Transcript
Page 1: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

Project CPM Scheduling Fundamentals

October 25, 2017October 25, 2017 1

Page 2: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

October 25, 2017 2

Presented to:

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCEby Department of General Services & PMI, Montgomery County Chapter

Presented by:

Page 3: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

Agenda

October 25, 2017 3

I. Introduction – Back to Basics

II. Development of the Schedule

III. Basic Scheduling Computations

IV. Practical Applications

V. Delay Analysis

VI. Communicating Complex Analyses To The Non-technical Audience

Page 4: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

• Schedule−A plan of procedure listing the sequence of events and the time allotted

for each. 1−Time sequence of activities and events. 2

• Scheduling−To make a schedule. 3

07-APR-16 4

1 Webster’s Dictionary – ISBN 0-345-40095-X2 The Contractors’ Dictionary – ISBN 0-471-11523-13 Webster’s Dictionary – ISBN 0-345-40095-X

Page 5: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

• Planning−The process of preparing for the commitment of resources in the most

effective fashion.−Planning can be thought of as determining “what” is going to be done,

“how,” “where,” and by “whom.”− In Scheduling, this information is needed in order to determine “when.” 4

07-APR-16 5

4 Construction Planning and Scheduling – ISBN 13: 978-0-13-247398-9

Page 6: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

• Estimating−To form an approximate judgement regarding the worth, amount, size,

etc. 5− “To determine the probable cost of the project, construction estimates

are prepared before a project is constructed. Thus, an estimate is, at best, a close approximation of the actual cost.” 6

07-APR-16 6

5 Webster’s Dictionary – ISBN 0-345-40095-X6 Construction Planning and Scheduling – ISBN 13: 978-0-13-247398-9

Page 7: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

• Estimating− “The soundness of the completed estimate depends on the following

two factors: (1) the accuracy of the quantity take-off and (2) the judicious selection of the unit costs and production rates to be used.” 7

07-APR-16 7

7 Construction Planning and Scheduling – ISBN 13: 978-0-13-247398-9

Page 8: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 8

“inextricably related”

“an iterative process”Plan

Schedule

Estimate

Page 9: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. IntroductionHumpty Dumpty Syndrome

07-APR-16 9

• Design−Plans and Specifications

• Estimate

• Schedule

Cost Code

Schedule Activity

Project

Page 10: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. IntroductionHumpty Dumpty Syndrome

07-APR-16 10

• Design−Plans and Specifications

• Estimate

• Schedule

Project

Cost Code

Project

Schedule Activity

Page 11: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. IntroductionHumpty Dumpty Syndrome

07-APR-16 11

• Design−Plans and Specifications

• Estimate

• Schedule

Project

Cost Code

Project

Schedule Activity

Page 12: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

• Scheduling• Planning• Estimating

3 inextricably related terms in Project Management

3 different functions

07-APR-16 12

Page 13: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. IntroductionThe Schedule

July 19, 2016 13

• What is the purpose of a Construction Schedule?− “When used properly, the project schedule is effective in project

management, analysis, control, and overall performance, not just as a device for telling subcontractors where to move their workforces.”

− “Network-Based project management methodology (Schedule) is a dynamic planning and control procedure.”

Page 14: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. IntroductionBasics and Definitions

July 19, 2016 14

• Planning and Scheduling−Different−Distinction in Construction Management/Scheduling Planning – What, how, where, and by whom Scheduling – When

−Need Planning first to develop a schedule

Page 15: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. IntroductionBasics and Definitions

July 19, 2016 15

• Major objective of project planning−Completely define all work required If project well understood, easier to plan Not well understood -> changes in resource allocation, schedule, budget, etc. Risk is scope not well defined at beginning

Page 16: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. IntroductionProject(s)

July 19, 2016 16

• A project is a set of tasks or activities related to the achievement of some planned objective, where that planned objective is normally unique.

Page 17: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. IntroductionProject(s)

July 19, 2016 17

Every Project is Unique

Page 18: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. IntroductionProject(s)

July 19, 2016 18

• Projects are− Finite−Complex−Homogeneous−Non-repetitive

Page 19: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. IntroductionProject(s)

July 19, 2016 19

• Finite− Specific definable beginning and end point−End point = all project goals are met

Page 20: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. IntroductionProject(s)

July 19, 2016 20

• Complex−A “non-trivial” number of activities−Concurrent/success and uses resources

• Activity−A unique unit of the project which can be described within prescribed

limits of time.−Any portion of a project which consumes resources and has a definable

beginning and ending.

Page 21: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. IntroductionProject(s)

July 19, 2016 21

• Homogeneous−Activities “belong” to the project.

Page 22: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. IntroductionProject(s)

July 19, 2016 22

• Non-repetitive−Unique

Page 23: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 23

• Activity−A unique unit of the project which can be described within prescribed

limits of time.−Any portion of a project which consumes resources and has a definable

beginning and ending.

Page 24: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 24

• Types of Activities−Production−Procurement−Management Decisions

Page 25: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 25

• Responsibility for Activities−Contractor−Owner−Designer−3rd Party

Page 26: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 26

• Critical Path−Many definitions…most are incomplete.

−The critical path is the ________ path to a point in the Schedule (usually the end). Shortest? Longest?

longest

Page 27: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. IntroductionHistorical Development of Construction Schedules

07-APR-16 27

• Early forms of scheduling date back over 3000 years to the construction of Egyptian pyramids.

• 1765: Joseph Priestley first developed the bar chart to plot the lifetimes of various famous people.

• 1759-1823: William Playfair is the first to develop a range of statistical charts including line, bar, and pie charts.

• 1896: Polish researcher Karol Adamiecki developed the Harmonygraph (Harmonogram).

Page 28: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. IntroductionHistorical Development of Construction Schedules

07-APR-16 28

• 1910’s: Henry L. Gantt developed the Gantt Chart.− Similar to the Harmonygraph, but more accessible and versatile

• 1950’s: Network-Based Scheduling Methodologies.−3 Developments Central Electricity Generating Board, Great Britain (1957-1960) Polaris Missile Project (1958) DuPont Company (1956-1959)

Page 29: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 29

• CPM: Critical Path Method−Developed by DuPont & Remington Rand Univac−Activity durations are “fixed” / “deterministic”−Objective to determine how best to reduce the time required to perform

plant overhaul

Page 30: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 30

• CPM: Critical Path Method − Involves both a graphical portrayal of the interrelationships among the

elements of a project (activities), and an arithmetic procedure which identifies the relative importance of each element (activity) in the overall schedule.

− “Importance” with respect to timely completion.

Network

Page 31: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 31

• PERT: Program Evaluation and Review Technique−Developed by US Navy & Booz Allen Hamilton− Includes uncertainty in calculations (optimistic time, pessimistic time,

and mostly likely time)−Developed for schedules contacting activities with uncertain durations−Probabilistic method−Requires more technical understanding than CPM

Page 32: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 32

• Construction Industry−Utilizes CPM almost exclusively−Recent trends towards risk analysis in CPM

Page 33: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 33

• Historical Development of Construction Schedules−Three “Generations”

Page 34: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 34

• Generation 1−Bar Charts−Harmonygraphs− Intuition/Experience 1950

• Generation 2−Network Based Schedule Methods−Graphical and Mathematical Procedure 1990

• Generation 3−Expansion of Logic

Page 35: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 35

• Elements of a Construction Schedule−Activities− and how they are connected Logic

Page 36: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 36

• Fundamental Activity Attributes−Description – Name that provides insight into scope/location.−Activity ID – Used by computer to recognize activities.−Duration – An estimate of the time required to complete the scope of

work included in the activity.− Logic – Defines the relationship between/among the activities.− Float

Page 37: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 37

• Float−What is float? Measure of that “relative importance” discussed earlier. Measure of an Activity’s flexibility with respect to when it is performed. More later…

Page 38: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 38

• Logic− Simple Precedence What has to be completed before the Activity can start?

• Predecessor(s) What activities can not start until the Activity is finished?

• Successor(s)

Page 39: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 39

Predecessor(s) Successor(s)

Activity

Page 40: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 40

• Network-Based Schedules (CPM)−Consists of 2 main components

1. Network – a graphical portrayal of the plan for carrying out the work (schedule) showing the dependency relationship among the project activities.

2. Arithmetic Procedure (Scheduling Computations) – an algorithm is applied, based on network logic, to determine how long the project is expected to take and when each activity may be scheduled.

Page 41: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 41

• Software−Microsoft Project−Primavera – By Oracle (P6 Professional)*

Page 42: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 42

• Primavera ConventionsMidnight

By convention, all activities start 1 click

after midnight

By convention, all activities end 1 click

before midnight

Midnight

Day X

Page 43: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 43

• If A ends on day 4, when can B start?

A B C4 5

AB

CDay 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day 10 Day 11 Day 12

Page 44: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 44

• When can C start?

• If C’s duration is 3 days, when will C finish?

AC D

47

B 69

Page 45: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 45

• Arithmetic Procedure− Forward Pass Beginning at a specified project start time, proceed sequentially from the

beginning to the end of the project giving the earliest (expected) start and finish times for each activity.

−Backward Pass Beginning at the end of the project, proceed sequentially from the end to the

beginning of the project giving the latest allowable start and finish times for each activity. 8

8 Project Management with CPM, PERT and Precedence Diagraming – ISBN 0-960-63448-7

Page 46: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 46

• The Forward Pass answers the question: −When can this activity start?

• The Backward Pass answers the question:−When must this activity finish?

(earliest time)

(latest time)

Page 47: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 47

• Forward Pass−Early Start (ES)−Early Finish (EF)−Project Duration

• Backward Pass− Late Start (LS)− Late Finish (LF)− Float

Critical Path

Page 48: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

• The Four (4) Activity Times

• Float = LS-ES or LF-EF

I. Introduction

07-APR-16 48

Activity X

Duration

ES EF LS LF

Activity X

Duration

Time Availableor Period of Performance

Page 49: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

• What if?

• Float = 0

I. Introduction

07-APR-16 49

Activity X

ES EF

LS LF

Activity X

Page 50: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 50

• Generation 3 – Network Based Schedules (CPM)−The real world, today

−Graphic Utilizes Activity-On-Node Diagrams

−Arithmetic Procedure Based on enhanced logic

Activity A Activity B Activity C

Page 51: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 51

• Primavera Conventions

Activity

Left Side“Start”

Right Side“Finish”

Arrows used to show logical connection

Page 52: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 52

• Primavera Convention

ES EFTFODRD

LFLS

ACT ID

ACT DES

Page 53: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 53

• Generation 3−Enhanced / Additional Logic Finish-Start (FS) (simple precedence – 1st generation) Start-Start (SS) Finish-Finish (FF)

Lag

Page 54: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 54

* Simple Precedence

A

B

FS=0*

Time

A BFS

A

B

FS=3

Time

Page 55: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 55

A BSS

A

B

SS=0

Time

A

B

SS=2

Time

Page 56: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 56

A BFF

A

B

FF=0

Time

A

B

FF=4

Time

Page 57: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 57

• Categories of Schedules−As-Planned (aka. Baseline or Initial)−Updated−Refined− “As-Built”

Page 58: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

I. Introduction

07-APR-16 58

• A CPM Construction Schedule is a model of how the project is planned to be built.

• “Project is to be constructed in accordance with the Schedule.”

Page 59: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

II. Development of the Schedule

07-APR-16 59

Page 60: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

II. Development of the Schedule

07-APR-16 60

• Identify Contractual Requirements (e.g., required finish date)• Break the project down into activities (Activity List)• Develop Logic between/among activities

−Determine Predecessors/Successors−Determine relationship types−Determine lag values

• Develop Network

Page 61: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

II. Development of the Schedule

07-APR-16 61

• Estimate Original Durations (based on Planning/Estimating Assumptions)

• Add durations to Network (Network + Durations = Schedule)• Perform Scheduling Computations

− Forward Pass−Backward Pass

• Time/Cost Tradeoff (iterative process to meet contractual requirements)

Page 62: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

II. Development of the Schedule

07-APR-16 62

• “Scheduling Computations”

• “Calculating the Schedule”

• “Schedule”

Perform Forward and Backward Pass

Page 63: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

II. Development of the Schedule

July 19, 2016 63

• Dynamic network-basedplanning and control procedures

Page 64: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

Sele

ct P

rofe

ssio

nals

Preq

ualif

icat

ion

Bid

Revi

ew

II. Development of the ScheduleProject Phases

July 19, 2016 64

Concept Design Bid Construction

Idea

DeliverySystem

Professional Services

1 Year

Constructability Reviews

QA/QC

3 Weeks

Missed Scope

Unqualified Subs

Page 65: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

II. Development of the Schedule

July 19, 2016 65

• When is a schedule developed?

• During 3-week bid?

• Makes No Sense!

• When should a schedule be developed?

Page 66: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

II. Development of the Schedule

July 19, 2016 66

• Concept Phase− Schedule−Budget−Manage Expectations (of client/end-user)− Select Delivery System (roles of professionals)− Select Design Professionals

Page 67: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

II. Development of the Schedule

July 19, 2016 67

• Design Phase−Control Client−Control Design Team−Constructability (Contractor)−Contract (Define Standard of Care) – Use Initial Decision Maker (IDM)−Control Changes−QA/QC Inspection−Peer Review−Dispute Resolution (AIA, DRB)− Schedule

Page 68: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

II. Development of the Schedule

July 19, 2016 68

• Bid Phase−Prequalification−Allow appropriate Bid Time−Manage Addenda−Control Client, Design Team, Changes−Requisite preparation of Schedule− Schedule?

Page 69: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

II. Development of the Schedule

July 19, 2016 69

• Construction Phase− Schedule / Budget (Done)−Control Client−Control Design Team−Constructability−Change Management−Consistency [Contract Enforcement]

Page 70: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

III. Basic Scheduling Computations

07-APR-16 70

Page 71: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

III. Basic Scheduling Computations

07-APR-16 71

• Example

3A

3C

2B

2D

4F

4E

2G

FS2

SS2

FF4

FS0 FS0

FS0FS2

FS4

Page 72: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

III. Basic Scheduling Computations

07-APR-16 72

3A

3C

2B

2D

4F

4E

2G

FS2

SS2

FF4

FS0 FS0

FS0FS2

1 3

1 3

4 5

4 5

8 10

8 10

10 11

11 12

13 16

13 16

17 20

17 20

21 22

21 22

TF=0 TF=0

TF=0

TF=1

TF=0 TF=0 TF=0

FS4

13,12 17,15

16,185, 6

Ordinal Time

Page 73: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

III. Basic Scheduling Computations

07-APR-16 73

3A

3C

2B

2D

4F

4E

2G

FS2

SS2

FF4

FS0 FS0

FS0FS2

1 3

1 3

4 5

4 5

8 10

8 10

10 11

11 12

13 16

13 16

17 20

17 20

21 22

21 22

TF=0 TF=0

TF=0

TF=1

TF=0 TF=0 TF=0

FS4

CRITICAL PATH: A-B-C-E-F-G

Page 74: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

III. Basic Scheduling Computations

07-APR-16 74

ES EFTFODRD

LFLS

ACT ID

ACT DES

Page 75: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

III. Basic Scheduling Computations

07-APR-16 75

• Comments on:−Calendars−Weather− Float−Critical Path

Page 76: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

IV. Practical Applications

07-APR-16 76

Page 77: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

IV. Practical Applications

July 19, 2016 77

• Project Management−Management – a process concerned with the achievement of goals or

objectives−Project Management – involves the coordination of group activities

wherein the manager Plans Organizes Staffs Directs Controls

to achieve an objective with constraints on time, cost, and performance of the end product.

Page 78: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

IV. Practical Applications

July 19, 2016 78

• Project Management• Scheduling is one component of Project Management System • Question: How is your project doing?

−Money−Time

Answer must be integrated

Page 79: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

IV. Practical Applications

July 19, 2016 79

• Money Budget

Cost Code

• Time Schedule

Activity

Page 80: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

IV. Practical Applications

July 19, 2016 80

• Comparative Analysis

Plan Actual

Page 81: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

IV. Practical Applications

July 19, 2016 81

• Comparative AnalysisMoney (Budget)

Time (Schedule)B e h i n d A h e a d

Under

Over

Page 82: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

IV. Practical Applications

July 19, 2016 82

• Project Management Functions−Planning− Scheduling−Monitoring−Controlling

Page 83: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

IV. Practical Applications

July 19, 2016 83

• Controlling−The process of making events conform to schedules by coordinating the

action of all parts of the organization according to the plan

Page 84: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

IV. Practical Applications

July 19, 2016 84

• How do you measure success?−On Time−On Budget−Acceptable Quality−Acceptable Function− Safety−No Claims−No Lawsuits

Page 85: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

IV. Practical Applications

July 19, 2016 85

• What is failure?

Page 86: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

IV. Practical Applications

July 19, 2016 86

Introduction to Planning and Scheduling

Page 87: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

IV. Practical Applications

July 19, 2016 87

Suddenly, a heated exchange took place between the king and the moat Contractor.

THE FAR SIDE COPYRIGHT 1990 UNIVERSAL PRESS SYNDICATEAll rights reserved.

Page 88: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

IV. Practical Applications

July 19, 2016 88

• Importance of Time in Construction Contracts

−How duties and responsibilities are defined in the contract:1.Scope: What will be provided2.Price: How much compensation will be paid for the item or performance

provided3.Time: When is the performance required

−The project schedule… Baseline for performance of contracting parties Used to assess parties’ respective rights and obligations

Page 89: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

IV. Practical Applications

07-APR-16 89

• As-Planned (Baseline) Schedule−Project Scope at time of award/bid−Represent contractor’s plan before: Any Changes (Change Orders) Starting construction

−Comply with contract requirements−Good for about _______30 days

Page 90: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

IV. Practical Applications

07-APR-16 90

• Updated Schedule−Reflect “current” status of project as of a certain date (Data Date)−Contain accurate information on work completed per activity: Actual Start Actual Finish Status of activities started but not yet finished

−Recalculate a schedule looking forward

Page 91: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

IV. Practical Applications

07-APR-16 91

• What can change in an updated schedule?−A lot Projected dates for activities Float values The Critical Path Project Completion Date(s)

Page 92: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

IV. Practical Applications

07-APR-16 92

• Revised Schedule−Whenever a fundamental change is made to the schedule. Add activities Delete activities Change, add or delete any relationship(s) Change a duration

−When is this appropriate?

Page 93: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

IV. Practical Applications

07-APR-16 93

• It’s all about:

Schedule Maintenance

“Living, breathing document”“Dynamic Tool”

“Forward Looking”

Page 94: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

IV. Practical Applications

07-APR-16 94

• “As-Built” Schedule−All activities completed−Really a database of information...not a schedule

Page 95: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

IV. Practical Applications

07-APR-16 95

• A CPM Construction Schedule is a model of how the project is planned to be built.

• At the “end-of-the-day”The “As-Built” Schedule becomes a record of how the project was built.

Page 96: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

V. Delay Analysis

07-APR-16 96

Page 97: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

V. Delay Analysis

07-APR-16 97

• It’s all about:

Schedule Maintenance

“Living, breathing document”“Dynamic Tool”

“Forward Looking”

Page 98: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

V. Delay Analysis

07-APR-16 98

• Delay−To put off to a later time: postpone−To impede or retard−An instance of being delayed 9

9 Webster’s Dictionary – ISBN 0-345-40095-X

Page 99: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

V. Delay Analysis

07-APR-16 99

• Delay in the Context of the Construction Industry− In construction claims, the term “delay” is used to mean two different

but related matters. Delay is often used to mean the time period during which some part of the construction project has been extended beyond what was originally planned due to unanticipated circumstances.

−Delay can also be the incident that affects the performance of a particular activity, with or without affecting project completion.

Page 100: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

V. Delay Analysis

07-APR-16 100

• Delay in the Context of the Construction Industry−Although there may be unique aspects of the different projects, sites,

contract terms, and customs and practices in different parts of the world, for the most part the reality of delay unfortunately is universal to the construction industry. 10

10 Construction Delay Claims – ISBN 978-1-4548-4517-1

Page 101: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

V. Delay Analysis

07-APR-16 101

• Delay v. Critical Delay−Critical project delays are those that extend the overall project

completion date. 11

Milestones Distinction in terms of damages

11 Construction Delay Claims – ISBN 978-1-4548-4517-1

Page 102: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

V. Delay Analysis

07-APR-16 102

• Other related terms:−Disruption “An activity-specific loss of productivity caused by changes in the working

conditions under which that activity was (is) performed.” 12

“A material alteration in the performance conditions that were reasonably expected at the time of bid, resulting in increased cost of performance.” 13

12 Construction Delay Claims – ISBN 978-1-4548-4517-113 Construction Delay Claims – ISBN 978-1-4548-4517-1

Page 103: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

V. Delay Analysis

07-APR-16 103

• Other related terms:−Acceleration “Is an attempt to speed up the progress of the work to achieve an earlier project

completion or to overcome previous delays.” 14

−Constructive Acceleration “Is based on the premise that a contractor is entitled to a time extension for

excusable delays but it is not granted.” 15

14 Construction Delay Claims – ISBN 978-1-4548-4517-115 Construction Delay Claims – ISBN 978-1-4548-4517-1

Page 104: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

V. Delay Analysis

07-APR-16 104

• Constructive Acceleration Hurdles1. There must be an excusable delay.2. There must have been timely notice of the delay and a proper request

for a time extension.3. The time extension request must either be postponed or refused.4. The owner or other party must by coercion, direction, or in some other

manner that reasonably can be construed as a command order completion within the unextended performance period.

5. The contractor must actually accelerate its performance and thereby incur added costs. 16

16 Construction Delay Claims – ISBN 978-1-4548-4517-1

Page 105: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

V. Delay Analysis

07-APR-16 105

• Causes of Delay−Owner−Designer−Contractor−Delays That May Be Beyond the Control of the Parties

Page 106: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

V. Delay Analysis

• Owner− Changes− Access to Project Site− Right-of-Way− Utility relocation delays− Unidentified or mislocated utilities− Demolition of existing structures− Differing site conditions− Relocation of tenants− Approvals from governing authorities− Payment delays− Project financing− Design defects (vicarious liability)

− Defective specifications− Tardy shop drawing processing− Inspection delays− Delayed notice to proceed/contract

award− Inappropriate stop work orders− Owner-furnished items− Over-inspection− Constructive changes− Owner interference− Failure to coordinate multiple prime

contractors

07-APR-16 106

Page 107: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

V. Delay Analysis

• Designer− Design defects, errors, and omissions− Slow correction of defects− Tardy shop drawing review− Delayed testing and inspections− Poor contract administration− Late responses to Requests for

Information (RFI)

07-APR-16 107

Page 108: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

V. Delay Analysis

• Contractor− Inadequacy of labor force− Failure to evaluate site− Failure to evaluate design− Underbidding− Management failures− Scheduling and planning

07-APR-16 108

− Coordination and subcontractors− Subcontractor delays− Material procurement− Equipment failures− Financial resources− Construction defects

Page 109: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

V. Delay Analysis

• Delays That May Be Beyond the Control of the Parties

07-APR-16 109

− Floods− Governmental acts− Vandalism− Fire− Strikes

− Unusually severe weather conditions− Labor disputes− Unavoidable calamities− Force Majeure “Acts of God”− Unusual delays in transportation

Page 110: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

V. Delay Analysis

07-APR-16 110

• Categories of Delay

Excusable Non-Excusable

Compensable Non-Compensable

Page 111: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

V. Delay Analysis

07-APR-16 111

• Concurrent Delay−What is it?

−Proper analysis of Concurrent Delay adds an order of magnitude to the difficulty.

Page 112: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

V. Delay Analysis

07-APR-16 112

“Evaluation of delay claims and schedule disruptions is as much an art as it is a science, even though scheduling may involve mathematical formulas, calculations, and computer models.” 17

17 Construction Delay Claims – ISBN 978-1-4548-4517-1

Page 113: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

V. Delay Analysis

113

• General MethodologiesA. Impacted As-PlannedB. As-Built As-Planned to As-Built Comparison As-Built Collapsed As-Built

C. Time Impact Analysis aka. Update Impact Method

07-APR-16

Page 114: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

V. Delay Analysis

114

A. Impacted As-Planned– Measures impact on planned not actual performance.– Uses only the planned schedule.– Assumes as-planned logic is followed.

07-APR-16

Page 115: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

V. Delay Analysis

115

B. As-Built− All As-Built methods are founded on the use of as-built data or “As-Built

Schedules.” As-Planned to As-Built Comparison

• Logic may be different• Critical Path is not static

As-Built (Alone)• Critical Path ???

Collapsed As-Built• Remove delays systematically = but for “would have completed”

07-APR-16

Page 116: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

V. Delay Analysis

116

C. Time Impact Analysis− aka. Corps method, windows analysis, update impact method,

contemporaneous impact, snapshot techniques1. Update schedule at time of delay2. Impact (insert delay fragnet)3. Determine impact (calculate schedule)4. Update

− Goal: develop a stop-action picture of project each time a delay or disruption occurs

07-APR-16

Page 117: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

V. Delay Analysis

07-APR-16 117

• Forensic−Of, suited to, or used in courts of law or in public debate 18

18 Webster’s Dictionary – ISBN 0-345-40095-X

Page 118: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

V. Delay Analysis

07-APR-16 118

• Issues−Retrospective v. Prospective Analysis

Page 119: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

V. Delay Analysis

07-APR-16 119

• Is there one authoritative text on forensic schedule analysis?

• Is there any authoritative text on forensic schedule analysis?

Page 120: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

07-APR-16 120

• It’s all about:

Schedule Maintenance

“Living, breathing document”“Dynamic Tool”

“Forward Looking”

Page 121: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

VI. Communicating Complex Analyses To The Non-technical Audience

October 25, 2017 121

Page 122: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

Laurel Mountain Wind Project, WV

122

Page 123: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-6

CD-5

CD-7

CD-8

CD-9CD-10

CD-11

AB-10AB-9

AB-8AB-7

AB-6AB-5

AB-4AB-3

AB-2

AB-1

33

11

6564

6362

61 60 59

5655 53 52

51

1

234

56

78910

1112

1413

1516171819

2021

222324

2526

272829

3031323334

SUBSTATION36

373839

40414243

35

45 4446

4847

4950

545758

GAS PIPELINE

575251

50

Site OverviewIII.A. Graphical Representation

Page 124: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

20 21 22 23 24 25 26 27 28 29 30 31 322 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

III.A. Graphical Representation

As-Planned

33

1

11

WEEKS 33 34 35 36 37

Page 125: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

III.A. Graphical Representation

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37

33

11

LNTP (6/14/10)

WEEKS

As-Planned – June 2010

Page 126: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

III.A. Graphical Representation

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37

SE-1

SE-2

33

11

Clearing and Grubbing

WEEKS

As-Planned – June 2010

Page 127: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

III.A. Graphical Representation

• As-Planned – June 2010

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37

33

11

SE-1

CD-1

SE-2

WEEKS

Page 128: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

III.A. Graphical Representation

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37

33

11

SE-1

CD-1

SE-2

CD-2

WEEKS

As-Planned – July 2010

Page 129: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

III.A. Graphical Representation

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

WEEKS

As-Planned – July 2010

Page 130: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

WEEKS

III.A. Graphical Representation

As-Planned – July 2010

Page 131: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37WEEKS

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6

III.A. Graphical Representation

As-Planned – July 2010

Page 132: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37WEEKS

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6CD-7

CD-8

III.A. Graphical Representation

As-Planned – August 2010

Page 133: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37WEEKS

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6CD-7

CD-8

CD-9

III.A. Graphical Representation

As-Planned – August 2010

Page 134: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37WEEKS

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6CD-7

CD-8

CD-9CD-10

63

61 60 59 58

6564

62

III.A. Graphical Representation

As-Planned – August 2010

Page 135: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37WEEKS

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6CD-7

CD-8

CD-9CD-10

63

61 60 59 58

6564

62

CD-11

5655 53

5457

III.A. Graphical Representation

As-Planned – August 2010

Page 136: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37WEEKS

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6CD-7

CD-8

CD-9CD-10

63

61 60 59 58

6564

62

CD-11

5655 53

5457

AB-2

AB-1

4647

49

52

5051

48

III.A. Graphical Representation

As-Planned – September 2010

Page 137: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37WEEKS

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6CD-7

CD-8

CD-9CD-10

63

61 60 59 58

6564

62

CD-11

5655 53

5457

AB-2

AB-1

4647

49

52

5051

48

AB-3

40414245 44

43

III.A. Graphical Representation

As-Planned – September 2010

Page 138: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37WEEKS

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6CD-7

CD-8

CD-9CD-10

63

61 60 59 58

6564

62

CD-11

5655 53

5457

AB-2

AB-1

4647

49

52

5051

48

AB-3

40414245 44

AB-4

323334

363738

35

39

43

III.A. Graphical Representation

As-Planned – September 2010

Page 139: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37WEEKS

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6CD-7

CD-8

CD-9CD-10

63

61 60 59 58

6564

62

CD-11

5655 53

5457

AB-2

AB-1

4647

49

52

5051

48

AB-3

40414245 44

AB-4

323334

363738

35

39

AB-5

28293031

43

III.A. Graphical Representation

As-Planned – September 2010

Page 140: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37WEEKS

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6CD-7

CD-8

CD-9CD-10

63

61 60 59 58

6564

62

CD-11

5655 53

5457

AB-2

AB-1

4647

49

52

5051

48

AB-3

40414245 44

AB-4

323334

363738

35

39

AB-5

28293031

AB-6

2425

2627

43

III.A. Graphical Representation

As-Planned – September 2010

Page 141: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37WEEKS

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6CD-7

CD-8

CD-9CD-10

63

61 60 59 58

6564

62

CD-11

5655 53

5457

AB-2

AB-1

4647

49

52

5051

48

AB-3

40414245 44

AB-4

323334

363738

35

39

AB-5

28293031

AB-6

2425

2627

AB-7

1922

23

2120 18

43

III.A. Graphical Representation

As-Planned – October 2010

Page 142: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37WEEKS

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6CD-7

CD-8

CD-9CD-10

63

61 60 59 58

6564

62

CD-11

5655 53

5457

AB-2

AB-1

4647

49

52

5051

48

AB-3

40414245 44

AB-4

323334

363738

35

39

AB-5

28293031

AB-6

2425

2627

AB-7

1922

23

2120 18

AB-8

GAS PIPELINE1112

1413

17 16 15

109 8

43

III.A. Graphical Representation

As-Planned – October 2010

Page 143: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

• Component deliveries and WTG erection begin 10/18/2010

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37WEEKS

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6CD-7

CD-8

CD-9CD-10

63

61 60 59 58

6564

62

CD-11

5655 53

5457

AB-2

AB-1

4647

49

52

5051

48

AB-3

40414245 44

AB-4

323334

363738

35

39

AB-5

28293031

AB-6

2425

2627

AB-7

1922

23

2120 18

AB-8

GAS PIPELINE1112

1413

17 16 15

109 8

AB-9

34

56

7

43

III.A. Graphical Representation

As-Planned – October 2010

Page 144: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

• Concrete pours complete 10/25/2010

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37WEEKS

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6CD-7

CD-8

CD-9CD-10

63

61 60 59 58

6564

62

CD-11

5655 53

5457

AB-2

AB-1

4647

49

52

5051

48

AB-3

40414245 44

AB-4

323334

363738

35

39

AB-5

28293031

AB-6

2425

2627

AB-7

1922

23

2120 18

AB-8

GAS PIPELINE1112

1413

17 16 15

109 8

AB-9

34

56

7

AB-10 1

2

43

III.A. Graphical Representation

As-Planned – October 2010

Page 145: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

• Foundation backfill and crane pads complete 11/1/2010

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37WEEKS

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6CD-7

CD-8

CD-9CD-10

63

61 60 59 58

6564

62

CD-11

5655 53

5457

AB-2

AB-1

4647

49

52

5051

48

AB-3

40414245 44

AB-4

323334

363738

35

39

AB-5

28293031

AB-6

2425

2627

AB-7

1922

23

2120 18

AB-8

GAS PIPELINE1112

1413

17 16 15

109 8

AB-9

34

56

7

AB-10 1

2

43

III.A. Graphical Representation

As-Planned – November 2010

Page 146: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37WEEKS

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6CD-7

CD-8

CD-9CD-10

63

61 60 59 58

6564

62

CD-11

5655 53

5457

AB-2

AB-1

4647

49

52

5051

48

AB-3

40414245 44

AB-4

323334

363738

35

39

AB-5

28293031

AB-6

2425

2627

AB-7

1922

23

2120 18

AB-8

GAS PIPELINE1112

1413

17 16 15

109 8

AB-9

34

56

7

AB-10 1

2

43

III.A. Graphical Representation

As-Planned – November 2010

Page 147: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37WEEKS

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6CD-7

CD-8

CD-9CD-10

63

61 60 59 58

6564

62

CD-11

5655 53

5457

AB-2

AB-1

4647

49

52

5051

48

AB-3

40414245 44

AB-4

323334

363738

35

39

AB-5

28293031

AB-6

2425

2627

AB-7

1922

23

2120 18

AB-8

GAS PIPELINE1112

1413

17 16 15

109 8

AB-9

34

56

7

AB-10 1

2

43

III.A. Graphical Representation

As-Planned – November 2010

Page 148: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37WEEKS

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6CD-7

CD-8

CD-9CD-10

63

61 60 59 58

6564

62

CD-11

5655 53

5457

AB-2

AB-1

4647

49

52

5051

48

AB-3

40414245 44

AB-4

323334

363738

35

39

AB-5

28293031

AB-6

2425

2627

AB-7

1922

23

2120 18

AB-8

GAS PIPELINE1112

1413

17 16 15

109 8

AB-9

34

56

7

AB-10 1

2

43

III.A. Graphical Representation

As-Planned – November 2010

Page 149: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37WEEKS

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6CD-7

CD-8

CD-9CD-10

63

61 60 59 58

6564

62

CD-11

5655 53

5457

AB-2

AB-1

4647

49

52

5051

48

AB-3

40414245 44

AB-4

323334

363738

35

39

AB-5

28293031

AB-6

2425

2627

AB-7

1922

23

2120 18

AB-8

GAS PIPELINE1112

1413

17 16 15

109 8

AB-9

34

56

7

AB-10 1

2

43

III.A. Graphical Representation

As-Planned – December 2010

Page 150: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37WEEKS

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6CD-7

CD-8

CD-9CD-10

63

61 60 59 58

6564

62

CD-11

5655 53

5457

AB-2

AB-1

4647

49

52

5051

48

AB-3

40414245 44

AB-4

323334

363738

35

39

AB-5

28293031

AB-6

2425

2627

AB-7

1922

23

2120 18

AB-8

GAS PIPELINE1112

1413

17 16 15

109 8

AB-9

34

56

7

AB-10 1

2

43

III.A. Graphical Representation

As-Planned – December 2010

Page 151: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37WEEKS

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6CD-7

CD-8

CD-9CD-10

63

61 60 59 58

6564

62

CD-11

5655 53

5457

AB-2

AB-1

4647

49

52

5051

48

AB-3

40414245 44

AB-4

323334

363738

35

39

AB-5

28293031

AB-6

2425

2627

AB-7

1922

23

2120 18

AB-8

GAS PIPELINE1112

1413

17 16 15

109 8

AB-9

34

56

7

AB-10 1

2

43

III.A. Graphical Representation

As-Planned – December 2010

Page 152: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37WEEKS

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6CD-7

CD-8

CD-9CD-10

63

61 60 59 58

6564

62

CD-11

5655 53

5457

AB-2

AB-1

4647

49

52

5051

48

AB-3

40414245 44

AB-4

323334

363738

35

39

AB-5

28293031

AB-6

2425

2627

AB-7

1922

23

2120 18

AB-8

GAS PIPELINE1112

1413

17 16 15

109 8

AB-9

34

56

7

AB-10 1

2

43

III.A. Graphical Representation

As-Planned – December 2010

Page 153: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

20 21 22 23 24 25 26 27 28 29 30 31 321 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19WEEKS

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6CD-7

CD-8

CD-9CD-10

63

61 60 59 58

6564

62

CD-11

5655 53

5457

AB-2

AB-1

4647

49

52

5051

48

AB-3

40414245 44

AB-4

323334

363738

35

39

AB-5

28293031

AB-6

2425

2627

AB-7

1922

23

2120 18

AB-8

GAS PIPELINE1112

1413

17 16 15

109 8

AB-9

34

56

7

AB-10 1

2

43

III.A. Graphical Representation

As-Planned – December 2010

Page 154: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

20 21 22 23 24 25 26 27 28 29 30 31 321 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19WEEKS

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6CD-7

CD-8

CD-9CD-10

63

61 60 59 58

6564

62

CD-11

5655 53

5457

AB-2

AB-1

4647

49

52

5051

48

AB-3

40414245 44

AB-4

323334

363738

35

39

AB-5

28293031

AB-6

2425

2627

AB-7

1922

23

2120 18

AB-8

GAS PIPELINE1112

1413

17 16 15

109 8

AB-9

34

56

7

AB-10 1

2

43

III.A. Graphical Representation

As-Planned – January 2011

Page 155: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

• Final rotor installed 1/10/11

20 21 22 23 24 25 26 27 28 29 30 31 321 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19WEEKS

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6CD-7

CD-8

CD-9CD-10

63

61 60 59 58

6564

62

CD-11

5655 53

5457

AB-2

AB-1

4647

49

52

5051

48

AB-3

40414245 44

AB-4

323334

363738

35

39

AB-5

28293031

AB-6

2425

2627

AB-7

1922

23

2120 18

AB-8

GAS PIPELINE1112

1413

17 16 15

109 8

AB-9

34

56

7

AB-10 1

2

43

III.A. Graphical Representation

As-Planned – January 2011

Page 156: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 2573124JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 917

20 21 22 23 24 25 26 27 28 29 30 31 321 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19WEEKS

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6CD-7

CD-8

CD-9CD-10

63

61 60 59 58

6564

62

CD-11

5655 53

5457

AB-2

AB-1

4647

49

52

5051

48

AB-3

40414245 44

AB-4

323334

363738

35

39

AB-5

28293031

AB-6

2425

2627

AB-7

1922

23

2120 18

AB-8

GAS PIPELINE1112

1413

17 16 15

109 8

AB-9

34

56

7

AB-10 1

2

43

III.A. Graphical Representation

As-Planned – January 2011

Page 157: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 362 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

As-Built

33

371

11

III.A. Graphical Representation

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 158: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

As-Built – June 2010

33

37

11

LNTP (6/14/10)

III.A. Graphical Representation

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 159: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

As-Built – June 2010

33

37

11

III.A. Graphical Representation

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 160: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

• Site Issues– Logging SE1 / SE2– Lack of fill

As-Built – June 2010

33

SE-1

SE-2

37

11

Clearing and Grubbing

III.A. Graphical Representation

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 161: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

As-Built – July 2010

33

SE-1

SE-2

CD-1CD-3

CD-4

37

11

Dead Zone

III.A. Graphical Representation

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 162: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

As-Built – July 2010

33

SE-1

SE-2

CD-1CD-3

CD-4

37

11

Dead Zone

III.A. Graphical Representation

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 163: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

As-Built – July 2010

33

SE-1

SE-2

CD-1CD-3

CD-4

CD-8

CD-9

37

11

Dead Zone

III.A. Graphical Representation

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 164: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

III.A. Graphical Representation

As-Planned – July 2010

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37 38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 165: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

• Site Issues– CD-2 Dead Zone– CD-5,6,7 Dead Zone– CD-3,4 Safety / Emergency Access– Lack of fill

As-Built – July 2010

33

SE-1

SE-2

CD-1CD-3

CD-4

CD-8

CD-9CD-10

CD-11

37

11

Dead Zone

III.A. Graphical Representation

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 166: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

As-Built – August 2010

33

SE-1

SE-2

CD-1CD-3

CD-4

CD-8

CD-9CD-10

CD-11

37

11

Dead Zone

III.A. Graphical Representation

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 167: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

As-Built – August 2010

33

SE-1

SE-2

CD-1CD-3

CD-4

CD-8

CD-9CD-10

CD-11

37

11

Dead Zone

III.A. Graphical Representation

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 168: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

As-Built – August 2010

33

SE-1

SE-2

CD-1CD-3

CD-4

CD-8

CD-9CD-10

CD-11

CD-2

CD-6

CD-5

CD-7

37

11

III.A. Graphical Representation

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 169: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

• Site Issues– CD-2 Dead Zone– Bat Habitat– Lack of Fill

As-Built – August 2010

33

SE-1

SE-2

CD-1CD-3

CD-4

CD-8

CD-9CD-10

CD-11

CD-2

CD-6

CD-5

CD-7

AB-2

AB-1

AB-3AB-4

37

11

Bat HabitatIII.A. Graphical Representation

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 170: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6CD-7

CD-8

CD-9CD-10

63

61 60 59 58

6564

62

CD-11

5655 53

5457

III.A. Graphical Representation

As-Planned – August 2010

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37 38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 171: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

• Site Issues– CD-2 Dead Zone– Bat Habitat– Lack of Fill

As-Built – August 2010

33

SE-1

SE-2

CD-1CD-3

CD-4

CD-8

CD-9CD-10

CD-11

CD-2

CD-6

CD-5

CD-7

AB-2

AB-1

AB-3AB-4

37

11

Bat HabitatIII.A. Graphical Representation

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 172: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

SE-1

SE-2

CD-1CD-3

CD-4

CD-8

CD-9CD-10

CD-11

CD-2

CD-6

CD-5

CD-7

AB-2

AB-1

AB-3AB-4

37

11

Bat HabitatIII.A. Graphical Representation

As-Built – September 2010

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 173: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

SE-1

SE-2

CD-1CD-3

CD-4

CD-8

CD-9CD-10

CD-11

CD-2

CD-6

CD-5

CD-7

AB-2

AB-1

AB-3AB-4

AB-8

37

GAS PIPELINE

11

III.A. Graphical Representation

As-Built – September 2010

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 174: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

SE-1

SE-2

CD-1CD-3

CD-4

CD-8

CD-9CD-10

CD-11

CD-2

CD-6

CD-5

CD-7

AB-2

AB-1

AB-3AB-4

AB-8

AB-10AB-9

AB-5

37

GAS PIPELINE

11

III.A. Graphical Representation

As-Built – September 2010

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 175: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

CD-1

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

SE-1

SE-2

CD-3CD-4

CD-8

CD-9CD-10

CD-11

CD-2

CD-6

CD-5

CD-7

AB-2

AB-1

AB-3AB-4

AB-8

AB-10AB-9

AB-5

AB-7

37

64

62

GAS PIPELINE

11

III.A. Graphical Representation

As-Built – September 2010

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 176: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

CD-1

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

• Site Issues– 1.6 MW Design Changes– CD-2 Dead Zone– Lack of fill

33

SE-1

SE-2

CD-3CD-4

CD-8

CD-9CD-10

CD-11

CD-2

CD-6

CD-5

CD-7

AB-2

AB-1

AB-3AB-4

AB-8

AB-10AB-9

AB-5

64

AB-7

62

37

AB-6

65

56 54

GAS PIPELINE

11

III.A. Graphical Representation

As-Built – September 2010

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 177: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6CD-7

CD-8

CD-9CD-10

63

61 60 59 58

6564

62

CD-11

5655 53

5457

AB-2

AB-1

4647

49

52

5051

48

AB-3

40414245 44

AB-4

323334

363738

35

39

AB-5

28293031

AB-6

2425

2627

43

III.A. Graphical Representation

As-Planned – September 2010

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37 38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 178: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

CD-1

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

• Site Issues– 1.6 MW Design Changes– CD-2 Dead Zone– Lack of fill

33

SE-1

SE-2

CD-3CD-4

CD-8

CD-9CD-10

CD-11

CD-2

CD-6

CD-5

CD-7

AB-2

AB-1

AB-3AB-4

AB-8

AB-10AB-9

AB-5

64

AB-7

62

37

AB-6

65

56 54

GAS PIPELINE

11

III.A. Graphical Representation

As-Built – September 2010

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 179: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

CD-3CD-4

CD-1

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

SE-1

SE-2

CD-8

CD-9CD-10

CD-11

CD-2

CD-6

CD-5

CD-7

AB-2

AB-1

AB-3AB-4

AB-8

AB-10AB-9

AB-5

64

AB-7

62

37

AB-6

65

56 54

GAS PIPELINE

63 55 53 5257

51

11

III.A. Graphical Representation

As-Built – October 2010

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 180: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

CD-1

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

SE-1

SE-2

CD-3CD-4

CD-8

CD-9CD-10

CD-11

CD-2

CD-6

CD-5

CD-7

AB-2

AB-1

AB-3AB-4

AB-8

AB-10AB-9

AB-5

64

AB-7

37

AB-6

65

56 546263 55 53 52

57

5150

GAS PIPELINE

11

III.A. Graphical Representation

As-Built – October 2010

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 181: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

CD-8

CD-2

CD-6

CD-5

CD-7

CD-1

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

SE-1

SE-2

CD-3CD-4

CD-9CD-10

CD-11

AB-2

AB-1

AB-3AB-4

AB-8

AB-10AB-9

AB-5

64

AB-7

37

AB-6

65

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

GAS PIPELINE

11

III.A. Graphical Representation

As-Built – October 2010

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 182: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

CD-8

CD-2

CD-6

CD-5

CD-7

CD-1

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

• Site Issues– Better than Expected Progress

33

SE-1

SE-2

CD-3CD-4

CD-9CD-10

CD-11

AB-2

AB-1

AB-3AB-4

AB-8

AB-10AB-9

AB-5

64

AB-7

37

AB-6

65

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

35

GAS PIPELINE

11

III.A. Graphical Representation

As-Built – October 2010

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 183: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

CD-8

CD-2

CD-6

CD-5

CD-7

CD-1

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

SE-1

SE-2

CD-3CD-4

CD-9CD-10

CD-11

AB-2

AB-1

AB-3AB-4

AB-8

AB-10AB-9

AB-5

64

AB-7

37

AB-6

65

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

GAS PIPELINE

11

III.A. Graphical Representation

As-Built – November 2010

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 184: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

• Foundation backfill and crane pads complete 11/1/2010

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6CD-7

CD-8

CD-9CD-10

63

61 59 58

6564

62

CD-11

5655 53

5457

AB-2

AB-1

4647

49

52

5051

48

AB-3

40414245 44

AB-4

323334

363738

35

39

AB-5

28293031

AB-6

2425

2627

AB-7

1922

23

2120 18

AB-8

GAS PIPELINE1112

1413

17 16 15

109 8

AB-9

34

56

7

AB-10 1

2

43

III.A. Graphical Representation

As-Planned – November 2010

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37 38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 185: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

CD-8

CD-2

CD-6

CD-5

CD-7

CD-1

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

SE-1

SE-2

CD-3CD-4

CD-9CD-10

CD-11

AB-2

AB-1

AB-3AB-4

AB-8

AB-10AB-9

AB-5

64

AB-7

37

AB-6

65

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

GAS PIPELINE

11

III.A. Graphical Representation

As-Built – November 2010

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 186: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

CD-8

CD-2

CD-6

CD-5

CD-7

CD-1

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

SE-1

SE-2

CD-3CD-4

CD-9CD-10

CD-11

AB-2

AB-1

AB-3AB-4

AB-8

AB-10AB-9

AB-5

64

AB-7

37

AB-6

65

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

GAS PIPELINE

11

III.A. Graphical Representation

As-Built – November 2010

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 187: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

SE-1

SE-2

CD-9

CD-8

CD-2

CD-6

CD-5

CD-7

CD-1

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

CD-3CD-4

CD-10

CD-11

AB-2

AB-1

AB-3AB-4

AB-8

AB-10AB-9

AB-5

64

AB-7

37

AB-6

65

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

39

1617

1921

18

GAS PIPELINE

11

III.A. Graphical Representation

As-Built – November 2010

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 188: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

SE-1

SE-2

AB-5

CD-9

CD-8

CD-2

CD-6

CD-5

CD-7

CD-1

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

• Site Issues– Haphazard Component Deliveries– Coal Seams / Foundation Undercut– KR Wind Crane Incident– Snow Removal / Road Maintenance

33

CD-3CD-4

CD-10

CD-11

AB-2

AB-1

AB-3AB-4

AB-8

AB-10AB-9

64

AB-7

37

AB-6

65

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

39

1617

1921

18

GAS PIPELINE

11

III.A. Graphical Representation

As-Built – November 2010

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 189: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

SE-1

SE-2

AB-5

AB-2

AB-1

CD-9

CD-8

CD-2

CD-6

CD-5

CD-7

CD-1

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

CD-3CD-4

CD-10

CD-11

AB-3AB-4

AB-8

AB-10AB-9

64

AB-7

37

AB-6

65

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

39

1617

1921

1820

2627

GAS PIPELINE

11

III.A. Graphical Representation

As-Built – December 2010

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 190: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

SE-1

SE-2

CD-9

AB-5

AB-2

AB-1

CD-8

CD-2

CD-6

CD-5

CD-7

CD-1

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

CD-3CD-4

CD-10

CD-11

AB-3AB-4

AB-8

AB-10AB-9

64

AB-7

37

AB-6

65

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

39

1617

1921

1820

2627

15

37

GAS PIPELINE

11

III.A. Graphical Representation

As-Built – December 2010

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 191: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

SE-1

SE-2

CD-9

AB-5

AB-2

AB-1

CD-8

CD-2

CD-6

CD-5

CD-7

CD-1

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

CD-3CD-4

CD-10

CD-11

AB-3AB-4

AB-8

AB-10AB-9

64

AB-7

37

AB-6

65

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

39

1921

1820

2627

37

16 1517GAS PIPELINE

11

III.A. Graphical Representation

As-Built – December 2010

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 192: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

SE-1

SE-2

CD-9

AB-5

AB-2

AB-1

CD-8

CD-2

CD-6

CD-5

CD-7

CD-1

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

CD-3CD-4

CD-10

CD-11

AB-3AB-4

AB-8

AB-10AB-9

64

AB-7

37

AB-6

65

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

39

1921

1820

2627

37

16 1517GAS PIPELINE

11

III.A. Graphical Representation

As-Built – December 2010

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 193: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

CD-9

AB-5

AB-2

AB-1

CD-8

CD-2

CD-6

CD-5

CD-7

CD-1

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

• Site Issues– Haphazard Component Delivery– Coal Seams / Foundation Undercut– Stevens’ Demobilization– Snow Removal / Road Maintenance– Weather / Safety

33

SE-1

SE-2

CD-3CD-4

CD-10

CD-11

AB-3AB-4

AB-8

AB-10AB-9

64

AB-7

37

AB-6

65

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

39

1921

1820

2627

37

16 1517GAS PIPELINE

11

III.A. Graphical Representation

As-Built – December 2010

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 194: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

CD-1

SE-1

SE-2

AB-6AB-7

CD-9

AB-5

AB-2

AB-1

CD-8

CD-2

CD-6

CD-5

CD-7

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

CD-3CD-4

CD-10

CD-11

AB-3AB-4

AB-8

AB-10AB-9

64

37

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

39

1921

1820

2627

37

16 1517

1112

1413 GAS PIPELINE

65

11

III.A. Graphical Representation

As-Built – January 2011

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 195: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

CD-1

AB-6

65

AB-7

CD-9

AB-5

AB-2

AB-1

CD-8

CD-2

CD-6

CD-5

CD-7

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

SE-1

SE-2

CD-3CD-4

CD-10

CD-11

AB-3AB-4

AB-8

AB-10AB-9

64

37

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

39

1921

1820

2627

37

16 1517

1112

1413 GAS PIPELINE

11

III.A. Graphical Representation

As-Built – January 2011

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 196: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

• Final rotor installed 1/10/11

33

11

SE-1

CD-1

SE-2

CD-2

CD-3CD-4

CD-5

CD-6CD-7

CD-8

CD-9CD-10

63

59 58

6564

62

CD-11

5655 53

5457

AB-2

AB-1

4647

49

52

5051

48

AB-3

40414245 44

AB-4

323334

363738

35

39

AB-5

28293031

AB-6

2425

2627

AB-7

1922

23

2120 18

AB-8

GAS PIPELINE1112

1413

17 16 15

109 8

AB-9

34

56

7

AB-10 1

2

43

III.A. Graphical Representation

As-Planned – January 2011

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 37 38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 197: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

CD-1

AB-6

65

AB-7

CD-9

AB-5

AB-2

AB-1

CD-8

CD-2

CD-6

CD-5

CD-7

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

SE-1

SE-2

CD-3CD-4

CD-10

CD-11

AB-3AB-4

AB-8

AB-10AB-9

64

37

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

39

1921

1820

2627

37

16 1517

1112

1413 GAS PIPELINE

11

III.A. Graphical Representation

As-Built – January 2011

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 198: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

AB-6

65

AB-7

CD-9

AB-5

AB-2

AB-1

CD-8

CD-2

CD-6

CD-5

CD-7

CD-1

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

SE-1

SE-2

CD-3CD-4

CD-10

CD-11

AB-3AB-4

AB-8

AB-10AB-9

64

37

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

39

1921

1820

2627

37

16 1517

1112

1413 GAS PIPELINE

11

III.A. Graphical Representation

As-Built – January 2011

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 199: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

CD-1

AB-7AB-6

65

CD-9

AB-5

AB-2

AB-1

CD-8

CD-2

CD-6

CD-5

CD-7

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

• Site Issues– Haphazard Component Deliveries– Lack of Completed Pad Sites / Roadway Segments– Snow Removal / Road Maintenance– Weather / Safety

33

SE-1

SE-2

CD-3CD-4

CD-10

CD-11

AB-3AB-4

AB-8

AB-10AB-9

64

37

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

39

1921

1820

2627

37

16 1517

1112

1413

10

GAS PIPELINE

11

III.A. Graphical Representation

As-Built – January 2011

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 200: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

AB-7AB-6

65

CD-9

AB-5

AB-2

AB-1

CD-8

CD-2

CD-6

CD-5

CD-7

CD-1

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

SE-1

SE-2

CD-3CD-4

CD-10

CD-11

AB-3AB-4

AB-8

AB-10AB-9

64

37

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

39

1921

1820

2627

37

16 1517

1112

1413 GAS PIPELINE

11

III.A. Graphical Representation

As-Built – February 201189

10

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 201: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

CD-1

AB-7AB-6

65

CD-9

AB-5

AB-2

AB-1

CD-8

CD-2

CD-6

CD-5

CD-7

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

SE-1

SE-2

CD-3CD-4

CD-10

CD-11

AB-3AB-4

AB-8

AB-10AB-9

64

37

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

39

1921

1820

2627

37

16 1517

1112

1413

5

GAS PIPELINE

11

III.A. Graphical Representation

As-Built – February 20117

68

109

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 202: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

AB-7AB-8

CD-1

SE-1

SE-2

AB-6

65

CD-9

AB-5

AB-2

AB-1

CD-8

CD-2

CD-6

CD-5

CD-7

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

CD-3CD-4

CD-10

CD-11

AB-3AB-4

AB-10AB-9

64

37

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

39

1921

1820

2627

37

16 1517

1112

1413

109

5

23

GAS PIPELINE

68

11

III.A. Graphical Representation

As-Built – February 20117

1

4

38 39 40 41 42 43 44 45 46 47 48 49WEEKS

Page 203: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

AB-7AB-8

CD-1

SE-1

SE-2

AB-10AB-9

AB-6

CD-9

AB-5

AB-2

AB-1

CD-8

CD-2

CD-6

CD-5

CD-7

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

CD-3CD-4

CD-10

CD-11

AB-3AB-4

64

37

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

39

1921

1820

2627

37

16 1517

1112

1413

109

5

23

GAS PIPELINE

• Site Issues– Haphazard Component Delivery– Coal Seams / Foundation Undercut– Weather / Safety

As-Built – February 2011

65

11

III.A. Graphical Representation

7

1

4

38 39 40 41 42 43 44 45 46 47 48 49

68

WEEKS

Page 204: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

AB-7AB-8

CD-1

SE-1

SE-2

AB-10AB-9

AB-6

CD-9

AB-5

AB-2

AB-1

CD-8

CD-2

CD-6

CD-5

CD-7

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

CD-3CD-4

CD-10

CD-11

AB-3AB-4

64

37

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

39

1921

1820

2627

37

16 1517

1112

1413

109

5

23

GAS PIPELINE

As-Built – March 2011

65

11

III.A. Graphical Representation

7

1

4

38 39 40 41 42 43 44 45 46 47 48 49

68

WEEKS

Page 205: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

AB-7AB-8

CD-1

SE-1

SE-2

AB-10AB-9

AB-6

CD-9

AB-5

AB-2

AB-1

CD-8

CD-2

CD-6

CD-5

CD-7

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

CD-3CD-4

CD-10

CD-11

AB-3AB-4

64

37

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

39

1921

1820

2627

37

16 1517

1112

1413

109

5

23

GAS PIPELINE

As-Built – March 2011

65

11

III.A. Graphical Representation

7

1

4

38 39 40 41 42 43 44 45 46 47 48 49

68

WEEKS

Page 206: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

AB-7AB-8

CD-1

SE-1

SE-2

AB-10AB-9

AB-6

CD-9

AB-5

AB-2

AB-1

CD-8

CD-2

CD-6

CD-5

CD-7

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

CD-3CD-4

CD-10

CD-11

AB-3AB-4

64

37

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

39

1921

1820

2627

37

16 1517

1112

1413

109

5

23

GAS PIPELINE

As-Built – March 2011

65

11

III.A. Graphical Representation

7

1

4

38 39 40 41 42 43 44 45 46 47 48 49

68

WEEKS

Page 207: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

AB-7AB-8

CD-1

SE-1

SE-2

AB-10AB-9

AB-6

CD-9

AB-5

AB-2

AB-1

CD-8

CD-2

CD-6

CD-5

CD-7

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

CD-3CD-4

CD-10

CD-11

AB-3AB-4

64

37

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

39

1921

1820

2627

37

16 1517

1112

1413

109

5

23

GAS PIPELINE

As-Built – March 2011

65

11

III.A. Graphical Representation

7

1

4

38 39 40 41 42 43 44 45 46 47 48 49

68

WEEKS

Page 208: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

AB-7AB-8

CD-1

SE-1

SE-2

AB-10AB-9

AB-6

CD-9

AB-5

AB-2

AB-1

CD-8

CD-2

CD-6

CD-5

CD-7

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

CD-3CD-4

CD-10

CD-11

AB-3AB-4

64

37

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

39

1921

1820

2627

37

16 1517

1112

1413

109

5

23

GAS PIPELINE

As-Built – April 2011

65

11

III.A. Graphical Representation

7

1

4

38 39 40 41 42 43 44 45 46 47 48 49

68

WEEKS

Page 209: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

AB-7AB-8

CD-1

SE-1

SE-2

AB-10AB-9

AB-6

CD-9

AB-5

AB-2

AB-1

CD-8

CD-2

CD-6

CD-5

CD-7

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

CD-3CD-4

CD-10

CD-11

AB-3AB-4

64

37

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

39

1921

1820

2627

37

16 1517

1112

1413

109

5

23

GAS PIPELINE

As-Built – April 2011

65

11

III.A. Graphical Representation

7

1

4

38 39 40 41 42 43 44 45 46 47 48 49

68

WEEKS

Page 210: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

AB-7AB-8

CD-1

SE-1

SE-2

AB-10AB-9

AB-6

CD-9

AB-5

AB-2

AB-1

CD-8

CD-2

CD-6

CD-5

CD-7

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

CD-3CD-4

CD-10

CD-11

AB-3AB-4

64

37

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

39

1921

1820

2627

37

16 1517

1112

1413

109

5

23

GAS PIPELINE

As-Built – April 2011

65

11

III.A. Graphical Representation

7

1

4

38 39 40 41 42 43 44 45 46 47 48 49

68

WEEKS

Page 211: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

AB-7AB-8

CD-1

SE-1

SE-2

AB-10AB-9

AB-6

CD-9

AB-5

AB-2

AB-1

CD-8

CD-2

CD-6

CD-5

CD-7

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

CD-3CD-4

CD-10

CD-11

AB-3AB-4

64

37

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

39

1921

1820

2627

37

16 1517

1112

1413

109

5

23

GAS PIPELINE

As-Built – April 2011

65

11

III.A. Graphical Representation

7

1

4

38 39 40 41 42 43 44 45 46 47 48 49

68

WEEKS

Page 212: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

AB-7AB-8

CD-1

SE-1

SE-2

AB-10AB-9

AB-6

CD-9

AB-5

AB-2

AB-1

CD-8

CD-2

CD-6

CD-5

CD-7

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

CD-3CD-4

CD-10

CD-11

AB-3AB-4

64

37

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

39

1921

1820

2627

37

16 1517

1112

1413

109

5

23

GAS PIPELINE

As-Built – April 2011

65

11

III.A. Graphical Representation

7

1

4

38 39 40 41 42 43 44 45 46 47 48 49

68

WEEKS

Page 213: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

AB-7AB-8

CD-1

SE-1

SE-2

AB-10AB-9

AB-6

CD-9

AB-5

AB-2

AB-1

CD-8

CD-2

CD-6

CD-5

CD-7

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

CD-3CD-4

CD-10

CD-11

AB-3AB-4

64

37

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

39

1921

1820

2627

37

16 1517

1112

1413

109

5

23

GAS PIPELINE

As-Built – May 2011

65

11

III.A. Graphical Representation

7

1

4

38 39 40 41 42 43 44 45 46 47 48 49

68

WEEKS

Page 214: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

AB-7AB-8

CD-1

SE-1

SE-2

AB-10AB-9

AB-6

CD-9

AB-5

AB-2

AB-1

CD-8

CD-2

CD-6

CD-5

CD-7

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

CD-3CD-4

CD-10

CD-11

AB-3AB-4

64

37

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

39

1921

1820

2627

37

16 1517

1112

1413

109

5

23

GAS PIPELINE

As-Built – May 2011

65

11

III.A. Graphical Representation

7

1

4

38 39 40 41 42 43 44 45 46 47 48 49

68

WEEKS

Page 215: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

AB-7AB-8

CD-1

SE-1

SE-2

AB-10AB-9

AB-6

CD-9

AB-5

AB-2

AB-1

CD-8

CD-2

CD-6

CD-5

CD-7

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

CD-3CD-4

CD-10

CD-11

AB-3AB-4

64

37

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

39

1921

1820

2627

37

16 1517

1112

1413

109

5

23

GAS PIPELINE

As-Built – May 2011

65

11

III.A. Graphical Representation

7

1

4

38 39 40 41 42 43 44 45 46 47 48 49

68

WEEKS

Page 216: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

LAUREL MOUNTAINWIND ENERGY PROJECT

KEY

Pad Site Excavation

Roadway

Foundation and Crane Pad

Completed During Current Week

Clearing and Grubbing

Scale: 1 mile

Base/Mid Grouted

WTG Mechanical Completion

25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 714 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 14 21 28 4 11 18 257JUN 2010 JUL 2010 AUG 2010 SEP 2010 OCT 2010 NOV 2010 DEC 2010 JAN 2011 FEB 2011 MAR 2011 APR 2011

2 9MAY 2011

16 23 30

AB-7AB-8

CD-1

SE-1

SE-2

AB-10AB-9

AB-6

CD-9

AB-5

AB-2

AB-1

CD-8

CD-2

CD-6

CD-5

CD-7

20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 361 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

33

CD-3CD-4

CD-10

CD-11

AB-3AB-4

64

37

56 546263 55 53 52

57

5150

4041424345 44

46

4847

49

313233

3534

36

29

38

28

30

222324

25

39

1921

1820

2627

37

16 1517

1112

1413

109

5

23

GAS PIPELINE

As-Built – May 2011

65

11

III.A. Graphical Representation

7

1

4

38 39 40 41 42 43 44 45 46 47 48 49 50

68

WEEKS

Page 217: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

2017 REGIONAL BUILDING CONSTRUCTION CONFERENCE

Rocky Pen Run Reservoir, VA

Page 218: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

Anticipated vs. As-built Progression of Work Areas by Week

Privileged and Confidential | For Mediation Purposes Only 218

Page 219: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 219

Production Drilling Anticipated to Start on 9/22/10

Work Zone Wk 1 to Wk 675% of work to be available per Subcontract Agreement

Page 220: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 220

Week 1: 9/22/10 to 9/28/10

NO PRODUCTION DRILLING THIS WEEK

Work Zone Wk 1 to Wk 6

Page 221: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 221

Week 2: 9/29/10 to 10/5/10

NO PRODUCTION DRILLING THIS WEEK

Work Zone Wk 1 to Wk 6

Page 222: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 222

Week 3: 10/6/10 to 10/12/10

NO PRODUCTION DRILLING THIS WEEK

Work Zone Wk 1 to Wk 6

Page 223: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 223

Week 4: 10/14/10 to 10/19/10

NO PRODUCTION DRILLING THIS WEEK

Work Zone Wk 1 to Wk 6

Page 224: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 224

Week 5: 10/20/10 to 10/26/10

NO PRODUCTION DRILLING THIS WEEK

Work Zone Wk 1 to Wk 6

Page 225: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 225

Week 6: 10/27/10 to 11/2/10

NO PRODUCTION DRILLING THIS WEEK

RIGHT SIDE COMPLETE. BEGIN MIDDLE.Work Zone Wk 1 to Wk 6Work Zone Wk 6 to Wk 10

Page 226: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 226

Week 7: 11/3/10 to 11/9/10

PRODUCTION DRILLING STARTS ON 11/8/10

COMPLETED WK 6Work Zone Wk 6 to Wk 10

Work Zone Wk 7 to Wk 6

Page 227: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 227

Week 8: 11/10/10 to 11/16/10

COMPLETED WK 6Work Zone Wk 6 to Wk 10

Work Zone Wk 7 to Wk 24

Page 228: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 228

Week 9: 11/17/10 to 11/23/10

COMPLETED WK 6Work Zone Wk 6 to Wk 10

Work Zone Wk 7 to Wk 24

Page 229: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 229

Week 10: 11/24/10 to 11/30/10

COMPLETED WK 6COMPLETED WK 10

Work Zone Wk 7 to Wk 24

MIDDLE COMPLETE. BEGIN LEFT SIDE.

Page 230: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 230

Week 11: 12/1/10 to 12/7/10

COMPLETED WK 6Work Zone Wk 11 to Wk 16

Work Zone Wk 7 to Wk 24

COMPLETED WK 10

Page 231: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 231

Week 12: 12/8/10 to 12/14/10

COMPLETED WK 6Work Zone Wk 11 to Wk 16

Work Zone Wk 7 to Wk 24

COMPLETED WK 10

Page 232: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 232

Week 13: 12/15/10 to 12/21/10

COMPLETED WK 6Work Zone Wk 11 to Wk 16

Work Zone Wk 7 to Wk 24

COMPLETED WK 10

Page 233: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 233

Week 14: 12/22/10 to 12/28/10

COMPLETED WK 6Work Zone Wk 11 to Wk 16

Work Zone Wk 7 to Wk 24

COMPLETED WK 10

Page 234: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 234

Week 15: 12/29/10 to 1/4/11

COMPLETED WK 6Work Zone Wk 11 to Wk 16

Work Zone Wk 7 to Wk 24

COMPLETED WK 10

Page 235: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 235

Week 16: 1/5/11 to 1/11/11

PRODUCTION DRILLING 100% COMPLETE ON 1/11/11

PRODUCTION DRILLING 18.52% COMPLETE ON 1/11/11

COMPLETED WK 6COMPLETED WK 16

Work Zone Wk 7 to Wk 24

COMPLETED WK 10

Page 236: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 236

Week 17: 1/12/11 to 1/18/11

Work Zone Wk 7 to Wk 24

COMPLETED WK 6COMPLETED WK 16 COMPLETED WK 10

PRODUCTION DRILLING 100% COMPLETE ON WK 16

Page 237: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 237

Week 18: 1/19/11 to 1/25/11

Work Zone Wk 7 to Wk 24

COMPLETED WK 6COMPLETED WK 16 COMPLETED WK 10

PRODUCTION DRILLING 100% COMPLETE ON WK 16

Page 238: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 238

Week 19: 1/26/11 to 2/1/11

Work Zone Wk 7 to Wk 24

COMPLETED WK 6COMPLETED WK 16 COMPLETED WK 10

PRODUCTION DRILLING 100% COMPLETE ON WK 16

Page 239: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 239

Week 20: 2/2/11 to 2/8/11

Work Zone Wk 7 to Wk 24

COMPLETED WK 6COMPLETED WK 16 COMPLETED WK 10

PRODUCTION DRILLING 100% COMPLETE ON WK 16

Page 240: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 240

Week 21: 2/9/11 to 2/15/11

Work Zone Wk 7 to Wk 24

COMPLETED WK 6COMPLETED WK 16 COMPLETED WK 10

PRODUCTION DRILLING 100% COMPLETE ON WK 16

Page 241: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 241

Week 22: 2/16/11 to 2/22/11

Work Zone Wk 7 to Wk 24

COMPLETED WK 6COMPLETED WK 16 COMPLETED WK 10

PRODUCTION DRILLING 100% COMPLETE ON WK 16

Page 242: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 242

Week 23: 2/23/11 to 3/1/11

Work Zone Wk 7 to Wk 24

COMPLETED WK 6COMPLETED WK 16 COMPLETED WK 10

PRODUCTION DRILLING 100% COMPLETE ON WK 16

Page 243: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 243

Week 24: 3/2/11 to 3/8/11

RIGHT SIDE COMPLETED 18 WKS LATER THAN ANTICIPATED.BEGIN LEFT SIDE

COMPLETED WK 24

COMPLETED WK 6COMPLETED WK 16 COMPLETED WK 10

PRODUCTION DRILLING 100% COMPLETE ON WK 16

Page 244: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 244

Week 25: 3/9/11 to 3/15/11

COMPLETED WK 6COMPLETED WK 16 COMPLETED WK 10

PRODUCTION DRILLING 100% COMPLETE ON WK 16

COMPLETED WK 24Work Zone Wk 25 to Wk 44 (Determined by GEI's release of Work Areas)

Page 245: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 245

Week 26: 3/16/11 to 3/22/11

COMPLETED WK 6COMPLETED WK 16 COMPLETED WK 10

PRODUCTION DRILLING 100% COMPLETE ON WK 16

COMPLETED WK 24Work Zone Wk 25 to Wk 44 (Determined by GEI's release of Work Areas)

Page 246: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 246

Week 27: 3/23/11 to 3/29/11

COMPLETED WK 6COMPLETED WK 16 COMPLETED WK 10

PRODUCTION DRILLING 100% COMPLETE ON WK 16

COMPLETED WK 24Work Zone Wk 25 to Wk 44 (Determined by GEI's release of Work Areas)

Page 247: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 247

Week 28: 3/30/11 to 4/5/11

COMPLETED WK 6COMPLETED WK 16 COMPLETED WK 10

PRODUCTION DRILLING 100% COMPLETE ON WK 16

COMPLETED WK 24Work Zone Wk 25 to Wk 44 (Determined by GEI's release of Work Areas)

Page 248: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 248

Week 29: 4/6/11 to 4/12/11

COMPLETED WK 6COMPLETED WK 16 COMPLETED WK 10

PRODUCTION DRILLING 100% COMPLETE ON WK 16

COMPLETED WK 24Work Zone Wk 25 to Wk 44 (Determined by GEI's release of Work Areas)

Page 249: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 249

Week 30: 4/13/11 to 4/19/11

COMPLETED WK 6COMPLETED WK 16 COMPLETED WK 10

PRODUCTION DRILLING 100% COMPLETE ON WK 16

COMPLETED WK 24Work Zone Wk 25 to Wk 44 (Determined by GEI's release of Work Areas)

Page 250: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 250

Week 31: 4/20/11 to 4/26/11

COMPLETED WK 6COMPLETED WK 16 COMPLETED WK 10

PRODUCTION DRILLING 100% COMPLETE ON WK 16

COMPLETED WK 24Work Zone Wk 25 to Wk 44 (Determined by GEI's release of Work Areas)

Page 251: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 251

Week 32: 4/27/11 to 5/3/11

COMPLETED WK 6COMPLETED WK 16 COMPLETED WK 10

PRODUCTION DRILLING 100% COMPLETE ON WK 16

COMPLETED WK 24Work Zone Wk 25 to Wk 44 (Determined by GEI's release of Work Areas)

Page 252: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 252

Week 33: 5/4/11 to 5/10/11

COMPLETED WK 6COMPLETED WK 16 COMPLETED WK 10

PRODUCTION DRILLING 100% COMPLETE ON WK 16

COMPLETED WK 24Work Zone Wk 25 to Wk 44 (Determined by GEI's release of Work Areas)

Page 253: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 253

Week 34: 5/11/11 to 5/17/11

COMPLETED WK 6COMPLETED WK 16 COMPLETED WK 10

PRODUCTION DRILLING 100% COMPLETE ON WK 16

COMPLETED WK 24Work Zone Wk 25 to Wk 44 (Determined by GEI's release of Work Areas)

Page 254: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 254

Week 35: 5/18/11 to 5/24/11

COMPLETED WK 6COMPLETED WK 16 COMPLETED WK 10

PRODUCTION DRILLING 100% COMPLETE ON WK 16

COMPLETED WK 24Work Zone Wk 25 to Wk 44 (Determined by GEI's release of Work Areas)

Page 255: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 255

Week 36: 5/25/11 to 5/31/11

COMPLETED WK 6COMPLETED WK 16 COMPLETED WK 10

PRODUCTION DRILLING 100% COMPLETE ON WK 16

COMPLETED WK 24Work Zone Wk 25 to Wk 44 (Determined by GEI's release of Work Areas)

Page 256: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 256

Week 37: 6/1/11 to 6/7/11

COMPLETED WK 6COMPLETED WK 16 COMPLETED WK 10

PRODUCTION DRILLING 100% COMPLETE ON WK 16

COMPLETED WK 24Work Zone Wk 25 to Wk 44 (Determined by GEI's release of Work Areas)

Page 257: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 257

Week 38: 6/8/11 to 6/14/11

COMPLETED WK 6COMPLETED WK 16 COMPLETED WK 10

PRODUCTION DRILLING 100% COMPLETE ON WK 16

COMPLETED WK 24Work Zone Wk 25 to Wk 44 (Determined by GEI's release of Work Areas)

Page 258: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 258

Week 39: 6/15/11 to 6/21/11

COMPLETED WK 6COMPLETED WK 16 COMPLETED WK 10

PRODUCTION DRILLING 100% COMPLETE ON WK 16

COMPLETED WK 24Work Zone Wk 25 to Wk 44 (Determined by GEI's release of Work Areas)

Page 259: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 259

Week 40: 6/22/11 to 6/28/11

COMPLETED WK 6COMPLETED WK 16 COMPLETED WK 10

PRODUCTION DRILLING 100% COMPLETE ON WK 16

COMPLETED WK 24Work Zone Wk 25 to Wk 44 (Determined by GEI's release of Work Areas)

Page 260: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 260

Week 41: 6/29/11 to 7/5/11

COMPLETED WK 6COMPLETED WK 16 COMPLETED WK 10

PRODUCTION DRILLING 100% COMPLETE ON WK 16

COMPLETED WK 24Work Zone Wk 25 to Wk 44 (Determined by GEI's release of Work Areas)

Page 261: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 261

Week 42: 7/6/11 to 7/12/11

COMPLETED WK 6COMPLETED WK 16 COMPLETED WK 10

PRODUCTION DRILLING 100% COMPLETE ON WK 16

COMPLETED WK 24Work Zone Wk 25 to Wk 44 (Determined by GEI's release of Work Areas)

Page 262: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 262

Week 43: 7/13/11 to 7/19/11

COMPLETED WK 6COMPLETED WK 16 COMPLETED WK 10

PRODUCTION DRILLING 100% COMPLETE ON WK 16

COMPLETED WK 24Work Zone Wk 25 to Wk 44 (Determined by GEI's release of Work Areas)

Page 263: Project CPM Scheduling Fundamentals...• CPM: Critical Path Method −Involves both a graphical portrayalof the interrelationships among the elements of a project (activities), and

Rocky Pen Run Reservoir

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

19+00 18+00 17+00 16+00 15+00 14+00 13+00 12+00 11+00 10+00 9+00 8+00 7+00 6+00 5+00 4+00

PROFILE VIEW

100

150

200

250

ANTICIPATED Grout Hole Drilling Sequence

AS-BUILT Grout Hole Drilling Sequence

Privileged and Confidential | For Mediation Purposes Only | Not to Scale 263

Week 44: 7/20/11 to 7/26/11

PRODUCTION DRILLING COMPLETED ON 7/26/11: 28 WKS LATER THAN ANTICIPATED.

COMPLETED WK 6COMPLETED WK 16 COMPLETED WK 10

PRODUCTION DRILLING 100% COMPLETE ON WK 16

COMPLETED WK 24COMPLETED WK 24


Recommended