Transcript
Page 1: Project Horoscope V5€¦ · Critical Path Length Index Critical Path Length+CriticalPath Total Float CPI Cost Performance Index Budgeted cost work performed EV Critical path length

Project Horoscope Project Horoscope or PM or PM HorrorscopeHorrorscopeor PM or PM HorrorscopeHorrorscope

Page 2: Project Horoscope V5€¦ · Critical Path Length Index Critical Path Length+CriticalPath Total Float CPI Cost Performance Index Budgeted cost work performed EV Critical path length

• Face reading: by means of variations in face and head shape.

• Onomancy: by names.

• Clairvoyance: by spiritual vision or inner sight

• Necromancy: by the dead, or by spirits or souls of the dead.

• Parrot astrology: by parakeets picking up fortune cards

• Numerology: by numbers.

• Spirit board: by planchette or talking board

• Palmistry : foretelling the future through the study of the palm

• Horary astrology: an astrologer attempts to answer a question

by constructing a horoscope for the exact time at which the

question was received and understood by the astrologer.

What we practice (Sub) consciously

Fortune Telling Methods

Page 3: Project Horoscope V5€¦ · Critical Path Length Index Critical Path Length+CriticalPath Total Float CPI Cost Performance Index Budgeted cost work performed EV Critical path length

Fortune Telling

Page 4: Project Horoscope V5€¦ · Critical Path Length Index Critical Path Length+CriticalPath Total Float CPI Cost Performance Index Budgeted cost work performed EV Critical path length

Fortune Teller and his Parrot

Project Manager

Team Member(s)

Artifacts & Supporting Slides

Page 5: Project Horoscope V5€¦ · Critical Path Length Index Critical Path Length+CriticalPath Total Float CPI Cost Performance Index Budgeted cost work performed EV Critical path length

Project Status

What is shown to client

Project Review

Page 6: Project Horoscope V5€¦ · Critical Path Length Index Critical Path Length+CriticalPath Total Float CPI Cost Performance Index Budgeted cost work performed EV Critical path length

After the Review

Project Manager

Team Member(s)

After the Review

Page 7: Project Horoscope V5€¦ · Critical Path Length Index Critical Path Length+CriticalPath Total Float CPI Cost Performance Index Budgeted cost work performed EV Critical path length

If If so, where does it take so, where does it take us?us?

Answer: to Answer: to the places where we don’t want to the places where we don’t want to gogo

Is it “Jungle Is it “Jungle meinmein

MangalMangal” ” attitude?attitude?

Projects are “on

time every time”

till declared as delayed

Project costs are “always within budget” till we have nothing to

exhaust

Don’t fear failure but transparency

Lesson learnt to wait till next

project to implement, not

now

Project Fundamentals

Page 8: Project Horoscope V5€¦ · Critical Path Length Index Critical Path Length+CriticalPath Total Float CPI Cost Performance Index Budgeted cost work performed EV Critical path length

Statutory Warning

Judgement based on perception kills

Management decision out of mere judgement

is detrimental to both project and organization

&

Page 9: Project Horoscope V5€¦ · Critical Path Length Index Critical Path Length+CriticalPath Total Float CPI Cost Performance Index Budgeted cost work performed EV Critical path length

Astrology

� movements and relative positions of celestial bodies interpreted

as having an influence on human affairs and the natural world.

PM Astrology

� relative position of various indices is believed to have influence

on project outcome.

Towards Measurement >> Judgement >> Management

Project Management & Astrology

Page 10: Project Horoscope V5€¦ · Critical Path Length Index Critical Path Length+CriticalPath Total Float CPI Cost Performance Index Budgeted cost work performed EV Critical path length

Predictive Measures in ProjectsPredictive Measures in Projects

Source: National Defense Industry Association(NDIA) Predictive Measures Guide 2014.

S.No Metrics Category # of Metrics

1 Schedule Metrics 8

2 Cost Metrics 3

3 Staffing Metrics 3

4 Risk and Opportunity Metrics 4

5 Requirement Metrics 4

6 Technical Performance Measures 3

7 Contract Health Metric 6

8 Supply Chain Metrics 4

Total Metrics 35

Page 11: Project Horoscope V5€¦ · Critical Path Length Index Critical Path Length+CriticalPath Total Float CPI Cost Performance Index Budgeted cost work performed EV Critical path length

Schedule & Cost Metrics

1. SPI : Schedule Performance Index

2. SPI(t) : Time based Schedule Performance Index

3. TSPI : To complete Schedule Performance Index

4. BEI : Baseline Execution Index

5. BEI(Start) : Baseline Execution Index - Start

6. CEI : Current Execution Index

7. CPLI : Critical Path Length Index

8. CPI : Cost Performance Index

9. TCPI(EAC) : To Complete Cost Performance Index

Page 12: Project Horoscope V5€¦ · Critical Path Length Index Critical Path Length+CriticalPath Total Float CPI Cost Performance Index Budgeted cost work performed EV Critical path length

BEIBaseline Execution

Index# tasks actually completed

SPI Schedule

Performance

Index

Budgeted Cost work performed (BCWP) EV

# tasks planned to be completed Budgeted Cost work scheduled (BCWS) PV

BEI(start) Baseline Execution

Index (start)

# tasks actually started SPI(t)

Time based SPI

Earned Schedule ES

# tasks planned to have started Actual Duration AD

CPLICritical Path Length

Index

Critical Path Length+Critical Path Total Float

CPI Cost

Performance

Index

Budgeted cost work performed EV

Critical path length Actual cost work performed AC

CEICurrent Execution

Index

# tasks actually completed during the windowTCPI (EAC)

To complete

CPI(Estimate at

completion)

Budget at completion (BAC) -BCWP

# of tasks previously forecasted to complete

during a defined window

Estimate at completion (EAC)-ACWP

TSPI (ED)

To complete-SPI

Estimated Duration

Time planned to go from current BCWP to BAC PDWR

Time we are now forecasting to do it in RD

Schedule Metrics EV/ES Metrics

Critical Path Length Index - CPLI

Earned Schedule / To Complete Schedule Performance Index

Page 13: Project Horoscope V5€¦ · Critical Path Length Index Critical Path Length+CriticalPath Total Float CPI Cost Performance Index Budgeted cost work performed EV Critical path length

ScheduleScheduleEV/ESEV/ES

0.70

0.85

0.95

0.70

0.85

0.95

1.00 >1.00 1.00

0.500.50 0.00

CPLI = 1.00TCPIEAC = 1.00

PROJECT HOROSCOPE

@ START DATE

TSPI(ed) = 1.00

Start – 01 Feb 2015

Finish – 30 Jul 2016

BAC - 218Cr

EAC – 218Cr

Plan-0.00% Actual-0.00%

Courtesy:

M/s. Karle Infra

SPIt = N.A

SPI =N.A

CPI = N.A CEI =N.A

BEIs = N.A

BEI = N.A

Page 14: Project Horoscope V5€¦ · Critical Path Length Index Critical Path Length+CriticalPath Total Float CPI Cost Performance Index Budgeted cost work performed EV Critical path length

13.49%

29.81%

Performance issues.• Midcourse change in design had cascading

effect

• MEP contractor appointment delayed due to

above

• Civil contractor delivery efficiency is poor

• Procurement – Value for money >> delayed

key packages ordering

8.82%

19.83%

Status @ 20% Planned Completion

(7 Months from Start)

Page 15: Project Horoscope V5€¦ · Critical Path Length Index Critical Path Length+CriticalPath Total Float CPI Cost Performance Index Budgeted cost work performed EV Critical path length

ScheduleScheduleEV/ESEV/ES

0.70

0.85

0.95

0.70

0.85

0.95

1.0 >1.10 1.0

0.500.50 0.00

CPLI = 0.83

Status @ 20% Planned Completion

(7 Months from Start)

SPI = 0.44 BEI = 0.51BEIS = 0.50

CEI = 0.33SPIt = 0.70

TCPIEAC = 1.04CPI = 0.98

TSPI(ed) = 0.98

Start – 01 Feb 2015

Forecast – 08 Oct 2016

BAC - 218Cr

EAC – 210Cr

Plan-19.8% Actual-8.82%

Courtesy:

M/s. Karle Infra

Page 16: Project Horoscope V5€¦ · Critical Path Length Index Critical Path Length+CriticalPath Total Float CPI Cost Performance Index Budgeted cost work performed EV Critical path length

Performance issues.• Procurement of natural stone enormous

delay.

• Delay of DG delivery due to change in SEZ

rules.

• Interior commencement delayed due to

enormous delay in supply of material

• Delay in civil activities (Critical path)

delayed all subsequent activity completion

• Façade work package revisited in the

midcourse. – Derisking strategy

98.01%

70.67%

SPI – 0.72

SPIt - 0.72

Status after 16 Months of the

Project

Page 17: Project Horoscope V5€¦ · Critical Path Length Index Critical Path Length+CriticalPath Total Float CPI Cost Performance Index Budgeted cost work performed EV Critical path length

ScheduleScheduleEV/ESEV/ES

0.70

0.85

0.95

0.70

0.85

0.95

1.0 >1.10 1.0

0.500.50 0.00

CPLI = 0.30

Status after 16 Months of the

Project

SPI = 0.72

BEI = 0.49

BEIS = 0.55

CEI = 0.02

TCPIEAC = 1.21

CPI = 1.01

SPIt = 0.72

TSPI(ed) = 0.92

Start – 01 Feb 2015

Forecast – 31 Dec 2016

BAC - 218Cr

EAC – 207Cr

Plan-98.00% Actual-70.67%

Courtesy:

M/s. Karle Infra

Page 18: Project Horoscope V5€¦ · Critical Path Length Index Critical Path Length+CriticalPath Total Float CPI Cost Performance Index Budgeted cost work performed EV Critical path length

Let the dog wag it’s tail,

not the tail wag the dog

We should control projects, not have projects control us

Page 19: Project Horoscope V5€¦ · Critical Path Length Index Critical Path Length+CriticalPath Total Float CPI Cost Performance Index Budgeted cost work performed EV Critical path length

Cell: +91 – 97415 96853, +91 – 99000 60178

Email: [email protected]

Thank YouThank You

Page 20: Project Horoscope V5€¦ · Critical Path Length Index Critical Path Length+CriticalPath Total Float CPI Cost Performance Index Budgeted cost work performed EV Critical path length
Page 21: Project Horoscope V5€¦ · Critical Path Length Index Critical Path Length+CriticalPath Total Float CPI Cost Performance Index Budgeted cost work performed EV Critical path length

Sponsored in India by

www.aacei.org | [email protected] | [email protected]