling the plates.
WCT No.4930/D.943/08 Dt.06.11.2008
30 days TNEB
IN THE YEAR 2007
12. ETPS – Mechanical maintenance – I Circle – turbine Maintenance division – 110 MW Unit IV Positioning of Debris filter flab at a time intervals and online removal of debris chocked in the debris filters in 110 MW Unit IV
WCT No.2223/D.55/09
Dt:28.01.2009
20 days TNEB
SUPPLY ORDERS
1. Supply of coupling bolt and nuts for cooling water main pumps. LP & HP Flush water pumps
PO NO. 07 S.178 D.1596/ Dt 01.12.07
2 Months TNEB
2. Supply of HT studs and nuts for control valves inter connection pipes
PO NO. 07 S.134 D.1576/ Dt 05.09.07
2 Months TNEB
3. Supply of stringer steps of JT 5 PO NO.2007 S. 161 D. 1463/ Dt 12.11.07
2 Months TNEB
4. Supply of SS Mesh oil Strainer PO NO.2007 S. 182 D. 1632/ Dt 13.12.07
2 Months TNEB
IN THE YEAR 2007
1. Supply of semi circular door PO NO. 2008 S. 71 D. 175/ Dt 05.02.08
2 Months TNEB
2. Supply of Capnut and Thrust block for drum manhole doors in unit iii and iv (110MW)
PO NO. 2008 S. 06 D. 38 Dt 14.01.08
2 Months TNEB
3. Supply of Bearing and cooling coil for110 mW unit for soft water pump
PO NO. 2008 S. 94 D. 241 Dt 08.02.08
2 Months TNEB
4. Supply of main steam stop valve actuator connector with universal coupling for 110MW
PO NO. 2008 S. 44 D. 257 Dt 17.03.08
2 Months TNEB
5. Fabrication and supply of modified recirculation flap valve for vapour fans 60 MW with self lubricating
PO NO. 2008 - 212 D. 367 Dt 23.04.08
2 Months TNEB
6. Supply of MC Pump bearing and cooling coil
P.O NO. 2008 - S - 90 D - 803/08. Dt 13.05.08
2 Months TNEB
7. Supply of M.S Fabricated platform grills
P.O.No.2008 - 275 D - 452/08.Dt 23.05.08
3 Months TNEB
8. SS guide Roller with Bracket Pin and bush for travelling water
ETPS - CWS Specn No 2238/ PO No 2008 423/D 556/08 /DT 03.07.08
3 Months TNEB
9. Design fabrication supply and erection of WATER CHAMBER for K1 & K2 Condenser Unit V 110 MW
6 Months
IN THE YEAR 2008
1. Fabrication, Supply errection with supporting and commissioning of silenser for CBD with vent and drain arrangement for unit iv ( 110 MW ) Boiler
P.O.No.2009- 06 D050/09 Dt.17.01.09
2 Months TNEB
2. Supply of Ignitor guide tube assembly for Unit V 110 MW - boiler filter for unit V 110 MW Boiler
P.O.No.2009- 40 D126/09 Dt.05.01.09
2 Months TNEB
OUR VALUED CUSTOMERS :
1. BHEL – CHENNAI
2. TAMILNADU ELECTRICITY BOARD
3. M/s. SKODA EXPORT
CHENNAI-600 057
4. M/s ALSTOM POWER INDIA LTD
CHENNAI-600 018
5. M/s. LARSON TOUBRO LIMITED
CHENNAI- 600 057
6. U-TECH CONSULTANTS & ENGINEERS P LTD CHENNAI-06
7. FICHTNER Consulting Engineers ( India ) P LTD.
8. ANDRITZ Separation ( India ) P LTD.
9. M/s. RADHA ENGINEERING P LTD
CHENNAI-600 057
10. M/s.KUMARAN ENGINEERING WORKS
CHENNAI-600 057
PHATO GALLERY
RE TUBING OF PLATE HEAT EXCHANGERS FOR UNIT IV 110 MW ETPS
BURNER ASSEMBLY ERECTION UNIT I - 60 MW ETPS
BURNER ASSEMBLY ERECTION UNIT I - 60 MW ETPS
TUBE CLEANING FOR AIR PRE HEATER UNIT I -60 MW ETPS
RE TUBING OF PLATE HEAT EXCHANGERS UNIT IV 110 MW ETPS
TUBLAR AIR PRE HEATER POOJA WITH SKODA EXPORT OFFICALS
MODIFIED RE CIRCULATION DAMPER ASSY. FOR UNIT III&IV 110MW ETPS
COLD AIR CONTROL DAMPER ASSY. FOR UNIT III&IV 110MW ETPS
HOT AIR CONTROL DAMPER ASSY. FOR UNIT III&IV 110MW ETPS
HOT AIR CONTROL DAMPER ASSY. FOR UNIT III&IV 110MW ETPS
HOT AIR CONTROL DAMPER ASSY. FOR UNIT III&IV 110MW ETPS
HOT AIR CONTROL DAMPER ASSY. FOR UNIT III&IV 110MW ETPS
DURING LOYDS INSPECTION GROUP INSPECTING WATER CHAMBER UNTI V 110 MW ETPS
DURING LOYDS INSPECTION GROUP INSPECTING WATER CHAMBER UNTI V 110 MW ETPS
DURING LOYDS INSPECTION GROUP INSPECTING WATER CHAMBER UNTI V 110 MW ETPS
DURING LOYDS INSPECTION GROUP INSPECTING WATER CHAMBER UNTI V 110 MW ETPS
DURING LOYDS INSPECTION GROUP INSPECTING WATER CHAMBER UNTI V 110 MW ETPS
DURING LOYDS INSPECTION GROUP INSPECTING WATER CHAMBER UNTI V 110 MW ETPS
WATER CHAMBER
MACHINING OF STAY BOLT FOR CONENSER ETPS
OIL GUN SPARES FOR UNIT V 110 MW ETPS
FRONT WATER CHAMBER FOR 110 MW
FABRICATION OF SHED TRESS WORK IN OUR FACTORY
FABRICATION OF SHED TRESS WORK IN OUR FACTORY
FABRICATION OF SHED TRESS WORK IN OUR FACTORY
FABRICATION OF SHED TRESS WORK IN OUR FACTORY
FABRICATION OF SHED TRESS WORK IN OUR FACTORY
ARM FOR WATER CHAMBER
REAR WATER CHAMBER
BRACKET ASSEMBLY
DURING POOJA FOR COMPLETION OF WATER CHAMBER
OUR WORK SHOP
WATER CHAMBER DOOR FOR UNIT V 110 MW
FABRICATION OF SHED TRESS WORK IN OUR FACTORY
DURING TNEB OFFICAL INSPECTION
DURING HYDRO TEST TNEB OFFICAL INSPECTION
OUR MACHINIRIES
RAW COAL RUN BACK SYATEM FOR CONVEYOR - 29
DURING DNV INSPECTION LOW PRESSURE HEAT EXCHANGERS
WATER CHAMBER FOR UNIT V 110 MW
GUILLOTINE GATE SPARES
DURING THE ERECTION OF COAL AND VAPOUR PIPES AND BENDS
MITRE BENDS FOR COAL AND VAPOUR PIPING
MITRE BEND PREPARATION
BEARING COOLING COIL FOR BOILER FEED PUMPS
MANUFACTURING GRILLS FOR ENNORE THERMAL POWER STATION
DURING THE PLATE CUTTING
P.A.FAN LAYOUT MARKING AND INSPECTION WITH TNEB OFFICALS
P.A.FAN LAYOUT CUTTING
P.A.FAN PRE - ASSEMBLY INSPECTION WITH TNEB OFFICALS
P.A.FAN CASING
P.A.FAN CASING
P.A.FAN CASING
DURING ASSEMBLY OF DIFFUSER MOUTH PIECE FOR P.A.FAN
DURING ASSEMBLY OF DIFFUSER MOUTH PIECE FOR P.A.FAN
AFTER WELDING DIFFUSER MOUTH PIECE FOR P.A.FAN
AFTER WELDING SUCTION BRANCH FOR P.A.FAN
DURING FULL ASSEMBLY OF P.A.FAN
DURING FULL ASSEMBLY OF P.A.FAN AND LOYDS INSPECTION GROUP INSPECTING THE ASSEMBLY
AFTER WELDING DIFFUSER MOUTH PIECE FOR P.A.FA
DURING FULL ASSEMBLY OF P.A.FAN
DURING FULL ASSEMBLY OF P.A.FAN